CN206827974U - A kind of tower crane overhaul protective device - Google Patents

A kind of tower crane overhaul protective device Download PDF

Info

Publication number
CN206827974U
CN206827974U CN201720545434.9U CN201720545434U CN206827974U CN 206827974 U CN206827974 U CN 206827974U CN 201720545434 U CN201720545434 U CN 201720545434U CN 206827974 U CN206827974 U CN 206827974U
Authority
CN
China
Prior art keywords
steel pile
pile casting
tower crane
protective device
overhaul protective
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720545434.9U
Other languages
Chinese (zh)
Inventor
程方成
刁操金
庞晓瑜
徐进文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Fifth Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN201720545434.9U priority Critical patent/CN206827974U/en
Application granted granted Critical
Publication of CN206827974U publication Critical patent/CN206827974U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of tower crane overhaul protective device, it includes:Steel pile casting, steel pile casting are covered on outside tower crane, and the inside of steel pile casting is provided with some crosses, and spaced set between cross, the periphery of steel pile casting is connected with pier shaft, and steel pile casting sealed bottom is connected on cushion cap;The length of steel pile casting is not less than highest water level.Tower crane overhaul protective device of the present utility model is simple in construction, reasonable in design, easy to process, efficiency high, reduces artificial and equipment input.

Description

A kind of tower crane overhaul protective device
Technical field
It the utility model is related to building machinery field, and in particular to a kind of easy tower crane overhaul protective device.
Background technology
As across rivers bridges are more and more, the Engineering Projects of tower crane coordinative construction is also more and more in water.Tower crane in water Installing citation form is:On subaqueous work platform to waterline, the pre-buried tower crane on workbench, then tower crane is installed.
The installation form of tower crane is more complicated in water at present.In river is flowed, tower crane it is basic unstable, rushed by river Rinse, the tower crane platform that water hammering effects are larger and current can not recycle substantially.
The content of the invention
The purpose of this utility model is to overcome problem above existing for prior art, there is provided a kind of simple tower crane maintenance is anti- Protection unit, the utility model is easy to process, and installation is quick, wide adaptability, and efficiency of construction is high, can meet construction requirement.
To realize above-mentioned technical purpose and the technique effect, the utility model is achieved through the following technical solutions:
A kind of tower crane overhaul protective device, it includes:Steel pile casting, the steel pile casting are covered on outside tower crane, the steel pile casting Inside be provided with some crosses, spaced set between the cross, the periphery of the steel pile casting is connected with pier shaft, described Steel pile casting sealed bottom is connected on cushion cap;
The length of the steel pile casting is not less than highest water level.
Further comprise, the steel pile casting includes some standard steel pile casting sections, and the standard steel pile casting section is welded to form institute Steel pile casting is stated, the length of the steel pile casting is higher 1-2m than peak level.
Further comprise, the steel pile casting bottom is connected on the cushion cap by sealing ring.
Further comprise, concrete lift is provided with outside the sealing ring.
Further comprise, the periphery of the steel pile casting and pier shaft are by steel structure connection.
Further comprise there is 20~30cm spacing between the steel pile casting and the tower crane.
Further comprise there is 20~30cm spacing between the cross and the tower crane.
The beneficial effects of the utility model are:
1st, tower crane overhaul protective device of the present utility model is simple in construction, reasonable in design, easy to process, efficiency high, reduces Artificial and equipment input.
2nd, tower crane overhaul protective device of the present utility model is simple to operate, wide adaptability, repeats and utilizes, and material can also return Receive and utilize.
3rd, tower crane overhaul protective device base fixed of the present utility model, the potential safety hazard during tower crane use is reduced.
Described above is only the general introduction of technical solutions of the utility model, in order to better understand skill of the present utility model Art means, and being practiced according to the content of specification, with preferred embodiment of the present utility model and coordinate accompanying drawing detailed below Describe in detail bright as after.Specific embodiment of the present utility model is shown in detail by following examples and its accompanying drawing.
Brief description of the drawings
In order to illustrate more clearly of the technical scheme in the utility model embodiment technology, embodiment technology will be retouched below The required accompanying drawing used is briefly described in stating, it should be apparent that, drawings in the following description are only the utility model Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also basis These accompanying drawings obtain other accompanying drawings.
Fig. 1 is structural solid figure of the present utility model;
Fig. 2 is the utility model cross-sectional view;
Wherein, 1- steel pile castings, 2- crosses, 3- steel constructions, 4- sealing rings, 5- concrete, 6- tower cranes, 7- pier shafts.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Embodiment
A kind of tower crane overhaul protective device is disclosed shown in reference picture 1-2, in the present embodiment, it includes:Steel pile casting 1, on State steel pile casting 1 to be made up of some standard steel pile casting sections, the standard steel pile casting section is welded to form the steel pile casting 1, above-mentioned steel The length of casing 1 is determined by peak level, typically not less than highest water level.
In the present embodiment, the length of steel pile casting 1 is higher 1-2m than peak level.
The steel pile casting 1 is covered on outside tower crane 6, and the inside of the steel pile casting 1 is provided with some crosses 2, the cross 2 Between spaced set, be processed into cross 2 using I-steel, installation be set in the steel pile casting 1, and the spacing of cross 2 is according to water It is deep to determine.
The periphery of the steel pile casting 1 is connected with pier shaft 7, and the periphery of steel pile casting 1 and pier shaft 7 are effective by steel construction 3 Connection, and be connected firmly.
The sealed bottom of steel pile casting 1 is connected on cushion cap;In the present embodiment, the bottom of steel pile casting 1 passes through sealing Circle 4 is connected on the cushion cap.
For further firm and sealing, the outside of sealing ring 4 is provided with the LIFT of concrete 5, the bottom periphery of steel pile casting 1 The thickness of concrete 5 is unsuitable blocked up, to facilitate casing to remove.
Further, there is 20~30cm spacing between the steel pile casting 1 and the tower crane 6.The cross and the tower There is 20~30cm spacing between hanging.20~30cm spacing is reserved between steel pile casting 1, cross 2 and tower crane 6, prevents steel pile casting 1 from producing Raw displacement, influence the safe handling of tower crane 6.
The application method of the present embodiment:
1st, the pre-buried tower crane on underwater support table, install more than standard knot to peak level;
2nd, steel pile casting is transferred, and tower crane is covered in casing, one layer of sealing ring of place laying of steel pile casting and raft contact;
3rd, cross is installed every a segment distance in steel pile casting;
4th, steel pile casting bottom periphery pours a layer concrete, and sealing ring is used cooperatively;
5th, steel pile casting and pier shaft are effectively connected by steel construction.
Tower crane overhaul protective device in the present embodiment is simple in construction, reasonable in design, easy to process, efficiency high, reduces Artificial and equipment input.Device is simple to operate, wide adaptability, repeats and utilizes, material also recoverable.Device basic is steady It is fixed, reduce the potential safety hazard during tower crane use.
The foregoing description of the disclosed embodiments, professional and technical personnel in the field are enable to realize or new using this practicality Type.A variety of modifications to these embodiments will be apparent for those skilled in the art, determine herein The General Principle of justice can be realized in other embodiments in the case where not departing from spirit or scope of the present utility model.Cause This, the utility model is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein The most wide scope consistent with features of novelty.

Claims (7)

1. a kind of tower crane overhaul protective device, it is characterised in that it includes:Steel pile casting, the steel pile casting are covered on outside tower crane, institute The inside for stating steel pile casting is provided with some crosses, spaced set, the periphery of the steel pile casting and pier shaft between the cross Connection, the steel pile casting sealed bottom are connected on cushion cap;
The length of the steel pile casting is not less than highest water level.
2. tower crane overhaul protective device according to claim 1, it is characterised in that the steel pile casting includes some standard steels Casing section, the standard steel pile casting section are welded to form the steel pile casting, and the length of the steel pile casting is higher 1-2m than peak level.
3. tower crane overhaul protective device according to claim 1, it is characterised in that the steel pile casting bottom passes through sealing ring It is connected on the cushion cap.
4. tower crane overhaul protective device according to claim 3, it is characterised in that be provided with concrete outside the sealing ring LIFT.
5. tower crane overhaul protective device according to claim 1, it is characterised in that the periphery of the steel pile casting and pier shaft by Steel structure connection.
6. tower crane overhaul protective device according to claim 1, it is characterised in that between the steel pile casting and the tower crane There is 20~30cm spacing.
7. tower crane overhaul protective device according to claim 1, it is characterised in that between the cross and the tower crane There is 20~30cm spacing.
CN201720545434.9U 2017-05-17 2017-05-17 A kind of tower crane overhaul protective device Active CN206827974U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720545434.9U CN206827974U (en) 2017-05-17 2017-05-17 A kind of tower crane overhaul protective device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720545434.9U CN206827974U (en) 2017-05-17 2017-05-17 A kind of tower crane overhaul protective device

Publications (1)

Publication Number Publication Date
CN206827974U true CN206827974U (en) 2018-01-02

Family

ID=60771945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720545434.9U Active CN206827974U (en) 2017-05-17 2017-05-17 A kind of tower crane overhaul protective device

Country Status (1)

Country Link
CN (1) CN206827974U (en)

Similar Documents

Publication Publication Date Title
CN205152976U (en) Marine precast concrete cushion cap wind turbine foundation
CN103510529A (en) Steel hanging box system for underwater high-rise pile cap construction and construction technology thereof
CN102644290A (en) Steel cofferdam construction method suitable for deep silt-layer bridge construction in shallow sea area
CN106638530A (en) Process for lifting offshore booster station jacket in shallow water
CN201746845U (en) Pile foundation type foundation structure applicable to ocean engineering
CN204475266U (en) Automatic disconnecting type water-permeable frame group polishing apparatus
CN210315612U (en) Pull-up type quick bottom sealing structure for through hole of hanging box and pile
CN109372006B (en) Scour prevention protection structure for offshore wind turbine foundation and construction method thereof
CN204570712U (en) Suspension steel cofferdam hermetic seal structure
CN206827974U (en) A kind of tower crane overhaul protective device
CN103158839A (en) Wave-proofing float bowl combination device
CN209260667U (en) Side slope anti-scouring system
CN206736920U (en) A kind of internal-expansion type pipe drawing device
CN103015459A (en) Construction method for underwater baring platform steel cover box on storm surge river mouth
CN202626963U (en) Water-borne conversion platform for installation and construction of prefabricated parts in off-sea intertidal zone
CN211057824U (en) Gap plugging structure between steel crane bottom plate and steel casing
CN105129597A (en) Lifting beam special for floating container bulwark
CN204021215U (en) A kind of job platform that is applicable to the excessive big vast tower of Tailings Dam
CN108149704A (en) A kind of prefabricated assembled High-Rise Pile Cap Foundation structure of offshore wind turbine and installation method
CN204898696U (en) Telescopic steel cofferdam
CN211690397U (en) Anti-floating single-wall steel hanging box
CN203238655U (en) Offshore wind power single pile foundation-based tidal current energy power generation foundation structure
CN206784354U (en) A kind of U-shaped casing seal installation
CN217896583U (en) Grouting plugging system for auxiliary components of high-rise pile cap
CN203080496U (en) Portal infrastructure capable of utilizing ocean wind energy and tidal current energy simultaneously to generate power

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant