CN206753041U - Drainage pipeline antiseep plugging device - Google Patents
Drainage pipeline antiseep plugging device Download PDFInfo
- Publication number
- CN206753041U CN206753041U CN201720490312.4U CN201720490312U CN206753041U CN 206753041 U CN206753041 U CN 206753041U CN 201720490312 U CN201720490312 U CN 201720490312U CN 206753041 U CN206753041 U CN 206753041U
- Authority
- CN
- China
- Prior art keywords
- ring
- semi
- plugging device
- arc
- drainage pipeline
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Sink And Installation For Waste Water (AREA)
Abstract
The utility model discloses a kind of drainage pipeline antiseep plugging device, its drip irrigation device is to include the semi-ring of structure identical first and the second semi-ring, first semi-ring and the second semi-ring include arc and are fixedly connected on the bearing plate of arc periphery, and first semi-ring and the second semi-ring connect the domain to form the middle through hole for carrying and being passed through for pipeline by fixture.The utility model solves the problems, such as not meeting energy-saving and emission-reduction in existing toilet drainage root pipe waterproofing and leakage-stopping measure.
Description
Technical field
The toilet warterproof leak stopping such as residential building and office building field is the utility model is related to, in particular, it is related to one
Kind drainage pipeline antiseep plugging device.
Background technology
Waterproofing and leakage-stopping is a very crucial link in construction.According to investigations, Beijing's cellular engineering 6 is lived
Residence building is delivered for use, and leakage problems appearance is more universal, has 40 families quality complaint occur and accounts for 100%, leakage in toilets accounts for respectively
Class complains problem to account for 75.5%, wherein, toilet Guan Gen peripheries seepage problems is complained and accounts for leakage in toilets 66.6%, from than
For example it can be seen that leakage in toilets the rate of complaints remains high, seepage is even more to occupy very high ratio at toilet pipe root, can
See in work progress and the closure processing at pipe root is particularly important, be worth research.
In order to reduce the requirement done over again with green construction:Drainage conduit of toilet root generally use iron wire coordinates three-ply board
Or multi-layer sheet hangs mould, but three-ply board and multi-layer sheet are all that use can seldom reuse afterwards, belong to disposable, cause
The material such as three-ply board or multi-layer sheet largely wastes, and iron wire easily gets rusty, and place of getting rusty causes floor leakage water, easily does over again,
So as to have influence on the durability of waterproof layer, requirement of the green construction on saving and saving material is not met yet, according to《Architectural engineering is green
Color construction evaluation criterion》(GB/T50640-2010)With《Architectural engineering green construction specification》(50905-2014)Regulation:
On the premise of green construction, energy-saving and emission-reduction, it is necessary to save material, reduce three-ply board or multiple-plate usage amount, it is ensured that draining
Standpipe plugging material is recycled for multiple times.
Utility model content
For insufficient existing for existing toilet root pipe blocking technology, the purpose of this utility model is to provide a kind of draining
Pipeline antiseep plugging device, it has reached the effect of energy-saving and emission-reduction.
To achieve the above object, the utility model provides following technical scheme:A kind of drainage pipeline antiseep closure dress
Put, including the semi-ring of structure identical first and the second semi-ring, first semi-ring and the second semi-ring include arc and fixation
Be connected to the bearing plate of arc periphery, first semi-ring and the second semi-ring connected by fixture to be formed it is middle with supplying pipeline
The domain of the through hole passed through.
By using above-mentioned technical proposal, the first semi-ring and the second semi-ring are connected to form middle carry for pipe by fixture
After the domain for the through hole that road passes through, it is installed on floor top surface and is set in the outer ring of pipeline.Now, then can be to root pipe
Plugging material is filled in the gap of surrounding.Wherein, the arc of the first semi-ring and the second semi-ring is embraced to form pipeline and held tightly, from
And the fixation of the drainage pipeline antiseep plugging device is realized, the bearing plate of the first semi-ring and the second semi-ring is played to plugging material
Undertaking effect.Treat plugging material solidification i.e. dismountable drainage pipeline antiseep plugging device afterwards, the waterproof so formed
Leak stopping structure appearance looks elegant, and drainage pipeline antiseep plugging device can reuse, and reach the effect of energy-saving and emission-reduction.
Also, the waterproofing and leakage-stopping structure so formed, because no iron wire is deposited in the structure, got rusty the leakage brought so avoiding iron wire
Water problems, further increase anti-seepage effect.
Preferably, the fixture include one end be connected on the first semi-ring tie down screw, be threadedly connected to the locking
Locking nut on screw rod and the fixture block being fixedly installed on the second semi-ring, it is provided with for the tie down screw card on the fixture block
If neck.
By using above-mentioned technical proposal, the first semi-ring and the second semi-ring are docked, the free end of tie down screw passes through card
Groove, the free end of tie down screw is connected to locking nut afterwards, can the first semi-ring and the second half by tightening nut
Ring is constantly tightened up.
Preferably, described tie down screw one end is rotationally connected with first semi-ring.
By using above-mentioned technical proposal so that tie down screw can rotate relative to the first semi-ring, and its flexibility ratio is bigger,
Using more convenient.
Preferably, the one side that first semi-ring and the second semi-ring are bonded to each other is fixedly installed sealing strip.
By using above-mentioned technical proposal, the sealing after the first semi-ring and the fitting of the second semi-ring is improved, reduces and is filling
Material leakage during plugging material.
Preferably, it is fixedly installed supple buffer layer on the inside of the arc.
By using above-mentioned technical proposal, coordinate in the arc of the first semi-ring and the second semi-ring and encircle in the periphery of pipeline
When, supple buffer layer can make the first semi-ring and the second half encircle tighter, and be not easy to rack pipeline.
Preferably, it is connected with reinforcement between the outside of the arc and the bearing plate.
By using above-mentioned technical proposal, arc and bearing plate can not only be played a part of to reinforce connection, moreover it is possible to
Enough reduce arc root property to deform upon for bearing plate, so as to reduce the deformation at the top of arc so that arc and pipe
The stickiness in road is more preferable.
In summary, the utility model has the advantages that compared to prior art:The utility model not only has
The effect of energy-saving and emission-reduction, also there is the progress for improving waterproofing and leakage-stopping effect, and its cost is low, it is suitable for large-scale promotion, have
Very high economic benefit.
Brief description of the drawings
Fig. 1 is structural representation when the first semi-ring of embodiment and the second semi-ring separate;
Structural representation when Fig. 2 is the first semi-ring and the second semi-ring fastening of embodiment;
Fig. 3 is the partial structural diagram that floor opens up hole to be provided;
Fig. 4 is structural representation of the pipeline through the hole to be provided of floor;
Fig. 5 is the structural representation that antiseep plugging device is installed on floor top surface.
In figure:1st, the first semi-ring;11st, arc;111st, spongy layer;12nd, bearing plate;121st, rubber strip;13rd, surrounding edge;14、
Reinforcement;2nd, the second semi-ring;3rd, floor;31st, hole to be provided;4th, pipeline;5th, fixture;51st, fixture block;511st, neck;52nd, bearing pin;53、
Tie down screw;54th, locking nut.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
Embodiment:A kind of drainage pipeline antiseep plugging device, referring to Fig. 1, including the He of the first semi-ring 1 being made of plastics
Second semi-ring 2, the first semi-ring 1 is identical with the structure of the second semi-ring 2, therefore cost is lower in process of production.The present embodiment
In, illustrated by taking the first semi-ring 1 as an example, the first semi-ring 1 includes arc 11 and is fixedly connected on holding for the periphery of arc 11
Fishplate bar 12, bearing plate 12 are set in fan-shaped, and arc 11 is fixedly connected on the inner side edge of bearing plate 12, the outer side edges of bearing plate 12
Surrounding edge 13 is provided with, some reinforcements 14 are provided between surrounding edge 13 and arc 11.It is bonded in the inner side of arc 11
Spongy layer 111 is adhesive with, is bonded in the inner side edge of arc 11 and bearing plate 12 and is adhesive with rubber strip 121.
Referring to Fig. 2, the first semi-ring 1 and the second semi-ring 2 form middle carry by the connection of fixture 5 and led to for what pipeline 4 passed through
The domain in hole.
Fig. 1 is reviewed, fixture 5 is further described in detail, fixture 5 includes being fixedly connected on the first semi-ring 1, the second half
The fixture block 51 at the both ends of arc 11 of ring 2, neck 511 is provided with fixture block 51, in the first semi-ring 1 or the second semi-ring 2 wherein
Tie down screw 53 is rotatably connected to by bearing pin 52 on one fixture block 51, locking nut 54 is threaded with tie down screw 53.
When the first semi-ring 1 and the second semi-ring 2 are connected, by the slice bar side phase of the first semi-ring 1 and the second semi-ring 2
Mutually fitting so that two arcs 11 form a domain, then go to two tie down screws 53, make tie down screw 53 be fastened on card
In groove 511, locking nut 54 is then gone to so that the end face of locking nut 54 is supported to the end face of fixture block 51.
How to be installed next, illustrating using the antiseep plugging device:As shown in figure 3, it is the top of floor 3
Face structural representation, hole to be provided 31 is provided through on floor 3.Referring to Fig. 4, pipeline 4 is fed through the hole to be provided 31, reserved
Gap is formed between hole 31 and pipeline 4.Next mainly seek to repair the gap i.e. antiseep closure processing.Referring to
Fig. 5, the first semi-ring 1 and the second semi-ring 2 are docked from the both sides of pipeline 4 respectively, the first semi-ring 1 and the second semi-ring 2 is formed one
The individual domain, then fixed with fixture 5.
In order to ensure the tightness of antiseep plugging device closure, percolating water is prevented, the filling closure coagulation into gap
When native, it can divide 2 times and pour, such as 3 thick 120mm of floor, can first pour 70mm thickness concrete, will after after concrete initial set and drying
Leak stopping spirit waterproof material is filled into around pipe root, and after drying, finally casting concrete is extremely concordant with the face of floor 3 again.By checking,
Antiseep positive effect, and cost is relatively low, it is economical and practical.Construction speed is accelerated, while reduces and reprocesses cost, energy-conservation subtracts
Row, meets green construction.
A specific experiment is named to illustrate:By carrying out closure experiment, final inspection to 1980,220 family pipe root
When, draw following result:1st, 1980 Guan Genzhong only have 36 pipe roots seepage occur, and percolation ratio only has 1.8%, works well.
2nd, the duration shortens:This engineering shares 8 monomer buildings, and 220 family, each household toilet, kitchen etc. need to block pipe root altogether
It it is about 9 including drainage pipeline 4, pipe washer 4, sewage conduct 4, each household, it is 1980 to add up to closure quantity.Propped up using original
Top hangs modulus method and completes 15 pipe root closure work for each person every day, arranges 3 people to carry out closure work, and closure quantity amounts to 1980,
It is 1980/45=44 day, i.e., estimated to complete the duration as 44 days;Now it is operated using the antiseep plugging device, is completed for each person every day
33 pipe roots block work, arrange 2 people to carry out closure work, 1980/66=30 day, it was 30 days to complete the duration, saves the duration:44
My god -30 days=14 days.
3rd, economic benefit:The antiseep plugging device has prevented repair for 2nd time and repairing after coming into operation, and greatly reduces
Unnecessary artificial and material input, save human and material resources, the floor flatness that root pipe portion position is greatly improved and sight
Sense, meets the requirement of green construction.
4th, social benefit:This antiseep plugging device effectively solves leakage problem at toilet pipe root, so as to
Solves leakage in toilets well.
Described above is only preferred embodiment of the present utility model, and the scope of protection of the utility model is not limited merely to
Above-described embodiment, all technical schemes belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to
Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and
Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.
Claims (6)
- A kind of 1. drainage pipeline antiseep plugging device, it is characterised in that:Including the semi-ring of structure identical first (1) and the second half Ring (2), first semi-ring (1) and the second semi-ring (2) include arc (11) and are fixedly connected on arc (11) periphery Bearing plate (12), first semi-ring (1) and the second semi-ring (2) are connected by fixture (5) formed among with supplying pipeline (4) The domain of the through hole passed through.
- 2. drainage pipeline antiseep plugging device according to claim 1, it is characterised in that:The fixture (5) includes one Hold the tie down screw (53) being connected on the first semi-ring (1), the locking nut being threadedly connected on the tie down screw (53) (54) and the fixture block (51) that is fixedly installed on the second semi-ring (2), it is provided with the fixture block (51) for the tie down screw (53) neck (511) set is blocked.
- 3. drainage pipeline antiseep plugging device according to claim 2, it is characterised in that:The tie down screw (53) one End is rotationally connected with first semi-ring (1).
- 4. drainage pipeline antiseep plugging device according to claim 1, it is characterised in that:First semi-ring (1) and The one side that second semi-ring (2) is bonded to each other is fixedly installed sealing strip.
- 5. drainage pipeline antiseep plugging device according to claim 1, it is characterised in that:The arc (11) it is interior Side is fixedly installed supple buffer layer.
- 6. drainage pipeline antiseep plugging device according to claim 1, it is characterised in that:Outside the arc (11) Reinforcement (14) is connected between side and the bearing plate (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720490312.4U CN206753041U (en) | 2017-05-04 | 2017-05-04 | Drainage pipeline antiseep plugging device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720490312.4U CN206753041U (en) | 2017-05-04 | 2017-05-04 | Drainage pipeline antiseep plugging device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206753041U true CN206753041U (en) | 2017-12-15 |
Family
ID=60617382
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720490312.4U Active CN206753041U (en) | 2017-05-04 | 2017-05-04 | Drainage pipeline antiseep plugging device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206753041U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111677273A (en) * | 2020-05-22 | 2020-09-18 | 浙江新中源建设有限公司 | Anti-seepage structure for reserved hole in kitchen and toilet and construction method |
CN114855854A (en) * | 2022-05-25 | 2022-08-05 | 广东省建筑工程机械施工有限公司 | Construction protection structure and construction method for double open caisson connecting wall protection wall |
-
2017
- 2017-05-04 CN CN201720490312.4U patent/CN206753041U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111677273A (en) * | 2020-05-22 | 2020-09-18 | 浙江新中源建设有限公司 | Anti-seepage structure for reserved hole in kitchen and toilet and construction method |
CN114855854A (en) * | 2022-05-25 | 2022-08-05 | 广东省建筑工程机械施工有限公司 | Construction protection structure and construction method for double open caisson connecting wall protection wall |
CN114855854B (en) * | 2022-05-25 | 2024-02-09 | 广东省建筑工程机械施工有限公司 | Double open caisson connecting wall protection wall construction protection structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206753041U (en) | Drainage pipeline antiseep plugging device | |
CN205557856U (en) | Leakage structure is prevented at building expansion joint | |
CN103437556A (en) | Waterproof and heat-preservation construction method for building water supply and drainage and heating engineering | |
CN210163948U (en) | Construction system for pouring post-cast strip of basement roof | |
CN203977368U (en) | Pressure-bearing reinforced concrete structure leakage repair device | |
CN206607873U (en) | A kind of pre-buried structure of anti-dropout | |
CN206521812U (en) | A kind of anti-leakage structure of toilet | |
CN215635443U (en) | Water-proof structure for hanging hole of drain pipe and floor slab | |
CN203307900U (en) | Adjusting type floor drain | |
CN108385981A (en) | A kind of outdoor basement roof post-cast strip anti-seepage construction method | |
CN209066926U (en) | A kind of simple roof leakage controlling device | |
CN202148539U (en) | Composite waterproof structure using underground engineering waterproof leaking stoppage treatment and construction method | |
CN219604931U (en) | Bathroom water leakage repair structure | |
CN208618507U (en) | A kind of anticlogging pipe fitting of soil stack | |
CN207749590U (en) | A kind of toilet ponding exclusion structure | |
CN208395671U (en) | Intercept water groove arrangement for a kind of bridge drain hole | |
CN207672628U (en) | Cast-in-place concrete Box-shaped Drainage Culvert docks deformation joint processing unit with existing box culvert | |
CN206616786U (en) | The ventilation structure for having completed roof is poured suitable for structure | |
CN206503249U (en) | A kind of expansion joint structure of reinforced concrete water pond structure | |
CN204983097U (en) | Structure of leak protection water | |
CN215166653U (en) | Leakage-proof structure for root of pipeline | |
CN206681114U (en) | A kind of water supply and sewage work build leakage preventing structure | |
CN205153160U (en) | Bathroom waterproof construction and water catch bowl | |
CN206521838U (en) | A kind of secondary anti-leakage structure in toilet | |
CN201148549Y (en) | Drainage arrangement of washing machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |