CN206554609U - The detachable prefabricated enclosure wall of job site - Google Patents

The detachable prefabricated enclosure wall of job site Download PDF

Info

Publication number
CN206554609U
CN206554609U CN201621315887.4U CN201621315887U CN206554609U CN 206554609 U CN206554609 U CN 206554609U CN 201621315887 U CN201621315887 U CN 201621315887U CN 206554609 U CN206554609 U CN 206554609U
Authority
CN
China
Prior art keywords
fixture
enclosure wall
job site
column
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621315887.4U
Other languages
Chinese (zh)
Inventor
韦晓峰
伍孝波
谭江山
张志永
李建东
周秋勇
王大群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Housing Guarantee Investment Centre Of Beijing
Beijing Urban and Rural Construction Group Co Ltd
Original Assignee
Housing Guarantee Investment Centre Of Beijing
Beijing Urban and Rural Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Housing Guarantee Investment Centre Of Beijing, Beijing Urban and Rural Construction Group Co Ltd filed Critical Housing Guarantee Investment Centre Of Beijing
Priority to CN201621315887.4U priority Critical patent/CN206554609U/en
Application granted granted Critical
Publication of CN206554609U publication Critical patent/CN206554609U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to enclosure wall technical field, discloses a kind of detachable prefabricated enclosure wall of job site.The utility model includes supporting the supporting frame of the curtain wall penel and support curtain wall penel between the column of fixed enclosure wall, the concrete foundation of column bottom vertical columns, column, the column includes horizontally disposed cube frame, the hound being located at respectively between the vertical rod on the outside of the drift angle of cube frame four and neighboring cubes framework, the cube frame is distributed along vertical rod uniform intervals, and the hound is separately positioned on cube frame opposite sides face;The concrete foundation surface is provided with buried plate, and column bottom is connected with chemical anchor bolts with buried plate;The curtain wall penel is connected with bolt with supporting frame, and curtain wall penel is bolted to connection with column.The utility model is simple in construction, cost is low, easy installation and removal, live turnover rate are high.

Description

The detachable prefabricated enclosure wall of job site
Technical field
The utility model is related to enclosure wall technical field, the detachable prefabricated enclosure wall of more particularly to a kind of job site.
Background technology
Job site provides extremely favourable guarantee using enclosure wall for engineering safety, to the whole project construction normally operation and Safety has extremely important meaning.Traditional enclosure wall is disposable mostly, and multi-purpose concreting is formed, or is brick Structure, or iron sheet are enclosed, and can not be reused, and are a very big waste, scene to human and material resources, financial resources The interim enclosure wall that makes delays construction speed and not environmentally friendly enough, it is impossible to meet the requirement of green construction.
Utility model content
The utility model provides a kind of low simple in construction, cost, easy installation and removal, live turnover rate high job site Detachable prefabricated enclosure wall.
The technical problem to be solved is:Traditional enclosure wall is disposable mostly, can not be reused, in manpower, It is great waste in terms of material resources, financial resources.
In order to solve the above technical problems, the utility model is adopted the following technical scheme that:
The detachable prefabricated enclosure wall of the utility model job site, including support are fixed the column of enclosure wall, column bottom and consolidated Determine the curtain wall penel between the concrete foundation of column, column and support the supporting frame of curtain wall penel, the column is set including level The cube frame put, the diagonal brace being located at respectively between the vertical rod on the outside of the drift angle of cube frame four and neighboring cubes framework Bar, the cube frame is distributed along vertical rod uniform intervals, and the hound is separately positioned on cube frame opposite sides face; The concrete foundation surface is provided with buried plate, and column bottom is connected with chemical anchor bolts with buried plate;The curtain wall penel is with spiral shell Bolt is connected with supporting frame, and curtain wall penel is bolted to connection with column.
The detachable prefabricated enclosure wall of the utility model job site, further, the vertical rod, cube frame and diagonal brace Bar is made of equal leg angle.
The detachable prefabricated enclosure wall of the utility model job site, further, the vertical rod and cube frame etc. The hem width of corner angle and the equal leg angle hem width ratio of hound are 4:3.
The detachable prefabricated enclosure wall of the utility model job site, further, the strength grade of the concrete foundation For C30.
The detachable prefabricated enclosure wall of the utility model job site, further, support frame as described above body include main longitudinal grider, master Crossbeam, support beam and support stringer, main longitudinal grider and main beam are enclosed to be set in the middle part of the supporting frame housing to form rectangle, main longitudinal grider There is support beam, the parallel main beam of support beam is set, and the end of support beam is fixedly connected by fixture group with vertical rod, is propped up Support longeron to be distributed along main beam uniform intervals, support stringer be arranged in parallel with main longitudinal grider.
The detachable prefabricated enclosure wall of the utility model job site, further, the main longitudinal grider, main beam and support are horizontal Liang Jun is made of channel-section steel.
The detachable prefabricated enclosure wall of the utility model job site, further, the fixture group include fixture one With fixture two, fixture one and fixture two are square fixture, and the one side of fixture one is weldingly fixed on support On the upper side wing of beam-end, the notch direction of fixture one and the notch of support beam are set in the opposite direction, fixture one Another side and the one side of fixture two be bolted, the another side of fixture two is weldingly fixed on the side of vertical rod On wall, the notch direction of fixture two is identical with the notch direction of support beam to be set.
The detachable prefabricated enclosure wall of the utility model job site, further, in addition to cover plate, the cover plate, which is located at, to be led At the top of longeron.
The detachable prefabricated enclosure wall of the utility model job site, further, the cover plate is with bolt or welding and master It is connected at the top of longeron.
The detachable prefabricated enclosure wall of the utility model job site, further, the curtain wall penel use cold-rolled steel sheet system Into.
The detachable prefabricated enclosure wall of the utility model job site has the advantages that compared with prior art:
The detachable prefabricated enclosure wall prefabricated components of the utility model job site, Assembling is carried out large-scale without scene Construction, easy for installation, speed of application is fast, improves the efficiency of construction of workman, substantially reduces construction period;Using steel construction as The agent structure of enclosure wall, it is ensured that the intensity and durability of enclosure wall, stable safety, convenient disassembly is harmless dismounting, transferable Place is reused, and live turnover rate is high, reduces cost, reduces the waste of material, and assembling realizes smoke dust construction, subtracted Lack the pollution to environment, realize green construction;Can be according to the requirements of different job sites, flexible assembling different length encloses Wall, adjusts the position of every section of enclosure wall, different construction sites is adapted to greatest extent, the scope of application is more extensive.
The detachable prefabricated enclosure wall of job site of the present utility model is described further below in conjunction with the accompanying drawings.
Brief description of the drawings
Fig. 1 is the structural representation of the detachable prefabricated enclosure wall of the utility model job site;
Fig. 2 is the left view of column;
Fig. 3 is the connection diagram of column and concrete foundation;
Fig. 4 is the support beam of supporting frame and the connection left view of vertical rod;
Fig. 5 is the support beam of supporting frame and the connection front view of vertical rod;
Fig. 6 is the support beam of supporting frame and the connection top view of vertical rod.
Reference:
1- columns;11- cube frames;12- vertical rods;13- hounds;2- concrete foundations;21- buried plates;3- curtain wall penels; 4- supporting frames;41- main longitudinal griders;42- main beams;43- support beams;44- support stringers;45- cover plates;46- fixtures one; 47- fixtures two;5- chemical anchor bolts.
Embodiment
As shown in figure 1, column 1 of the detachable prefabricated enclosure wall of the utility model job site including the fixed enclosure wall of support, Curtain wall penel 3 between the concrete foundations 2 of the bottom vertical columns 1 of column 1, column 1 and the supporting frame 4 for supporting curtain wall penel 3, stand Post 1 includes horizontally disposed cube frame 11, the vertical rod 12 being located at respectively on the outside of the drift angle of cube frame 11 4 and adjacent vertical Hound 13 between cube framework 11, cube frame 11 is distributed along the uniform intervals of vertical rod 12, and hound 13 is separately positioned on Adjacent hound 13 on the opposite sides face of cube frame 11, same side is symmetrical arranged along the minute surface of cube frame 11, is stood Bar 12, cube frame 11 and hound 13 are made of equal leg angle, the equal leg angle of vertical rod 12 and cube frame 11 The equal leg angle hem width ratio of hem width and hound 13 be 4:3;As shown in figure 3, the surface of concrete foundation 2 is provided with buried plate 21, The bottom of column 1 is connected with chemical anchor bolts 5 with buried plate 21, and the strength grade of concrete foundation 2 is C30;Supporting frame 4 includes Main longitudinal grider 41, main beam 42, support beam 43 and support stringer 44, main longitudinal grider 41 and main beam 42 enclose the support to form rectangle The housing of support body 4, main longitudinal grider 41 and main beam 42 are welded and fixed, and main longitudinal grider 41 and main beam 42 are made of channel-section steel, main longitudinal grider 41 Top is provided with cover plate 45, and cover plate 45 is connected with bolt or welding with the top of main longitudinal grider 41, and the middle part of main longitudinal grider 41 is provided with support Crossbeam 43, support beam 43 is made of channel-section steel, and the parallel main beam 42 of support beam 43 is set, and the end of support beam 43 passes through solid Determine part group to be fixedly connected with vertical rod 12, as Figure 4-Figure 6, fixture group includes fixture 1 and fixture 2 47, fixture One 46 and fixture 2 47 are square fixture, and the one side of fixture 1 is weldingly fixed on the end of support beam 43 On upper side wing, the notch direction of fixture 1 is set in the opposite direction with the notch of support beam 43, fixture 1 it is another The one side of one side and fixture 2 47 is bolted, and the another side of fixture 2 47 is weldingly fixed on vertical rod 12 On the wall of side, the notch direction of fixture 2 47 is identical with the notch direction of support beam 43 to be set, and support stringer 44 is along main beam 42 uniform intervals are distributed, and support stringer 44 is made of angle steel, and support stringer 44 be arranged in parallel with main longitudinal grider 41;Curtain wall penel 3 with Bolt is connected with supporting frame 4, and curtain wall penel 3 is made of cold-rolled steel sheet;Curtain wall penel 3 and the company of being bolted of column 1 Connect.
The construction method of the detachable prefabricated enclosure wall of the utility model job site is operated according to following steps:
Step 1: the installation of column 1:Positioning and accurate measurement are carried out according to arrangement and method for construction, and on the surface of concrete foundation 2 Buried plate 21 is set, the cross centre line of column 1 is alignd with the cross centre line of concrete foundation 2, and the position in adjustment bolt hole Put, be fastenedly connected with chemical anchor bolts 5, crab-bolt exposed parts keep protruded length consistent;
Step 2: the assembling of curtain wall penel 3:Supporting frame 4 is assembled at the construction field (site), is then fastened with curtain wall penel 3 with bolt Connection;
Step 3: the installation of curtain wall penel 3:The curtain wall penel 3 assembled is sling close to column with automobile or rubber tired crane 1, after hovering is static, adjustment position, align curtain wall penel 3 and the bolt hole on column 1, is fastenedly connected with bolt, after installation, Loosen steel cable, extract suspension hook;
Step 4: the dismounting of enclosure wall:After the completion of construction, the Bolt dismantling between each part can be transported to next construction Ground, is reused.
Embodiment described above is only that preferred embodiment of the present utility model is described, not to this practicality New scope is defined, on the premise of the utility model design spirit is not departed from, and those of ordinary skill in the art are to this Various modifications and improvement that the technical scheme of utility model is made, all should fall into the protection of the utility model claims determination In the range of.

Claims (10)

1. the detachable prefabricated enclosure wall of job site, it is characterised in that:Include the column of the fixed enclosure wall of support(1), column(1)Under Portion's vertical columns(1)Concrete foundation(2), column(1)Between curtain wall penel(3)With support curtain wall penel(3)Supporting frame (4), the column(1)Including horizontally disposed cube frame(11), respectively be located at cube frame(11)On the outside of four drift angles Vertical rod(12)With neighboring cubes framework(11)Between hound(13), the cube frame(11)Along vertical rod(12) It is even to be spaced apart, the hound(13)It is separately positioned on cube frame(11)Opposite sides face;The concrete foundation(2) Surface is provided with buried plate(21), column(1)Bottom is with chemical anchor bolts(5)With buried plate(21)It is connected;The curtain wall penel(3)With Bolt and supporting frame(4)It is connected, curtain wall penel(3)With column(1)It is bolted to connection.
2. the detachable prefabricated enclosure wall of job site according to claim 1, it is characterised in that:The vertical rod(12), it is vertical Cube framework(11)And hound(13)It is made of equal leg angle.
3. the detachable prefabricated enclosure wall of job site according to claim 2, it is characterised in that:The vertical rod(12)With it is vertical Cube framework(11)Equal leg angle hem width and hound(13)Equal leg angle hem width ratio be 4:3.
4. the detachable prefabricated enclosure wall of job site according to claim 1, it is characterised in that:The concrete foundation (2)Strength grade be C30.
5. the detachable prefabricated enclosure wall of job site according to claim 1, it is characterised in that:Support frame as described above body(4) Including main longitudinal grider(41), main beam(42), support beam(43)And support stringer(44), main longitudinal grider(41)And main beam(42)Enclose Close the supporting frame for forming rectangle(4)Housing, main longitudinal grider(41)Middle part is provided with support beam(43), support beam(43)Parallel master Crossbeam(42)Set, support beam(43)End pass through fixture group and vertical rod(12)It is fixedly connected, support stringer(44)Edge Main beam(42)Uniform intervals are distributed, support stringer(44)With main longitudinal grider(41)It is arranged in parallel.
6. the detachable prefabricated enclosure wall of job site according to claim 5, it is characterised in that:The main longitudinal grider(41)、 Main beam(42)And support beam(43)It is made of channel-section steel.
7. the detachable prefabricated enclosure wall of job site according to claim 6, it is characterised in that:The fixture group includes Fixture one(46)With fixture two(47), fixture one(46)With fixture two(47)It is square fixture, fixture One(46)One side be weldingly fixed on support beam(43)On the upper side wing of end, fixture one(46)Notch direction with Support beam(43)Notch set in the opposite direction, fixture one(46)Another side and fixture two(47)One side lead to Cross bolt connection, fixture two(47)Another side be weldingly fixed on vertical rod(12)Side wall on, fixture two(47)Groove Mouth direction and support beam(43)Notch direction it is identical set.
8. the detachable prefabricated enclosure wall of job site according to claim 5, it is characterised in that:Also include cover plate(45), The cover plate(45)Positioned at main longitudinal grider(41)Top.
9. the detachable prefabricated enclosure wall of job site according to claim 8, it is characterised in that:The cover plate(45)With spiral shell Bolt or welding and main longitudinal grider(41)Top is connected.
10. the detachable prefabricated enclosure wall of the job site according to claim 1-9 any one, it is characterised in that:It is described Curtain wall penel(3)It is made of cold-rolled steel sheet.
CN201621315887.4U 2016-12-02 2016-12-02 The detachable prefabricated enclosure wall of job site Expired - Fee Related CN206554609U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621315887.4U CN206554609U (en) 2016-12-02 2016-12-02 The detachable prefabricated enclosure wall of job site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621315887.4U CN206554609U (en) 2016-12-02 2016-12-02 The detachable prefabricated enclosure wall of job site

Publications (1)

Publication Number Publication Date
CN206554609U true CN206554609U (en) 2017-10-13

Family

ID=60369852

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621315887.4U Expired - Fee Related CN206554609U (en) 2016-12-02 2016-12-02 The detachable prefabricated enclosure wall of job site

Country Status (1)

Country Link
CN (1) CN206554609U (en)

Similar Documents

Publication Publication Date Title
CN208009863U (en) A kind of tool-type pier stud construction operation platform device
CN108532968A (en) A kind of assembled support device of steel bar truss floor support plate composite floor system
CN210216163U (en) Self-supporting cantilever formwork support system
CN208415293U (en) Integral prefabricated assembled main transformer foundation for indoor substation
CN103774838A (en) Assembly type safe operation platform for elevator shaft construction and use method thereof
CN212582721U (en) Bearing platform of tower crane for vertical tower of top plate of foundation garage
CN203271096U (en) Operating platform
CN206554609U (en) The detachable prefabricated enclosure wall of job site
CN205257792U (en) Bridge crane with triangular support girder
CN204139631U (en) The guard rail of building site fast demountable
CN207728104U (en) A kind of detachable hoarding
CN212866842U (en) Frame structure type building scaffold
CN211473320U (en) Tool type external hanging rack for corridor
CN208023608U (en) A kind of post-cast strip can have enough to meet the need steel channel formwork system
CN203654789U (en) Combined type shaping safety net on periphery of building
CN207003765U (en) Assembling type steel structure builds self-bearing type steel truss form bracing system
CN210178376U (en) Combined main frame body device of tunnel lining gantry-free trolley
CN204850162U (en) Combination formula feed bin partition wall by steel sheet preparation
CN215054690U (en) Temporary steel wall-attached frame for roof on construction elevator
CN218323856U (en) Detachable scaffold connecting piece
CN212897769U (en) Scaffold ascending channel capable of being used in turnover mode
CN205036162U (en) Basis is kept off to prefabricated enclosing of repeatedly usable
CN203113384U (en) Detachable top plate reinforcing supporting device
CN203420271U (en) Purlin part
CN214885385U (en) Can have enough to meet need limit entrance to a cave wall post formwork operation platform that uses

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171013

Termination date: 20211202

CF01 Termination of patent right due to non-payment of annual fee