CN206538735U CN201720099024.6U CN201720099024U CN206538735U CN 206538735 U CN206538735 U CN 206538735U CN 201720099024 U CN201720099024 U CN 201720099024U CN 206538735 U CN206538735 U CN 206538735U
Authority
CN
China
Prior art keywords
slope section
net cage
horizontal segment
river
shore structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720099024.6U
Other languages
Chinese (zh)
Inventor
郭维东
刘冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENYANG SHUNYUANDE ENGINEERING CONSULTING Co Ltd
Original Assignee
SHENYANG SHUNYUANDE ENGINEERING CONSULTING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENYANG SHUNYUANDE ENGINEERING CONSULTING Co Ltd filed Critical SHENYANG SHUNYUANDE ENGINEERING CONSULTING Co Ltd
Priority to CN201720099024.6U priority Critical patent/CN206538735U/en
Application granted granted Critical
Publication of CN206538735U publication Critical patent/CN206538735U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

A kind of environmental compound shore structure, including the bank protection between riverbank (1) and riverbed bed (5);Bank protection constitute by the slope section (2) that connects with riverbank and with the horizontal segment (4) that riverbed bed connects, and the upper end of slope section is higher than the design water level (10) in river, and the height of horizontal segment is higher than river water level (9);The bottom of horizontal segment and slope section is the net cage (8) equipped with stone, and the top of slope section is the shrub (3) for having plantation in backfill (7), backfill.The shore structure have the advantages that to make river course not " hardening ", good visual effect, adaptive ability is strong, impact resistance is strong, stability good, profitable on ecology.

Description

A kind of environmental compound shore structure
Technical field
The utility model is related to hydraulic engineering, particularly a kind of environmental compound shore structure.
Background technology
River water area and contacting for land-based area is caused to be cut river progress human intervention using hardening riverbank due to the mankind It is weak, cause river ecosystem to be degenerated.To solve this problem, the theory that river course carries out ecological management is arisen at the historic moment.
Being presently used for the building of river course two sides bank slope protection mainly includes concrete revetment, gabion bank protection, grass-planting brick shield Slope and vegetation slope pavement etc..Wherein, the shortcoming of concrete revetment is that construction investment is big and easily cause river course " three change " (linearization(-sation), rule Then change and harden), do not meet ecology and control river theory;The shortcoming of gabion bank protection is to be also easy to produce current scour and poor visual effect;Plant The shortcoming of careless brick bank protection is more sensitive to ground, once produce sedimentation, easy large area deformation and damage;Simple plant shield The defect on slope is that impact resistance is poor, and washing away for river course bank slope can not be prevented effectively from the case of flood.
Utility model content
To overcome the problem of above-mentioned riverbank bank slope protection building is present, the utility model provide a kind of construction investment compared with Low, good visual effect, adaptive ability are strong and it is possible to prevente effectively from the ecotype that river course bank slope washes away is combined shore structure.
The ecotype that the utility model is provided is combined shore structure, including the bank protection between riverbank and riverbed bed; The bank protection is constituted by the slope section that connects with riverbank and with the horizontal segment that riverbed bed connects, upper end the setting higher than river of slope section Water level is counted, the height of horizontal segment is higher than river water level;The bottom of horizontal segment and slope section is the net cage equipped with stone, slope section Top is the shrub for having plantation in backfill, backfill.
The net cage is square, is worked out by 8#-10# galvanized wires or lattice guest material;The size (length × width × height) of net cage For 4m × 1m × 0.5m or 2m × 1m × 0.5m;The mesh of net cage is hexagon, the size (B × H) of net cage is 8cm × 10cm, Any of 12cm × 10cm, 12cm × 15cm, 15cm × 15cm.
Compared with existing bank slope protection building, the advantage of the compound shore structure of the utility model ecotype is:
1st, it is combined by shrub with the net cage equipped with stone and constitutes bank protection, river course " hardening " can be avoided.
2nd, shrub is planted in the backfill of slope section, with preferable visual effect.
3rd, make shore structure that there is good adaptive ability using shrub and the flexibility of the net cage equipped with stone.
4th, compared with simple plantation plant bank protection, this shore structure has stronger impact resistance, it can be ensured that bank slope There is good stability under design conditions.
5th, using the growth characteristics of shrub, coordinate with the net cage equipped with stone, can reach and control the soil erosion, promotion organic Pollutant decomposition, improved soil and the effect prevented erosion, with good ecological benefits.
Brief description of the drawings
Fig. 1 is the schematic diagram (view profile) of the compound shore structure of the utility model ecotype;
Fig. 2 is the stereogram of single net cage in Fig. 1 (upper lid opens shape);
Fig. 3 is the grid enlarged drawing of Fig. 2 net cages.
In figure:1- riverbanks, 2- slope sections, 3- shrubs, 4- horizontal segments, 5- riverbeds bed, 6- excavation lines, 7- backfills, 8- nets Case, 9- river water levels, 10- design water levels.
Embodiment
Below in conjunction with accompanying drawing, the utility model is described in further detail.
As shown in figure 1, the compound shore structure of the utility model ecotype is included between riverbank 1 and riverbed bed 5 Bank protection;The bank protection is constituted by the slope section 2 that connects with riverbank and with the horizontal segment 4 that riverbed bed 5 connects, and the upper end of slope section is higher than The design water level 10 in river, the height of horizontal segment is higher than river water level 9;The bottom of horizontal segment and slope section be equipped with stone (not Diagram) net cage 8, net cage be Fig. 2 shown in it is square, worked out by 8#-10# galvanized wires, size (length × width × height) be 4m × 1m × 0.5m, the mesh of net cage is the hexagon shown in Fig. 3, and its size (B × H) is 8cm × 10cm.The top of slope section is back Banket 7, the shrub 3 for having plantation in backfill.
With reference to Fig. 1, Fig. 2 and Fig. 3, the construction of above-mentioned shore structure is carried out in the steps below:
1st, excavate bank protection basis, wherein excavation line 6 slope section the gradient according to edaphic condition according to specification value;Excavate Line is determined in the length of horizontal segment by 2-3 times of river channel erosion depth.
2nd, after bank protection foundation excavation is finished, determine stake unwrapping wire, carry out the laying of net cage basis.
3rd, by design and installation net cage after the laying of net cage basis is finished, by net cage justified margin, partition is installed, during assembling gauze pad Partition is set to intersect with the tank wall of net cage in 90 °, then colligation assembles gauze pad.
4th, shaping is carried out to mounted net cage, then carries out colligation with materials such as bamboo pole, wooden stick, steel pipe or planks, be Filling stone is prepared.
5th, stone is filled into the net cage by shaping and colligation, the particle diameter of stone is greater than the mesh of net cage.
6th, after filled stone block end, with the side silk of diameter 2.0mm multiple twin iron wire fixed cage:Multiple twin iron wire is every 8- 15cm double helixs once, make the side silk of net cage mutually be close to, it is ensured that net cage is neat;Then colligation net cage before filling stone is removed The materials such as bamboo pole, wooden stick, steel pipe or plank.
7th, 30cm-50cm backfill is covered on the net cage top of slope section;Connect in the net cage of horizontal segment with riverbed bed Also backfill is dosed in place.
8th, shrub is planted in the backfill of slope section:From the raw amorpha fruticosa saplings of 1-2, dug by seeding row spacing 0.5m-1.0m Cave, cave depth 30cm-50cm plants 2-3 plants per cave, every plant 2-3, is highly 0.5m-1.0m after trimming, earths up and tread after cultivation If (antecedent soil moisture is earthed up and treaded again after need to first pouring water).

Claims (2)

1. a kind of environmental compound shore structure, including the bank protection between riverbank (1) and riverbed bed (5);Its feature exists Constituted in, the bank protection by the slope section (2) that connects with riverbank and with the horizontal segment (4) that riverbed bed connects, the upper end of slope section Higher than the design water level (10) in river, the height of horizontal segment is higher than river water level (9);The bottom of horizontal segment and slope section be equipped with The net cage (8) of stone, the top of slope section is the shrub (3) for having plantation in backfill (7), backfill.
2. environmental compound shore structure according to claim 1, it is characterised in that the net cage (8) be it is square, by 8#-10# galvanized wires or the establishment of lattice guest material;The size of net cage is 4m × 1m × 0.5m or 2m × 1m × 0.5m;The net of net cage Hole is hexagon, and the size of mesh is any of 8cm × 10cm, 12cm × 10cm, 12cm × 15cm, 15cm × 15cm.
CN201720099024.6U 2017-01-23 2017-01-23 A kind of environmental compound shore structure Expired - Fee Related CN206538735U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720099024.6U CN206538735U (en) 2017-01-23 2017-01-23 A kind of environmental compound shore structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720099024.6U CN206538735U (en) 2017-01-23 2017-01-23 A kind of environmental compound shore structure

Publications (1)

Publication Number Publication Date
CN206538735U true CN206538735U (en) 2017-10-03

Family

ID=59940320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720099024.6U Expired - Fee Related CN206538735U (en) 2017-01-23 2017-01-23 A kind of environmental compound shore structure

Country Status (1)

Country Link
CN (1) CN206538735U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111926766A (en) * 2020-07-06 2020-11-13 上海崇明水利工程有限公司 Soil erosion and water loss prevention type revetment structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111926766A (en) * 2020-07-06 2020-11-13 上海崇明水利工程有限公司 Soil erosion and water loss prevention type revetment structure

Similar Documents

Publication Publication Date Title
CN103898870A (en) Gabion box ecological gabion river channel slope protection construction method
CN208685545U (en) A kind of bank protection structure improving land and water domain ecological environment
CN206681021U (en) Multi-functional side slope reinforced structure
CN103397613A (en) Biological check dam used for erosion gully control and construction method
CN103774627A (en) Method for constructing anti-seepage type ecological channel in irrigation region
CN103362135B (en) Fang Beng hilllock, protect water and soil net grass bank protection
CN206693140U (en) A kind of protection slope
CN112144552A (en) Damaged mountain ecological vegetation restoration structure, implementation method and application thereof
CN105672198B (en) A kind of reservoir inundation submergence area restores abandoned land to cultivation structure and its construction method with making
CN207109721U (en) A kind of river channel ecology Afforestation Landscape structure
CN203755322U (en) Channel pipe network guarded body used for slope protection and drainage and soil fixation of slope collapse
CN206189345U (en) Dry rubble ecological landscape bank protection is filled on concrete check ridge
CN206538735U (en) A kind of environmental compound shore structure
CN104695379A (en) Ecological river channel revetment structure
CN207525721U (en) A kind of eco-drainage ditch structure
CN206625181U (en) River course soil layer safeguard structure
CN206189348U (en) A ecological brick for river levee soil and water conservation
CN205501928U (en) Structure of restoreing abandoned land to cultivation is distinguished in reservoir inundation submergence with making
CN205954574U (en) Ecological bank protection of river course dykes and dams
CN111321700B (en) Overflowing energy dissipation type ecological bank protection method for anti-scouring and anti-landslide barrier plugs
CN202090355U (en) Plant-growing side slope ecological protection structure capable of preventing rain wash
CN205152966U (en) Ecological concrete bank protection earth embankment
CN212405181U (en) Granite mountain ecological remediation structure
CN211498716U (en) Stone planting wall
CN204000745U (en) A kind of bulwark

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171003