CN206503156U - A kind of photovoltaic bracket basis - Google Patents
A kind of photovoltaic bracket basis Download PDFInfo
- Publication number
- CN206503156U CN206503156U CN201621308659.4U CN201621308659U CN206503156U CN 206503156 U CN206503156 U CN 206503156U CN 201621308659 U CN201621308659 U CN 201621308659U CN 206503156 U CN206503156 U CN 206503156U
- Authority
- CN
- China
- Prior art keywords
- cage
- photovoltaic bracket
- bracket basis
- standards
- steel reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model provides a kind of photovoltaic bracket basis, it includes the vertical steel reinforcement cage that bottom is embedded under earth's surface, and be set in the steel hoop cage that on vertical steel reinforcement cage and bottom is embedded under earth's surface, vertical steel reinforcement cage and the steel hoop cage and poured concrete.The utility model can reduce because dust storm corrodes and to the injury caused by photovoltaic bracket basis, it is and simple in construction, with low cost.
Description
Technical field
The utility model is related to technical field of photovoltaic power generation, and in particular to a kind of photovoltaic bracket basis.
Background technology
Photovoltaic bracket basis is mainly used in installing, supports photovoltaic bracket and solar cell module.Photovoltaic bracket basis
Design will fully take into account the factors such as load-bearing, wind resistance, antidetonation.
At present, photovoltaic bracket foundation main will include isolated footing, strip footing, prefabricated pile basis, bored concrete pile foundation, spiral
Pile foundation etc..For the extreme terrain geomorphological structure of desert area, when carrying out the design selection on photovoltaic power plant bracket basis, greatly
Majority uses bored concrete pile foundation.
In desert area, the dust storm of photovoltaic plant place be lost in it is more serious because dust storm is than larger throughout the year, sand sometimes
Photovoltaic module can be buried, the partial denudation that photovoltaic bracket basis can be eroded and cause its original to be located under earth's surface sometimes exists
Outside, load-bearing and wind loading rating that now can be to photovoltaic bracket basis have a negative impact, so as to influence the matter of whole photovoltaic plant
Amount.
Specifically, the structure of existing bored concrete pile foundation is as shown in Figure 1.After strong wind runs into bored concrete pile 1, strong wind can be round filling
Note stake 1 and produce whirlwind, after being eroded by a period of time, the earth's surface around bored concrete pile 1 just occurs that swirl shape is recessed, so that
Originally be located at earth's surface under bored concrete pile foundation it is naked be exposed on the external, and then reduce bored concrete pile foundation bearing capacity and wind resistance power.
In order to solve the above problems, generally checked winds and fixed drifting sand at present using following two modes:
1) windbreak method.
Windbreak is set up in photovoltaic place periphery, wind erosion of the strong wind to photovoltaic plant place is prevented by windbreak, is lacked
Point is construction cost than larger, and is not very big to the wind erosion barrier effect on photovoltaic bracket basis.
2) straw checkerboard barrier sand-protecting barrier fixes the sand method.
Long stalk etc. is embedded in grid prefabricated in advance in photovoltaic place periphery and fixed the sand, has the disadvantage that straw etc. is similar
Thing easily, it is necessary to often safeguard, and cost is than larger, typically in a photovoltaic plant surrounding using straw checkerboard barrier fixed the sand method by corruption
Costs up to a million or even up to ten million are then needed, while the dust storm loss to place inside bracket basis does not have good work yet
With.
It can be seen that, design it is a kind of can reduce because dust storm corrodes and to the injury caused by photovoltaic bracket basis and with low cost
Scheme of checking winds and fixing drifting sand turn into technical problem urgently to be resolved hurrily at present.
Utility model content
Technical problem to be solved in the utility model is that there is provided one kind for the drawbacks described above in the presence of prior art
Photovoltaic bracket basis, it can be reduced because of dust storm erosion to the injury caused by photovoltaic bracket basis, and simple in construction, cost is low
It is honest and clean.
Solving the technical scheme that is used of the utility model technical problem is:
The utility model provides a kind of photovoltaic bracket basis, and it includes the vertical steel reinforcement cage that bottom is embedded under earth's surface, with
And it is set in the steel hoop cage that on vertical steel reinforcement cage and bottom is embedded under earth's surface, vertical steel reinforcement cage and the steel hoop cage
Concrete is inside poured.
Alternatively, the vertical steel reinforcement cage includes many first standards being along the circumferential direction uniformly arranged, and fixed
The first helical member on the outside of many first standards, and the bearing of trend and the first standards of first helical member
Bearing of trend is identical.
Alternatively, top, the bottom of the top of first helical member, bottom respectively with many first standards are concordant.
Alternatively, the diameter range of the vertical steel reinforcement cage is 250-400mm.
Alternatively, the vertical steel reinforcement cage is located at the height and whole vertical steel of the part on steel hoop cage upper surface
The ratio of the height of muscle cage is 1/3~1/2.
Alternatively, the steel hoop cage includes many second standards being along the circumferential direction uniformly arranged, and fixed
The second helical member on the outside of many second standards, and the bearing of trend and the second standards of second helical member
Bearing of trend is identical.
Alternatively, top, the bottom of the top of second helical member, bottom respectively with the second standards are concordant.
Alternatively, the external diametrical extent of the steel hoop cage is that 500-800mm, inside diameter ranges are 250-400mm;The ring
The height of shape steel reinforcement cage is 50-100mm.
Alternatively, the altitude range of the part under the steel hoop cage embedment earth's surface is 20-50mm;And/or, it is described
The height of part and the ratio of the height of whole steel hoop cage under steel hoop cage embedment earth's surface are 2/3~1.
Alternatively, the ratio of the diameter of the vertical steel reinforcement cage and the external diameter of steel hoop cage is 1/2.5~1/2.
Beneficial effect:
Photovoltaic bracket described in the utility model basis due to being arranged steel hoop cage outside vertical steel reinforcement cage, and the two it
Inside concern has concrete, so as to play a part of checking winds and fixing drifting sand, reduces caused by dust storm erosion and to photovoltaic bracket basis
Injury;Steel hoop cage and its concrete of interior perfusion can be reinforced to sandy soil earth's surface simultaneously, it is ensured that photovoltaic bracket base
The normal work of plinth, reduces the maintaining expense in later stage, while also improving the service life of bracket basis.
Brief description of the drawings
Fig. 1 is the structural representation of bored concrete pile foundation in the prior art;
The structural representation on the photovoltaic bracket basis that Fig. 2 provides for the utility model embodiment.
In figure:A- wind directions;1- bored concrete piles;2- photovoltaic brackets basis;The vertical steel reinforcement cages of 21-;22- steel hoop cages;
23- concrete.
Embodiment
To make those skilled in the art more fully understand the technical solution of the utility model, with reference to the accompanying drawings and examples
The utility model is described in further detail.
As shown in Fig. 2 the utility model embodiment provides a kind of photovoltaic bracket basis 2, it includes bottom and is embedded in earth's surface
Under vertical steel reinforcement cage 21, and be set on vertical steel reinforcement cage 21 and bottom is embedded in the steel hoop cage 22 under earth's surface, institute
State in vertical steel reinforcement cage 21 and steel hoop cage 22 and poured concrete 23, wherein, the diameter Ying Yuhuan of vertical steel reinforcement cage 21
The internal diameter of shape steel reinforcement cage 22 is adapted.
Specifically, the vertical steel reinforcement cage 21 includes many first standards being along the circumferential direction uniformly arranged, Yi Jigu
It is scheduled on the first helical member on the outside of many first standards, and the bearing of trend and the first standards of first helical member
Bearing of trend it is identical, concrete 23 is cast in the cylindrical region that the first helical member and many first standards are surrounded.Compared with
Excellently, top, the bottom of the top of first helical member, bottom respectively with many first standards are concordant, to play more preferably
Fixation.
In the present embodiment, the diameter range of the vertical steel reinforcement cage 21 is 250-400mm, preferably 250mm.
The vertical steel reinforcement cage 21 is located at the height and whole vertical reinforcing bar of the part on the upper surface of steel hoop cage 22
The ratio of the height of cage 21 is 1/3~1/2.
Specifically, the steel hoop cage 22 includes many second standards being along the circumferential direction uniformly arranged, Yi Jigu
It is scheduled on the second helical member on the outside of many second standards, and the bearing of trend and the second standards of second helical member
Bearing of trend it is identical, concrete 23 is cast in the cylindrical region that the second helical member and many second standards are surrounded.Compared with
Excellently, top, the bottom of the top of second helical member, bottom respectively with the second standards are concordant, preferably solid to play
It is set for using.
In the present embodiment, the external diametrical extent of the steel hoop cage 22 is 500-800mm, preferably 500mm, the annular
The inside diameter ranges of steel reinforcement cage 22 are 250-400mm, preferably 250mm;The height of the steel hoop cage 22 is 50-100mm, excellent
Elect 50mm as.
The altitude range of part under the embedment of steel hoop cage 22 earth's surface is 20-50mm;And/or, the annular
The height of part and the ratio of the height of whole steel hoop cage 22 under the embedment earth's surface of steel reinforcement cage 22 are 2/3~1.
The ratio of the diameter of the vertical steel reinforcement cage 21 and the external diameter of steel hoop cage 22 is 1/2.5~1/2.
When strong wind is blown along wind direction a against photovoltaic bracket basis 2, due to there is the concrete foundation of above-mentioned special construction
Protection, so as to reduce wind erosion, effectively protects photovoltaic bracket basis, plays the effect checked winds and fixed drifting sand.
The affected process on photovoltaic bracket basis 2 is described below in detail:
First, a diameter of 250mm vertical steel reinforcement cage 21 is prepared, and external diameter is that 500mm, internal diameter are 250mm, are highly
50mm steel hoop cage 22;
Secondly, drilled in the earth's surface of predeterminated position, bore diameter is 250mm, drilling depth can be by operating personnel
Set according to field condition, ream operation is then carried out on the basis of existing aperture, counter bore diameter is 500mm, reaming
Depth is in 20mm, and device to hole and earth's surface is pre-processed, and surface soil layer is compacted so that without loosened soil in hole;
Again, vertical steel reinforcement cage 21 is put into drilling, be then enclosed on steel hoop cage 22 on vertical steel reinforcement cage 21 simultaneously
It is put into reaming;
Finally, the casting concrete 23 in vertical steel reinforcement cage 21 and steel hoop cage 22, to form structure of checking winds and fixing drifting sand.
It is understood that embodiment of above be merely to illustrate that principle of the present utility model and use it is exemplary
Embodiment, but the utility model is not limited thereto.For those skilled in the art, this is not being departed from
In the case of the spirit and essence of utility model, various changes and modifications can be made therein, and these variations and modifications are also considered as this reality
With new protection domain.
Claims (10)
1. a kind of photovoltaic bracket basis, it is characterised in that the vertical steel reinforcement cage under earth's surface is embedded in including bottom, and is set in
On vertical steel reinforcement cage and bottom, which is embedded in the steel hoop cage under earth's surface, vertical steel reinforcement cage and the steel hoop cage, to be poured
There is concrete.
2. photovoltaic bracket basis according to claim 1, it is characterised in that the vertical steel reinforcement cage is included along the circumferential direction
Many first standards being uniformly arranged, and the first helical member on the outside of many first standards is fixed on, and it is described
The bearing of trend of first helical member is identical with the bearing of trend of the first standards.
3. photovoltaic bracket basis according to claim 2, it is characterised in that top, the bottom point of first helical member
Top, bottom not with many first standards is concordant.
4. according to any one of claim 1-3 photovoltaic bracket basis, it is characterised in that the vertical steel reinforcement cage it is straight
Footpath scope is 250-400mm.
5. the photovoltaic bracket basis according to any one of claim 1-3, it is characterised in that the vertical steel reinforcement cage is located at
The ratio of the height of part on steel hoop cage upper surface and the height of whole vertical steel reinforcement cage is 1/3~1/2.
6. photovoltaic bracket basis according to claim 1, it is characterised in that the steel hoop cage is included along the circumferential direction
Many second standards being uniformly arranged, and the second helical member on the outside of many second standards is fixed on, and it is described
The bearing of trend of second helical member is identical with the bearing of trend of the second standards.
7. photovoltaic bracket basis according to claim 6, it is characterised in that top, the bottom point of second helical member
Top, bottom not with the second standards is concordant.
8. the photovoltaic bracket basis according to any one of claim 1,6-7, it is characterised in that the steel hoop cage
External diametrical extent is that 500-800mm, inside diameter ranges are 250-400mm;The height of the steel hoop cage is 50-100mm.
9. the photovoltaic bracket basis according to any one of claim 1,6-7, it is characterised in that the steel hoop cage is buried
The altitude range for entering the part under earth's surface is 20-50mm;And/or, the steel hoop cage is embedded to the part under earth's surface
The ratio of height and the height of whole steel hoop cage is 2/3~1.
10. the photovoltaic bracket basis according to any one of claim 1-3,6-7, it is characterised in that the vertical reinforcing bar
The ratio of the diameter of cage and the external diameter of steel hoop cage is 1/2.5~1/2.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621308659.4U CN206503156U (en) | 2016-12-01 | 2016-12-01 | A kind of photovoltaic bracket basis |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621308659.4U CN206503156U (en) | 2016-12-01 | 2016-12-01 | A kind of photovoltaic bracket basis |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206503156U true CN206503156U (en) | 2017-09-19 |
Family
ID=59842681
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621308659.4U Expired - Fee Related CN206503156U (en) | 2016-12-01 | 2016-12-01 | A kind of photovoltaic bracket basis |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206503156U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117966801A (en) * | 2024-03-28 | 2024-05-03 | 中国电建集团西北勘测设计研究院有限公司 | Support foundation for a photovoltaic power plant for sand |
-
2016
- 2016-12-01 CN CN201621308659.4U patent/CN206503156U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117966801A (en) * | 2024-03-28 | 2024-05-03 | 中国电建集团西北勘测设计研究院有限公司 | Support foundation for a photovoltaic power plant for sand |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206289651U (en) | A kind of offshore wind power foundation structure of single pile anchoring | |
CN103225304B (en) | A kind of marine foundation supporting structure and construction method thereof | |
CN103469808B (en) | The offshore wind turbine foundation that a kind of concrete caisson and jacket combine | |
US20160047107A1 (en) | Underwater support concrete structure construction method | |
KR101189681B1 (en) | A support apparatus for sea wind power generator | |
CN103195076A (en) | Method for constructing silt deep foundation pit tower crane foundation | |
US20120301227A1 (en) | Foundation pile and installing method thereof | |
CN204676584U (en) | A kind of high stake truss-like offshore wind turbine foundation structure | |
CN104499501B (en) | Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line | |
CN206503156U (en) | A kind of photovoltaic bracket basis | |
CN107476316B (en) | Building foundation pit internal and external support structure and construction method | |
CN206052761U (en) | A kind of marine wind electric field single-pile foundation | |
CN106013213B (en) | A kind of offshore wind farm pile foundation and its application method for increasing single-machine capacity | |
Jensen et al. | European offshore wind engineering–past, present and future | |
CN209082546U (en) | A kind of composite base structure suitable for marine wind electric field fan | |
CN105155573A (en) | Offshore wind turbine barrel-in-barrel foundation | |
CN110670620A (en) | Cast-in-place gravity type suction caisson foundation with wing plates | |
KR101384168B1 (en) | installation method of slab foundation for offshore wind power generator using position senser | |
CN202482886U (en) | Cast-in-place pile steel reinforcement cage for ultra-thick high compression peat soil layer structure | |
CN206143801U (en) | Photovoltaic case contravariant basis that adapts to multiple ambient condition | |
CN205502070U (en) | A dual -purpose underground gallery structure | |
CN210712864U (en) | Deep foundation pit supporting system of Larsen steel sheet pile and cement mixing pile for soft soil field | |
RU2530142C2 (en) | Method of construction of sheet piling when conducting works at major pipeline and mountable-dismountable sheet piling for development of foundation pit | |
CN106120846A (en) | A kind of marine wind electric field single-pile foundation and construction method | |
CN105908773A (en) | Two-stage socketed pile wind turbine foundation for shallow covering stratum foundation of offshore wind plant and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170919 Termination date: 20201201 |
|
CF01 | Termination of patent right due to non-payment of annual fee |