CN206668275U - A kind of subsurface excavation method Pipe rack - Google Patents

A kind of subsurface excavation method Pipe rack Download PDF

Info

Publication number
CN206668275U
CN206668275U CN201720348456.6U CN201720348456U CN206668275U CN 206668275 U CN206668275 U CN 206668275U CN 201720348456 U CN201720348456 U CN 201720348456U CN 206668275 U CN206668275 U CN 206668275U
Authority
CN
China
Prior art keywords
piping lane
main body
excavation method
subsurface excavation
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720348456.6U
Other languages
Chinese (zh)
Inventor
王星星
宋晓翔
章华东
陈少兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiamen Co Ltd Of Zhong Ping Highway Survey And Design Institute
Original Assignee
Xiamen Co Ltd Of Zhong Ping Highway Survey And Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiamen Co Ltd Of Zhong Ping Highway Survey And Design Institute filed Critical Xiamen Co Ltd Of Zhong Ping Highway Survey And Design Institute
Priority to CN201720348456.6U priority Critical patent/CN206668275U/en
Application granted granted Critical
Publication of CN206668275U publication Critical patent/CN206668275U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

It the utility model is related to underground pipe gallery field, disclose a kind of new subsurface excavation method Pipe rack, include piping lane main body, support column, support beam, supporting plate, let, detachable piping lane support and ventilation equipment, piping lane main body uses rebuilding, by to subsurface excavation method piping lane Section Design research, on the premise of piping lane function, easy access and installation is ensured, it is proposed optimal section arrangement, its arrangement can further adjust in space according to needed for all kinds of pipelines, and subsurface excavation method pipe gallery is small on surrounding enviroment destruction and does not influence traffic.

Description

A kind of subsurface excavation method Pipe rack
Technical field
Urban construction field is the utility model is related to, particularly a kind of subsurface excavation method Pipe rack.
Background technology
With the fast development of Modernized City Construction, the various number of lines of Urban Underground are more and more, planning and designing Become increasingly complex, pipe gallery is present among urban construction as a kind of very important civilian infrastructure.Integrated pipe Corridor has huge in the maintenance management of various underground utilities, resistance natural calamity and raising underground space utilization rate etc. Advantage.
At present, the city integrated piping lane in China mainly secretly buries method or pipe jacking method using open cut, and method construction is secretly buried in open cut Piping lane be primarily adapted for use in the shallow location of buried depth, the piping lane of pipe jacking method is primarily adapted for use in the short location of tunneling paragraph.But Run into that buried depth is big, the location of tunneling paragraph length can not use above-mentioned engineering method.
The content of the invention
The purpose of this utility model is to provide a kind of subsurface excavation method Pipe rack, by being ground to subsurface excavation method piping lane Section Design Study carefully, ensure piping lane function, just with maintenance and installation on the premise of, propose optimal section arrangement.
To realize above-mentioned technical purpose and the technique effect, the utility model discloses a kind of subsurface excavation method piping lane knot Structure, include piping lane main body, support column, support beam, supporting plate, let, detachable piping lane support and ventilation equipment, manage Corridor main body uses rebuilding, and bottom both sides are provided with sewage pressure pipe and corresponding cement substrate, and left upper portion passes through support Post, support beam and setting up for supporting plate are provided with feed pipe and corresponding cement substrate, and right upper portion is provided with detachable piping lane branch Frame, ventilation equipment are installed on the center of top of piping lane main body, and let is arranged at the lower surface of piping lane main body.
Wherein, support column is as bottom force structure, is reinforced concrete structure, 30 × 30cm of sectional dimension, at interval of At 5m arrangements one, support beam is reinforced concrete structure as top force structure, longitudinally arranged, in bracket type, supporting plate It is reinforced concrete structure for top force structure, thickness of slab 20cm.
Wherein, let is used to collect surface gathered water and rinse water, and the cross-section of river is 30 × 30cm, let Upper surface is provided with reinforced concrete cover plate.
Preferably, weeper drain is also included, the bottom that weeper drain is arranged at piping lane main body is used to collect lining cutting behind Crevice water, cross-section of river diameter 40cm.
The utility model has the advantages that:
1. the utility model is by subsurface excavation method piping lane Section Design research, ensureing piping lane function, easy access and peace On the premise of dress, optimal section arrangement is proposed, its arrangement can further adjust in space according to needed for all kinds of pipelines, and secretly Digging method pipe gallery is small on surrounding enviroment destruction and does not influence traffic.
2. by the subsurface excavation method piping lane section rationally designed, see that the new technology is drawn by the actual operating result of case history The tunneling section structure entered is buried depth is big, has its unique advantage, its construction investment, environmental protection in the piping lane engineering of piping lane length And traffic support etc. has its superiority.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Critical piece symbol description:
1:Piping lane main body, 2:Support column, 3:Support beam, 4:Supporting plate, 5:Let, 6:Weeper drain, 7:It is removable Unload piping lane support, 8:Sewage pressure pipe, 9:Feed pipe, 10:Cement substrate, 11:Ventilation equipment.
Embodiment
In order that the purpose of this utility model, technical scheme and advantage are more clearly understood, below in conjunction with accompanying drawing and implementation Example, the utility model is further elaborated.
As shown in figure 1, the utility model discloses a kind of subsurface excavation method Pipe rack, include piping lane main body 1, support column 2, Support beam 3, supporting plate 4, let 5, weeper drain 6, detachable piping lane support 7 and ventilation equipment 11, piping lane main body 1 are adopted With rebuilding, bottom both sides are provided with sewage pressure pipe 8 and corresponding cement substrate 9, and left upper portion passes through support column 2, branch The setting up of support beam 3 and supporting plate 4 is provided with feed pipe 9 and corresponding cement substrate 10, right upper portion are provided with detachable piping lane branch Frame 7, ventilation equipment 11 are installed on the center of top of piping lane main body 1, and let 5 is arranged at the lower surface of piping lane main body 1, row The bottom that water french drain 6 is arranged at piping lane main body 1 is used to collect lining cutting behind crevice water, cross-section of river diameter 40cm.
Support column 2 is used as bottom force structure, is reinforced concrete structure, 30 × 30cm of sectional dimension, at interval of 5m cloth Put at one, support beam 3 is used as top force structure, is reinforced concrete structure, longitudinally arranged, in bracket type, supporting plate 4 is Top force structure, is reinforced concrete structure, thickness of slab 20cm.
Wherein, let 5 is used to collect surface gathered water and rinse water, and the cross-section of river is 30 × 30cm, road surface drainage The upper surface of ditch 5 is provided with reinforced concrete cover plate.
By research, tunneling pipe gallery track clearance is drafted according to duct size, installing space, and it is wide that 2.5m is laid in centre Maintenance and installation vehicle pass-through track, maintaining roadway clear height 3.5m.To improve tunneling piping lane scetion utilization, piping lane section is by bilayer Arrangement, the structure being combined using support column 2, support beam 3 and supporting plate 4.See that this is new by the actual operating result of case history The tunneling section structure that technology is introduced into is buried depth is big, has its unique advantage, its construction investment, ring in the piping lane engineering of piping lane length Border protection and traffic support etc. have its superiority.
It is described above, the only preferable embodiment of the utility model, but the scope of protection of the utility model is not This is confined to, any one skilled in the art can readily occur in the technical scope that the utility model discloses Change or replacement, should all cover within the scope of protection of the utility model.

Claims (4)

1. a kind of subsurface excavation method Pipe rack, it is characterised in that include piping lane main body, support column, support beam, supporting plate, road surface Gutter, detachable piping lane support and ventilation equipment, described piping lane main body use rebuilding, and bottom both sides are provided with sewage Pressure pipe and corresponding cement substrate, left upper portion by support column, support beam and supporting plate set up be provided with feed pipe and Corresponding cement substrate, right upper portion are provided with detachable piping lane support, and described ventilation equipment is installed on the top of piping lane main body Center, described let are arranged at the lower surface of piping lane main body.
A kind of 2. subsurface excavation method Pipe rack as claimed in claim 1, it is characterised in that:Described support column is as bottom stress Structure, it is reinforced concrete structure, 30 × 30cm of sectional dimension, at 5m arrangements one, described support beam is as top Force structure, it is reinforced concrete structure, longitudinally arranged, in bracket type, described supporting plate is top force structure, is steel Tendon concrete structure, thickness of slab 20cm.
A kind of 3. subsurface excavation method Pipe rack as claimed in claim 1, it is characterised in that:Described let is used to collect Surface gathered water and rinse water, the cross-section of river are 30 × 30cm, and let upper surface is provided with reinforced concrete cover plate.
A kind of 4. subsurface excavation method Pipe rack as claimed in claim 1, it is characterised in that:Also include weeper drain, it is described The bottom that weeper drain is arranged at piping lane main body is used to collect lining cutting behind crevice water, cross-section of river diameter 40cm.
CN201720348456.6U 2017-04-05 2017-04-05 A kind of subsurface excavation method Pipe rack Active CN206668275U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720348456.6U CN206668275U (en) 2017-04-05 2017-04-05 A kind of subsurface excavation method Pipe rack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720348456.6U CN206668275U (en) 2017-04-05 2017-04-05 A kind of subsurface excavation method Pipe rack

Publications (1)

Publication Number Publication Date
CN206668275U true CN206668275U (en) 2017-11-24

Family

ID=60366720

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720348456.6U Active CN206668275U (en) 2017-04-05 2017-04-05 A kind of subsurface excavation method Pipe rack

Country Status (1)

Country Link
CN (1) CN206668275U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518542A (en) * 2018-11-26 2019-03-26 中铁四院集团西南勘察设计有限公司 A kind of track traffic synthetic pipe trench service pit structure and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518542A (en) * 2018-11-26 2019-03-26 中铁四院集团西南勘察设计有限公司 A kind of track traffic synthetic pipe trench service pit structure and construction method

Similar Documents

Publication Publication Date Title
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN102654055A (en) Construction method for compound construction of large-scale underground space structure by holes, groove and piles
CN205776249U (en) A kind of combined inner supporting structure
CN102704957A (en) Shed-frame method for shallowly burying large-sized underground structure construction
CN109868838B (en) A kind of rail traffic of underground utilities close quarters is without column station construction method
CN105972313B (en) One kind is across base pit engineering conduit wiring suspension method and overhung construction
CN104631466A (en) Construction method of structural system with structural floors as horizontal braces
Faustin et al. Case studies of circular shaft construction in London
CN104343131A (en) Semi-prefabricated semi-cast-in-situ underground continuous wall and construction process
CN110004935A (en) A kind of locally deep pit drain measure trench system and construction method
CN105421461A (en) Excavation method of building foundation pit adjacent to existing tunnel under soil-rock geological condition
CN107514262A (en) The construction method of shield piping lane
CN111139837A (en) Method for simultaneously excavating multiple base pits at crossed subway in soft soil area
Yao et al. Numerical analysis of the influence of isolation piles in metro tunnel construction of adjacent buildings
CN206668275U (en) A kind of subsurface excavation method Pipe rack
CN211922135U (en) Prevent subsiding highway subgrade
CN207176700U (en) A kind of solid matter perfusion inner support of pile foundation ditch permanent support structure under complex environment
CN204456131U (en) A kind of structural floor that utilizes is as the structural system of horizontal support
Song et al. The overall design of Qingdao Jiaozhou Bay subsea tunnel
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN209760299U (en) light and shade of avoiding house to tear open and move is dug and is combined subway station structure
CN208668202U (en) A kind of sponge city square paving structure based on earthen ruins protection
CN104793262B (en) A kind of monitoring method of strata division displacement
CN208815560U (en) A kind of structure of Underground Subway Station construction period full station sealing
CN108978679A (en) A kind of method that cable tunnel is constructed in high water level region

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant