CN206859402U - Prefabricated constructional column attachment structure - Google Patents

Prefabricated constructional column attachment structure Download PDF

Info

Publication number
CN206859402U
CN206859402U CN201720733181.8U CN201720733181U CN206859402U CN 206859402 U CN206859402 U CN 206859402U CN 201720733181 U CN201720733181 U CN 201720733181U CN 206859402 U CN206859402 U CN 206859402U
Authority
CN
China
Prior art keywords
post
reinforcing bar
constructional column
superstructure
attachment structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720733181.8U
Other languages
Chinese (zh)
Inventor
吴亚峰
杨晓艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720733181.8U priority Critical patent/CN206859402U/en
Application granted granted Critical
Publication of CN206859402U publication Critical patent/CN206859402U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

It the utility model is related to the technical field of construction, disclose a kind of prefabricated constructional column attachment structure, including prefabricated superstructure post and infrastructure post, one end of the superstructure post is provided with projection, raised both sides are extended with the pre- reinforcing bar A being embedded in inside superstructure post, and the other end offers groove corresponding with the reinforcing bar A respectively and groove is through on the two relative side of superstructure post;One end of the infrastructure post is extended with the reinforcing bar B in pre-buried portion in the inner, and reinforcing bar B is corresponding with the reinforcing bar A in the groove, the other end is embedded with bellows corresponding with reinforcing bar B respectively, solves the problems, such as that existing constructional column quality is not readily reachable by backward acceptance criteria, technique, molding effect difference and implementation speed is slow and construction cost is high.

Description

Prefabricated constructional column attachment structure
Technical field
Technical field of building construction is the utility model is related to, in particular it relates to a kind of prefabricated constructional column attachment structure.
Background technology
In the predetermined portion of masonry house wall, by constructional reinforcement, and it is suitable by the construction of placing concrete post after first building a wall Concrete column made of sequence, commonly referred to as concrete-constituted pile, abbreviation constructional column.Constructional column is important in brick-and-concrete buildingses Concrete component.To improve the anti-seismic performance of tier building masonry structure, code requirement appropriate site should be set in the masonry in house Reinforced column is simultaneously connected with collar tie beam, and the common stability for strengthening building, this reinforced column is generally thus referred to as Constructional column.Constructional column is primarily not to undertake vertical load, but for resisting the lateral loads such as shearing, antidetonation.From construction Angle says that constructional column will be with collar tie beam grade beam, foundation beam one-piece casting.There is horizontal connecting lacing wire to connect in Structural Engineering with brick wall body Connect.If constructional column in building, structures centre position, will be connected with distributing reinforcement.
Existing constructional column is primarily present following problem substantially by the way of cast-in-place:
1st, because by the way of cast-in-place, construction cannot be guaranteed, quality is not readily reachable by acceptance criteria;
2nd, technique falls behind, and molding effect is poor, has influence on overall aesthetics;
3rd, need to carry out the welding of reinforcing bar at the scene and close cast-in-place after mould, implement that speed is slow and construction cost is high.
Utility model content
In order to solve the above technical problems, the utility model provides a kind of prefabricated constructional column attachment structure to reach improvement structure The structure of post, the quality standard of raising constructional column and the purpose for reducing construction cost are made, solves existing constructional column quality It is not readily reachable by acceptance criteria, implements the problem of speed is slow and construction cost is high.
In order to realize above-mentioned technique effect, technical scheme provided by the utility model is:Prefabricated constructional column attachment structure, Including prefabricated superstructure post and infrastructure post, one end of the superstructure post is provided with projection, and raised both sides are stretched Go out to have the pre- reinforcing bar A being embedded in inside superstructure post, the other end offers groove corresponding with the reinforcing bar A respectively and groove Through on the two relative side of superstructure post;One end of the infrastructure post is extended with the reinforcing bar B in pre-buried portion in the inner, And reinforcing bar B is corresponding with the reinforcing bar A in the groove, the other end is embedded with bellows corresponding with reinforcing bar B respectively.
Further, the groove is set to rectangular through slot.
Further, the both sides of the superstructure post and infrastructure post are set to horse tooth trough structure.
Further, the projection is set to rectangular preiection.
Further, the infrastructure post is provided with the grouting mouth being connected with bellows.
Compared to prior art, the beneficial effects of the utility model are:
1. the superstructure post of the application and infrastructure post be carried out in advance in factory it is prefabricated, relative to cast-in-place Constructional column has better quality, enables the building acceptance criteria for reaching country;
2. the pre-buried bellows of the infrastructure post of the application can starch the connection of anchor between polycrystalline substance plate by reinforcing bar Mode, and superstructure post is connected between roof beam and infrastructure post by the way of reinforcement welding respectively, whole construction Process can use lifting mode to realize, its difficulty of construction is small, saves manual labor, has relative to prior art and implements faster Speed;
3. after superstructure post installation, the projection and groove at its both ends are subjected to pass mould respectively and poured, is made whole Constructional column has overall outward appearance degree, and realizes good stability and intensity.
Brief description of the drawings
Fig. 1 is the mounting structure schematic diagram of prefabricated constructional column attachment structure provided by the utility model;
Fig. 2 is the front view of prefabricated constructional column attachment structure provided by the utility model;
Fig. 3 is Fig. 2 partial enlarged drawing.
Embodiment
The utility model is further described in detail with reference to specific embodiment, following word is intended to indicate that The utility model, and unrestricted the scope of protection of the utility model.
As shown in Figure 1, Figure 2 and Figure 3, the utility model can be implemented as follows, a kind of prefabricated constructional column connection knot Structure, including prefabricated superstructure post 1 and infrastructure post 2, one end of the superstructure post 1 are provided with projection 3, that is, form class The structure of convex shape is similar to, the both sides of projection 3 are extended with the pre- reinforcing bar A4 being embedded in inside superstructure post 1, and reinforcing bar A4 is located at The both sides of projection 3, are easy to reinforcing bar A4 welding, the other end offers groove 6 corresponding with the reinforcing bar A4 respectively and groove 6 Through on the two relative side of superstructure post 1, the reinforcing bar A4 other end is located at the inside of groove 6, is easy to superstructure post 1 After being spliced with infrastructure post 2, reinforcing bar A4 being welded to connect between the two with reinforcing bar B5;The one of the infrastructure post 2 End is extended with the reinforcing bar B5 in pre-buried portion in the inner, and reinforcing bar B5 is corresponding with the reinforcing bar A4 in the groove 6, and the other end is pre- Bellows 7 corresponding with reinforcing bar B5 respectively is embedded with, reinforcing bar B5 is located in described bellows 7.Wherein, the superstructure post 1 and the both sides of infrastructure post 2 be set to horse tooth trough structure, this structure is easy to superstructure post 1 and infrastructure post 2 to splice Afterwards, can be bonded between wall.
As preferable, above-mentioned groove 6 is set to rectangular through slot 6, described raised 3 are set to rectangular preiection 3, rectangular preiection 3 end face is in contact with the roof beam 9 of the top of superstructure post 1.
The infrastructure post 2 is provided with the grouting mouth being connected with bellows 7, and grouting mouth is easy into bellows 7 Portion carries out joints cement slurry, and as preferable, grouting mouth, which may be provided with, is provided with two, and one of them is used for into bellows 7 Poured, another is used to observe and test whether pour filling by bellows 7.
Any one skilled in the art can readily occur in change in the technical scope that the utility model discloses Change or replace, should all cover within the scope of protection of the utility model.Therefore, the scope of protection of the utility model should be with right It is required that described protection domain is defined.

Claims (5)

1. a kind of prefabricated constructional column attachment structure, it is characterised in that described including prefabricated superstructure post and infrastructure post One end of superstructure post is provided with projection, and raised both sides are extended with the pre- reinforcing bar A being embedded in inside superstructure post, the other end Offer groove corresponding with the reinforcing bar A respectively and groove is through on the two relative side of superstructure post;Under described One end of cage structure post is extended with the reinforcing bar B in pre-buried portion in the inner, and reinforcing bar B is corresponding with the reinforcing bar A in the groove, The other end is embedded with bellows corresponding with reinforcing bar B respectively.
2. prefabricated constructional column attachment structure according to claim 1, it is characterised in that the groove is set to rectangular through slot.
3. prefabricated constructional column attachment structure according to claim 1, it is characterised in that the superstructure post and bottom structure The both sides for making post are set to horse tooth trough structure.
4. prefabricated constructional column attachment structure according to claim 1, it is characterised in that the projection is set to rectangular preiection.
5. prefabricated constructional column attachment structure according to claim 1, it is characterised in that the infrastructure post be provided with The grouting mouth that bellows is connected.
CN201720733181.8U 2017-06-22 2017-06-22 Prefabricated constructional column attachment structure Expired - Fee Related CN206859402U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720733181.8U CN206859402U (en) 2017-06-22 2017-06-22 Prefabricated constructional column attachment structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720733181.8U CN206859402U (en) 2017-06-22 2017-06-22 Prefabricated constructional column attachment structure

Publications (1)

Publication Number Publication Date
CN206859402U true CN206859402U (en) 2018-01-09

Family

ID=60827028

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720733181.8U Expired - Fee Related CN206859402U (en) 2017-06-22 2017-06-22 Prefabricated constructional column attachment structure

Country Status (1)

Country Link
CN (1) CN206859402U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060084A (en) * 2017-06-22 2017-08-18 吴亚峰 Prefabricated constructional column attachment structure and attaching method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060084A (en) * 2017-06-22 2017-08-18 吴亚峰 Prefabricated constructional column attachment structure and attaching method thereof

Similar Documents

Publication Publication Date Title
CN107100290A (en) A kind of prefabricated shear wall and overlapping plate node
CN207194006U (en) A kind of prefabricated concrete retaining wall
CN107060084A (en) Prefabricated constructional column attachment structure and attaching method thereof
CN107044177A (en) A kind of assembly concrete shear wall fractionation, assembled attachment structure and connection method
CN109356173A (en) A kind of pin-connected panel anchor bolt frame girder construction and its construction method
CN104895092A (en) Method for using inner-support temporary latticed column as permanent structure column
CN106968381A (en) With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection
CN209227831U (en) Wall and floor connection structure and assembled arthitecutral structure system
CN106894587A (en) Precast stair connection method
CN107090908B (en) A kind of vertical prefabricated components joint connecting method
CN106245817A (en) A kind of fabricated shear wall vertical connection structure and installation method thereof
CN206174195U (en) Assembled concrete shear force wall split, assemble connection structure
CN208792505U (en) A kind of precast wall body and assembling structure of assembled architecture
CN109386050A (en) A kind of multi-layer combined type house structure
CN110409900A (en) Hybrid connection precast prestressed concrete circle warehouse structure
CN109914644A (en) A kind of assembled heat insulation masonry wall and preparation method thereof
CN108708452A (en) The U-shaped integral prefabricated window member that floats, assembled float window joint structure and its construction method
CN208632986U (en) A kind of rectangular channel structure of precast assembly
CN206859402U (en) Prefabricated constructional column attachment structure
CN208650333U (en) A kind of compound Coupled Shear Wall structure of assembled integral steel reinforced concrete frame support
CN104141358A (en) Mortar-free self-embedded masonry structure system and building comprising system
US9523194B2 (en) Reinforced blockwork construction method
CN208996310U (en) A kind of prefabricated constructional column connection structure
CN105971196A (en) Method for constructing masonry structure embedded square concrete filled steel tube ring beam-constructional column
CN208039023U (en) A kind of assembled bridge pier structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180109