CN206969989U - A kind of pile foundation reinforcement cage hoisting equipment - Google Patents
A kind of pile foundation reinforcement cage hoisting equipment Download PDFInfo
- Publication number
- CN206969989U CN206969989U CN201720832852.6U CN201720832852U CN206969989U CN 206969989 U CN206969989 U CN 206969989U CN 201720832852 U CN201720832852 U CN 201720832852U CN 206969989 U CN206969989 U CN 206969989U
- Authority
- CN
- China
- Prior art keywords
- pile foundation
- reinforcement cage
- hoisting equipment
- steel bar
- foundation reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 37
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 58
- 239000010959 steel Substances 0.000 claims abstract description 58
- 239000000725 suspension Substances 0.000 claims abstract description 14
- 238000003466 welding Methods 0.000 claims description 5
- 239000004744 fabric Substances 0.000 claims 1
- 238000005516 engineering process Methods 0.000 abstract description 3
- 238000010276 construction Methods 0.000 abstract description 2
- 230000004048 modification Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000003014 reinforcing effect Effects 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model technology is related to construction engineering technical field, specially a kind of pile foundation reinforcement cage hoisting equipment.Pile foundation reinforcement cage hoisting equipment includes:Some transverse support ribs, transverse support ribs are arranged at intervals;Two vertical fixed plates, two vertical fixed plates are located at the both ends of transverse support ribs respectively, and are vertically arranged with transverse support ribs, through hole are respectively arranged with two vertical fixed plates, the vertical reserved steel bar of pile foundation steel bar cage passes through through hole;Fastener, the vertical reserved steel bar through through hole is fixed on hanging device;Suspension ring are provided with every vertical fixed plate, and suspension ring are located at the both sides of through hole.Using the hanging device can quickly, the lifting pile foundation steel bar cage of safety, can increase substantially pile foundation reinforcement cage hoisting efficiency, and can flexible modulation pile foundation steel bar cage position in casing, improve stake position precision.
Description
Technical field
The utility model technology is related to construction engineering technical field, specially a kind of pile foundation reinforcement cage hoisting equipment.
Background technology
In the prior art, it is general directly to sling pile foundation steel bar cage using crane.But directly slinging pile foundation using crane
During steel reinforcement cage, perpendicularity, less stable when steel reinforcement cage is sling, easily to rock, security is poor, and nor
Often inconvenient, the versatility of crane is poor, and the accuracy for putting steel reinforcement cage is poor.
Based on above description, a kind of pile foundation reinforcement cage hoisting equipment is needed badly, to solve steel reinforcement cage present in prior art
Perpendicularity, less stable when slinging, are easily rocked, and security is poor, and also very inconvenient, the versatility of crane
It is poor, put steel reinforcement cage accuracy it is poor the problem of.
Utility model content
To solve the problems, such as the above, the purpose of this utility model is to provide a kind of pile foundation reinforcement cage hoisting equipment, uses
The hanging device can quickly, the lifting pile foundation steel bar cage of safety, can increase substantially pile foundation reinforcement cage hoisting efficiency, and can spirit
Regulation pile foundation steel bar cage position in casing living, improves stake position precision.
To achieve the above object, the utility model adopts the following technical scheme that:
A kind of pile foundation reinforcement cage hoisting equipment, including:
Some transverse support ribs, transverse support ribs are arranged at intervals;
Two vertical fixed plates, two vertical fixed plates are located at the both ends of transverse support ribs, and and transverse support ribs respectively
It is vertically arranged, through hole is respectively arranged with two vertical fixed plates, the vertical reserved steel bar of pile foundation steel bar cage passes through through hole;
Fastener, the vertical reserved steel bar through through hole is fixed on hanging device;
Suspension ring are provided with every vertical fixed plate, and suspension ring are located at the both sides of through hole.
As preferred, all transverse support ribs are evenly distributed.
As preferred, two through holes are respectively arranged with each vertical fixed plate.
Preferably, be provided with two pairs of suspension ring in every vertical fixed plate, two pairs of suspension ring are respectively positioned at two through holes
Both sides.
Preferably, described be vertically provided with pad between fixed plate and fastener, the pad reserves steel from vertical
The upper end of muscle passes through, and fastener is fixed on pad upper end.
As preferred, the pad is steel plate washer.
As preferred, the fastener is nut or sleeve.
As preferred, the transverse support ribs are made using 2-18a I-steel.
As preferred, the vertical fixed plate is made using 2cm steel plates.
As preferred, the transverse support ribs both ends pass through welding manner respectively and corresponding vertical fixed plate is fixed and connected
Connect.
Compared with prior art, the pile foundation reinforcement cage hoisting equipment that the application provides has the characteristics that and beneficial effect:
The pile foundation reinforcement cage hoisting equipment that the application provides is suitably applied high-volume pile foundation steel bar cage fast hoisting, uses
The method of welding produces pile foundation reinforcement cage hoisting equipment, the vertical reserved steel bar of pile foundation steel bar cage is connected with hanging device, so
Suspender and steel reinforcement cage are sling and be accurately placed in casing by crane afterwards.The hanging device have safely, conveniently, versatility
By force, the advantages that steel reinforcement cage is accurate is put.
Brief description of the drawings
Fig. 1 is the top view of hanging device provided by the utility model;
Fig. 2 is the vertical reserved steel bar and hanging device installation diagram of pile foundation steel bar cage provided by the utility model.
Reference,
1- transverse support ribs;The vertical fixed plates of 2-;21- through holes;3- fasteners;The vertical reserved steel bars of 4-;5- suspension ring;6-
Pad.
Embodiment
The utility model is described in further detail below by specific examples of the implementation combination accompanying drawing.
As shown in Figure 1 to Figure 2, a kind of pile foundation reinforcement cage hoisting equipment provided by the utility model, including:
Some transverse support ribs 1, transverse support ribs 1 are arranged at intervals;
Two vertical fixed plates 2, two vertical fixed plates 2 are located at the both ends of transverse support ribs 1, and and cross-brace respectively
Rib 1 is vertically arranged, and through hole is respectively arranged with two vertical fixed plates 2, and the vertical reserved steel bar 4 of pile foundation steel bar cage, which passes through, to be led to
Hole;
Fastener 3, the vertical reserved steel bar 4 through through hole is fixed on hanging device;
Suspension ring 5 are provided with every vertical fixed plate 2, and suspension ring 5 are located at the both sides of through hole.
Using the hanging device can quickly, safety lifting pile foundation steel bar cage, pile foundation steel bar cage can be increased substantially and hung
Efficiency, and energy flexible modulation pile foundation steel bar cage position in casing are filled, improves stake position precision.
In the present embodiment, preferably, all transverse support ribs 1 are evenly distributed.And the transverse support ribs 1
Number be preferably 4, but be not limited thereto.
In the present embodiment, preferably, two through holes are respectively arranged with each vertical fixed plate 2, but
It is not limited thereto.
In the present embodiment, preferably, two pairs of suspension ring 5, two pairs of suspension ring are provided with every vertical fixed plate 2
5 respectively positioned at the both sides of two through holes.
It is preferably, described that pad 6 is vertically provided between fixed plate 2 and fastener 3 in the present embodiment,
The pad 6 passes through from the upper end of vertical reserved steel bar 4, and fastener 3 is fixed on the upper end of pad 6.
In the present embodiment, preferably, the pad 6 is steel plate washer, but is not limited thereto.
In the present embodiment, preferably, the fastener 3 is nut or sleeve, but is not limited thereto.
In the present embodiment, preferably, the transverse support ribs 1 are made using 2-18a I-steel, but simultaneously
It is not limited to this material.
In the present embodiment, preferably, the vertical fixed plate 2 is made using 2cm steel plates, but not
It is confined to this material.
In the present embodiment, preferably, the both ends of transverse support ribs 1 respectively by welding manner with it is corresponding
Vertical fixed plate 2 is fixedly connected.
The idiographic flow for making and using for pile foundation steel bar cage below:
(1)According to pile foundation steel bar cage size welding hanging device.
Pile foundation steel bar cage drawing is first looked at, determines the hanging device of suitable dimension.
(2)Connect hanging device, pile foundation steel bar cage
4 steel reinforcement cage vertical reinforcements are passed through into hanging device reserved through hole and pad, using nut or sleeve by reinforcing bar with
Steel plate washer is fixed.
(3)Put pile foundation steel bar cage
Pile foundation steel bar cage is sling, the position of pile foundation steel bar cage is adjusted while pile foundation steel bar cage is placed, to ensure stake
Level is true.
Another advantage of this programme is that pile foundation reinforcement cage hoisting is quick, safe, and certain modification can be applied to difference
The steel reinforcement cage in stake footpath.
In the present embodiment, when selection is connected reinforcing bar with hanging device, to ensure that steel reinforcement cage can firmly, surely when slinging
It is fixed, every two of 4 reinforcing bars must be selected mutually on steel reinforcement cage diameter symmetry, and be vertically optimal with normal between any two.
Preferred embodiment of the present utility model is the foregoing is only, is not limited to the utility model, for this
For the technical staff in field, the utility model can have various modifications and variations.It is all in the spirit and principles of the utility model
Within, any modification, equivalent substitution and improvements made etc., it should be included within the scope of protection of the utility model.
Claims (10)
- A kind of 1. pile foundation reinforcement cage hoisting equipment, it is characterised in that including:Some transverse support ribs, cross-brace rib space Set;Two vertical fixed plates, two vertical fixed plates are located at the both ends of transverse support ribs respectively, and are hung down with transverse support ribs It is straight to set, through hole is respectively arranged with two vertical fixed plates, the vertical reserved steel bar of pile foundation steel bar cage passes through through hole;Fastening dress Put, the vertical reserved steel bar through through hole is fixed on hanging device;Suspension ring are provided with every vertical fixed plate, and are hung Ring is located at the both sides of through hole.
- 2. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that all transverse support ribs are in uniform point Cloth.
- 3. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that divide in each vertical fixed plate Two through holes are not provided with.
- 4. pile foundation reinforcement cage hoisting equipment according to claim 3, it is characterised in that be respectively provided with every vertical fixed plate There are two pairs of suspension ring, two pairs of suspension ring are respectively positioned at the both sides of two through holes.
- 5. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the vertical fixed plate fills with fastening Pad is provided between putting, the pad passes through from the upper end of vertical reserved steel bar, and fastener is fixed on pad upper end.
- 6. pile foundation reinforcement cage hoisting equipment according to claim 5, it is characterised in that the pad is steel plate washer.
- 7. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the fastener is nut or set Cylinder.
- 8. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the transverse support ribs use 2- 18a I-steel is made.
- 9. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the vertical fixed plate uses 2cm Steel plate is made.
- 10. pile foundation reinforcement cage hoisting equipment according to claim 1, it is characterised in that the transverse support ribs both ends point It is not fixedly connected by welding manner with corresponding vertical fixed plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720832852.6U CN206969989U (en) | 2017-07-11 | 2017-07-11 | A kind of pile foundation reinforcement cage hoisting equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720832852.6U CN206969989U (en) | 2017-07-11 | 2017-07-11 | A kind of pile foundation reinforcement cage hoisting equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206969989U true CN206969989U (en) | 2018-02-06 |
Family
ID=61402482
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720832852.6U Expired - Fee Related CN206969989U (en) | 2017-07-11 | 2017-07-11 | A kind of pile foundation reinforcement cage hoisting equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206969989U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111705664A (en) * | 2020-06-08 | 2020-09-25 | 中铁北京工程局集团第一工程有限公司 | Hoisting process of prefabricated pier stud of assembled bridge |
CN113734954A (en) * | 2021-08-12 | 2021-12-03 | 广东地山基础工程有限公司 | Bored concrete pile steel reinforcement cage hoist and mount auxiliary device of stress point can quick adjustment |
-
2017
- 2017-07-11 CN CN201720832852.6U patent/CN206969989U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111705664A (en) * | 2020-06-08 | 2020-09-25 | 中铁北京工程局集团第一工程有限公司 | Hoisting process of prefabricated pier stud of assembled bridge |
CN113734954A (en) * | 2021-08-12 | 2021-12-03 | 广东地山基础工程有限公司 | Bored concrete pile steel reinforcement cage hoist and mount auxiliary device of stress point can quick adjustment |
CN113734954B (en) * | 2021-08-12 | 2023-05-16 | 广东地山基础工程有限公司 | Cast-in-place pile reinforcement cage hoisting auxiliary device capable of quickly adjusting stress point |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207294093U (en) | A kind of large span steel truss integral lifting apparatus | |
CN206267139U (en) | A kind of pile foundation steel bar cage positioning and concrete pouring support | |
CN206969989U (en) | A kind of pile foundation reinforcement cage hoisting equipment | |
CN105129602A (en) | Sling capable of integrally lifting long and large-diameter vertical steel bars | |
CN209455933U (en) | A kind of superimposed sheet lifting appliance for hoisting | |
CN204038849U (en) | A kind of cable drum lifting device | |
CN207538483U (en) | A kind of steel box-girder suspender | |
CN206665955U (en) | A kind of high-strength steel triangle suspender lifts framework constructing device | |
CN206971084U (en) | The supporting construction of bridge coping template | |
CN203976209U (en) | A kind of hoisting large-size is without the lid that hangs of hanger equipment | |
CN103556626A (en) | Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage | |
CN202785257U (en) | Control device used for hoisting and positioning steel reinforcement cage of manual hole digging piles | |
CN108516454A (en) | A kind of hanging apparatus of prefabricated components | |
CN206580440U (en) | A kind of girder steel string device for hoisting | |
CN208265608U (en) | Large-tonnage hoisting device for reinforcement cage | |
CN207685827U (en) | The punching piling machine for square hole pile foundation of constructing | |
CN202830787U (en) | Duplex beam for bridge construction | |
CN203625891U (en) | Hanging structure for large-diameter hole drilling cast pile reinforcement cage hanging | |
CN205976550U (en) | Cluster hangs instrument of girder steel | |
CN206735623U (en) | Framework of steel reinforcement hanging apparatus | |
CN106629377A (en) | Large-scale steel reinforcement cage lifting appliance | |
CN216515543U (en) | Steel reinforcement cage suspension device | |
CN205474858U (en) | Bridge bent cap or binder formwork support adjusting device | |
CN205346596U (en) | Balanced type precast beam side form hoist device | |
CN204199271U (en) | A kind of filling pile cage of reinforcement hangs fastening devices |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180206 |