CN206740007U - A kind of blast working blasthole position indicator - Google Patents
A kind of blast working blasthole position indicator Download PDFInfo
- Publication number
- CN206740007U CN206740007U CN201720473294.9U CN201720473294U CN206740007U CN 206740007 U CN206740007 U CN 206740007U CN 201720473294 U CN201720473294 U CN 201720473294U CN 206740007 U CN206740007 U CN 206740007U
- Authority
- CN
- China
- Prior art keywords
- protractor
- vertical
- horizontal
- blasthole
- pointer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Length-Measuring Instruments Using Mechanical Means (AREA)
Abstract
The utility model discloses a kind of blast working blasthole position indicator, including support, horizontal protractor, vertical protractor and lining rope, support has vertical main shaft, and horizontal protractor fixed disk is fixed with main shaft;Horizontal protractor is arranged on horizontal protractor fixed disk, and vertical protractor is connected through the hinge on main shaft;The pointer of horizontal protractor links together with vertical protractor, and the pointer of horizontal protractor and vertical protractor remain the fixation of relative position;The pointer of vertical protractor is connected with lining rope.The reading and range reading of two protractors are read, three reading cans are accurately positioned the position of this blasthole.The blasthole position indicator is simple in construction, and cost is cheap, and measuring accuracy, can extensive use in vertical core blast working up to 1~5cm.
Description
Technical field
The utility model belongs to Technology of Blasting field, and in particular to a kind of blast working blasthole position indicator.
Background technology
Blasting engineering is the huge energy using explosive charge abrupt release, destroys explosive surrounding medium or makes its deformation,
So as to reach the technology of certain engineering purpose.In mining engineering, Drilling borehole is referred to as rock drilling on ore or rock, by explosive
Load borehole, ore or rock are got off from avalanche on their parent, referred to as explosion.Mine blasting engineering is exactly to utilize explosive
Blast carrys out the technology of fractured rock and ore.
In current blast working, although various blasting conditions, blasting technique relative maturity, blind big gun occurs
Probability is also present.The harm of blind big gun is it will be apparent that such as due to the shortcoming of Technology of Blasting, explosion design unreasonable
And after causing blind big gun, if to its timely discovery, solution, also just without what risk, if but shot rock or slungshot will be quick-fried
Broken face covering, or explosion step are subjected to displacement, and cause blind big gun undiscovered, and power shovel will be triggered to fill or round cloth hole is mechanical afterwards
Major accident occurs during jewel hole, jeopardizes workmen's life security, its consequence brought is catastrophic.
According to present scientific development condition, more ready-made location instrument has various GPS location instruments, still
One is cost is high, second, its position error is difficult to control within 5CM, it is most important that GPS location instrument passes through satellite
The current emissions of position can directly threaten the security of the explosive of electric cap etc, according to《Blast working safety management is advised
It is fixed》, this electronic product is not allow to bring blast working into.So lack at present a kind of precision is higher, cost is cheap,
Location equipment safe to use.
Utility model content
The purpose of this utility model is to provide a kind of blast working blasthole position indicator, solve existing location instrument precision compared with
It is low, cost is cheap, uses unsafe problem.
The utility model is the technical scheme adopted is that a kind of blast working blasthole position indicator, including support, horizontal angulation
Device, vertical protractor and lining rope, support have vertical main shaft, and horizontal protractor fixed disk is fixed with main shaft;Horizontal angulation
Device is arranged on horizontal protractor fixed disk, and vertical protractor is connected through the hinge on main shaft;The finger of horizontal protractor
Pin links together with vertical protractor, and the pointer of horizontal protractor and vertical protractor remain consolidating for relative position
It is fixed;The pointer of vertical protractor is connected with lining rope.
The principle of the blast working blasthole position indicator is to place a horizontal protractor in fixed measuring point horizontal direction,
Towards big gun area, a vertical protractor that can be swung is placed in vertical direction, then measure between fixed measuring point and blasthole
Distance, read the reading and range reading of two protractors, three reading cans are accurately positioned the position of this blasthole.
The characteristics of the utility model, also resides in:
Further, air-bubble level is provided with flat protractor, horizontal plane is remained at the horizontal protractor of guarantee
On.
Further, compass is provided with horizontal protractor, when in use the position of 0 ° of recording level protractor, with solid
Fixed horizontal protractor towards angle.
Further, vertical protractor has sided scale and bilateral pointer, and bilateral pointer is connected with each other and synchronous movement,
To ensure that the semicircular protractor plate being stuck between two pointers can follow pointer to move.
Further, the scale precision of horizontal protractor and vertical protractor is 1/4 degree, and reading is more accurate, positioning precision
It is higher.
The beneficial effects of the utility model are that part used in the blasthole position indicator does not include any current emissions, system
Make simple, cost is cheap, measuring accuracy up to 1~5cm, in vertical core blast working can extensive use, being capable of maximum limit
Degree reduces the engineering accident that blind big gun is brought.
Brief description of the drawings
Fig. 1 is the schematic diagram of blast working blasthole position indicator of the present utility model;
Fig. 2 is the structural representation of blast working blasthole position indicator of the present utility model;
Fig. 3 is the structural representation of horizontal protractor;
Fig. 4 is the structural representation of vertical protractor;
Fig. 5 is the selection schematic diagram of fixed measuring point.
In figure, 1. supports, 2. horizontal protractors, 3. vertical protractors, 4. lining ropes, 5. main shafts, 6. horizontal protractors fix
Disk, 7. horizontal protractor installation axles, 8. supporting legs, 9. fixed feets, 10. air-bubble levels, 11. compasses, 12. hinges dress
Put;13. steel wire.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and detailed description, but the utility model
It is not limited to these embodiments.
Blast working blasthole position indicator of the present utility model is as shown in figure 1, by support 1, horizontal protractor 2, vertical angulation
Device 3 and lining rope 4 form.Support is made up of stainless steel tube, has a vertical main shaft 5, main shaft upper end is fixed with horizontal angulation
Device fixed disc 6, fixed disc is using main shaft as the center of circle, and circle centre position is provided with vertical horizontal protractor installation axle 7, such as Fig. 2 institutes
Show;The lower end of main shaft 5 is welded with three supporting legs 8, and the support of whole bracket stable is made in the form of triangle on the ground.Support
The one end on leg contact ground is connected with fixed feet 9, and fixed feet is circular or semicircle iron ring, can also pass through gland stone above
Or the stability of other weights increase support.Supporting leg 8 and the junction of iron ring 9 are provided with leveling nut, can by leveling nut
To adjust the left and right of fixed feet, upper and lower distance, with the balance of adjusting bracket.Under normal circumstances, support main axis length takes 1.2m, branch
Spike length takes 30cm, and support feet is in 45 ° with support main shaft.
Horizontal protractor 2 is the center of circle as shown in Figure 3 semicircular protractor with holes, is put through horizontal protractor mounting sleeve
On the horizontal protractor fixed disc of main shaft upper end, fixed by nut and support main shaft, horizontal protractor fixed disc table
Relatively rough material is selected in face, it is therefore an objective to after having adjusted horizontal protractor, can be played a part of necessarily fixing protractor, not made
It deflects.Two air-bubble levels 10 are provided with horizontal protractor, one is used for measuring horizontal protractor left-right balance,
Another is used for measuring horizontal protractor anterior-posterior balance, is remained in the horizontal plane with the horizontal protractor of guarantee.Horizontal angulation
Compass 11 is also equipped with device, when in use the position of 0 ° of recording level protractor, with the horizontal protractor of fixation towards angle
Degree.Horizontal protractor diameter takes 80cm specifications, and protractor is bigger, and the angle number of marking is more accurate on dial, marking number of degrees essence
Exactness is preferably up to 1/4 degree.
Vertical protractor 3 is semicircular protractor as shown in Figure 4 positioned at the horizontal lower section of protractor 2, its size, precision, material
Matter is as horizontal protractor 2.The straight line of vertical protractor is arranged on main shaft 5 by Hinge 12, makes vertical angulation
Device can rotate around the spindle.The pointer outer end of horizontal protractor 2 is fixedly connected by steel wire 13 with the upper edge of vertical protractor plate, is made
The pointer of horizontal protractor and vertical protractor remain the fixation of relative position, can band during the vertical protractor of left-right rotation
The pointer for moving horizontal protractor is swung in the horizontal plane.Vertical protractor 3 has sided scale and a bilateral pointer, bilateral two
Pointer is coaxially disposed in protractor circle centre position, two pointer activities, while two pointer outer ends also link together simultaneously, to protect
Semicircular protractor plate of the card between two pointers can follow pointer to move.Bilateral pointer outer end junction with it is with a scale
Lining rope 4 connects.
The blast working blasthole position indicator application method is:
1. choose fixed measuring point;
As shown in figure 5, the measurement blasthole on explosion step is point to be determined, the fixed measuring point measured on step is then whole
The positioning measurement point of each blasthole of Ge Bao areas.If fixed measuring point and big gun area are located at same level, one can be simply used
Individual semi-circle ruler and a tape measure are positioned, it is contemplated that the complexity of blasting condition, the irregularities in explosion face, for more
Extensively, blasthole positioning is accurately carried out, fixed measuring point is typically higher than explosion face, and blasthole position indicator of the present utility model is in itself
Containing support, so either blast working terminates how rear explosion face changes, be all advantageous to reposition.
Fixed measuring point chosen position will will have a certain distance with burst region, prevent blast action drawing crack heel row area
Domain, cause fixed measuring point to be subjected to displacement, and to ensure fixed measuring point at whole big gun area rear, but can not take in step just
Bottom, prevent concussion of blasting from causing step falling rocks or landslide not only to bury fixed measuring point, and security incident can be caused.If
Step area is small, and suitable fixed measuring point can not be searched out on explosion step, then can be in the upper step at step rear
Or fixed measuring point is found on massif.
Fixed measuring point is chosen at burst region dead astern, if burst region is excessive, is segmented into a few part measurements, often
The measurement point of individual part is all located at the dead astern of each burst region part, in addition, choose will be from for the position in fixation measuring place
Main armament area 10-15m is remote, prevents drawing crack fixed measuring point position after the explosion of main armament area, prevents fixed measuring point from moving forward, and choose
Place is higher than big gun area 20cm or so, also can be artificially padded.After having chosen fixed measuring point, nailed in selected point and easily find color
Iron nail or reinforcing bar, its diameter is less than position indicator support main shaft internal diameter, and stand-down above length is in 11cm or so.
2. fixed blasthole position indicator;
The stainless steel tube of blasthole position indicator support main shaft is enclosed on selected point iron nail, it is more short better to be inserted in depth, avoids
Iron nail aspect effect is to whole holder orientation.
By horizontal protractor towards big gun area, leveling nut is adjusted, makes two level vials of horizontal protractor placed in the middle.Root
According to compass, 0 degree of scale on compass of recording level protractor.
3. measure blasthole;
Lining rope is moved to aperture, measures the distance between fixed measuring point and blasthole, in lining rope drawing process, is driven perpendicular
Straight protractor pointer movement, and vertical protractor swings around support main shaft, and then drive the horizontal protractor beat of pointer.Note
Record the scale of horizontal protractor and vertical protractor, and lining rope scale.All blasthole position indicator is taken away after measurement record.
The position of this blasthole is accurately positioned with three measured value cans of record.
4. position blasthole;
After explosion terminates, if finding blind big gun and blind big gun is capped, after chosen position installs blasthole position indicator, use
Blind big gun is found in the data positioning of record.
If blind big gun localized ground reduces, blind blasthole is in the underface of anchor point.If the rise of blind big gun localized ground it is excessive or
Covering excessively causes ground rise excessive, then blind big gun localized ground is cleared up, then and carry out positioning searching.
Part used in the blasthole position indicator does not include any current emissions, makes simply, and cost is cheap, and measurement is accurate
Degree up to 1~5cm, in vertical core blast working can extensive use, the engineering accident that blind big gun is brought can be reduced to greatest extent.
Claims (5)
- A kind of 1. blast working blasthole position indicator, it is characterised in that including support, horizontal protractor, vertical protractor and lining rope, The support has vertical main shaft, and horizontal protractor fixed disk is fixed with main shaft;The horizontal protractor is arranged on level On protractor fixed disk, the vertical protractor is connected through the hinge on main shaft;The pointer of horizontal protractor with it is vertical Protractor links together, and the pointer of horizontal protractor and vertical protractor remain the fixation of relative position;Vertical amount The pointer of angle device is connected with the lining rope.
- 2. blast working blasthole position indicator according to claim 1, it is characterised in that be provided with the horizontal protractor Air-bubble level.
- 3. blast working blasthole position indicator according to claim 1, it is characterised in that be provided with the horizontal protractor Compass.
- 4. blast working blasthole position indicator according to claim 1, it is characterised in that the vertical protractor has two-sided Scale and bilateral pointer, bilateral pointer is connected with each other and synchronous movement.
- 5. blast working blasthole position indicator according to claim 1, it is characterised in that the horizontal protractor and vertical amount The scale precision of angle device is 1/4 degree.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720473294.9U CN206740007U (en) | 2017-05-02 | 2017-05-02 | A kind of blast working blasthole position indicator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720473294.9U CN206740007U (en) | 2017-05-02 | 2017-05-02 | A kind of blast working blasthole position indicator |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206740007U true CN206740007U (en) | 2017-12-12 |
Family
ID=60563362
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720473294.9U Active CN206740007U (en) | 2017-05-02 | 2017-05-02 | A kind of blast working blasthole position indicator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206740007U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111623677A (en) * | 2020-05-27 | 2020-09-04 | 山东省淮海工程建设监理有限公司 | Pilot hole smooth blasting construction method and blast hole positioning device |
CN112031781A (en) * | 2020-08-28 | 2020-12-04 | 青岛市地铁四号线有限公司 | Rotary measuring scale device capable of realizing accurate hole distribution in blasting construction and hole distribution method |
CN112729036A (en) * | 2021-01-25 | 2021-04-30 | 华侨大学 | Accurate control auxiliary device of tunnel blasting big gun hole angle |
CN112985203A (en) * | 2021-02-06 | 2021-06-18 | 中国水利水电第九工程局有限公司 | Blast hole positioning method for basalt blasting fine particles |
CN115289925A (en) * | 2022-08-29 | 2022-11-04 | 四川中鼎爆破工程有限公司 | Blast hole inclination and inclination angle control device |
-
2017
- 2017-05-02 CN CN201720473294.9U patent/CN206740007U/en active Active
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111623677A (en) * | 2020-05-27 | 2020-09-04 | 山东省淮海工程建设监理有限公司 | Pilot hole smooth blasting construction method and blast hole positioning device |
CN112031781A (en) * | 2020-08-28 | 2020-12-04 | 青岛市地铁四号线有限公司 | Rotary measuring scale device capable of realizing accurate hole distribution in blasting construction and hole distribution method |
CN112031781B (en) * | 2020-08-28 | 2022-07-26 | 青岛市地铁四号线有限公司 | Rotary measuring scale device capable of realizing accurate hole distribution in blasting construction and hole distribution method |
CN112729036A (en) * | 2021-01-25 | 2021-04-30 | 华侨大学 | Accurate control auxiliary device of tunnel blasting big gun hole angle |
CN112985203A (en) * | 2021-02-06 | 2021-06-18 | 中国水利水电第九工程局有限公司 | Blast hole positioning method for basalt blasting fine particles |
CN112985203B (en) * | 2021-02-06 | 2022-08-19 | 中国水利水电第九工程局有限公司 | Blast hole positioning method for basalt blasting fine particles |
CN115289925A (en) * | 2022-08-29 | 2022-11-04 | 四川中鼎爆破工程有限公司 | Blast hole inclination and inclination angle control device |
CN115289925B (en) * | 2022-08-29 | 2023-10-13 | 四川中鼎爆破工程有限公司 | Control device for inclination and inclination angle of blast hole |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206740007U (en) | A kind of blast working blasthole position indicator | |
CN204461414U (en) | The portable two-way laser of a kind of mining tunnel launches section detector | |
CN108253946A (en) | Multi-functional vertical measurement connection survey integrated three-dimensional coordinate transfer device and method | |
CN107246864B (en) | Tunnel hidden karst cave space detection device and detection method | |
CN207540512U (en) | A kind of laser rail smooth degree detection device | |
CN110644973A (en) | Drilling angle measuring instrument and measuring method thereof | |
CN207335629U (en) | Ground displacement monitoring device | |
CN103808236A (en) | Blasthole measuring instrument | |
CN205940327U (en) | Geological engineering angular instrument | |
CN202937253U (en) | Tester for depth, dip angle and azimuth angle of blast hole | |
CN205482955U (en) | Device is laid to circular sample prescription | |
CN208059776U (en) | Portable core structural plane inclination angle field measurement device | |
CN109655923B (en) | Wall-mounted directional fixing device for measuring electrode and measuring method thereof | |
CN207963859U (en) | A kind of ground fractures measuring device | |
CN207351459U (en) | A kind of novel and multifunctional circumferentor | |
CN206942752U (en) | Water prospection of mine rig precise positioning instrument | |
CN100523725C (en) | Anchor horizontal oblique angle measuring device and using method thereof | |
CN101762719B (en) | Portable laser indicator used in galleries | |
CN209468794U (en) | One kind being used for tunnel foundation settlement measurement coefficient of subgrade reaction analyzer | |
CN103806898B (en) | Anchor hole hole depth, inclination angle, azimuth and slope/wall angle analyzer | |
CN214540080U (en) | Transient electromagnetic geophysical prospecting wire frame rotating device for coal mine | |
Neman et al. | Probability of failure and slope safety factors based on geological structure of plane failure on Open Pit Batu Hijau Nusa Tenggara Barat | |
CN217155255U (en) | Angle detection device in stock hole | |
CN216695018U (en) | Multifunctional geological compass for geological mineral exploration of nonferrous metals | |
CN213179984U (en) | Portable mine hydraulic support stand inclination measuring device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180917 Address after: 721401 Yao Jia Gou town Fengxiang County Baoji city Shaanxi Province Patentee after: SHAANXI HONGQI INDUSTRIAL EXPLOSIVE GROUP CO., LTD. Address before: 710065 Shaanxi Xi'an High-tech Zone, Tang Yan Road south city gate C, D block 2 Building 1 units 12 stories 11204 rooms. Patentee before: Shaanxi hung an explosion engineering Co., Ltd. |
|