CN206539354U CN201720219155.3U CN201720219155U CN206539354U CN 206539354 U CN206539354 U CN 206539354U CN 201720219155 U CN201720219155 U CN 201720219155U CN 206539354 U CN206539354 U CN 206539354U
Authority
CN
China
Prior art keywords
layer
lining
seep water
water cure
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720219155.3U
Other languages
Chinese (zh)
Inventor
和兆建
郭殿军
原国华
吕船
黄帅
赵铭伟
陈军军
何广宝
邓秦峰
宋萍
杨平波
李青
安定宇
赵云川
刘涛
姚剑
安鹏
靳秀红
马志强
牟开
王程宏
张坤
陈亚军
赵博文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd
Original Assignee
Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd filed Critical Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd
Priority to CN201720219155.3U priority Critical patent/CN206539354U/en
Application granted granted Critical
Publication of CN206539354U publication Critical patent/CN206539354U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of tunnel double-lining surface seep water cure structure, and along at seam at the construction joint of secondary lining or infiltration crack, the structure includes:U-type groove, waterproof layer, heat-insulation layer and epoxy anticracking grout layer, wherein, YAS semicanals are laid in U-type groove, and the concrete layer of secondary lining is fixed on by hydro-expansive rubber bar and rivet.The utility model provides the lining surface seep water cure construction of one kind two to have runed for many years and being in the tunnel of water enrichment area, plays ponding after exclusion lining cutting, prevents the water leaked out from flowing on runway, influence traffic safety, while improving the effect of tunnel durability.

Description

A kind of tunnel double-lining surface seep water cure structure
Technical field
The utility model is related to Tunnel Engineering technical field, specifically provides a kind of tunnel double-lining surface seep water cure knot Structure.
Background technology
The anti-of domestic new highway tunnel, water discharge technology there has been set of designing technique specification and construction technique normalizing. Because early stage construction construction technology of tunnel waterproof is limited, a large amount of water seepage of tunnel, the construction disaster of leak are occurred in that.
Newly built tunnels both make to use present guarded drainage technology, due to the limiting of execution conditions, complicated geological structure And splash guard hang during construction technology defect, cause newly built tunnels after building up soon also easily occur infiltration, leakage The situation of water.
Therefore, water seepage of tunnel, leak how are prevented, the reparation punishment after infiltration, leak has become Current Highway maintenance One technical barrier of work.
Utility model content
Technical problem to be solved in the utility model is to provide the lining of one kind two surface for the tunnel in water enrichment area to ooze Leak treatment structures, play ponding after exclusion lining cutting, prevent the water leaked out from flowing on runway, influence traffic safety, simultaneously Improve the effect of tunnel durability.
A kind of tunnel double-lining surface seep water cure structure, along seam at the construction joint of secondary lining 1 or infiltration crack 2 Place, the structure includes:U-type groove 3, waterproof layer 7, heat-insulation layer 8 and epoxy anticracking grout layer 9, wherein, YAS semicanals 4 are laid in U In type groove 3, the concrete layer of secondary lining 1 is sealingly fastened in by hydro-expansive rubber bar 5 and rivet 6.
It is preferred that, the depth of the U-type groove 3 is not less than 15cm.
It is preferred that, the YAS semicanals 4 are arranged on by way of back-off in U-type groove 3.
It is preferred that, the waterproof layer 7 is leak stopping oxidant layer, and thickness is 7cm.
It is preferred that, the insulation layer thickness is 5cm.
It is preferred that, epoxy anticracking grout layer 9 is repair layer, and thickness is 3cm.
Set this construction can in the tunnel runed for many years and be in water enrichment area for being not provided with seepage water cure construction Ponding after lining cutting is effectively excluded, the traffic safety in tunnel durability and tunnel is improved.
Brief description of the drawings
Fig. 1 is the schematic diagram for the tunnel double-lining surface seep water cure structure that the utility model is provided.
Component, toponym and corresponding mark are shown in figure:
It is secondary lining 1, construction joint or infiltration crack 2, U-type groove 3, Yas semicanals 4, hydro-expansive rubber bar 5, rivet 6, anti- Water layer (sealing agent) 7, heat-insulation layer 8, epoxy anticracking grout layer 9.
Embodiment
The utility model is further illustrated with example below in conjunction with the accompanying drawings.
Reference picture 1, tunnel double-lining surface seep water cure structure of the present utility model, including:In the construction of secondary lining 1 U-type groove 3 is opened at seam or permeable joints 2, YAS semicanals 4, hydro-expansive rubber bar 5, rivet 6, waterproof layer (sealing agent) 7, insulation are installed Layer 8, epoxy anticracking grout layer 9.YAS semicanals and hydro-expansive rubber bar 5 between rivet 6 and secondary lining concrete by reliably connecting Connect.
YAS semicanals 4 are arranged on by way of back-off in U-type groove 3.The depth of U-type groove 3 is not less than 15cm.Waterproof layer 7 is Leak stopping oxidant layer, thickness is 7cm.Insulation layer thickness is 5cm.Epoxy anticracking grout layer 9 is repair layer, and thickness is 3cm.
During construction, first, the particular location of construction joint or permeable joints is determined, then edge is stitched each 7.5cm unwrapping wire in both sides, cut Cut, slot, bottom land, which is tried one's best, ensures smooth;Second step, rises drills in groove, and drilling depth is not less than lining thickness;3rd Step, YAS semicanals are installed along groove center line, and hydro-expansive rubber bar and rivet are installed while installing semicanal;4th step, live mixing Sealing agent, blocks U-type groove 7cm depths with sealing agent, then installs 5cm heat-insulation layers, finally repairs U-shaped using epoxy anticracking grout Groove, repairs thickness 3cm.
Engineering practice shows, is installed on the secondary lining surface of seepage aqua region after this drain structure effectively can exclude lining cutting Ponding, prevents ponding from flowing to road surface, has ensured the traffic safety of road traffic and the durability of tunnel concrete.
Example of the present utility model is explained in detail above in conjunction with accompanying drawing, but the utility model be not limited to it is above-mentioned Example, can also be before the utility model objective not be departed from the knowledge that those of ordinary skill in the art possess The various change made is put, protection domain of the present utility model is also should be regarded as.

Claims (6)

1. a kind of tunnel double-lining surface seep water cure structure, it is characterised in that construction joint or infiltration positioned at secondary lining (1) Crack (2) place is along at seam, and the structure includes:U-type groove (3), waterproof layer (7), heat-insulation layer (8) and epoxy anticracking grout layer (9), Wherein, YAS semicanals (4) are laid in U-type groove (3), are sealingly fastened in by hydro-expansive rubber bar (5) and rivet (6) secondary The concrete layer of lining cutting (1).
2. tunnel double-lining surface seep water cure structure according to claim 1, it is characterised in that the U-type groove (3) Depth is not less than 15cm.
3. tunnel double-lining surface seep water cure structure according to claim 2, it is characterised in that the YAS semicanals (4) It is arranged on by way of back-off in U-type groove (3).
4. tunnel double-lining surface seep water cure structure according to claim 3, it is characterised in that the waterproof layer (7) It is leak stopping oxidant layer, thickness is 7cm.
5. tunnel double-lining surface seep water cure structure according to claim 4, it is characterised in that the heat-insulation layer (8) Thickness be 5cm.
6. tunnel double-lining surface seep water cure structure according to claim 5, it is characterised in that the epoxy cracking resistance sand Pulp layer (9) is repair layer, and thickness is 3cm.
CN201720219155.3U 2017-03-08 2017-03-08 A kind of tunnel double-lining surface seep water cure structure Expired - Fee Related CN206539354U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720219155.3U CN206539354U (en) 2017-03-08 2017-03-08 A kind of tunnel double-lining surface seep water cure structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720219155.3U CN206539354U (en) 2017-03-08 2017-03-08 A kind of tunnel double-lining surface seep water cure structure

Publications (1)

Publication Number Publication Date
CN206539354U true CN206539354U (en) 2017-10-03

Family

ID=59941503

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720219155.3U Expired - Fee Related CN206539354U (en) 2017-03-08 2017-03-08 A kind of tunnel double-lining surface seep water cure structure

Country Status (1)

Country Link
CN (1) CN206539354U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316942A (en) * 2018-01-11 2018-07-24 中交路桥建设有限公司 A kind of tunnel double-lining microcrack reinforcement
CN108825272A (en) * 2018-09-07 2018-11-16 西南交通大学 Lining construction seam infiltration drain structure and its implementation method
CN108914968A (en) * 2018-09-13 2018-11-30 中冶长天国际工程有限责任公司 A kind of pipe gallery and its installation method with waterproof connector
CN108952774A (en) * 2018-06-12 2018-12-07 济南城建集团有限公司 A kind of method that tunnel double-lining construction joint leakage water blocking row combines punishment
CN109113768A (en) * 2018-11-06 2019-01-01 中南大学 A kind of lining construction seam waterproof construction and waterproof method
CN109915180A (en) * 2019-04-01 2019-06-21 大连市市政设计研究院有限责任公司 A kind of Tunnel Second Lining cracking method for treating seepage
CN111088996A (en) * 2020-01-15 2020-05-01 四川省交通勘察设计研究院有限公司 A drainage structures for highway tunnel hoop construction joint
CN111287792A (en) * 2020-02-17 2020-06-16 四川省交通勘察设计研究院有限公司 Drainage device for water seepage of tunnel pavement and construction process

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316942A (en) * 2018-01-11 2018-07-24 中交路桥建设有限公司 A kind of tunnel double-lining microcrack reinforcement
CN108952774A (en) * 2018-06-12 2018-12-07 济南城建集团有限公司 A kind of method that tunnel double-lining construction joint leakage water blocking row combines punishment
CN108825272A (en) * 2018-09-07 2018-11-16 西南交通大学 Lining construction seam infiltration drain structure and its implementation method
CN108914968A (en) * 2018-09-13 2018-11-30 中冶长天国际工程有限责任公司 A kind of pipe gallery and its installation method with waterproof connector
CN108914968B (en) * 2018-09-13 2023-10-27 中冶长天国际工程有限责任公司 Utility tunnel with waterproof connector and installation method thereof
CN109113768A (en) * 2018-11-06 2019-01-01 中南大学 A kind of lining construction seam waterproof construction and waterproof method
CN109915180A (en) * 2019-04-01 2019-06-21 大连市市政设计研究院有限责任公司 A kind of Tunnel Second Lining cracking method for treating seepage
CN111088996A (en) * 2020-01-15 2020-05-01 四川省交通勘察设计研究院有限公司 A drainage structures for highway tunnel hoop construction joint
CN111287792A (en) * 2020-02-17 2020-06-16 四川省交通勘察设计研究院有限公司 Drainage device for water seepage of tunnel pavement and construction process

Similar Documents

Publication Publication Date Title
CN206539354U (en) A kind of tunnel double-lining surface seep water cure structure
CN102797266B (en) Well sealing waterproof construction method for dewatering well
CN107217691A (en) For city underground leak stopping and the method for strengthening construction
CN109441535A (en) A kind of tunnel waterproof and water drainage system and its construction method
CN107387123A (en) The construction method of pressure grouting leak stopping is carried out for shield duct piece piece Seepage
CN109610504A (en) A kind of progressive regulation method of railway open trench tunnel lining deformation joints percolating water
JP2016173003A (en) Water leakage countermeasure construction method for tunnel constructed using natm construction method
CN109371861A (en) A kind of culvert of reinforced concrete subsiding crack infiltration Treatment Methods and repair structure
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN109208651A (en) Underground engineering super-long structural body deformation joint waterproof/drainage structure construction method and structure
CN202730786U (en) Well-sealing waterproof construction structure of dewatering well
CN107012893A (en) A kind of basement bottom wall board post poured band waterproof construction and its construction method
CN108843386A (en) Tunnel roof waterproof drainage structure and water seepage treatment method thereof
CN106245688B (en) One kind prevention basement water leakage of floor constructing structure and its construction technology
CN107100206A (en) A kind of prevention and controls of basement leakage
CN208982109U (en) A kind of tunnel structure with antiseepage drain function
CN108590752A (en) Draining repair system and its construction method after a kind of underdrain formula tunnel-liner
CN107587434A (en) Culvert of reinforced concrete percolating water prevention and disposition method
CN208619166U (en) Waterproof drainage structure of tunnel roof
CN208072433U (en) A kind of interim precipitation steel sleeve being used for basic posthole and catch pit
CN217176564U (en) Water gushing plugging device for base drilling
CN112901222B (en) Treatment process for concrete water seepage cracks of inverted arch of tunnel
CN205954651U (en) Concrete open caisson back cover structure
CN112593981B (en) Water leakage treatment method for segment splicing seam of shield section

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171003

Termination date: 20190308

CF01 Termination of patent right due to non-payment of annual fee