CN206571130U - A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony - Google Patents

A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony Download PDF

Info

Publication number
CN206571130U
CN206571130U CN201720131204.8U CN201720131204U CN206571130U CN 206571130 U CN206571130 U CN 206571130U CN 201720131204 U CN201720131204 U CN 201720131204U CN 206571130 U CN206571130 U CN 206571130U
Authority
CN
China
Prior art keywords
support body
outside
scaffold board
square steel
protective frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720131204.8U
Other languages
Chinese (zh)
Inventor
侯鹏飞
叶文启
林鸿炜
张建强
周洌铖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN201720131204.8U priority Critical patent/CN206571130U/en
Application granted granted Critical
Publication of CN206571130U publication Critical patent/CN206571130U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Steps, Ramps, And Handrails (AREA)

Abstract

The utility model discloses a kind of outside the pale of civilization protective frame of the sizing for Fabricated balcony, including horizontal protective device, the support meanss being supported on below horizontal protective device and the vertical protector located at horizontal protective device lateral surface, the horizontal protective device includes the scaffold board support body being welded by square steel and the scaffold board being laid on scaffold board support body, row's square steel sleeve pipe is welded with the outside of the scaffold board support body, skirting board is fixed between the square steel sleeve pipe, the vertical protector includes the protection network support body being welded by square steel and the protection network being fixed on protection network support body, the support meanss include the sheer pole being fixed on prefabricated balcony and the cross tube being supported in below scaffold board support body, it is supported between the cross tube and sheer pole provided with montant and diagonal brace, the scaffold board support body and cross tube are joined with bolts.The utility model assembling is convenient, meets security protection and construction requirement.

Description

A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony
Technical field
The utility model is related to building construction technology, more particularly to the protective frame that external wall Decorative Construction is used.
Background technology
At present, in construction by the way of floor scaffolding or builder's jack, there is following ask in external wall facing Topic:1st, floor scaffolding construction usage limited height system;2nd, the I-steel of builder's jack will be in the pre- of the prefabricated components such as exterior wall Box out opening is big, and later stage repair procedure is complicated, it is difficult to meet the quality requirements such as insulation and seepage;3rd, steel pipe scaffold is being set up When, the exterior finish that destructible precast facade is processed causes the patch work that the later stage is extra.
Utility model content
Technical problem to be solved in the utility model is just to provide a kind of outside the pale of civilization protection of sizing for Fabricated balcony Frame, assembles convenient and convenient dismounting.
In order to solve the above technical problems, the utility model is adopted the following technical scheme that:A kind of determining for Fabricated balcony The outside the pale of civilization protective frame of type, including horizontal protective device, the support meanss that are supported on below horizontal protective device and anti-located at level The vertical protector of protection unit lateral surface, the horizontal protective device include the scaffold board support body that is welded by square steel and It is laid on the outside of the scaffold board on scaffold board support body, the scaffold board support body and is welded with row's square steel sleeve pipe, the square steel set Skirting board is fixed between pipe, the vertical protector includes the protection network support body being welded by square steel and is fixed on protection Protection network on rack body, the support meanss include the sheer pole being fixed on prefabricated balcony and are supported in scaffold board support body The cross tube of lower section, is supported between the cross tube and sheer pole provided with montant and diagonal brace, the scaffold board support body and upper Cross bar is joined with bolts, in the vertical square steel bottom insertion square steel sleeve pipe in the protection network support body.
Preferably, be embedded with screw shell in the prefabricated balcony, pass through screw rod in the sheer pole, the screw rod with Screw shell is threadedly coupled, and is combined with nut on the screw rod, the screw nut pressing is on sheer pole.
Preferably, being ridden on the outside of the sheer pole on the anti-bank of prefabricated balcony, the lumps of wood is used on the inside of the sheer pole Pad is extremely with anti-bank with high.
Preferably, being fastened by bolts square steel cushion block between the diagonal brace and montant.
Preferably, welding angle steel diagonal brace between the montant and scaffold board support body.
Preferably, the bottom of the scaffold board support body is provided with the channel-section steel used as backing plate, channel-section steel and the pin hand The square steel of grillage body uses inverted U fixture conjunction, and is fixed inverted U fixture using bolt.
Preferably, being welded with the siffener angle plate of reinforcement between the square steel sleeve pipe and scaffold board support body.
Preferably, the protection network support body is included between some unit frameworks being arranged side by side, the adjacent framework of Unit two It is fixed with bolts.
The technical solution adopted in the utility model, mainly by support meanss, horizontal protective device, vertical protector three Point constitute, three parts be bolted it is integral, be fixed on prefabricated balcony and other kinds of outer protective frame together Use, can also be used as the operating platform of workmen as the protective fence of construction floor.
The mode of scaffold is set up compared to tradition, and the prefabricated balcony protective frame is used as one of new outer protection frame system Point, with multiple advantages:1st, it is convenient to assemble, and meets security protection and construction requirement;2nd, two sets of outer protective frame body circulations are used, nothing Use height limitation;3rd, the neat and artistic of construction main image alien invasion is ensure that, and in the hole to be provided very little of prefabricated balcony, after Phase repairing is convenient.
Brief description of the drawings
The utility model is further described with reference to the accompanying drawings and detailed description:
Fig. 1 is the dimensional structure diagram of the outer protective frame of the utility model;
Fig. 2 is the front elevation view of the outer protective frame of the utility model;
Fig. 3 is the side elevational view of the outer protective frame of the utility model;
Fig. 4 is the upward view of the outer protective frame of the utility model;
Fig. 5 is the support system schematic diagram of the outer protective frame of the utility model;
Fig. 6 is the horizontal protective system schematic diagram of the outer protective frame of the utility model;
Fig. 7 is the vertical protection system schematic diagram of the outer protective frame of the utility model;
In figure:1. the screw shell 8. of 6. prefabricated balcony of sheer pole 2. montant, 3. cross tube, 4. diagonal brace, 5. screw rod 7. The scaffold board support body 16. of 14. bolt of balcony slab anti-9. lumps of wood of bank 10. steel plate washer, 11. bolt, 12. bolt, 13 bolt 15. The bolt 23. of 21. siffener angle plate of scaffold board 17. bolt, 18. inverted U fixture, 19. channel-section steel, 20. square steel sleeve pipe 22. is protected The short bolt of 28. angle steel diagonal brace of square steel cushion block 29. of 24. protection network of rack body, 25. bolt, 26. skirting board 27..
Embodiment
As shown in Figures 1 to 7, the utility model is a kind of outside the pale of civilization protection of the sizing for assembled architecture prefabricated balcony Frame, it includes horizontal protective device, the support meanss being supported on below horizontal protective device and outside horizontal protective device The vertical protector of side.Level, vertical protection system are customized in factory using modulus, are carried out for various sizes of balcony Combination, is assembled into the support body for meeting and going along with sb. to guard him range size, and design corresponding support system.Lower horizontal stroke wherein below support system Bar and prefabricated balcony are connected with high-strength bolt, above support system and the connection of horizontal protective system and horizontal protective system and are hung down Straight protection system is connected by screw bolts.
Wherein, support meanss are made up of sheer pole 1, montant 2, cross tube 3, diagonal brace 4, are connected by screw bolts integral, branch Support arrangement primarily serves connection prefabricated balcony 6 and support top support body transmits the function of load.Wherein sheer pole 1 be 120mm × 120mm × 10mm square steel, montant 2 and cross tube 3 be 100mm × 100 × 10mm square steel, diagonal brace 4 using 75mm × 75mm × 10mm angle steel;Sheer pole 1 and diagonal brace 4, sheer pole 1 and montant 2, montant 2 and diagonal brace 4, montant 2 and cross tube 3, cross tube 3 with Diagonal brace 4, connects integral with bolt 11, bolt 12, bolt 13, bolt 14, bolt 29 respectively, wherein because diagonal brace 4 and montant 2 Between have a spacing, therefore place short square steel cushion block 27 and ensure both contacts;Support system is with screw rod 5 by sheer pole 1 and prefabricated balcony 6 In pre-buried screw shell 7 be connected, the outside of sheer pole 1 is ridden on the anti-bank 8 of balcony slab, the inner side lumps of wood 9 of sheer pole 1 pad to With the anti-bank of balcony slab 8 with high, it is ensured that support system level;During site operation, user can take welding angle steel diagonal brace 28 Measure is strengthened.
As shown in fig. 6, horizontal protective system is made up of scaffold board support body 15 and scaffold board 16, make as operating platform With.Scaffold board support body 15 uses 50mm × 50mm × 4mm square steel, and scaffold board 16 is using the thick punching sheet metals of 3mm;Scaffold board support body 15 and the cross tube 3 of support system be connected with bolt 17;High 50mm × the 50mm of 250mm are welded with the outside of horizontal protective system × 4mm square steel sleeve pipe 20, and reinforcement is welded with siffener angle plate 21, square steel sleeve pipe is easy to vertical protection system insertion connection, Scaffold board support body 15 is provided with inverted U fixture with the junction of cross tube 3, and channel-section steel 19 is provided with below cross tube 3 as backing plate Use, the tool of inverted U card 18 is fixed on whole support body with bolt, suspension ring when installing, dismantling as protective frame outside prefabricated balcony Use.
As shown in fig. 7, vertical protection system is primarily referred to as protective fence, mainly by 24 groups of protection network support body 23 and protection network Into the vertical protection system of prefabricated balcony position and other adjacent protection support bodys play construction operation and face frontier defense shield together Function.Wherein protection network support body is 40mm × 40mm × 4mm square steel composition, and protection network is using the thick punching sheet metals of 1.5mm.It is adjacent Protection network support body 23 is connected with twice bolt 25 up and down;The insertion horizontal protective body of protection network support body 23 of vertical protection system In square steel sleeve pipe 20 in system, and it is connected with twice bolt 22.
Technological principle of the present utility model is as follows:
The outside the pale of civilization protective frame of sizing of prefabricated balcony is mainly made up of support system, horizontal protective system, vertical protection system, It is bolted the fixed structure for forming overall stress, the pre-buried screw shell 7 of the support body screw rod 5 and prefabricated balcony 6 enters Row connection.During construction, the outer protective frame of two sets of balconies is generally set, it is a set of to be fixed on (n-1)th layer of prefabricated balcony 6 as n-th layer Outer protective frame is used, and a set of n-th layer prefabricated balcony 6 that is fixed on is used as (n+1)th layer of outer protective frame, treat (n+1)th layer it is prefabricated After the completion of balcony 6 is lifted, you can (n-1)th layer of outer protective frame is removed to the outer protection of lifting to (n+1)th layer as the n-th+2 layers Frame, is so recycled until the architecture construction is finished.
Specific construction process of the present utility model includes following steps:
Step 1:Lifting, the inverted U card 18 of outer protective frame is caught on using hanging device, outer protective frame is hung to corresponding pre- The position of balcony 6 processed;
Step 2:Install and fix, connected the pre-buried screw shell 7 on the outer plate of 1 prefabricated balcony of protective frame sheer pole 6 with screw rod 5 Fixation is connect, so that whole outer protective frame is fixed on prefabricated balcony 6;
Step 3:Adult is connected, protective frame outside mounted balcony is connected with other adjacent outer protection support bodys;From And ring whole building beyond the region of objective existence encloses the outer protection system to form an integrally closed, the protection system also can as workmen behaviour Used as platform.
Step 4:Remove and recycle, treat after the completion of upper layer main body structure construction, protective frame outside the balcony of lower floor is torn open Remove and be hung to new construction floor and installed and used;
The technical solution adopted in the utility model, mainly by support meanss, horizontal protective device, vertical protector three Point constitute, three parts be bolted it is integral, be fixed on prefabricated balcony and other kinds of outer protective frame together Use, can also be used as the operating platform of workmen as the protective fence of construction floor.
Compared to traditional floor scaffolding, builder's jack, the water of the outer protective frame of prefabricated balcony of the utility model description Flat safeguard structure and vertical safeguard structure use punching sheet metal, and hole is small, can be prevented effectively from small objects falling from high altitude, protect Lower section workmen has been demonstrate,proved to be hardly damaged safely;Whole frame structure is simple, can accomplish that dismounting is assembled again completely, recycling rate of waterused It is high;Single building is compared using the outer protective frame of the type with traditional defense system uses material few, can effectively save and use The hiring cost of person;And the protective frame of prefabricated balcony is installed and is not take up operation side, can save the duration.
A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony of foregoing description is not used alone typically, it is necessary to coordinate it The prefabricated components pylon of his type, which is used in combination, could form complete protection system.The sizing of utility model description is outside the pale of civilization Protective frame applies in general to external wall facing and the one-time formed assembled-type house project of prefabricated components or industrial project.
Above-mentioned is only the description of implementation example preferable to the utility model, not does any limit to scope of the present utility model Calmly, the others skilled in the art in the utility model field make according to the utility model content any change, modification, belong to power The protection domain of sharp claim.

Claims (8)

1. a kind of outside the pale of civilization protective frame of sizing for Fabricated balcony, it is characterised in that:Including horizontal protective device, it is supported on water Support meanss below flat protector and the vertical protector located at horizontal protective device lateral surface, the horizontal protective Device includes the scaffold board support body being welded by square steel and the scaffold board being laid on scaffold board support body, the scaffold board frame It is welded with the outside of body between row's square steel sleeve pipe, the square steel sleeve pipe and is fixed with skirting board, the vertical protector includes The protection network support body being welded by square steel and the protection network being fixed on protection network support body, the support meanss include being fixed on Sheer pole on prefabricated balcony and the cross tube being supported in below scaffold board support body, are provided between the cross tube and sheer pole Montant and diagonal brace are supported, and the scaffold board support body and cross tube are joined with bolts, perpendicular in the protection network support body Into square steel bottom insertion square steel sleeve pipe.
2. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:It is described pre- It is embedded with balcony processed in screw shell, the sheer pole and passes through screw rod, the screw rod is threadedly coupled with screw shell, the spiral shell Nut is combined with bar, the screw nut pressing is on sheer pole.
3. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:Under described Ridden on the outside of cross bar on the anti-bank of prefabricated balcony, the inner side of the sheer pole is same high extremely with anti-bank with lumps of wood pad.
4. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:It is described oblique Square steel cushion block has been fastened by bolts between support and montant.
5. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:It is described perpendicular Angle steel diagonal brace is welded between bar and scaffold board support body.
6. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:The pin The bottom of palm support body is provided with the channel-section steel used as backing plate, and the square steel of channel-section steel and the scaffold board support body uses inverted U card Inverted U fixture is fixed conjunction using bolt by tool.
7. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:The side The siffener angle plate of reinforcement is welded between steel sleeve and scaffold board support body.
8. the outside the pale of civilization protective frame of a kind of sizing for Fabricated balcony according to claim 1, it is characterised in that:It is described anti- Protecting wire net support body includes being fixed with bolts between some unit frameworks being arranged side by side, the adjacent framework of Unit two.
CN201720131204.8U 2017-02-14 2017-02-14 A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony Expired - Fee Related CN206571130U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720131204.8U CN206571130U (en) 2017-02-14 2017-02-14 A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720131204.8U CN206571130U (en) 2017-02-14 2017-02-14 A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony

Publications (1)

Publication Number Publication Date
CN206571130U true CN206571130U (en) 2017-10-20

Family

ID=60058211

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720131204.8U Expired - Fee Related CN206571130U (en) 2017-02-14 2017-02-14 A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony

Country Status (1)

Country Link
CN (1) CN206571130U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677509A (en) * 2017-02-14 2017-05-17 中天建设集团有限公司 Design finalization external protective frame system used for assembly type building construction
CN108104454A (en) * 2017-12-29 2018-06-01 北京城建北方建设有限责任公司 Prefabricated outer wall panel safety protection frame
CN110965761A (en) * 2019-12-31 2020-04-07 广西建工集团第五建筑工程有限责任公司 Scaffold suitable for multilayer assembled shear wall and construction method thereof
CN110965757A (en) * 2019-12-31 2020-04-07 广西建工集团第五建筑工程有限责任公司 Scaffold applicable to wall with flanging structure and construction method thereof
CN112049397A (en) * 2020-09-01 2020-12-08 上海家树建筑工程有限公司 Protective frame for PC (polycarbonate) outer wall component

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677509A (en) * 2017-02-14 2017-05-17 中天建设集团有限公司 Design finalization external protective frame system used for assembly type building construction
CN108104454A (en) * 2017-12-29 2018-06-01 北京城建北方建设有限责任公司 Prefabricated outer wall panel safety protection frame
CN110965761A (en) * 2019-12-31 2020-04-07 广西建工集团第五建筑工程有限责任公司 Scaffold suitable for multilayer assembled shear wall and construction method thereof
CN110965757A (en) * 2019-12-31 2020-04-07 广西建工集团第五建筑工程有限责任公司 Scaffold applicable to wall with flanging structure and construction method thereof
CN112049397A (en) * 2020-09-01 2020-12-08 上海家树建筑工程有限公司 Protective frame for PC (polycarbonate) outer wall component

Similar Documents

Publication Publication Date Title
CN206571130U (en) A kind of outside the pale of civilization protective frame of sizing for Fabricated balcony
CN106677509A (en) Design finalization external protective frame system used for assembly type building construction
CN206722368U (en) One kind is used to protect frame system outside the working regularization of assembled architecture
CN101736893A (en) Overhanging type scaffold supporting system
CN103206074A (en) Elevator shaft template construction method, platform and support
CN206859068U (en) A kind of Cable-stayed Bridge Pylon sill segmental timbering structure
CN104314095B (en) A kind of shaped steel buttress for the construction of super thick raft plate and valve plate and construction method
CN203961276U (en) High-building construction steel form and handling frame Integral lifting stage apparatus
CN213329955U (en) Flower basket diagonal rod type overhanging scaffold
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN102912996A (en) Steel tube concrete column high-altitude construction safety protection system
CN202954552U (en) Steel tube concrete column high-altitude construction safety protection system
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN201190408Y (en) Tool type exterior scaffolding of section steel fastening tube
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN204126290U (en) Elevator shaft horizontal protective device
CN205134921U (en) Building outer wall concrete constructional column hangs construction platform
CN204662926U (en) A kind of operating platform for steel pipe column top construction operation
CN209703987U (en) Assembly of shear wall structure can have enough to meet the need outer protective frame
CN209509453U (en) A kind of skyscraper cast-in-place concrete structure tool-type builder's jack
CN208749071U (en) A kind of reinforcing heightening type hanging basket connection system
CN208749072U (en) A kind of hanging basket connection system
CN209620636U (en) Prefabricated assembled concrete structure outer hanging plate elevation of bottom regulating device
CN208039787U (en) The assembled operating platform of side operation is faced in a kind of high-altitude
CN207420069U (en) A kind of guard rail being used in turn

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171020

Termination date: 20180214

CF01 Termination of patent right due to non-payment of annual fee