CN108978679A - A kind of method that cable tunnel is constructed in high water level region - Google Patents

A kind of method that cable tunnel is constructed in high water level region Download PDF

Info

Publication number
CN108978679A
CN108978679A CN201810726366.5A CN201810726366A CN108978679A CN 108978679 A CN108978679 A CN 108978679A CN 201810726366 A CN201810726366 A CN 201810726366A CN 108978679 A CN108978679 A CN 108978679A
Authority
CN
China
Prior art keywords
cable tunnel
water level
construction
water
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810726366.5A
Other languages
Chinese (zh)
Inventor
周康杰
张俊禄
刘炜
张红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Taigang Stainless Steel Co Ltd
Original Assignee
Shanxi Taigang Stainless Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Taigang Stainless Steel Co Ltd filed Critical Shanxi Taigang Stainless Steel Co Ltd
Priority to CN201810726366.5A priority Critical patent/CN108978679A/en
Publication of CN108978679A publication Critical patent/CN108978679A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water

Abstract

A kind of method that cable tunnel is constructed in high water level region, belong to field of engineering building, solve the technical issues of local ponding influences construction quality and progress in the construction of high water level region, solution is the following steps are included: a, determine high water level region construction location, the height of water level for detecting water table at construction location designs the laying height of cable tunnel under a subterranean formation according to actual condition;B, it excavates: pumping conduit being installed in the groove of excavation;C, it rockfills: stone layer is backfilled in the groove of excavation;D, cable tunnel construction operation, pumping conduit persistently draws water during cable tunnel construction operation;E, pumping conduit is removed, checks cable tunnel leakage scenarios;F, backfill can load-bearing water penetration stone layer until water table water level line more than, backfill complete.Present invention construction is easy, easy to operate, can well solve high water level region conduit line construction problem, guarantees construction quality and project progress.

Description

A kind of method that cable tunnel is constructed in high water level region
Technical field
The invention belongs to field of engineering building, in particular to side that a kind of cable tunnel is constructed in high water level region Method.
Background technique
Because cable duct, cable tunnel lamp are in high water level region is constructed, there are newly-built construction of structures position is lower, after excavation Water level is higher, the case where can not constructing, and needs the operation of precipitation position.But since underground water belongs to slow infiltration type, if in construction not into Capable processing of drawing water, easily causes local ponding, influences construction quality and progress.
Summary of the invention
In order to overcome the shortcomings of the prior art, solves cable duct, cable tunnel etc. and deposited in the construction of high water level region Construction of structures it is lower, water level is higher after excavation, the case where can not constructing, and local ponding influences the skill of construction quality and progress Art problem provides a kind of method that cable tunnel is constructed in high water level region.
Technical solution of the present invention and design are as follows: use and dig deep working space, be laid with the stone of good water permeability, drop It water and builds the method that tunnel carries out simultaneously, guarantees that the water-impervious measures such as built cable tunnel are good, tape cable tunnel construction is complete Cheng Hou, then withdraw the interim of reduction water level and use water pump.
The present invention is achieved by the following technical programs.
A kind of method that cable tunnel is constructed in high water level region, comprising the following steps:
A, it determines high water level region construction location, detects the height of water level of water table at construction location, set according to actual condition Count the laying height of cable tunnel under a subterranean formation;
B, excavate: to groove is excavated at construction location, groove digs deep the distance between the cable tunnel bottom plate with step a design Not less than 500mm, pumping conduit is installed in the groove of excavation;
C, it rockfills: stone layer is backfilled in the groove of excavation, until stone layer is backfilled to the cable tunnel bottom plate of step a design At height, wherein the height of cable tunnel bottom plate is higher than the height of water level of water table;
D, cable tunnel construction operation, pumping conduit persistently draws water during cable tunnel construction operation;
E, pumping conduit is removed, the level of ground water of water table is gone up, and checks cable tunnel leakage scenarios;
F, backfill can load-bearing water penetration stone layer until water table water level line more than, backfill complete;
G, it in the top of water penetration stone layer, needs to backfill corresponding soil property according to site operation, completes cable tunnel in Gao Shui Position region construction operation.
Further, drawing water for pumping conduit a little avoids the construction access road of cable tunnel in the step b, and drinking-water pipe The end in road is placed in the point for excavating that topography is minimum in groove.
Compared with prior art the invention has the benefit that
Present invention construction is easy, easy to operate, can well solve high water level region conduit line construction problem, guarantees construction Quality and project progress.
Detailed description of the invention
Fig. 1 is step a status diagram of the present invention, and dotted line is the position of the cable tunnel designed according to actual condition in figure It sets.
Fig. 2 is step b status diagram of the present invention.
Fig. 3 is step c status diagram of the present invention.
Fig. 4 is step d status diagram of the present invention.
Fig. 5 is step e status diagram of the present invention.
Fig. 6 is step f status diagram of the present invention.
In figure, 1 is stratum, and 2 be water table, and 3 be groove, and 4 be pumping conduit, and 5 be stone layer, and 6 be cable tunnel, 7 For water penetration stone layer.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
The method that a kind of cable tunnel as shown in Figures 1 to 6 is constructed in high water level region, comprising the following steps:
A, it determines high water level region construction location, detects the height of water level of water table 2 at construction location, set according to actual condition Count laying height of the cable tunnel 6 under stratum 1;
B, it excavates: to excavation groove 3 at construction location, between 6 bottom plate of cable tunnel that the digging depth and step a of groove 3 design Distance is not less than 500mm, and pumping conduit 4 is installed in the groove 3 of excavation;
C, it rockfills: stone layer 5 is backfilled in the groove 3 of excavation, until stone layer 5 is backfilled to the cable tunnel 6 of step a design Floor level, wherein the height of 6 bottom plate of cable tunnel is higher than the height of water level of water table 2;
D, 6 construction operation of cable tunnel, pumping conduit 4 persistently draws water during 6 construction operation of cable tunnel;
E, pumping conduit 4 is removed, the level of ground water of water table 2 is gone up, and checks 6 leakage scenarios of cable tunnel;
F, backfill can load-bearing water penetration stone layer 7 until water table 2 water level line more than, backfill complete;
G, in the top of water penetration stone layer 7, according to site operation needs, (road surfacing pitch or Pavement Design are greening Band etc.) the corresponding soil property of backfill, cable tunnel is completed in high water level region construction operation.What the water penetration stone layer 7 used Stone is the railway ballast stone that track is paved the way with 16-63mm, thickness >=300mm of water penetration stone layer 7.
Further, drawing water for pumping conduit 4 a little avoids the construction access road of cable tunnel 6 in the step b, and draws water The end of pipeline 4 is placed in the point for excavating that topography is minimum in groove 3.
In the raw material plant on-site cable tunnel 110kV to be laid in the present embodiment, whole path is arranged by north orientation south, part Existing road is occupied, partially in greenbelt (shrub).The height distance ground of level of ground water is found only when excavating groove 3 800mm, and clear height 2100mm, top plate thickness 200mm in the cable tunnel 6 designed, need arrangement of reinforcement, tunnel outer top panel is apart from ground 500mm is constructed using common laying method, and groundwater mining is time-consuming and laborious, and cable tunnel is laid with cost and virtually improves;Electricity Clear span 1500mm in cable tunnel 6, sidewall thickness 200mm need arrangement of reinforcement, tunnel floor thickness 150mm, 6 bottom cushion of cable tunnel 300mm.The depth 3500mm of groove 3, the wide 2500mm in bottom, two sides punching block slab supporting, the gradient≤75 ° of groove 3.
It is constructed using method provided by the invention, in work progress, using deep working space is dug, is laid with good water permeability Stone, precipitation and build the method that tunnel carries out simultaneously, carry out cable tunnel water-impervious measure, tape cable tunnel construction is completed Afterwards, then withdraw the interim construction method with water pump for reducing water level, construction finishes, tunnel two sides stone layer height water level line with On, finally restore original road and greening.Operational effect is good after implementation.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any It is familiar with those skilled in the art in the technical scope disclosed by the present invention, any changes or substitutions that can be easily thought of, should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (2)

1. a kind of method that cable tunnel is constructed in high water level region, it is characterised in that the following steps are included:
A, it determines high water level region construction location, the height of water level of water table (2) at construction location is detected, according to actual condition Design the laying height of cable tunnel (6) under stratum (1);
B, it excavates: excavating groove (3) at construction location, deep cable tunnel (6) bottom plate with step a design of the digging of groove (3) The distance between be not less than 500mm, excavation groove (3) in install pumping conduit (4);
C, it rockfills: stone layer (5) is backfilled in the groove (3) into excavation, until stone layer (5) are backfilled to the electricity of step a design Cable tunnel (6) floor level, wherein the height of cable tunnel (6) bottom plate is higher than the height of water level of water table (2);
D, cable tunnel (6) construction operation, pumping conduit (4) persistently draws water during cable tunnel (6) construction operation;
E, it removes pumping conduit (4), the level of ground water of water table (2) is gone up, and checks cable tunnel (6) leakage scenarios;
F, backfill can load-bearing water penetration stone layer (7) until water table (2) water level line more than, backfill complete;
G, it in the top of water penetration stone layer (7), needs to backfill corresponding soil property according to site operation, completes cable tunnel in height Water level region construction operation.
2. the method that a kind of cable tunnel according to claim 1 is constructed in high water level region, it is characterised in that: the step Drawing water for pumping conduit (4) a little avoids the construction access road of cable tunnel (6) in rapid b, and the end of pumping conduit (4) is placed in Excavate the minimum point of groove (3) interior topography.
CN201810726366.5A 2018-07-04 2018-07-04 A kind of method that cable tunnel is constructed in high water level region Pending CN108978679A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810726366.5A CN108978679A (en) 2018-07-04 2018-07-04 A kind of method that cable tunnel is constructed in high water level region

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810726366.5A CN108978679A (en) 2018-07-04 2018-07-04 A kind of method that cable tunnel is constructed in high water level region

Publications (1)

Publication Number Publication Date
CN108978679A true CN108978679A (en) 2018-12-11

Family

ID=64536956

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810726366.5A Pending CN108978679A (en) 2018-07-04 2018-07-04 A kind of method that cable tunnel is constructed in high water level region

Country Status (1)

Country Link
CN (1) CN108978679A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886305A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Foundation pit water burst layered backfilling and plugging method based on protection karst water channel
CN110886308A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Rapid frozen groundwater plugging method based on protection karst water channel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0465932B2 (en) * 1987-11-06 1992-10-21 Toa Harbor Works Co Ltd
CN201770986U (en) * 2010-08-06 2011-03-23 云南白药集团股份有限公司 Structure for embedding outdoor process pipeline
CN103821525A (en) * 2014-03-10 2014-05-28 山西太钢不锈钢股份有限公司 Cable tunnel rapid construction method in high water level geological condition
CN107587557A (en) * 2017-09-27 2018-01-16 广东景源建设工程有限公司 Outdoor water engineering construction method
CN108149698A (en) * 2016-12-06 2018-06-12 吴方华 Guiding solid drainage and construction method and system inside a kind of airport high fill foundation

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0465932B2 (en) * 1987-11-06 1992-10-21 Toa Harbor Works Co Ltd
CN201770986U (en) * 2010-08-06 2011-03-23 云南白药集团股份有限公司 Structure for embedding outdoor process pipeline
CN103821525A (en) * 2014-03-10 2014-05-28 山西太钢不锈钢股份有限公司 Cable tunnel rapid construction method in high water level geological condition
CN108149698A (en) * 2016-12-06 2018-06-12 吴方华 Guiding solid drainage and construction method and system inside a kind of airport high fill foundation
CN107587557A (en) * 2017-09-27 2018-01-16 广东景源建设工程有限公司 Outdoor water engineering construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110886305A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Foundation pit water burst layered backfilling and plugging method based on protection karst water channel
CN110886308A (en) * 2019-11-08 2020-03-17 济南轨道交通集团有限公司 Rapid frozen groundwater plugging method based on protection karst water channel

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN102080548B (en) Construction method of tunnel to cross airport runway by shield method
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN203174616U (en) Clay foundation rain falling and water saving system
CN103993603A (en) Top-down construction method for anchor rod and rotary jet grouting back cover deep foundation pit without precipitation operation
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN107151950A (en) The construction method of desert area railway underground water route moat
CN206175812U (en) Powder sandy soil stratum push pipe construction structures based on steel bushing head instrument pipe
CN101718100B (en) Underground complex integrally co-constructed implementation design method
CN109469042B (en) Anti-seepage storage yard field karst cave processing structure
CN108978679A (en) A kind of method that cable tunnel is constructed in high water level region
CN214194602U (en) Precipitation structure suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN112609720A (en) Precipitation construction method suitable for deep foundation pit of high-pressure-bearing water-rich karst stratum
CN103276717B (en) The method of composite earthwork synthetic materials reinforcement cushion soft soil foundation
CN108755697A (en) Long and narrow deep foundation pit earthwork digging method under a kind of rainy weather
CN112983461A (en) Construction method for bias tunnel portal in slope volume
CN208293588U (en) A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages
CN106869165A (en) City integrated prefabricated piping lane open cut formula is from construction of prevention work method and self-propelled laydown machine
CN207828994U (en) It is a kind of draining and recharge constructing structure
CN216275788U (en) Drainage device used after failure of water interception curtain of deep foundation pit
CN109119943A (en) System of laying optimization method of the cable at push pipe both ends
CN204435321U (en) A kind of steam power station water intaking open channel
CN110792440B (en) Construction method of water-rich loess tunnel penetrating through loess towards valley
CN103774698B (en) Soil engineering drainage-free construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211

RJ01 Rejection of invention patent application after publication