CN206722088U - Steel pile foundation bolt positioning device - Google Patents
Steel pile foundation bolt positioning device Download PDFInfo
- Publication number
- CN206722088U CN206722088U CN201720505499.0U CN201720505499U CN206722088U CN 206722088 U CN206722088 U CN 206722088U CN 201720505499 U CN201720505499 U CN 201720505499U CN 206722088 U CN206722088 U CN 206722088U
- Authority
- CN
- China
- Prior art keywords
- steel
- foundation bolt
- semicircle
- hole
- pieces
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of steel pile foundation bolt positioning device, including steel plate, foundation bolt and scaffold steel pipe, the steel plate is spliced by two pieces of dismountable prefabricated steels axisymmetricly, the clamping rings being made by round steel is welded with the corner of the steel plate, the scaffold steel pipe may pass through the clamping rings;The consistent semicircle positioning hole of several diameters is arranged with two pieces of prefabricated steels, cross normal control wire is provided between adjacent semicircle positioning hole;The raised semicircle positioning tube equal with semicircle positioning hole number is also arranged with two pieces of prefabricated steels, the rear and front end of the semicircle positioning tube is welded with flank, the flank is provided with fixing hole, is fixed together two pieces of prefabricated steels through fixing hole and screwing by bolt.The utility model can effectively control foundation bolt location dimension and precision, and mould pacifies, tears simple, easy for construction, repeatable utilization open, and overall economic efficiency is preferable.
Description
Technical field
It the utility model is related to architectural engineering technical field of auxiliary equipment, and in particular to a kind of steel pile foundation bolt positioning
Device.
Background technology
Steel plant structure span is larger, and steel pile is more, therefore, in steel-structure factory building engineering, steel pile and base
Connection between plinth is realized by foundation bolt.At present, in building construction process, large equipment base foundation bolt is
Pre-buried in advance, the precision of embedding anchor bolts directly influences the lifting work of later stage large scale equipment, and because large scale equipment
Foundation bolt general requirements is big, quantity is more, installation accuracy requires the features such as high, Equipment Foundations physical dimension is changeable, corresponding increase
Foundation bolt installation difficulty.Therefore, whether sill anchor positioning is accurate, directly affects the integral installation essence of steel-structure factory building
Degree.
And typically constructed in the prior art, in embedding anchor bolts work progress using typified form, for large-scale positioning
Template has the following disadvantages:Large-scale locating template is required to make precision height, for lifting, requiring strict in work progress, gone out
Existing problem is difficult to adjust, and easily causes secondary construction;Large-scale locating template processing, transport are easily deformed, and increase difficulty of construction;Apply
After work, the bolt to go wrong individually is adjusted difficult.It is big that utility model patent CN202718136U discloses a kind
Type Equipment Foundations foundation bolt installation and positioning structure, including multiple foundation bolts and pour mold and reinforced frame accordingly;Eachly
Foot bolt is stood in be poured in mold accordingly, and corresponding main reinforcement frame is in the die cavity for pouring mold;Also include support frame, lower margin spiral shell
Bolt locating template and multiple precise positioning ring plates;The foundation bolt positioning mould grillage is on support frame;Foundation bolt positioning mould
Multiple anchor (bolt) holes are provided with plate, the aperture of anchor (bolt) hole is more than the diameter of foundation bolt;Each foundation bolt stretches into phase
The anchor (bolt) hole answered;The quantity of precise positioning ring plate is identical with the quantity of foundation bolt;Each precise positioning ring plate is sheet
Structure, through hole is provided with laminated structure, the diameter of the through hole is identical with the diameter of foundation bolt;Precise positioning ring plate passes through this
Through hole is enclosed on corresponding foundation bolt, and the bottom surface of precise positioning ring plate and the upper surface of foundation bolt locating template are closely connected.
But the utility model device complex operation, and the installation positioning of some large-scale chemical industry equipments is suitable only for, it is not appropriate for building
The construction in field.
Utility model content
In view of the shortcomings of the prior art, the utility model solves by providing a kind of steel pile foundation bolt positioning device
In existing work progress, the steel-structure factory building steel pile caused by foundation bolt deviations are excessive can not install and steel knot
The excessive technical problem of structure factory building integral installation accuracy error.
Steel pile foundation bolt positioning device, including steel plate, foundation bolt and scaffold steel pipe, the steel plate be in by two pieces
Axisymmetric dismountable prefabricated steel is spliced, and the fixed circle being made by round steel is welded with the corner of the steel plate
Ring, the scaffold steel pipe may pass through the clamping rings;Half of several diameters unanimously is arranged with two pieces of prefabricated steels
Justify positioning hole, cross normal control wire is provided between adjacent semicircle positioning hole;Also be arranged with two pieces of prefabricated steels and
The equal raised semicircle positioning tube of semicircle positioning hole number, the semicircle positioning tube and prefabricated steel are perpendicular, the semicircle
It is provided with positioning tube and positions bore dia identical through hole with semicircle, the foundation bolt can be worn out of semicircle positioning hole and through hole
Cross;The rear and front end of the semicircle positioning tube is welded with flank, and the flank is provided with fixing hole, is passed through and fixed by bolt
Two pieces of prefabricated steels are fixed together by hole and screwing.
Preferably, the thickness of the steel plate is 28mm.
Preferably, the thickness of the round steel is 8mm.
Preferably, the semicircle positioning tube is welded in prefabricated steel.
Compared with prior art, the beneficial effects of the utility model are:The utility model employs spliced prefabricated steel
Mould, solve in existing work progress, steel-structure factory building steel pile can not pacify caused by foundation bolt deviations are excessive
It is filled with and technical problem that steel-structure factory building integral installation accuracy error is excessive;It is perpendicular to be further also provided with prefabricated steel
Semicircle positioning tube, perpendicular to the ground not tilted when ensureing foundation bolt installation;Steel plate is made sliceable tear open by the utility model
It is more flexible and convenient that the formula of unloading uses the utility model, passes through the multiple fixation of scaffolding steel pipe, semicircle positioning tube and flank
The utility model is set to be not easy to shift after, fixation is more firm.Therefore, the utility model effectively can control foundation bolt to position
Size and precision, and mould pacifies, tears simple, easy for construction, repeatable utilization open, overall economic efficiency is preferable.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is Fig. 1 upward view;
Fig. 3 is Fig. 1 right view;
Reference:1st, steel plate;2nd, foundation bolt;3rd, scaffold steel pipe;4th, clamping rings;5th, semicircle positioning hole;6th, ten
Font normal control wire;7th, semicircle positioning tube;8th, through hole;9th, flank;10th, bolt;11st, prefabricated steel;12nd, fixing hole.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and detailed description.
Embodiment 1
Shown in 3, steel pile foundation bolt positioning device, including steel plate 1, foundation bolt 2 and scaffold steel pipe 3, the steel
The thickness of plate 1 is 28mm, and the steel plate 1 is spliced by two pieces of dismountable prefabricated steels 11 axisymmetricly.The steel plate 1
Corner at be welded with the clamping rings 4 being made by round steel, the thickness of the round steel is 8mm, and the scaffold steel pipe 3 can
Through the clamping rings 4.The consistent semicircle positioning hole 5 of several diameters is arranged with two pieces of prefabricated steels 11, it is adjacent
Cross normal control wire 6 is provided between semicircle positioning hole 5.Also it is arranged with two pieces of prefabricated steels 11 and semicircle positioning hole 5
The equal raised semicircle positioning tube 7 of quantity, the semicircle positioning tube 7 are welded in prefabricated steel 11, the semicircle positioning tube 7
It is perpendicular with prefabricated steel 11, it is provided with and the diameter identical through hole 8 of semicircle positioning hole 5, the lower margin in the semicircle positioning tube 7
Bolt 2 can pass through out of semicircle positioning hole 5 and through hole 8;The rear and front end of the semicircle positioning tube 7 is welded with flank 9, described
Flank 9 is provided with fixing hole 12, through fixing hole 12 and screws two pieces of prefabricated steels 11 being fixedly connected on one by bolt 10
Rise.
Method of manufacture and use thereof of the present utility model:Bored according to the relative position of foundation bolt on the steel plate of 25mm thickness
Hole forming, cross normal control wire being made between the positioning hole of steel plate, the round steel for being 8mm with thickness makes clamping rings,
And clamping rings is welded at the corner of steel plate, internal orifice dimension and positioning hole aperture identical positioning tube are welded on steel plate,
Steel plate is symmetrically cut and is divided into two, the flank for steel plate after segmentation to be docked is welded on positioning tube after dicing,
Flank just as being drilled with equal-sized fixing hole on position.In use, determined according to the cross normal control wire on steel plate
Foundation bolt, is then put into half-circle locating aperture by the position of good half-circle locating aperture, then, finally by using scaffold
Steel pipe passes through clamping rings by the utility model fixation so as to reach the purpose of control foundation bolt axial location, and bolt 10 passes through
Two pieces of prefabricated steels are fixed together by fixing hole on flank and screwing.
Embodiment 2
Different from embodiment 1, the utility model does not contain semicircle positioning tube 7, through hole 8, flank 9, fixing hole and bolt 10.
Although above having made detailed description to the utility model with generality explanation and specific embodiment,
On the basis of the utility model, it can be made some modifications or improvements, this is apparent to those skilled in the art
's.Therefore, the these modifications or improvements on the basis of without departing from the utility model spirit, belonging to the utility model will
Seek the scope of protection.
Claims (4)
1. steel pile foundation bolt positioning device, including steel plate, foundation bolt and scaffold steel pipe, it is characterised in that:The steel
Plate is spliced by two pieces of dismountable prefabricated steels axisymmetricly, be welded with the corner of the steel plate by round steel make and
Into clamping rings, the scaffold steel pipe may pass through the clamping rings;It is straight that several are arranged with two pieces of prefabricated steels
The consistent semicircle positioning hole in footpath, cross normal control wire is provided between adjacent semicircle positioning hole;In two pieces of prefabricated steels also
The raised semicircle positioning tube equal with semicircle positioning hole number is arranged with, the semicircle positioning tube mutually hangs down with prefabricated steel
Directly, it is provided with the semicircle positioning tube and positions bore dia identical through hole with semicircle, the foundation bolt can be from semicircle positioning hole
Passed through with through hole;The rear and front end of the semicircle positioning tube is welded with flank, and the flank is provided with fixing hole, passes through spiral shell
Bolt passes through fixing hole and screwed and is fixed together two pieces of prefabricated steels.
2. steel pile foundation bolt positioning device according to claim 1, it is characterised in that:The thickness of the steel plate is
28mm。
3. steel pile foundation bolt positioning device according to claim 1, it is characterised in that:The thickness of the round steel is
8mm。
4. steel pile foundation bolt positioning device according to claim 1, it is characterised in that:The semicircle positioning tube welding
In prefabricated steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720505499.0U CN206722088U (en) | 2017-05-09 | 2017-05-09 | Steel pile foundation bolt positioning device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720505499.0U CN206722088U (en) | 2017-05-09 | 2017-05-09 | Steel pile foundation bolt positioning device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206722088U true CN206722088U (en) | 2017-12-08 |
Family
ID=60509489
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720505499.0U Expired - Fee Related CN206722088U (en) | 2017-05-09 | 2017-05-09 | Steel pile foundation bolt positioning device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206722088U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110385783A (en) * | 2019-06-24 | 2019-10-29 | 中国一冶集团有限公司 | The prefabricated components and construction method of pre-buried hanging ring in a kind of pipe gallery plate member |
-
2017
- 2017-05-09 CN CN201720505499.0U patent/CN206722088U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110385783A (en) * | 2019-06-24 | 2019-10-29 | 中国一冶集团有限公司 | The prefabricated components and construction method of pre-buried hanging ring in a kind of pipe gallery plate member |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207829306U (en) | Assemble concrete structure prefabricated post reserved joint bar positioning sleeve board mold and vertical connection structure | |
CN203247603U (en) | High-position foundation bolt positioning device | |
CN105170836A (en) | Portable multi-jacking multifunctional high-tensile reinforcement bar bending and straightening machine and operation method thereof | |
CN106193330B (en) | A kind of steel building construction land tenure foot bolt pre-embedded construction method | |
CN110586815A (en) | Size-adjustable multi-layer steel bar net high-precision machining jig frame and using method | |
CN201377141Y (en) | Reinforcing steel bar positioning clamp of reinforced concrete column | |
CN206722088U (en) | Steel pile foundation bolt positioning device | |
CN104196248B (en) | Steel pipe column vertical locating device and construction method thereof is inserted after contrary sequence method | |
CN212104166U (en) | Accurate positioning device for embedded bolt of safety injection box of nuclear power station | |
CN205907609U (en) | Supplementary utensil in pre -buried hole of bridge supporting base stone location | |
CN202265906U (en) | Fixing device for anchor bolts of embedded type steel tube concrete column feet | |
CN206637189U (en) | A kind of large-scale tower crane foundation pre-embedded bolt fixing device | |
CN203834809U (en) | Steel pipe column structure for steel pipe column concrete side pouring method | |
CN215055464U (en) | Quick hoist and mount positioner of PC superimposed sheet | |
CN206189607U (en) | Rag bolt location structure | |
CN206600005U (en) | The positioning component and positioner of reserved joint bar in shear wall | |
CN204199323U (en) | For the positioning screw hole mould of pre-embedded bolt quick position | |
CN205343431U (en) | Prefabricated wall body grout sleeve strip solid matter exposes accurate positioning die of reinforcing bar | |
CN212771968U (en) | Full-prefabricated assembled bridge bearing platform positioning system | |
CN211547694U (en) | Bored concrete pile steel reinforcement cage location centering device | |
CN204040499U (en) | Steel pipe column vertical locating device is inserted after contrary sequence method | |
CN210685368U (en) | Convenient reinforcing complete die set for concrete wall formworks on two sides of deformation joint | |
CN209798804U (en) | assembled concrete-filled steel tube pile foundation | |
CN205918142U (en) | Aligning device is assembled to shear force wall | |
CN105643791A (en) | Accurate positioning die for prefabricated wall body grouting sleeve stripy closely spaced exposed steel bar |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171208 Termination date: 20180509 |