CN206503156U - A kind of photovoltaic bracket basis - Google Patents

A kind of photovoltaic bracket basis Download PDF

Info

Publication number
CN206503156U
CN206503156U CN201621308659.4U CN201621308659U CN206503156U CN 206503156 U CN206503156 U CN 206503156U CN 201621308659 U CN201621308659 U CN 201621308659U CN 206503156 U CN206503156 U CN 206503156U
Authority
CN
China
Prior art keywords
cage
photovoltaic bracket
bracket basis
standards
steel reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621308659.4U
Other languages
Chinese (zh)
Inventor
郭庆
李长龙
黄宁
刘佳
陈超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TBEA Xinjiang Sunoasis Co Ltd
Original Assignee
TBEA Xinjiang Sunoasis Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TBEA Xinjiang Sunoasis Co Ltd filed Critical TBEA Xinjiang Sunoasis Co Ltd
Priority to CN201621308659.4U priority Critical patent/CN206503156U/en
Application granted granted Critical
Publication of CN206503156U publication Critical patent/CN206503156U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model provides a kind of photovoltaic bracket basis, it includes the vertical steel reinforcement cage that bottom is embedded under earth's surface, and be set in the steel hoop cage that on vertical steel reinforcement cage and bottom is embedded under earth's surface, vertical steel reinforcement cage and the steel hoop cage and poured concrete.The utility model can reduce because dust storm corrodes and to the injury caused by photovoltaic bracket basis, it is and simple in construction, with low cost.

Description

A kind of photovoltaic bracket basis
Technical field
The utility model is related to technical field of photovoltaic power generation, and in particular to a kind of photovoltaic bracket basis.
Background technology
Photovoltaic bracket basis is mainly used in installing, supports photovoltaic bracket and solar cell module.Photovoltaic bracket basis Design will fully take into account the factors such as load-bearing, wind resistance, antidetonation.
At present, photovoltaic bracket foundation main will include isolated footing, strip footing, prefabricated pile basis, bored concrete pile foundation, spiral Pile foundation etc..For the extreme terrain geomorphological structure of desert area, when carrying out the design selection on photovoltaic power plant bracket basis, greatly Majority uses bored concrete pile foundation.
In desert area, the dust storm of photovoltaic plant place be lost in it is more serious because dust storm is than larger throughout the year, sand sometimes Photovoltaic module can be buried, the partial denudation that photovoltaic bracket basis can be eroded and cause its original to be located under earth's surface sometimes exists Outside, load-bearing and wind loading rating that now can be to photovoltaic bracket basis have a negative impact, so as to influence the matter of whole photovoltaic plant Amount.
Specifically, the structure of existing bored concrete pile foundation is as shown in Figure 1.After strong wind runs into bored concrete pile 1, strong wind can be round filling Note stake 1 and produce whirlwind, after being eroded by a period of time, the earth's surface around bored concrete pile 1 just occurs that swirl shape is recessed, so that Originally be located at earth's surface under bored concrete pile foundation it is naked be exposed on the external, and then reduce bored concrete pile foundation bearing capacity and wind resistance power.
In order to solve the above problems, generally checked winds and fixed drifting sand at present using following two modes:
1) windbreak method.
Windbreak is set up in photovoltaic place periphery, wind erosion of the strong wind to photovoltaic plant place is prevented by windbreak, is lacked Point is construction cost than larger, and is not very big to the wind erosion barrier effect on photovoltaic bracket basis.
2) straw checkerboard barrier sand-protecting barrier fixes the sand method.
Long stalk etc. is embedded in grid prefabricated in advance in photovoltaic place periphery and fixed the sand, has the disadvantage that straw etc. is similar Thing easily, it is necessary to often safeguard, and cost is than larger, typically in a photovoltaic plant surrounding using straw checkerboard barrier fixed the sand method by corruption Costs up to a million or even up to ten million are then needed, while the dust storm loss to place inside bracket basis does not have good work yet With.
It can be seen that, design it is a kind of can reduce because dust storm corrodes and to the injury caused by photovoltaic bracket basis and with low cost Scheme of checking winds and fixing drifting sand turn into technical problem urgently to be resolved hurrily at present.
Utility model content
Technical problem to be solved in the utility model is that there is provided one kind for the drawbacks described above in the presence of prior art Photovoltaic bracket basis, it can be reduced because of dust storm erosion to the injury caused by photovoltaic bracket basis, and simple in construction, cost is low It is honest and clean.
Solving the technical scheme that is used of the utility model technical problem is:
The utility model provides a kind of photovoltaic bracket basis, and it includes the vertical steel reinforcement cage that bottom is embedded under earth's surface, with And it is set in the steel hoop cage that on vertical steel reinforcement cage and bottom is embedded under earth's surface, vertical steel reinforcement cage and the steel hoop cage Concrete is inside poured.
Alternatively, the vertical steel reinforcement cage includes many first standards being along the circumferential direction uniformly arranged, and fixed The first helical member on the outside of many first standards, and the bearing of trend and the first standards of first helical member Bearing of trend is identical.
Alternatively, top, the bottom of the top of first helical member, bottom respectively with many first standards are concordant.
Alternatively, the diameter range of the vertical steel reinforcement cage is 250-400mm.
Alternatively, the vertical steel reinforcement cage is located at the height and whole vertical steel of the part on steel hoop cage upper surface The ratio of the height of muscle cage is 1/3~1/2.
Alternatively, the steel hoop cage includes many second standards being along the circumferential direction uniformly arranged, and fixed The second helical member on the outside of many second standards, and the bearing of trend and the second standards of second helical member Bearing of trend is identical.
Alternatively, top, the bottom of the top of second helical member, bottom respectively with the second standards are concordant.
Alternatively, the external diametrical extent of the steel hoop cage is that 500-800mm, inside diameter ranges are 250-400mm;The ring The height of shape steel reinforcement cage is 50-100mm.
Alternatively, the altitude range of the part under the steel hoop cage embedment earth's surface is 20-50mm;And/or, it is described The height of part and the ratio of the height of whole steel hoop cage under steel hoop cage embedment earth's surface are 2/3~1.
Alternatively, the ratio of the diameter of the vertical steel reinforcement cage and the external diameter of steel hoop cage is 1/2.5~1/2.
Beneficial effect:
Photovoltaic bracket described in the utility model basis due to being arranged steel hoop cage outside vertical steel reinforcement cage, and the two it Inside concern has concrete, so as to play a part of checking winds and fixing drifting sand, reduces caused by dust storm erosion and to photovoltaic bracket basis Injury;Steel hoop cage and its concrete of interior perfusion can be reinforced to sandy soil earth's surface simultaneously, it is ensured that photovoltaic bracket base The normal work of plinth, reduces the maintaining expense in later stage, while also improving the service life of bracket basis.
Brief description of the drawings
Fig. 1 is the structural representation of bored concrete pile foundation in the prior art;
The structural representation on the photovoltaic bracket basis that Fig. 2 provides for the utility model embodiment.
In figure:A- wind directions;1- bored concrete piles;2- photovoltaic brackets basis;The vertical steel reinforcement cages of 21-;22- steel hoop cages; 23- concrete.
Embodiment
To make those skilled in the art more fully understand the technical solution of the utility model, with reference to the accompanying drawings and examples The utility model is described in further detail.
As shown in Fig. 2 the utility model embodiment provides a kind of photovoltaic bracket basis 2, it includes bottom and is embedded in earth's surface Under vertical steel reinforcement cage 21, and be set on vertical steel reinforcement cage 21 and bottom is embedded in the steel hoop cage 22 under earth's surface, institute State in vertical steel reinforcement cage 21 and steel hoop cage 22 and poured concrete 23, wherein, the diameter Ying Yuhuan of vertical steel reinforcement cage 21 The internal diameter of shape steel reinforcement cage 22 is adapted.
Specifically, the vertical steel reinforcement cage 21 includes many first standards being along the circumferential direction uniformly arranged, Yi Jigu It is scheduled on the first helical member on the outside of many first standards, and the bearing of trend and the first standards of first helical member Bearing of trend it is identical, concrete 23 is cast in the cylindrical region that the first helical member and many first standards are surrounded.Compared with Excellently, top, the bottom of the top of first helical member, bottom respectively with many first standards are concordant, to play more preferably Fixation.
In the present embodiment, the diameter range of the vertical steel reinforcement cage 21 is 250-400mm, preferably 250mm.
The vertical steel reinforcement cage 21 is located at the height and whole vertical reinforcing bar of the part on the upper surface of steel hoop cage 22 The ratio of the height of cage 21 is 1/3~1/2.
Specifically, the steel hoop cage 22 includes many second standards being along the circumferential direction uniformly arranged, Yi Jigu It is scheduled on the second helical member on the outside of many second standards, and the bearing of trend and the second standards of second helical member Bearing of trend it is identical, concrete 23 is cast in the cylindrical region that the second helical member and many second standards are surrounded.Compared with Excellently, top, the bottom of the top of second helical member, bottom respectively with the second standards are concordant, preferably solid to play It is set for using.
In the present embodiment, the external diametrical extent of the steel hoop cage 22 is 500-800mm, preferably 500mm, the annular The inside diameter ranges of steel reinforcement cage 22 are 250-400mm, preferably 250mm;The height of the steel hoop cage 22 is 50-100mm, excellent Elect 50mm as.
The altitude range of part under the embedment of steel hoop cage 22 earth's surface is 20-50mm;And/or, the annular The height of part and the ratio of the height of whole steel hoop cage 22 under the embedment earth's surface of steel reinforcement cage 22 are 2/3~1.
The ratio of the diameter of the vertical steel reinforcement cage 21 and the external diameter of steel hoop cage 22 is 1/2.5~1/2.
When strong wind is blown along wind direction a against photovoltaic bracket basis 2, due to there is the concrete foundation of above-mentioned special construction Protection, so as to reduce wind erosion, effectively protects photovoltaic bracket basis, plays the effect checked winds and fixed drifting sand.
The affected process on photovoltaic bracket basis 2 is described below in detail:
First, a diameter of 250mm vertical steel reinforcement cage 21 is prepared, and external diameter is that 500mm, internal diameter are 250mm, are highly 50mm steel hoop cage 22;
Secondly, drilled in the earth's surface of predeterminated position, bore diameter is 250mm, drilling depth can be by operating personnel Set according to field condition, ream operation is then carried out on the basis of existing aperture, counter bore diameter is 500mm, reaming Depth is in 20mm, and device to hole and earth's surface is pre-processed, and surface soil layer is compacted so that without loosened soil in hole;
Again, vertical steel reinforcement cage 21 is put into drilling, be then enclosed on steel hoop cage 22 on vertical steel reinforcement cage 21 simultaneously It is put into reaming;
Finally, the casting concrete 23 in vertical steel reinforcement cage 21 and steel hoop cage 22, to form structure of checking winds and fixing drifting sand.
It is understood that embodiment of above be merely to illustrate that principle of the present utility model and use it is exemplary Embodiment, but the utility model is not limited thereto.For those skilled in the art, this is not being departed from In the case of the spirit and essence of utility model, various changes and modifications can be made therein, and these variations and modifications are also considered as this reality With new protection domain.

Claims (10)

1. a kind of photovoltaic bracket basis, it is characterised in that the vertical steel reinforcement cage under earth's surface is embedded in including bottom, and is set in On vertical steel reinforcement cage and bottom, which is embedded in the steel hoop cage under earth's surface, vertical steel reinforcement cage and the steel hoop cage, to be poured There is concrete.
2. photovoltaic bracket basis according to claim 1, it is characterised in that the vertical steel reinforcement cage is included along the circumferential direction Many first standards being uniformly arranged, and the first helical member on the outside of many first standards is fixed on, and it is described The bearing of trend of first helical member is identical with the bearing of trend of the first standards.
3. photovoltaic bracket basis according to claim 2, it is characterised in that top, the bottom point of first helical member Top, bottom not with many first standards is concordant.
4. according to any one of claim 1-3 photovoltaic bracket basis, it is characterised in that the vertical steel reinforcement cage it is straight Footpath scope is 250-400mm.
5. the photovoltaic bracket basis according to any one of claim 1-3, it is characterised in that the vertical steel reinforcement cage is located at The ratio of the height of part on steel hoop cage upper surface and the height of whole vertical steel reinforcement cage is 1/3~1/2.
6. photovoltaic bracket basis according to claim 1, it is characterised in that the steel hoop cage is included along the circumferential direction Many second standards being uniformly arranged, and the second helical member on the outside of many second standards is fixed on, and it is described The bearing of trend of second helical member is identical with the bearing of trend of the second standards.
7. photovoltaic bracket basis according to claim 6, it is characterised in that top, the bottom point of second helical member Top, bottom not with the second standards is concordant.
8. the photovoltaic bracket basis according to any one of claim 1,6-7, it is characterised in that the steel hoop cage External diametrical extent is that 500-800mm, inside diameter ranges are 250-400mm;The height of the steel hoop cage is 50-100mm.
9. the photovoltaic bracket basis according to any one of claim 1,6-7, it is characterised in that the steel hoop cage is buried The altitude range for entering the part under earth's surface is 20-50mm;And/or, the steel hoop cage is embedded to the part under earth's surface The ratio of height and the height of whole steel hoop cage is 2/3~1.
10. the photovoltaic bracket basis according to any one of claim 1-3,6-7, it is characterised in that the vertical reinforcing bar The ratio of the diameter of cage and the external diameter of steel hoop cage is 1/2.5~1/2.
CN201621308659.4U 2016-12-01 2016-12-01 A kind of photovoltaic bracket basis Expired - Fee Related CN206503156U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621308659.4U CN206503156U (en) 2016-12-01 2016-12-01 A kind of photovoltaic bracket basis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621308659.4U CN206503156U (en) 2016-12-01 2016-12-01 A kind of photovoltaic bracket basis

Publications (1)

Publication Number Publication Date
CN206503156U true CN206503156U (en) 2017-09-19

Family

ID=59842681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621308659.4U Expired - Fee Related CN206503156U (en) 2016-12-01 2016-12-01 A kind of photovoltaic bracket basis

Country Status (1)

Country Link
CN (1) CN206503156U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117966801A (en) * 2024-03-28 2024-05-03 中国电建集团西北勘测设计研究院有限公司 Support foundation for a photovoltaic power plant for sand

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117966801A (en) * 2024-03-28 2024-05-03 中国电建集团西北勘测设计研究院有限公司 Support foundation for a photovoltaic power plant for sand

Similar Documents

Publication Publication Date Title
CN206289651U (en) A kind of offshore wind power foundation structure of single pile anchoring
CN103225304B (en) A kind of marine foundation supporting structure and construction method thereof
CN103469808B (en) The offshore wind turbine foundation that a kind of concrete caisson and jacket combine
US20160047107A1 (en) Underwater support concrete structure construction method
KR101189681B1 (en) A support apparatus for sea wind power generator
CN103195076A (en) Method for constructing silt deep foundation pit tower crane foundation
US20120301227A1 (en) Foundation pile and installing method thereof
CN204676584U (en) A kind of high stake truss-like offshore wind turbine foundation structure
CN104499501B (en) Narrow-foundation-tower single-pile pier-type self-stabilized foundation for power transmission line
CN206503156U (en) A kind of photovoltaic bracket basis
CN107476316B (en) Building foundation pit internal and external support structure and construction method
CN206052761U (en) A kind of marine wind electric field single-pile foundation
CN106013213B (en) A kind of offshore wind farm pile foundation and its application method for increasing single-machine capacity
Jensen et al. European offshore wind engineering–past, present and future
CN209082546U (en) A kind of composite base structure suitable for marine wind electric field fan
CN105155573A (en) Offshore wind turbine barrel-in-barrel foundation
CN110670620A (en) Cast-in-place gravity type suction caisson foundation with wing plates
KR101384168B1 (en) installation method of slab foundation for offshore wind power generator using position senser
CN202482886U (en) Cast-in-place pile steel reinforcement cage for ultra-thick high compression peat soil layer structure
CN206143801U (en) Photovoltaic case contravariant basis that adapts to multiple ambient condition
CN205502070U (en) A dual -purpose underground gallery structure
CN210712864U (en) Deep foundation pit supporting system of Larsen steel sheet pile and cement mixing pile for soft soil field
RU2530142C2 (en) Method of construction of sheet piling when conducting works at major pipeline and mountable-dismountable sheet piling for development of foundation pit
CN106120846A (en) A kind of marine wind electric field single-pile foundation and construction method
CN105908773A (en) Two-stage socketed pile wind turbine foundation for shallow covering stratum foundation of offshore wind plant and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170919

Termination date: 20201201

CF01 Termination of patent right due to non-payment of annual fee