CN206646634U - Assemble prefabricated components formula house - Google Patents

Assemble prefabricated components formula house Download PDF

Info

Publication number
CN206646634U
CN206646634U CN201621217121.2U CN201621217121U CN206646634U CN 206646634 U CN206646634 U CN 206646634U CN 201621217121 U CN201621217121 U CN 201621217121U CN 206646634 U CN206646634 U CN 206646634U
Authority
CN
China
Prior art keywords
wallboard
prefabricated
directions
slot type
formula
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621217121.2U
Other languages
Chinese (zh)
Inventor
邓国付
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201621217121.2U priority Critical patent/CN206646634U/en
Application granted granted Critical
Publication of CN206646634U publication Critical patent/CN206646634U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses one kind assembling prefabricated components formula house, and it includes house foundation collar tie beam, the fluted formula structural column in four directions, prefabricated crossbeam, wallboard, floor, staircase boards, slot type connection section bar, the installation of wire casing and line box;The fluted formula structural column in four directions is built on foundation ring girder;Wallboard transverse side is placed in structure intercolumniation, is fixed at door, window box out with " U ", " H ", " L " shape slot type connection section bar;Prefabricated crossbeam is placed on wallboard, between structural column, and floor is placed on prefabricated crossbeam, between Liang Yuliang, Liang Yuzhu, beam and plate, cast-in-place collar tie beam, ensures its structure bonding strength globality.The utility model provides a kind of construction of assembling prefabricated components formula house and its installation method, has the characteristics of simple in construction, convenient transportation, prefabricated component factorial praluction, installation is quick, structural strength is high, versatile.

Description

Assemble prefabricated components formula house
Technical field
It the utility model is related to field of house buildings, more particularly to a kind of assembled monolithic concrete structure house.
Background technology
For a long time, people use brick mix structure in building construction more, in recent years, because to the natural calamity such as antiseismic, Use frame structure more.In building, builder's labor intensity is big, and low production efficiency, speed of application is slow, construction period length, High material consumption, scene stir up a cloud of dust, and generate flood tide building waste and have a strong impact on environment with gray haze, traditional building, which is needed badly, to be changed Leather, and emerging assembled house is mostly iron sheet movable plank house, and service life is low, poor insulativity, and this just needs one kind badly can be Factory mass produces, and convenient transportation, the prefabricated buildings that easily assembled, service life is long, intensity is high and safe and reliable.Cause This, adapting to building industry, " masses start an undertaking, millions of people innovation!" needs, new approaches must be started, use new technology build room Room.
The content of the invention
The purpose of the utility model is to overcome the deficiencies in the prior art, there is provided a kind of simple in construction, convenient transportation, installation are fast The assembling prefabricated components formula house fast, elegant in appearance, green, bonding strength is good and its installation method.
The utility model is implemented by following technical scheme:Prefabricated components formula house is assembled, it includes house foundation collar tie beam, and four The fluted formula structural column in side, prefabricated crossbeam, wallboard, floor, staircase boards, slot type connection section bar, the installation of wire casing and line box;House Pre-buried dowel on foundation ring girder, the fluted formula structural column in four directions are built on house foundation collar tie beam;Wallboard transverse side is laid Between corresponding cubic fluted formula structural column, wallboard faying surface is uniformly wiped with lean concrete grout;Prefabricated crossbeam is given birth in factory Simultaneously reserving rib and stirrup are produced, is placed between wallboard upper strata and corresponding cubic fluted formula structural column, reserved stirrup faces On;Between prefabricated crossbeam and prefabricated crossbeam, the fluted formula structural column of prefabricated crossbeam and four directions, overlap joint is welded or tied up between reserving rib The connection method of bundle, and cast-in-place concrete, ensure its structure bonding strength globality;Floor is empty for the prestressing force of " work " printed words formula Heart prefabricated board, and both ends reserving rib, floor level, which is taken, to be placed on prefabricated crossbeam;Between floor and floor, floor both ends and prefabricated horizontal stroke In indentation pattern and interconnected, the cast-in-situ steel reinforced concrete collar tie beam in groove between beam;The fluted formula structural column in four directions, prefabricated horizontal stroke Beam sides protrudes from wallboard, in frame-like formula house;Staircase boards segmentation is set up, and staircase boards both ends reserving rib, platen muscle of having a rest need Colligation connects, and cast-in-place concrete;Reserved door opening must be at the collar tie beam positioning on the outside of, punch and " U " be installed or the connection of " L " shape slot type Section bar, and it is firmly erected just, wallboard is placed between the fluted formula structural column in four directions and " U " or " L " shape slot type connection section bar, Reserve door opening;Reserved window opening at the bottom positioning of wallboard window on the outside of, lay " H " shape slot type connection section bar, wallboard be placed in four directions Between fluted formula structural column and " H " shape slot type connection section bar groove, window opening is reserved;Wire casing lays a point vertical and transverse direction, vertically Wire casing is arranged on the angle of wallboard and structural column, and horizontal wire casing is connected up using the build-in cavities of wallboard, vertical wire casing and transverse direction Wire casing overlapping must perforate connection;Line box installation place cuts correspondingly sized hole using cutting machine on wallboard, for line box Installation.
The house foundation collar tie beam, the pre-buried dowel of foundation ring girder palpus, and shaped with stirrup colligation, and unwrapping wire in the above With positioning.
The fluted formula structural column in four directions, using shaper formwork, the four directions of post is reserved fluted, cast in place reinforced bar and mixed Solidifying soil;Reserved recess width is slightly wider than wallboard;The planform of post is square column or cylinder;Right angle or fillet are divided in the corner of post.
The prefabricated crossbeam, prefabrication production, both ends reserving rib, surface layer reserve stirrup;The corner of prefabricated crossbeam is straight Angle or fillet.
The wallboard, is pre-stress hollow prefabricated board, double-layer rib, and cross section is smooth.
The floor, it is " work " pattern pre-stress hollow prefabricated board, is furnished with double steel bar and both ends reserving rib.
The staircase boards, it is board-like precast hollow staircase boards, prefabrication production, step inner chamber is hollow, and both ends are double-deck pre- Stay muscle.
The slot type connection section bar, metal system " U ", " H ", " L " shape, groove inboard width are slightly wider than wallboard, and " U " shape slot type connects Direct type material is made using channel-section steel, and multiple eyelets are opened in bottom, is fixed and is used for oncomelania bolt;" H " shape slot type connection section bar uses " work " Word steel make;" L " shape slot type connection section bar, makes of channel-section steel, and multiple eyelets are opened in bottom, fixes and uses for oncomelania bolt.
The installation of the wire casing and line box, laying point for wire casing is vertical and laterally, and vertical wire casing is arranged on wallboard and post Angle, horizontal wire casing are connected up using the build-in cavities of wallboard;Line box installation place is cut accordingly greatly with cutting machine on wallboard Hole, install line box.
Assembling prefabricated components formula house provided by the utility model, suitable for field of house buildings, its prefabricated component and Connection section bar is prefabricated in advance in factory, structural column, prefabricated crossbeam and prefabricated crossbeam connection, floor and floor connection, floor It is connected with prefabricated crossbeam, cast-in-situ steel reinforced concrete collar tie beam, it is more firm, globality is stronger;Job site can be according to the reality of client Border needs independent assortment to be built into the house type building construction different with style;Crane gear is used during installation, is reduced labor intensity, Construction speed is faster;Assemble prefabricated components formula house convenient transportation, easily assembled, heat-insulated, service life is long, intensity is high and safety can Lean on.
Brief description of the drawings
The utility model is further illustrated with reference to the accompanying drawings and examples.
Fig. 1 is:The square column plan of the fluted formula structural column in utility model four directions;
Fig. 2 is:The cylindrical plane figure of the fluted formula structural column in utility model four directions;
Fig. 3 is:The placement elevation of utility model wallboard;
Fig. 4 is:Utility model " L " shape slot type connection section bar;
Fig. 5 is:Utility model " U " shape slot type connection section bar;
Fig. 6 is:Utility model " H " shape slot type connection section bar;
Fig. 7 is:Utility model floor and prefabricated crossbeam attachment structure plan (part);
Fig. 8 is:Utility model staircase boards side view;
Fig. 9 is:Utility model simple circuit wiring method figure;
Figure 10 is:The fluted formula structural column in utility model four directions and prefabricated crossbeam attachment structure plan (part);
Figure 11 is:Utility model floor front view;
Figure 12 is:Utility model wallboard front view;
Figure 13 is:Utility model prefabricated crossbeam front view;
Figure 14 is:Utility model assembling prefabricated components formula house front view (part);
Description of reference numerals:1- " H " shape slot type connection section bar;2- " U " shape slot type connection section bar;3- " L " shapes slot type connects Section bar;4- wallboards;The fluted formula structural column in 5- four directions;6- prefabricated crossbeams;7- floors;
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describe, it is clear that described embodiment is only part of the embodiment of the present invention, rather than whole implementation Example.Based on the embodiment in the utility model, those of ordinary skill in the art are obtained under the premise of creative work is not made The every other embodiment obtained, belong to the scope of the utility model protection.
The utility model is from unwrapping wire on house foundation collar tie beam and positions the fluted formula structural column in cast-in-place four directions, wallboard cross side Face is placed in the fluted formula structure intercolumniation in four directions, and prefabricated crossbeam is placed in above wallboard between the fluted formula structural column in four directions, building Plate is placed on prefabricated crossbeam, between Liang Yuliang, Liang Yuzhu, beam and plate, the overlap joint welding of reserving rib or the connection side of colligation Method, and cast-in-situ steel reinforced concrete, ensure its structure bonding strength globality;The fluted formula structural column in four directions, prefabricated crossbeam are prominent For wallboard, in frame-like formula house.
Fig. 1 example shows the square column of the fluted formula structural column in the utility model four directions, and structural column is square shape, and four directions is pre- Groove is stayed, corner is fillet, and wallboard is slightly wider than in groove;Unwrapping wire, positioning on foundation ring girder, the scene at pre-buried connection reinforcing bar Assembling reinforcement skeleton, using typified form formwork, the cast-in-place fluted formula reinforcing bars of structural columns concrete in four directions;Cast-in-situ steel reinforced concrete The house of structural column is more firm, typified form can Reusability, be advantageous to cost savings.
Fig. 2 example shows the cylinder of the fluted formula structural column in the utility model four directions, and structural column is cylinder, and four directions is pre- Groove is stayed, wallboard is slightly wider than in groove;Unwrapping wire, positioning on foundation ring girder, the scene assembling reinforcement bone at pre-buried connection reinforcing bar Frame, using typified form formwork, the cast-in-place fluted formula reinforcing bars of structural columns concrete in four directions;The room of monolithic reinforced concrete structure post Room is more firm, typified form can Reusability, be advantageous to cost savings.
Fig. 3 example shows the placement of the utility model wallboard, and wallboard transverse side is placed between two posts in groove, Wallboard faying surface must smear plain slurry;The installation of wallboard at reserved door opening, on foundation ring girder at door opening positioning on the outside of, punch and install " U " shape slot type connection section bar, and allow it firmly to erect just, wallboard is hung and connected in the fluted formula structural column in four directions with " U " shape slot type Between direct type material, doorway positions are reserved;Door opening both sides wallboard stacks the connection of use " H " shape slot type connection section bar;Both sides at the top of door opening It is connected with " H " shape slot type connection section bar with crossing door opening wallboard;Prefabricated crossbeam is arranged on above wallboard, the fluted formula structure in four directions Between post, reserved stirrup is face-up, both ends reserving rib and the fluted formula reinforcing bars of structural columns skeleton racking seizing in four directions, and cast-in-place mixed Solidifying soil hardening;The fluted formula structural column in four directions, prefabricated crossbeam side protrude from metope, in frame-like formula structure.
Fig. 4 example shows the utility model " L " shape slot type connection section bar, and in " L " shape, groove insied width is slightly wider than wallboard Thickness, channel-section steel make, and channel-section steel bottom surface is provided with multiple mounting holes, are installed for oncomelania bolt;" L " shape slot type connection section bar, in door, window " U " shape slot type connection section bar can be replaced to use at hole to be provided, the reserved door opening installed using the connection section bar is more suitable for welding Process Installation door and window.
Fig. 5 example shows the utility model " U " shape slot type connection section bar, and in " U " shape, groove insied width is slightly wider than wallboard Thickness, channel-section steel make, and channel-section steel bottom surface is provided with multiple mounting holes;" U " shape slot type connection section bar, may be mounted on foundation ring girder and pacifies Put wallboard;" U " shape slot type connection section bar can also be mounted vertically on already installed wall, for laying partition plate.
Fig. 6 example shows the utility model " H " shape slot type connection section bar, and in " H " shape, groove insied width is slightly wider than wallboard Thickness, I-steel make;For stacking connection between the wallboard of reserved wall hole both sides.
Fig. 7 example shows the attachment structure of floor and prefabricated crossbeam in the utility model, and floor, which is taken, is placed on prefabricated horizontal stroke Liang Shang, floor are " work " pattern pre-stress hollow prefabricated board, are furnished with double steel bar and both ends reserving rib;Prefabricated crossbeam, both ends are pre- Muscle is stayed, surface layer reserves stirrup;It is in " recessed " groove that the floor put and prefabricated crossbeam surface layer are taken in prefabricated crossbeam both sides;Floor is kept flat with floor " recessed " groove is showed together;Framework of steel reinforcement and and building are laid in " recessed " groove between floor and prefabricated crossbeam, between floor and floor Plate reserving rib, prefabricated crossbeam reserve series connection and colligation between stirrup, cast-in-place concrete collar tie beam;Cast-in-place concrete collar tie beam and prefabricated crossbeam The integral formula aspect collar tie beam of beam conspired to create, ensure the structure bonding strength globality of floor and collar tie beam.
Fig. 8 example shows the utility model staircase boards, is board-like precast hollow gangboard, and prefabrication produces, step Inner chamber is hollow, both ends bilayer reserving rib.
Fig. 9 example shows the utility model simple circuit wiring method, and vertical wire casing is arranged on wallboard and structural column Angle, horizontal wire casing using wallboard build-in cavities connect up, vertical wire casing with horizontal wire casing overlapping palpus perforate be connected, Line box installation place borrows cutting machine and corresponding big hole is cut on wallboard, then installs line box, electric wire.
Figure 10 example shows the fluted formula structural column in the utility model four directions and prefabricated crossbeam attachment structure, prefabricated horizontal stroke Beam is placed in above wallboard and between corresponding cubic fluted formula structural column, reserves stirrup surface layer upward;Prefabricated crossbeam is pre- Stay muscle and the fluted formula reinforcing bars of structural columns skeleton racking seizing in four directions, cast-in-place concrete;Cast-in-place concrete can ensure prefabricated horizontal stroke Beam and the fluted formula structural column bonding strength globality in four directions.
Figure 11 example shows the utility model floor, is " work " pattern pre-stress hollow prefabricated board, is furnished with clad steel Muscle and both ends reserving rib, prefabrication production;Floor, which is taken, to be placed on floor prefabricated crossbeam.
Figure 12 example shows the utility model wallboard, is pre-stress hollow prefabricated board, double-layer rib, cross section is smooth to put down It is whole, prefabrication production.
Figure 13 example shows the utility model prefabricated crossbeam, prefabrication production, both ends reserving rib, the reserved hoop of surface layer Muscle or reserving rib;Prefabricated crossbeam lower floor two corners are fillet, upper strata two corners are corner.
Figure 14 example shows the utility model assembling prefabricated components formula house, and the fluted formula structural column in four directions is built in On house foundation collar tie beam, wallboard transverse side is placed between the corresponding fluted formula structural column in four directions, and prefabricated crossbeam is placed in wall On plate and between the corresponding fluted formula structural column in four directions, floor, which is taken, to be placed on prefabricated crossbeam, between floor and floor, floor with it is prefabricated Between crossbeam, cast-in-situ steel reinforced concrete collar tie beam, " U " or " L " shape slot type connection section bar must be installed at door opening on collar tie beam by reserving, will Wallboard transverse side is placed in the fluted formula structural column in four directions with " U " or " L " shape slot type connection section bar groove, reserving window opening in wall " H " shape slot type connection section bar is used on plate at positioning, wallboard is placed in " H " shape slot type connection section bar groove;Floor and floor, Between floor and prefabricated crossbeam, cast-in-situ steel reinforced concrete collar tie beam forms the dual collar tie beam of aspect with prefabricated crossbeam;The fluted formula knot in four directions Structure post, prefabricated crossbeam protrude from wallboard, in frame-like formula house;Prefabricated crossbeam protrudes from wallboard, and flowing through wallboard to rainwater oozes Thoroughly to there is certain inhibition within the walls.
In the prefabricated components design and installation method in above-mentioned assembling prefabricated components formula house, the main component wallboard of structure, Floor, prefabricated crossbeam, staircase boards, slot type connection section bar can factorial praluction, each component is assembled at the construction field (site) Construction, collar tie beam are connected with the fluted formula structural column cast-in-place concrete in four directions, building is turned into an entirety, this building structure Meet cast in place and precast construction design, prefabricated components formula house is assembled for a kind of utility model;Made using this utility model technology The house gone out, can the scene of reducing build by laying bricks or stones, avoid the generation of building waste, be not required to erecting scaffold, auxiliary material, only need a small amount of mould Plate, construction material, labour cost are saved, reduce comprehensive cost cost and preserve the ecological environment from felling, make building construction It is more ecological;Prefabricated components formula house is assembled, there is flexible structure, convenient transportation, quick, structural strength height, environmental protection, peace are installed Entirely, heat-insulated, sound insulation, it is attractive in appearance, versatile the characteristics of.

Claims (9)

1. assemble prefabricated components formula house, it is characterised in that it includes:House foundation collar tie beam, the fluted formula structural column in four directions, in advance Crossbeam processed, wallboard, floor, staircase boards, slot type connection section bar, the installation of wire casing and line box;Pre-buried connection on house foundation collar tie beam Muscle, the fluted formula structural column in four directions are built on house foundation collar tie beam;Wallboard transverse side be placed in corresponding four directions have it is recessed Between slot type structure post, wallboard faying surface is uniformly wiped with lean concrete grout;Prefabricated crossbeam is in plant produced and reserving rib and stirrup, peace It is placed between wallboard upper strata and corresponding cubic fluted formula structural column, it is face-up reserves stirrup;Prefabricated crossbeam and prefabricated horizontal stroke Between beam, the fluted formula structural column of prefabricated crossbeam and four directions, the connection method of overlap joint welding or colligation between reserving rib, and it is cast-in-place Concrete, ensure its structure bonding strength globality;Floor is the pre-stress hollow prefabricated board of " work " printed words formula, and both ends are reserved Muscle, floor level, which is taken, to be placed on prefabricated crossbeam;Between floor and floor, between floor both ends and prefabricated crossbeam in indentation pattern and mutually Connection, the cast-in-situ steel reinforced concrete collar tie beam in groove;The fluted formula structural column in four directions, prefabricated crossbeam side protrude from wallboard, In frame-like formula house;Staircase boards segmentation is set up, and staircase boards both ends reserving rib, platen muscle of having a rest need colligation to connect, and cast-in-place coagulation Soil;Reserved door opening must be at the collar tie beam positioning on the outside of, punch and " U " be installed or " L " shape slot type connection section bar, and it is firmly erected Just, wallboard is placed between the fluted formula structural column in four directions and " U " or " L " shape slot type connection section bar, reserves door opening;Reserved window opening On the outside of at the bottom positioning of wallboard window, lay " H " shape slot type connection section bar, by wallboard be placed in the fluted formula structural column in four directions with Between " H " shape slot type connection section bar groove, window opening is reserved;Laying point for wire casing is vertical and laterally, vertical wire casing be arranged on wallboard with The angle of structural column, horizontal wire casing are connected up using the build-in cavities of wallboard, and vertical wire casing must perforate with horizontal wire casing overlapping Connection;Line box installation place cuts correspondingly sized hole using cutting machine on wallboard, is installed for line box.
2. assembling prefabricated components formula house according to claim 1, it is characterised in that:The house foundation collar tie beam, basis The pre-buried dowel of collar tie beam palpus, and shaped with stirrup colligation, and unwrapping wire and positioning in the above.
3. assembling prefabricated components formula house according to claim 1, it is characterised in that:The fluted formula structure in four directions Post, using shaper formwork, fluted, cast-in-situ steel reinforced concrete is reserved in the four directions of post;Reserved recess width is slightly wider than wallboard; The planform of post is square column or cylinder;Right angle or fillet are divided in the corner of post.
4. assembling prefabricated components formula house according to claim 1, it is characterised in that:The prefabricated crossbeam, prefabrication Production, both ends reserving rib, surface layer reserve stirrup;The corner of prefabricated crossbeam is right angle or fillet.
5. assembling prefabricated components formula house according to claim 1, it is characterised in that:The wallboard, it is pre-stress hollow Prefabricated board, double-layer rib, cross section are smooth.
6. assembling prefabricated components formula house according to claim 1, it is characterised in that:The floor, it is that " work " pattern is pre- Stress hollow pre-fabricated panels, it is furnished with double steel bar and both ends reserving rib.
7. assembling prefabricated components formula house according to claim 1, it is characterised in that:The staircase boards, it is board-like prefabricated Hollow staircase boards, prefabrication production, step inner chamber is hollow, both ends bilayer reserving rib.
8. assembling prefabricated components formula house according to claim 1, it is characterised in that:The slot type connection section bar, metal " U ", " H ", " L " shape are made, groove inboard width is slightly wider than wallboard, and " U " shape slot type connection section bar is made using channel-section steel, and bottom is opened multiple Eyelet, fix and use for oncomelania bolt;" H " shape slot type connection section bar is made using " work " word steel;" L " shape slot type connection section bar, Made of channel-section steel, multiple eyelets are opened in bottom, fix and use for oncomelania bolt.
9. the placement of wire casing according to claim 1 and line box, it is characterised in that:The installation of the wire casing and line box, line Laying point for groove is vertical and laterally, and vertical wire casing is arranged on the angle of wallboard and post, and horizontal wire casing in wallboard using being empty Chamber connects up;Line box installation place cuts corresponding big hole with cutting machine on wallboard, installs line box.
CN201621217121.2U 2016-11-11 2016-11-11 Assemble prefabricated components formula house Active CN206646634U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621217121.2U CN206646634U (en) 2016-11-11 2016-11-11 Assemble prefabricated components formula house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621217121.2U CN206646634U (en) 2016-11-11 2016-11-11 Assemble prefabricated components formula house

Publications (1)

Publication Number Publication Date
CN206646634U true CN206646634U (en) 2017-11-17

Family

ID=60283800

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621217121.2U Active CN206646634U (en) 2016-11-11 2016-11-11 Assemble prefabricated components formula house

Country Status (1)

Country Link
CN (1) CN206646634U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019218235A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 Construction method for house having high-voltage wire separate from main structure
CN114215270A (en) * 2021-12-21 2022-03-22 浙江恒鸿建设有限公司 Outward convex line reinforced concrete landscape column and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019218235A1 (en) * 2018-05-16 2019-11-21 深圳市君盈建筑科技有限公司 Construction method for house having high-voltage wire separate from main structure
CN110945191A (en) * 2018-05-16 2020-03-31 广东博智林机器人有限公司 Construction method of house with separated strong-current electric wire and main body structure
CN114215270A (en) * 2021-12-21 2022-03-22 浙江恒鸿建设有限公司 Outward convex line reinforced concrete landscape column and construction method

Similar Documents

Publication Publication Date Title
CN107780576A (en) A kind of assembled architecture bottom composite floor and its connected mode
CN206016309U (en) A kind of overall assembled building system
CN108385904B (en) Roofing parapet wall and construction method thereof
CN211473051U (en) Prestressed truss wallboard and wall body manufactured by using same
CN108071169A (en) Assemble prefabricated components formula house
CN108252407A (en) A kind of building with prefabricated reinforced concrete bearing
CN108104284B (en) Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method
CN206646634U (en) Assemble prefabricated components formula house
CN210002551U (en) kinds of assembled house frame structure
CN102605902A (en) Penetrating rib and clamping hook combined steel mesh template and application method
CN111535488A (en) Prefabricated steel bar truss of assembled exempts from to tear open building carrier plate and cast-in-place and exempt from to strut truss floor
CN205976215U (en) Compound box roof beam of assembled concrete
CN103774777A (en) Assembly type skeleton multi-ribbed beam-plate composite structure big plate
CN106836632B (en) Connection structure of roof beam, floor and prefabricated wallboard
CN113389304A (en) Assembled double-blade cavity superposed wall system and construction method thereof
CN108951982A (en) Assembly concrete superposed floor plate and its construction method based on cement fibrolite plate composite reinforcing steel bar skeleton
CN111851827A (en) Assembly type prefabricated steel bar truss disassembly-free template system and manufacturing method thereof
CN217517862U (en) Assembled L shape post and ecological interior wall self-tapping nail cluster connection structure
CN217517861U (en) Assembled T-shaped column and ecological inner wall self-tapping nail cluster connecting structure
EP2402525A1 (en) Method for erecting a building having a cast-in-place frame and decorative outer finish
CN112832406B (en) Sleeving structure of assembled wall body and beam column
CN205444514U (en) Bearing light insulation intergral template
CN210288825U (en) Assembled and cast-in-situ combined beam plate structure
CN1313688C (en) Low-storey building and single-storey house anti-seismic building method
CN113323262A (en) 3D printed prefabricated wall module, wall and construction method of wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant