CN206873470U CN201720755366.9U CN201720755366U CN206873470U CN 206873470 U CN206873470 U CN 206873470U CN 201720755366 U CN201720755366 U CN 201720755366U CN 206873470 U CN206873470 U CN 206873470U
Authority
CN
China
Prior art keywords
swash plate
mainboard
main
fixedly connected
transverse slat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720755366.9U
Other languages
Chinese (zh)
Inventor
户振法
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan University
Original Assignee
Foshan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan University filed Critical Foshan University
Priority to CN201720755366.9U priority Critical patent/CN206873470U/en
Application granted granted Critical
Publication of CN206873470U publication Critical patent/CN206873470U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a kind of high slope rockmass structure, it includes the mainboard circumferentially extended along side slope, shingle nail, first main swash plate, transverse slat, second main swash plate, support swash plate, the shingle nail is fixed the middle part for standing on the mainboard and is extended in front and rear, the upper end of the first main swash plate is fixedly connected with metope plate surface, the lower end of the first main swash plate is fixedly connected with the left end of mainboard, the transverse slat has left and right ends and parallel above the mainboard, the left end of the transverse slat is fixedly connected with the top of the shingle nail, the lower end of the second main swash plate is fixedly connected with the upper end of the shingle nail while forms the angle less than 90 degree with the transverse slat.The utility model is set by the integral type of mainboard, shingle nail, the second main swash plate and transverse slat, form overall structure, own wt is placed on transverse slat and mainboard by High Slope Rock so that the impulse force of collapse of rock mass have to be larger than rock mass own wt, allow collapse of rock mass situation to greatly reduce.

Description

A kind of high slope rockmass structure
Technical field
Engineering construction field is the utility model is related to, more particularly to a kind of high slope rockmass structure.
Background technology
The side slope formed in engineering construction, when running into rainy day or sharp pounding, landslide, avalanche, expansion often occurs Or the generation of the geological disaster such as stripping, to prevent the generation of above-mentioned geological disaster, it is necessary to carry out slope treatment.Existing major part All using lattice anchor cable structure, spray shield anchor cable structure etc., although this solves the problems, such as slope construction, construction week be present in job site Phase is grown, and slope deforming is larger, the problems such as influenceing safety of surrounding environment.
Utility model content
The technical problems to be solved in the utility model is:For above-mentioned the deficiencies in the prior art, there is provided a kind of high slope branch Protection structure, its is rational in infrastructure, practical function, is adapted to be widely popularized.
The solution that the utility model solves its technical problem is:A kind of high slope rockmass structure, it is included along side Mainboard, shingle nail, the first main swash plate, transverse slat, the second main swash plate, the support swash plate of slope circumferentially extending, the mainboard have left and right Both ends and high slope bottom being horizontally placed on, the shingle nail is fixed the middle part for standing on the mainboard and is extended in front and rear, The upper end of the first main swash plate is fixedly connected with metope plate surface, and the lower end of the first main swash plate and the left end of mainboard are fixed Connection, the transverse slat has left and right ends and parallel above the mainboard, the left end of the transverse slat and the shingle nail Top is fixedly connected, and the lower end of the second main swash plate is fixedly connected with the upper end of the shingle nail while formed with the transverse slat Angle less than 90 degree, the upper end of the support swash plate are fixedly connected with transverse slat, are supported the lower end of swash plate to be fixed with shingle nail and are connected Connect, the upper end of the first main swash plate is positioned at the top of the lower end of the support swash plate.
As the further improvement of above-mentioned technical proposal, the first main swash plate includes some articles and is spaced the of setting One main cant beam.
As the further improvement of above-mentioned technical proposal, sustaining wall is provided with below the first main cant beam.
As the further improvement of above-mentioned technical proposal, the transverse slat includes some crossbeams for being spaced setting.
As the further improvement of above-mentioned technical proposal, the second main swash plate includes some articles and is spaced the of setting Two main cant beams.
As the further improvement of above-mentioned technical proposal, the support swash plate includes some supports for being spaced setting Cant beam.
As the further improvement of above-mentioned technical proposal, the mainboard, shingle nail, the first main cant beam, crossbeam, the second master are oblique Reinforcing bar group is embedded with beam, support cant beam.
As the further improvement of above-mentioned technical proposal, the mainboard, shingle nail, the first main cant beam, crossbeam, the second master are oblique The both ends for the reinforcing bar group that beam, support cant beam are buried between the two are fixedly connected by retainer ring.
As the further improvement of above-mentioned technical proposal, the right-hand member for the reinforcing bar group buried in the crossbeam is fixedly connected with the One steel reinforcement cage.
As the further improvement of above-mentioned technical proposal, the right-hand member for the reinforcing bar group buried in the mainboard is fixedly connected with the Two steel reinforcement cages.
The beneficial effects of the utility model are:The utility model by mainboard, shingle nail, the second main swash plate and transverse slat one Body formula is set, and forms overall structure, and own wt is placed on transverse slat and mainboard by High Slope Rock so that the impulse force of collapse of rock mass Rock mass own wt is have to be larger than, allows collapse of rock mass situation to greatly reduce, while setting up for the first main swash plate causes shingle nail Enabling capabilities greatly increase.The first main swash plate, transverse slat, the second main swash plate and support swash plate in the utility model are that hollow out is set Put, greatly reduce the usage amount of concrete.The utility model is rational in infrastructure, practical function, is adapted to be widely popularized.
Brief description of the drawings
, below will be to needed for embodiment description in order to illustrate more clearly of the technical scheme in the embodiment of the utility model The accompanying drawing to be used is briefly described.Obviously, described accompanying drawing is part of the embodiment of the present utility model, rather than entirely Portion's embodiment, those skilled in the art on the premise of not paying creative work, can also obtain it according to these accompanying drawings His design and accompanying drawing.
Fig. 1 is cross-sectional view of the present utility model;
Fig. 2 is reinforcing bar group distribution schematic diagram of the present utility model;
Fig. 3 is positive structure diagram of the present utility model.
Embodiment
Design, concrete structure and caused technique effect of the present utility model are carried out below with reference to embodiment and accompanying drawing Clear, complete description, to be completely understood by the purpose of this utility model, feature and effect.Obviously, described embodiment It is part of the embodiment of the present utility model, rather than whole embodiments, based on embodiment of the present utility model, the skill of this area The other embodiment that art personnel are obtained on the premise of not paying creative work, belong to the model of the utility model protection Enclose.In addition, all connection/annexations being previously mentioned in text, not singly refer to component and directly connect, and refer to can be according to specific reality Situation is applied, by adding or reducing couple auxiliary, to form more excellent draw bail.Each technology in the invention is special Sign, can be with combination of interactions on the premise of not conflicting conflict.
1~Fig. 3 of reference picture, a kind of high slope rockmass structure, it is included along the mainboard 1 of side slope circumferentially extending, shingle nail 2nd, the first main swash plate 3, transverse slat 4, the second main swash plate 5, support swash plate 6, the mainboard 1 have left and right ends and are horizontally placed on height Side slope bottom, the shingle nail 2 are fixed the middle part for standing on the mainboard 1 and are extended in front and rear, the first main swash plate 3 Upper end is fixedly connected with the surface of shingle nail 2, and the lower end of the first main swash plate 3 is fixedly connected with the left end of mainboard 1, the transverse slat 4 with left and right ends and parallel above the mainboard 1, the top fixation company of the left end of the transverse slat 4 and the shingle nail 2 Connect, the lower end of the second main swash plate 5, which is fixedly connected with the upper end of the shingle nail 2 while formed with the transverse slat 4, is less than 90 The angle of degree, the upper end of the support swash plate 6 are fixedly connected with transverse slat 4, and the lower end of support swash plate 6 is fixedly connected with shingle nail 2, The upper end of the first main swash plate 3 is positioned at the top of the lower end of the support swash plate 6.
Preferred embodiment is further used as, the first main swash plate 3 is spaced the first of setting including some Main cant beam 31.
Preferred embodiment is further used as, the first main lower section of cant beam 31 is provided with sustaining wall 7.
Preferred embodiment is further used as, the transverse slat 4 includes some crossbeams 41 for being spaced setting.
Preferred embodiment is further used as, the second main swash plate 5 is spaced the second of setting including some Main cant beam 51.
Preferred embodiment is further used as, it is oblique that the support swash plate 6 includes some supports for being spaced setting Beam 61.
Preferred embodiment is further used as, the mainboard 1, shingle nail 2, the first main cant beam 31, crossbeam 41, second are led Reinforcing bar group 8 is embedded with cant beam 51, support cant beam 61.
Preferred embodiment is further used as, the mainboard 1, shingle nail 2, the first main cant beam 31, crossbeam 41, second are led The both ends for the reinforcing bar group 8 that cant beam 51, support cant beam 61 are buried between the two are fixedly connected by retainer ring 81.
It is further used as preferred embodiment, the right-hand member of the reinforcing bar group 8 buried in the crossbeam 41 is fixedly connected with the One steel reinforcement cage 91.
Preferred embodiment is further used as, the right-hand member for the reinforcing bar group 8 buried in the mainboard 1 is fixedly connected with second Steel reinforcement cage 92.
Better embodiment of the present utility model is illustrated above, but the invention be not limited to it is described Embodiment, those skilled in the art can also make a variety of equivalent changes on the premise of without prejudice to the utility model spirit Type or replacement, these equivalent modifications or replacement are all contained in the application claim limited range.

Claims (10)

  1. A kind of 1. high slope rockmass structure, it is characterised in that:Including along the mainboard of side slope circumferentially extending, shingle nail, the first master Swash plate, transverse slat, the second main swash plate, support swash plate, the mainboard has left and right ends and is horizontally placed on high slope bottom, described Shingle nail is fixed the middle part for standing on the mainboard and is extended in front and rear, upper end and the metope plate surface of the first main swash plate It is fixedly connected, the lower end of the first main swash plate is fixedly connected with the left end of mainboard, and the transverse slat has left and right ends and parallel Above the mainboard, the left end of the transverse slat is fixedly connected with the top of the shingle nail, under the second main swash plate End is fixedly connected with the upper end of the shingle nail while forms the angle less than 90 degree with the transverse slat, described to support the upper of swash plate End is fixedly connected with transverse slat, supports the lower end of swash plate to be fixedly connected with shingle nail, and the upper end of the first main swash plate is positioned at described Support the top of the lower end of swash plate.
  2. A kind of 2. high slope rockmass structure according to claim 1, it is characterised in that:The first main swash plate includes some Bar is spaced the first main cant beam of setting.
  3. A kind of 3. high slope rockmass structure according to claim 2, it is characterised in that:It is provided with below the first main cant beam Sustaining wall.
  4. A kind of 4. high slope rockmass structure according to claim 3, it is characterised in that:The transverse slat includes some intervals The crossbeam of spread configuration.
  5. A kind of 5. high slope rockmass structure according to claim 4, it is characterised in that:The second main swash plate includes some Bar is spaced the second main cant beam of setting.
  6. A kind of 6. high slope rockmass structure according to claim 5, it is characterised in that:The support swash plate includes some It is spaced the support cant beam of setting.
  7. A kind of 7. high slope rockmass structure according to claim 6, it is characterised in that:The mainboard, shingle nail, the first master Reinforcing bar group is embedded with cant beam, crossbeam, the second main cant beam, support cant beam.
  8. A kind of 8. high slope rockmass structure according to claim 7, it is characterised in that:The mainboard, shingle nail, the first master The both ends for the reinforcing bar group that cant beam, crossbeam, the second main cant beam, support cant beam are buried between the two are fixedly connected by retainer ring.
  9. A kind of 9. high slope rockmass structure according to claim 7, it is characterised in that:The reinforcing bar group buried in the crossbeam Right-hand member be fixedly connected with the first steel reinforcement cage.
  10. A kind of 10. high slope rockmass structure according to claim 7, it is characterised in that:The reinforcing bar buried in the mainboard The right-hand member of group is fixedly connected with the second steel reinforcement cage.
CN201720755366.9U 2017-06-26 2017-06-26 A kind of high slope rockmass structure Expired - Fee Related CN206873470U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720755366.9U CN206873470U (en) 2017-06-26 2017-06-26 A kind of high slope rockmass structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720755366.9U CN206873470U (en) 2017-06-26 2017-06-26 A kind of high slope rockmass structure

Publications (1)

Publication Number Publication Date
CN206873470U true CN206873470U (en) 2018-01-12

Family

ID=61331086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720755366.9U Expired - Fee Related CN206873470U (en) 2017-06-26 2017-06-26 A kind of high slope rockmass structure

Country Status (1)

Country Link
CN (1) CN206873470U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059899A (en) * 2017-06-26 2017-08-18 佛山科学技术学院 A kind of high slope rockmass structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107059899A (en) * 2017-06-26 2017-08-18 佛山科学技术学院 A kind of high slope rockmass structure

Similar Documents

Publication Publication Date Title
CN101761338B (en) Gob-side entry retaining method of a solid filling coal mining half-section one-leg shed
CN107313358B (en) For the beam erecting method and Bridge Erector under big longitudinal slope operating condition
CN104727235B (en) Bridge integral reinforcing device
CN105862878A (en) Supporting system for deep foundation pit
CN206000543U (en) A kind of supporting construction protecting lane for gob side entry retaining
CN106121676A (en) A kind of supporting construction and method for protecting support thereof protecting lane for gob side entry retaining
CN206873470U (en) A kind of high slope rockmass structure
CN202416967U (en) Principal material length adjusting device for tower leg of inclined power transmission tower in coal mine subsidence area
CN203783620U (en) Self-moving type arch-shield-support and anchor-net spraying and dust-preventing all-in-one machine
CN205100527U (en) A cantilever construction platform for surmounting retaining wall
CN102817617B (en) Novel inhaul cable type shield originating backrest substrate system
CN203035204U (en) Large-section tunnel second lining grouping formwork trolley
CN204059901U (en) A kind of high-altitude construction operation platform
CN107059899A (en) A kind of high slope rockmass structure
CN202250119U (en) Totally-enclosed U-shaped shed support frame for roadway supporting
CN202401386U (en) Cable bridge for frame bridge
CN106592632A (en) Underground supporting structure for reverse construction method and construction method
CN107313355B (en) A kind of steel trestle construction method waterborne
CN204370828U (en) Tool-type protective screening
CN203961300U (en) Tool-type passage
CN207245741U (en) Tunnel low-angle lift canopy
CN204780613U (en) Pier shaft operation platform
CN205100242U (en) Three laminar cantilever operation platform systems
CN205653803U (en) High slope combination formula supporting construction
CN203938972U (en) The continuous girder bridge box type girder cast-in-place bracing frame that possesses whole vertical shift function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180112