CN206669224U - A kind of provisional bridge construction concrete conveying pipe - Google Patents

A kind of provisional bridge construction concrete conveying pipe Download PDF

Info

Publication number
CN206669224U
CN206669224U CN201720411271.5U CN201720411271U CN206669224U CN 206669224 U CN206669224 U CN 206669224U CN 201720411271 U CN201720411271 U CN 201720411271U CN 206669224 U CN206669224 U CN 206669224U
Authority
CN
China
Prior art keywords
straight tube
bridge construction
conveying pipe
concrete conveying
construction concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720411271.5U
Other languages
Chinese (zh)
Inventor
黄修奖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Institute of Occupational
Original Assignee
Guangxi Institute of Occupational
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Institute of Occupational filed Critical Guangxi Institute of Occupational
Priority to CN201720411271.5U priority Critical patent/CN206669224U/en
Application granted granted Critical
Publication of CN206669224U publication Critical patent/CN206669224U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing Resistance To Weather, Investigating Materials By Mechanical Methods (AREA)

Abstract

A kind of provisional bridge construction concrete conveying pipe,Including straight tube,The top of straight tube is provided with inner-walls of duct,The top of inner-walls of duct is provided with wearing layer,The top of wearing layer is provided with waterproof layer,The top of waterproof layer is provided with anticorrosive coat,The surface of straight tube is provided with non-return valve,The side of straight tube is provided with temperature measurer,The bottom of straight tube is provided with support frame,The bottom of support frame is provided with the second fixing bolt,The bottom of support frame is provided with installing plate,The opposite side of straight tube is provided with bend pipe,The top of bend pipe is provided with reinforcement,The top of reinforcement is provided with outer tube wall,The side of bend pipe is provided with the first fixing bolt,Temperature measurer is internally provided with display screen,The bottom of display screen is provided with power switch,The bottom of power switch is provided with thermometric line,The side of thermometric line is provided with temperature probe,Whole device is reasonable in design,It is easy to use,Real-time protection effectively is carried out to its pipeline,Improve practicality.

Description

A kind of provisional bridge construction concrete conveying pipe
Technical field
It the utility model is related to a kind of bridge construction and mix territory, and in particular to a kind of provisional bridge construction concrete is defeated Pipeline is sent, belongs to Architectural Equipment field.
Background technology
Conveyance conduit is the defeated mode by the use of pipeline as a kind of long distance delivery liquids and gases goods and materials of means of transport, is A kind of specially means of transportation from grown place to market transfer oil, coal and building concrete, it is that main line is transported in consolidated delivery net Defeated special part, sometimes, pneumatic tube can also accomplish similar work, with compressed gas conveying solid substance cabin, and be filled with Goods pipeline transportation oil product is more costly than water transport, but still cheaper than railway transportation, and most of pipeline is owned by it Person is used for transporting own product, and concrete delivery pipe includes straight tube, bend pipe, conical pipe, flexible pipe, pipe joint and stop valve, to defeated The requirement for sending pipeline be resistance it is small, it is wear-resistant, from heavy and light, easily assembly and disassembly, the at present big portion of the concrete conveying pipe seen by us Point temperature can not be measured to its inside and be unable to waterproof anti-corrosion.
The content of the invention
The technical problems to be solved in the utility model is to overcome existing concrete conveyance conduit can not be to itself monitoring temperature A kind of the problem of degree and waterproof anti-corrosion, there is provided provisional bridge construction concrete conveying pipe.
In order to solve the above-mentioned technical problem, the utility model provides following technical scheme:
The utility model provides a kind of provisional bridge construction concrete conveying pipe, including straight tube, the straight tube Top is provided with inner-walls of duct, and the top of the straight tube is provided with wearing layer, and the top of the wearing layer is provided with waterproof layer, the waterproof The top of layer is provided with anticorrosive coat, and the surface of the straight tube is provided with non-return valve, and the side of the straight tube is provided with temperature measurer, the straight tube Bottom be provided with support frame, the bottom of support frame as described above is provided with the second fixing bolt, and the bottom of support frame as described above is provided with installing plate, The opposite side of the straight tube is provided with bend pipe, and the top of the bend pipe is provided with the second reinforcement, and the top of second reinforcement is set There is outer tube wall, the side of the bend pipe is provided with the first fixing bolt, and the temperature measurer is internally provided with display screen, the display screen Bottom be provided with power switch, the bottom of the power switch is provided with thermometric line, and the side of the thermometric line is provided with temperature probe.
As a kind of optimal technical scheme of the present utility model, the temperature probe is put into pipeline by the surface of straight tube It is interior.
As a kind of optimal technical scheme of the present utility model, the straight tube is set in the outside of the bend pipe.
As a kind of optimal technical scheme of the present utility model, the wearing layer is covered by ceramics or ceramic ring and formed.
As a kind of optimal technical scheme of the present utility model, the bend pipe and the straight tube are fixed by fixing bolt and connected Connect.
As a kind of optimal technical scheme of the present utility model, the wearing layer, the waterproof layer, the anticorrosive coat and pipe Road inwall is fixedly connected.
As a kind of optimal technical scheme of the present utility model, support frame as described above and the installing plate fix spiral shell by second Bolt is fixed, and the surface of support frame as described above is provided with pipe sleeve.
The beneficial effect that the utility model is reached is:The utility model can measure concrete by setting temperature measurer Internal temperature, surface temperature of concrete is monitored, prevents to solidify, by setting non-return valve and waterproof layer, coagulation can be prevented Soil flows back and prevents the water of pipeline external from penetrating into portion, while prevents concrete from flowing out, and whole device is reasonable in design, user Just, real-time protection effectively is carried out to its pipeline, improves practicality.
Brief description of the drawings
Accompanying drawing is used for providing further understanding to of the present utility model, and a part for constitution instruction, with this practicality New embodiment is used to explain the utility model together, does not form to limitation of the present utility model.In the accompanying drawings:
Fig. 1 is overall structure diagram of the present utility model;
Fig. 2 is partial structural diagram of the present utility model;
In figure:1st, straight tube;2nd, wearing layer;3rd, waterproof layer;4th, anticorrosive coat;5th, non-return valve;6th, the first fixing bolt;7th, it is curved Pipe;8th, reinforcement;9th, outer tube wall;10th, support frame;11st, installing plate;12nd, temperature measurer;13rd, the second fixing bolt;14th, in pipeline Wall;15th, display screen;16th, power switch;17th, thermometric line;18th, temperature probe.
Embodiment
Preferred embodiment of the present utility model is illustrated below in conjunction with accompanying drawing, it will be appreciated that described herein excellent Select embodiment to be merely to illustrate and explain the utility model, be not used to limit the utility model.
Embodiment 1
As shown in Figure 1-2, the utility model provides a kind of provisional bridge construction concrete conveying pipe, including straight tube 1, the top of straight tube 1 is provided with inner-walls of duct 14, and the top of inner-walls of duct 14 is provided with wearing layer 2, and the top of wearing layer 2 is provided with waterproof Layer 3, the top of waterproof layer 3 is provided with anticorrosive coat 4, and the surface of straight tube 1 is provided with non-return valve 5, and the side of straight tube 1 is provided with temperature measurer 12, The bottom of straight tube 1 is provided with support frame 10, and the bottom of support frame 10 is provided with the second fixing bolt 13, and the bottom of support frame 10 is provided with peace Loading board 11, the opposite side of straight tube 1 are provided with bend pipe 7, and the top of bend pipe 7 is provided with reinforcement 8, and the top of reinforcement 8 is provided with outer tube wall 9, the side of bend pipe 7 is provided with the first fixing bolt 6, and temperature measurer 12 is internally provided with display screen 15, and the bottom of display screen 15 is provided with Power switch 16, the bottom of power switch 16 are provided with thermometric line 17, and the side of thermometric line 17 is provided with temperature probe 18.
Temperature probe 18 is put into pipeline by the surface of straight tube 1.
Straight tube 1 is set in the outside of bend pipe 7.
Wearing layer 2 is covered by ceramics or ceramic ring and formed, and the non-conductor of heat, can prevent concrete setting when ceramic.
Bend pipe 7 is fixedly connected with straight tube 1 by fixing bolt 6.
Wearing layer 2, waterproof layer 3, anticorrosive coat 4 are fixedly connected with inner-walls of duct 14.
Bridge construction concrete conveying pipe, it is characterised in that support frame 10 and installing plate 11 pass through second and fix spiral shell Bolt 13 is fixed, and the surface of support frame 10 is provided with pipe sleeve.
The device is a kind of provisional bridge construction concrete conveying pipe, including straight tube 1, by being set on straight tube 1 Inner-walls of duct 14, wearing layer 2, waterproof layer 3 and anticorrosive coat 4, wearing layer 2 covers by ceramics or ceramic ring and formed, heat when ceramic Non-conductor, concrete setting can be prevented, by setting non-return valve 5 to prevent the concrete inside pipeline from flowing back, passed through The side of straight tube 1 is set to obtain bend pipe 7, and bend pipe 7 and straight tube are connected by fixing bolt 6, by setting reinforcement 8 can to make Outer tube wall 9 can bear bigger load, and branch is played to pipeline by the support frame 10 and installing plate 11 that are set in the bottom of straight tube 1 Support acts on, and during temperature inside pipeline to be monitored, by pressing the power switch 16 on temperature measurer 12, can pass through thermometric line The temperature probe 18 of 17 one end, measured temperature is transferred on display screen 15, and it is observed in real time, prevents internal temperature Spend high or too low, pipeline breaking or damage can be caused.
The utility model can measure concrete internal temperature by setting temperature measurer, monitor surface temperature of concrete, Prevent to solidify, by setting non-return valve and waterproof layer, can prevent concrete from flowing back and prevent the water of pipeline external from penetrating into To portion, while prevent concrete from flowing out, whole device is reasonable in design, easy to use, effectively carries out real-time protection to its pipeline, Improve practicality.
Finally it should be noted that:Preferred embodiment of the present utility model is the foregoing is only, is not limited to this Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art For, it can still modify to the technical scheme described in foregoing embodiments, or to which part technical characteristic Carry out equivalent substitution.All any modification, equivalent substitution and improvements within the spirit and principles of the utility model, made etc., It should be included within the scope of protection of the utility model.

Claims (7)

1. a kind of provisional bridge construction concrete conveying pipe, including straight tube(1), it is characterised in that the straight tube(1)'s Top is provided with inner-walls of duct(14), the inner-walls of duct(14)Top be provided with wearing layer(2), the wearing layer(2)Top Provided with waterproof layer(3), the waterproof layer(3)Top be provided with anticorrosive coat(4), the straight tube(1)Surface be provided with non-return valve (5), the straight tube(1)Side be provided with temperature measurer(12), the straight tube(1)Bottom be provided with support frame(10), the support Frame(10)Bottom be provided with the second fixing bolt(13), support frame as described above(10)Bottom be provided with installing plate(11), the straight tube (1)Opposite side be provided with bend pipe(7), the bend pipe(7)Top set reinforcement(8), the reinforcement(8)Top be provided with it is outer Tube wall(9), the bend pipe(7)Side be provided with the first fixing bolt(6), the temperature measurer(12)It is internally provided with display screen (15), the display screen(15)Bottom be provided with power switch(16), the power switch(16)Bottom be provided with thermometric line (17), the thermometric line(17)Side be provided with temperature probe(18).
A kind of 2. provisional bridge construction concrete conveying pipe according to claim 1, it is characterised in that the survey Temperature probe(18)Pass through straight tube(1)Surface be put into pipeline.
3. a kind of provisional bridge construction concrete conveying pipe according to claim 1, it is characterised in that described straight Pipe(1)It is set in the bend pipe(7)Outside.
4. a kind of provisional bridge construction concrete conveying pipe according to claim 1, it is characterised in that described resistance to Grind layer(2)Covered and formed by ceramics or ceramic ring.
5. a kind of provisional bridge construction concrete conveying pipe according to claim 1, it is characterised in that described curved Pipe(7)With the straight tube(1)Pass through fixing bolt(6)It is fixedly connected.
6. a kind of provisional bridge construction concrete conveying pipe according to claim 1, it is characterised in that described resistance to Grind layer(2), the waterproof layer(3), the anticorrosive coat(4)And inner-walls of duct(14)It is fixedly connected.
A kind of 7. provisional bridge construction concrete conveying pipe according to claim 1, it is characterised in that the branch Support(10)With the installing plate(11)Pass through the second fixing bolt(13)It is fixed, support frame as described above(10)Surface be provided with pipe Set.
CN201720411271.5U 2017-04-19 2017-04-19 A kind of provisional bridge construction concrete conveying pipe Expired - Fee Related CN206669224U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720411271.5U CN206669224U (en) 2017-04-19 2017-04-19 A kind of provisional bridge construction concrete conveying pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720411271.5U CN206669224U (en) 2017-04-19 2017-04-19 A kind of provisional bridge construction concrete conveying pipe

Publications (1)

Publication Number Publication Date
CN206669224U true CN206669224U (en) 2017-11-24

Family

ID=60375085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720411271.5U Expired - Fee Related CN206669224U (en) 2017-04-19 2017-04-19 A kind of provisional bridge construction concrete conveying pipe

Country Status (1)

Country Link
CN (1) CN206669224U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116254842A (en) * 2023-01-10 2023-06-13 桐乡市众磊混凝土股份有限公司 Concrete pumping equipment and pumping method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116254842A (en) * 2023-01-10 2023-06-13 桐乡市众磊混凝土股份有限公司 Concrete pumping equipment and pumping method thereof
CN116254842B (en) * 2023-01-10 2023-10-27 桐乡市众磊混凝土股份有限公司 Concrete pumping equipment and pumping method thereof

Similar Documents

Publication Publication Date Title
CN105114763B (en) Steam low energy consumption long distance delivery device
CN206669224U (en) A kind of provisional bridge construction concrete conveying pipe
CN207062988U (en) A kind of pipe gallery
CN208816844U (en) A kind of underground water seal cave depot Shaft bank pipe-supporting device
CN204112332U (en) A kind of cooling structure for concrete in mass inside
CN206625639U (en) A kind of electric pole
CN201464427U (en) Ultrasonic detection pipe of bridge foundation pile
CN209942155U (en) Support piece for connecting smoke exhaust pipeline
CN207421617U (en) A kind of heat-insulated bellows of service life length
CN105384048A (en) Pipeline lifting sling
CN105908956B (en) A kind of automatic spray apparatus of waterproof material
CN106088097B (en) Construction method and fog chute device for delivering concrete under gentle slope and abrupt slope
CN107036588A (en) Tunnel surrounding rock displacement monitors point equipment
CN107152026B (en) A kind of the mud jacking pipe support and its distribution method of steel-pipe pile
CN207961770U (en) A kind of novel drainage pipe
CN207959740U (en) A kind of greenhouse air blowing type full width snow removing equipment
CN208201942U (en) Rubber fastening band stationary fixture
CN207179021U (en) A kind of antifreeze fireproof petroleum transportation pipe
CN207332940U (en) Constructing tunnel geomantic omen arrangement structure for pipelines
CN207421523U (en) Architectural design pipeline fixing device
CN106522267B (en) The steel of underground pipe gallery feeds intake chamber structure
CN206054944U (en) A kind of long distance pipeline River Crossing vertical shaft pipelines support
CN210395582U (en) Cement culvert pipe for chemical wastewater discharge
CN219082593U (en) Steel sleeve of inner and outer steel sleeve heating rings
CN219933219U (en) Concrete conveying device for mountain area complex terrain

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171124

Termination date: 20180419

CF01 Termination of patent right due to non-payment of annual fee