CN206707101U - Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling - Google Patents

Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling Download PDF

Info

Publication number
CN206707101U
CN206707101U CN201720318859.6U CN201720318859U CN206707101U CN 206707101 U CN206707101 U CN 206707101U CN 201720318859 U CN201720318859 U CN 201720318859U CN 206707101 U CN206707101 U CN 206707101U
Authority
CN
China
Prior art keywords
distribution box
scarf
walls
filling
housing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720318859.6U
Other languages
Chinese (zh)
Inventor
信国星
杨国庆
杨树林
郑彦瑞
孙绪友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Tanki Industry & Commerce Group Co Ltd
Original Assignee
Shandong Tanki Industry & Commerce Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Tanki Industry & Commerce Group Co Ltd filed Critical Shandong Tanki Industry & Commerce Group Co Ltd
Priority to CN201720318859.6U priority Critical patent/CN206707101U/en
Application granted granted Critical
Publication of CN206707101U publication Critical patent/CN206707101U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling, belongs to filling scarf electronic box mounting technique field within the walls.It is characterized in that:Including distribution box housing(4)And Massive Concrete Blocks(7), Massive Concrete Blocks(7)The rectangular housing of rectangular channel is provided with for inside, the close nested distribution box housing of rectangular channel inwall(4), distribution box housing(4)Two sides be provided with reserved threading sleeve pipe(5), reserve threading sleeve pipe(5)Top passes Massive Concrete Blocks(7)It is outside.The installation of distribution box is formed modularization by the utility model, while wall construction, realize distribution box installation module is pre-formed, with the construction of wall, distribution box is directly fitted in the specified location of wall, casing installation is carried out using embedded distributing box prefabricated components, prefabricated section installs with the completion distributing box of building wall, other component processing is prefabricated to be carried out in advance, do not influence to fill wall build by laying bricks or stones with the casing set-up time, improve installation effectiveness.

Description

Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling
Technical field
Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling, belongs to filling scarf electronic box installation skill within the walls Art field.
Background technology
In Building Construction, the distribution box in installing engineering needs the reserved location when secondary structure is constructed, And the installation effect of distributing cabinet directly affects to the overall perception and quality of masonry structure.At present, traditional distribution box peace Dress method is the way that blocks after reserved opening adds, i.e., according to the installation site and size of the distributing box required in drawing, Installation hole is reserved when masonry wall is built by laying bricks or stones.Reflected by engineering, above-mentioned hole to be provided installation casing method has following deficiency:
1st, in terms of construction quality, box back surface and four Charltons hollowings, crack;Reserved opening position deviation, forget hole to be provided Mouthful, reserved opening when be not provided with the lintel later stage and pick chisel wall, destroying wall body structure influences wall integrity;Installation casing position wall The difficult control of the vertical flatness of body, influences perception.
2nd, in terms of operability, casing is not fixed easily, and box back surface and surrounding closure are cumbersome.
3rd, in terms of speed of application, the installation of conventional method middle case includes cave entrance reservation, casing is fixed, the later stage blocks Step, installation period length, overall progress are slow.
The content of the invention
Technical problem to be solved in the utility model is:Overcome the deficiencies in the prior art, there is provided a kind of Stability Analysis of Structures, behaviour Scarf electronic box installs precast segment and prefabricated mould within the walls for the filling of work convenience, quick construction, reliable in quality.
The utility model solves the technical scheme that its technical problem uses:Scarf electronic box installs prefabricated group within the walls for the filling Part, it is characterised in that:Including distribution box housing and Massive Concrete Blocks, Massive Concrete Blocks are provided with the rectangle of rectangular channel for inside Housing, closely nested distribution box housing, two sides of distribution box housing are provided with reserved threading sleeve pipe, reserve threading rectangular channel inwall Sleeve pipe top is passed outside Massive Concrete Blocks.
The installation of distribution box is formed into modularization, while wall construction, realizes and is prefabricated into distribution box installation module Type, with the construction of wall, distribution box is directly fitted in the specified location of wall, entered using embedded distributing box prefabricated components Row casing is installed, and prefabricated section installs with the completion distributing box of building wall, and component processing is prefabricated in addition is carried out in advance, Do not influence fill wall build by laying bricks or stones with the casing set-up time, substantially increase installation effectiveness.By live practice of construction.Prefabricated components system Make simple, installation casing one-shot forming;And prefabricated components are integrally built by laying bricks or stones with masonry wall, massless hidden danger, perception is good;Reduce Mounting cost, shorten casing installation period.
The distance between the side of described distribution box housing and Massive Concrete Blocks outer side edges are more than or equal to 80mm.
Described distribution box housing is completely embedded into rectangular channel, and distribution box housing outer face opening is set, and opening surface is stretched Go out rectangular channel opening surface.
A kind of prefabricated mould for filling scarf electronic box installation precast segment within the walls, it is characterised in that:Including end template, side Template and positioner, end template upper shed rectangle preformed hole, the open end of described distribution box housing are withheld in preformed hole Interior, the rectangle frame surrounded by the longitudinally disposed side template of polylith, rectangle frame inwall and distribution box are installed in the outer ring of distribution box housing Formed between housing and pour reserved chamber, be fixed by positioning device respectively on each angle of rectangle frame, described reserved threading set Pipe is through outside side template.
End template upper shed rectangle preformed hole, the open end of distribution box housing are withheld in preformed hole, it is preferred that distribution Tank shell open end stretches out the segment distance of preformed hole one, and distribution box housing is largely sleeved in rectangle frame so that distribution box shell Body can protrude above a framework in wall, wall sealing is smeared around the framework, is opened on end template after being installed on wall Mouth rectangle preformed hole is for the ease of follow-up wall plastering preset space.
Described positioner is the locating piece being arranged in pairs, and is connected between two adjacent groups locating piece by clamping device solid It is fixed.Clamping device can use step fastener.
The size of described preformed hole is more than or equal to the size of the open end of distribution box housing.
Compared with prior art, beneficial effect possessed by the utility model is:
1st, the installation of distribution box is formed modularization by the utility model, while wall construction, is realized and is pacified distribution box Die-filling piece pre-formed, with the construction of wall, distribution box is directly fitted in the specified location of wall, using embedded distribution box Body prefabricated components carry out casing installation, and prefabricated section is installed with the completion distributing box of building wall, and component is processed in addition It is prefabricated to carry out in advance, do not influence fill wall build by laying bricks or stones with the casing set-up time, improve installation effectiveness.
2nd, prefabricated components make simple, installation casing one-shot forming;And prefabricated components are integrally built by laying bricks or stones with masonry wall, massless Hidden danger, perception are good;Mounting cost is reduced, shortens casing installation period.By live practice of construction, single distributing box peace The dress comprehensive deadline is prefabricated by making embedded distributing box by 2 hours of conventional method be reduced to new method 20 minutes Component carries out distributing box installation, and casing installation site fastness and accuracy rate 100%, wall leveling perpendicularity and perception accord with Close code requirement;And the installation quality at casing surrounding and the back side is ensure that, later stage casing dorsal part is avoided and surrounding often occurs Cracking and the common quality defect such as hollowing, reached the set goal.
3rd, it is applied widely, can be prefabricated according to the progress of different size casings, any distributing box of wall pre-embedded can be used.
4th, economy is strong:The component can early stage it is prefabricated, be mounted directly according to typesetting figure during masonry construction, without secondary installing Casing, greatly save casing installation period.The component scene ordinary skilled artisan can be made, and occupied ground and equipment are wanted without special Ask;Single prefabricated components make, transport and installed only 22.69 yuan of cost of labor, substantially reduce distribution box installation cost.
Brief description of the drawings
Fig. 1 is installation relation schematic diagram of the filling within the walls between scarf electronic box installation precast segment and wall.
For filling, scarf electronic box installs prefabricated mould structural representation to Fig. 2 within the walls.
For filling, scarf electronic box installs precast segment schematic diagram to Fig. 3 within the walls.
Wherein, 1, end template 2, locating piece 3, side template 4, distribution box housing 5, reserved threading sleeve pipe 6, pour it is pre- Stay chamber 7, Massive Concrete Blocks 8, distribution box cavity 9, building block joint filling 10, masonry mortar layer 11, walling unit.
Embodiment
Fig. 1 ~ 3 are most preferred embodiments of the present utility model, and 1 ~ 3 pair of the utility model is done furtherly below in conjunction with the accompanying drawings It is bright.
Referring to the drawings 1 ~ 3:One kind filling scarf electronic box installation precast segment, including distribution box housing 4 and concrete within the walls Pour 7, Massive Concrete Blocks 7 are provided with the rectangular housing of rectangular channel for inside, the close nested distribution box housing of rectangular channel inwall 4, two sides of distribution box housing 4 are provided with reserved threading sleeve pipe 5, and reserved threading sleeve pipe 5 top is passed outside Massive Concrete Blocks 7 Portion.
The distance between the side of distribution box housing 4 and the outer side edges of Massive Concrete Blocks 7 are more than or equal to 80mm.Concrete pours Build the outer ring of block 7 and pour masonry mortar layer 10.Distribution box housing 4 is completely embedded into rectangular channel, the outer face opening of distribution box housing 4 Set, and opening surface stretches out rectangular channel opening surface.
A kind of prefabricated mould for filling scarf electronic box installation precast segment within the walls, including end template 1, side template 3 and fixed Position device, the upper shed rectangle preformed hole of end template 1, the open end of distribution box housing 4 are withheld in preformed hole, the chi of preformed hole The size of the very little open end more than or equal to distribution box housing 4.Install by polylith longitudinally disposed side the outer ring of distribution box housing 4 The rectangle frame that template 3 surrounds, formed between rectangle frame inwall and distribution box housing 4 and pour reserved chamber 6, on each angle of rectangle frame It is fixed by positioning device respectively, reserves threading sleeve pipe 5 and pass through outside side template 3.Positioner is the locating piece being arranged in pairs 2, it is connected by clamping device between two adjacent groups locating piece 2.Clamping device preferably uses step fastener.
Operation principle and the course of work:The utility model when in use, firstly, it is necessary to determine the specific of distribution box housing 4 Size, and marched into the arena in advance according to node requirements.According to the distribution box size determined, scantling is designed, it is ensured that match somebody with somebody The basic requirement of electronic box.Wasted to ensure that masonry wall is attractive in appearance, reduces building block cutting, typesetting is carried out to wall, according to typesetting figure Further deepen scantling, be that scantling matches with masonry modulus, reduction is spliced, reaches attractive in appearance with saving material.
The precast segment makes and is mainly made up of supporting module, static housing, casting concrete three parts.
1st, supporting module
Template is made according to the size of conceptual design, template uses waste and old broken template.Whole template includes one piece of bed die Plate 1 and four pieces of side templates 3, a rectangular opening is opened according to size outside distributing box among end template 1, the height of side template 3 is builds Body wall thickness, four angles are reinforced with step fastener.
2nd, fixed distribution box
Distributing box is first stretched out into the outside 5cm of side template 3 with side template 3 by the reserved threading sleeve pipe 5 being connected with casing It is attached, then overall be buckled in is laid on smooth end template 1, is fixed with nail in surrounding.
3rd, casting concrete
For ease of the transport and installation of prefabricated components, poured using lightweight aggregate haydite concrete, pour height be with The height of side template 3 is concordant.Pour rear surface press polish, cover film maintenance, template should concrete strength reach can guarantee that it is prefabricated Component surface and corner angle are removed when not suffered damage because of form removal.
The installation of embedded distributing box precast segment is then carried out, close fit builds teams and groups by laying bricks or stones when precast segment is installed, sternly Lattice are placed according to the bright size positions of the typesetting icon that passes through of examination & approval.Related request in the building by laying bricks or stones of precast segment, with building Block builds requirement by laying bricks or stones.Because the prefabricated section is concrete for making, itself compressive strength is higher than building block;Distribution box size is little, and has Inner support power acts on, therefore need not add lintel.Finally, after the completion of building wall and top block, carried out using special groove cutting machine Fluting, threading conduit is attached with the reserved sleeve pipe being fixed in prefabricated section.
It is described above, only it is preferred embodiment of the present utility model, is not that other forms are made to the utility model Limitation, any person skilled in the art is changed or is modified as possibly also with the technology contents of the disclosure above equivalent The equivalent embodiment of change.But it is every without departing from the content of the technical scheme of the utility model, it is real according to technology of the present utility model Any simple modification, equivalent variations and the remodeling that confrontation above example is made, still fall within the guarantor of technical solutions of the utility model Protect scope.

Claims (6)

1. scarf electronic box installs precast segment within the walls for one kind filling, it is characterised in that:Including distribution box housing(4)Poured with concrete Build block(7), Massive Concrete Blocks(7)The rectangular housing of rectangular channel is provided with for inside, the close nested distribution box shell of rectangular channel inwall Body(4), distribution box housing(4)Two sides be provided with reserved threading sleeve pipe(5), reserve threading sleeve pipe(5)Top passes concrete Pour(7)It is outside.
2. scarf electronic box installs precast segment within the walls for a kind of filling according to claim 1, it is characterised in that:Described matches somebody with somebody Electronic box housing(4)Side and Massive Concrete Blocks(7)The distance between outer side edges are more than or equal to 80mm.
3. scarf electronic box installs precast segment within the walls for a kind of filling according to claim 1, it is characterised in that:Described matches somebody with somebody Electronic box housing(4)It is completely embedded into rectangular channel, distribution box housing(4)Outer face opening is set, and opening surface stretches out rectangular channel and opened Mouth face.
A kind of 4. prefabricated mould of filling described in claim 1 scarf electronic box installation precast segment within the walls, it is characterised in that: Including end template(1), side template(3)And positioner, end template(1)On open up rectangle preformed hole, described distribution box housing (4)Open end withhold in preformed hole, distribution box housing(4)Outer ring install by the longitudinally disposed side template of polylith(3) The rectangle frame surrounded, rectangle frame inwall and distribution box housing(4)Between formed pour reserved chamber(6), on each angle of rectangle frame It is fixed by positioning device respectively, described reserved threading sleeve pipe(5)Through side template(3)It is outside.
5. a kind of prefabricated mould for filling scarf electronic box installation precast segment within the walls according to claim 4, its feature It is:Described positioner is the locating piece being arranged in pairs(2), two adjacent groups locating piece(2)Between connected by clamping device Connect fixation.
6. a kind of prefabricated mould for filling scarf electronic box installation precast segment within the walls according to claim 4, its feature It is:The size of described preformed hole is more than or equal to distribution box housing(4)Open end size.
CN201720318859.6U 2017-03-29 2017-03-29 Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling Expired - Fee Related CN206707101U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720318859.6U CN206707101U (en) 2017-03-29 2017-03-29 Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720318859.6U CN206707101U (en) 2017-03-29 2017-03-29 Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling

Publications (1)

Publication Number Publication Date
CN206707101U true CN206707101U (en) 2017-12-05

Family

ID=60468152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720318859.6U Expired - Fee Related CN206707101U (en) 2017-03-29 2017-03-29 Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling

Country Status (1)

Country Link
CN (1) CN206707101U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678268A (en) * 2018-06-20 2018-10-19 中国五冶集团有限公司 A kind of building block mould and the Prefabricated building block construction method based on BIM
CN109083414A (en) * 2018-09-29 2018-12-25 北京首钢建设集团有限公司 The construction method of pre-buried concrete prefabricated frame concealed distribution box in masonry structure
CN109129826A (en) * 2018-09-29 2019-01-04 五冶集团上海有限公司 Precast concrete alcove production method as the indoor strong and weak electronic box of house
CN110185192A (en) * 2019-07-04 2019-08-30 中国建筑第七工程局有限公司 A kind of electronic box prepares block and its processing mold in advance
CN111042547A (en) * 2019-12-30 2020-04-21 中天建设集团有限公司 One-step forming damage-free construction method of electric box and auxiliary construction device of electric box
CN112339079A (en) * 2020-11-24 2021-02-09 中国三冶集团有限公司 Prefabricated mold for masonry special for electrical box and use method of prefabricated mold
CN113829478A (en) * 2021-09-28 2021-12-24 中国建筑第四工程局有限公司 Integral distribution box prefabricated frame mold and using method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108678268A (en) * 2018-06-20 2018-10-19 中国五冶集团有限公司 A kind of building block mould and the Prefabricated building block construction method based on BIM
CN108678268B (en) * 2018-06-20 2024-01-26 中国五冶集团有限公司 Building block mold and BIM-based prefabricated building block construction method
CN109083414A (en) * 2018-09-29 2018-12-25 北京首钢建设集团有限公司 The construction method of pre-buried concrete prefabricated frame concealed distribution box in masonry structure
CN109129826A (en) * 2018-09-29 2019-01-04 五冶集团上海有限公司 Precast concrete alcove production method as the indoor strong and weak electronic box of house
CN110185192A (en) * 2019-07-04 2019-08-30 中国建筑第七工程局有限公司 A kind of electronic box prepares block and its processing mold in advance
CN111042547A (en) * 2019-12-30 2020-04-21 中天建设集团有限公司 One-step forming damage-free construction method of electric box and auxiliary construction device of electric box
CN112339079A (en) * 2020-11-24 2021-02-09 中国三冶集团有限公司 Prefabricated mold for masonry special for electrical box and use method of prefabricated mold
CN113829478A (en) * 2021-09-28 2021-12-24 中国建筑第四工程局有限公司 Integral distribution box prefabricated frame mold and using method thereof

Similar Documents

Publication Publication Date Title
CN206707101U (en) Scarf electronic box installs precast segment and prefabricated mould within the walls for one kind filling
CN104746639B (en) A kind of installation method that the prefabricated window that floats is installed in composite wallboard
CN102116061B (en) Masonry construction method for filling wall core pillar, core girder and building blocks into framework structure
CN104652830B (en) The construction method that a kind of Prefabricated construction panel and prefabricated panel are built
CN103883026B (en) The construction method of the cast-in-situ thermal-insulated composite outer wall system of green energy conservation
CN103866885B (en) The construction method of the energy-saving heat preserving structure of light inlet window
CN103758272B (en) Autoclaved aerated concrete blocks built-in wall steel pipe buried in advance construction method
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
JP2002004610A (en) Prefabricated bathroom
CN106088148B (en) Pipe gallery template and its application
CN101818541A (en) Precast composite wallboard with door/window holes and manufacturing method thereof
CN102758451A (en) Concrete cable channel construction process
CN110924692A (en) Masonry pipeline direct-buried construction method
CN107718241A (en) Prefabricated panel with heat preservation sandwich layer and preparation method thereof
CN106808578A (en) A kind of prefabricated piping lane of two-piece unit formula and method for prefabricating
CN207079923U (en) A kind of adjustable hole to be provided construction mould
CN110042861A (en) A kind of subway station assembled rail road and the connecting node with prefabricated middle plate against the wind
CN113250494A (en) Assembled integrated toilet and construction method
CN108000689A (en) Concrete component gang form and its casting method and concrete component with window frame
CN109914644A (en) A kind of assembled heat insulation masonry wall and preparation method thereof
CN103572964A (en) Mounting method of precast air duct during construction stage of construction engineering structure
CN103883022B (en) The construction method of space enclosing structure inner-outer wall antidetonation and sound insulation cracking resistance integrated structure
CN108708489A (en) A kind of concrete segment curtain wall and its manufacture and installation method
CN107269001A (en) Concealed distribution box is with the whole construction method poured of concrete wall structure
CN203856099U (en) Environment-friendly energy-saving cast-in-place heat-insulating windowed composite exterior wall system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171205

Termination date: 20180329