CN206477344U - Foundation pit supporting construction - Google Patents

Foundation pit supporting construction Download PDF

Info

Publication number
CN206477344U
CN206477344U CN201720047937.3U CN201720047937U CN206477344U CN 206477344 U CN206477344 U CN 206477344U CN 201720047937 U CN201720047937 U CN 201720047937U CN 206477344 U CN206477344 U CN 206477344U
Authority
CN
China
Prior art keywords
pile
prestressed pipe
supporting construction
foundation pit
guan liang
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720047937.3U
Other languages
Chinese (zh)
Inventor
王锋刚
王志中
李有建
赵春鹏
梁凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201720047937.3U priority Critical patent/CN206477344U/en
Application granted granted Critical
Publication of CN206477344U publication Critical patent/CN206477344U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model is related to a kind of foundation pit supporting construction, including:It is embedded in the soil body of foundation ditch surrounding and spaced pile for prestressed pipe;It is inserted in the shaped steel part in the pile for prestressed pipe;And the Guan Liang being formed at the top of the pile for prestressed pipe is poured, multiple pile for prestressed pipe are connected by the Guan Liang.The utility model is arranged on using the pile for prestressed pipe combination in a row laid at the top of pile tube and elongated Guan Liang is as the supporting construction of foundation ditch, reduces the deformation of foundation pit side-wall, it is ensured that foundation ditch is in stable state.And inserted with shaped steel part in pile for prestressed pipe, improve bending resistance, the shear behavior of single pile tube, the final holistic resistant behavior for improving supporting construction.It ensure that the supporting of foundation ditch is stable.

Description

Foundation pit supporting construction
Technical field
The utility model is related to foundation pit supporting project field, refers in particular to a kind of foundation pit supporting construction.
Background technology
When being excavated to the deep basal pit that cutting depth is more than 10 meters, to prevent excavation construction from causing surface displacement, prevent Excessive deformation and destruction occur for foundation ditch periphery existing building, to ensure safe construction under deep basal pit, and reduce deep basal pit to attached Nearly existed building, the influence of road, need to carry out timely, firm supporting to foundation ditch.
During the existing progress supporting to foundation ditch, the supporting scheme of anchor pole is generally added using campshed, single drilling is specifically used Bored concrete pile adds the piled anchor formula supporting scheme that individual layer soil anchor bolt is combined.But campshed adds the supporting scheme of anchor pole to there is work progress The problems such as complexity, low construction efficiency, higher input cost.And the anchor force of anchor pole is not enough, for the supporting effect of deep basal pit It is poor.
Utility model content
The purpose of this utility model is that the defect for overcoming prior art, there is provided a kind of foundation pit supporting construction, is solved existing Work progress complexity, low construction efficiency and the input cost height that the supporting scheme of anchor pole is present etc. is added using campshed in technology Problem.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of foundation pit supporting construction, including:
It is embedded in the soil body of foundation ditch surrounding and spaced pile for prestressed pipe;
It is inserted in the shaped steel part in the pile for prestressed pipe;And
The Guan Liang being formed at the top of the pile for prestressed pipe is poured, multiple pile for prestressed pipe are linked to be one by the Guan Liang Body.
The utility model is combined using the pile for prestressed pipe in a row laid to be arranged at the top of pile tube and elongated Guan Liang conduct The supporting construction of foundation ditch, reduces the deformation of foundation pit side-wall, it is ensured that foundation ditch is in stable state.And in pile for prestressed pipe inserted with Shaped steel part, improves bending resistance, the shear behavior of single pile tube, the final holistic resistant behavior for improving supporting construction.It ensure that foundation ditch Supporting it is stable.
The utility model foundation pit supporting construction further improvement is that, the top of the shaped steel part is embedded to the Guan Liang It is interior.
The utility model foundation pit supporting construction further improvement is that, poured in the pile for prestressed pipe and be formed with a core Structure.
The utility model foundation pit supporting construction further improvement is that, the shaped steel part be I-steel.
The utility model foundation pit supporting construction further improvement is that, in addition to be completely hung on the pile for prestressed pipe and lean on The geotechnological layer of cloth of the nearly foundation ditch side.
The utility model foundation pit supporting construction further improvement is that, the geotechnological layer of cloth passes through in two prestressed pipes U-shaped card between stake in the insertion soil body hangs the side for being fixed on the pile for prestressed pipe.
Brief description of the drawings
Fig. 1 is the sectional view of the utility model foundation pit supporting construction.
Fig. 2 is the sectional view of pile for prestressed pipe in the utility model foundation pit supporting construction.
Fig. 3 is the sectional view of Guan Liang and pile for prestressed pipe in the utility model foundation pit supporting construction.
Fig. 4 is the sectional view of geotextiles in the utility model foundation pit supporting construction.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1 and Fig. 2, the utility model provides a kind of foundation pit supporting construction, particular for complexity such as weak soil, flour sands In limited, strict to the foundation pit deformation requirement deep-foundation pit engineering under the conditions of addressing context and proposed place.The supporting construction has There are good integrity, security performance stable, environmental protection, construction method is simple, economic benefit and duration remarkable benefit.With reference to Accompanying drawing is illustrated to the utility model foundation pit supporting construction.
As shown in figure 1, the utility model provides a kind of foundation pit supporting construction, for the supporting to foundation ditch 10, it is ensured that base The stabilization in hole 10.With reference to shown in Fig. 2, the foundation pit supporting construction includes pile for prestressed pipe 21, shaped steel part 22 and Guan Liang 23, in advance Stress pile tube 21 is embedded in the soil body 11 of the surrounding of foundation ditch 10, and pile for prestressed pipe 21 is arranged at intervals and in a row laid.Shaped steel part 22 are inserted in pile for prestressed pipe 21, so as to improve the bending resistance of single pile for prestressed pipe 21, shear behavior, finally play raising The effect of supporting construction holistic resistant behavior.Guan Liang 23 pours the top for being formed at pile for prestressed pipe 21, will be many by Guan Liang 23 Individual pile for prestressed pipe 21 is connected.
The utility model is combined using the pile for prestressed pipe in a row laid to be arranged at the top of pile tube and elongated Guan Liang conduct The supporting construction of foundation ditch, reduces the deformation of foundation pit side-wall, it is ensured that foundation ditch is in stable state.And in pile for prestressed pipe inserted with Shaped steel part, improves bending resistance, the shear behavior of single pile tube, the final holistic resistant behavior for improving supporting construction.It ensure that foundation ditch Supporting it is stable.
Further, with reference to shown in Fig. 3, when shaped steel part 22 is inserted into pile for prestressed pipe 21, the top of shaped steel part 22 is allowed Portion protrudes out the mouth of pipe of pile for prestressed pipe 21 so that when subsequently pouring Guan Liang 23, in the top embedment Guan Liang 23 of shaped steel part 22. The bonding strength between Guan Liang 23 and pile for prestressed pipe 21 is added, while also improving the stress performance of supporting construction.
As a better embodiment of the present utility model, with reference to shown in Fig. 2, shaped steel part 22 is being inserted into prestressed pipe After in stake 21, a cored structure 211 is formed with being poured in pile for prestressed pipe 21, shaped steel part 22 is anchored by stake cored structure 211, This cored structure 211 is formed by pouring microdilatancy pea gravel concreten into pile for prestressed pipe 21.It is preferred that shaped steel part 22 is adopted With I-steel, include two flange plates and the web being connected between flange plate, web is with the direction at the edge of vertical foundation pit 10 Set, the edge of such two of which flange plate and foundation ditch be arranged in parallel.
As shown in Figure 1 and Figure 4, as a better embodiment of the present utility model, foundation pit supporting construction also includes full extension In the geotechnological layer of cloth 24 on pile for prestressed pipe 21 close to the side of foundation ditch 10, geotechnological layer of cloth 24 is attached at the internal face of foundation ditch 10, applied The excavation of foundation ditch can be carried out after pile for prestressed pipe and Guan Liang after work, foundation ditch is when excavating, the internal face and prestressing force of the foundation ditch Pile tube 21 is affixed, so the geotechnological layer of cloth 24 is covered in the side on pile for prestressed pipe 21 close to foundation ditch 10, that is, by geotechnique Layer of cloth 24 is covered on the internal face of foundation ditch 10.It is preferred that the geotechnological layer of cloth 24 is fixed by U-shaped card 25, the U-shaped card 25 is from soil The outside of work layer of cloth 24 is through in geotechnological layer of cloth 24 and the soil body 11 that is inserted into two pile for prestressed pipe 21, so that by geotechnique Layer of cloth 24 is fixed on the side of pile for prestressed pipe 21.
Pile for prestressed pipe 21 of the present utility model is used using PHC piles (PHC), I-steel 12.6# I-steel, first uses hammering method in place, then to be pressed I-steel according to pile tube anchor point successively pile sinking concrete tubular pile Go deep into pile for prestressed pipe according to perpendicular to foundation pit side-wall direction total length.In tube pile construction, after after earth excavation to designed elevation, according to Secondary releasing piling foundation plan, it is then -- loose to press from both sides -- rising -- according to pushing successively from two ends to middle or from centre to two ends orders Press from both sides again -- the order pressed again carries out that alignment straightening, pile extension and Stake head handling should be carried out in piling construction, pile driving process.I-steel Interpolation is constructed, after prestressing pipe pile construction is finished, and the 12.6# I-steel made according to the long processing of stake is sequentially placed into pre- answer In solenoid stake, reinforcing bar is welded in the depth anchored into according to I-steel in Guan Liang so that I-steel vertical foundation pit sidewall direction is placed in the middle It is placed in Guan Liang.
After pile tube and I-steel construction are finished, then required according to construction drawing, the earthwork of Guan Liang position is cleared up Totally, reinforcing bar colligation, formwork are carried out successively, microdilatancy pea gravel concreten is finally poured in pile for prestressed pipe, treat to mix in pile tube Solidifying soil, which is poured, to be finished after static a period of time, then carried out Guan Liang concrete construction, concrete construction should be carried out after finishing insulation and Maintenance work.
When being preced with beam steel bar colligation and model sheetinstallat, the earthwork to the Guan Liang design bottom at Guan Liang is cleaned out according to drawing requirement and is marked Height, then carries out that cover to reinforcement thickness should be stopped in the work such as hat beam steel bar colligation, model sheetinstallat, reinforcing bar process of binding successively Degree.
In pile for prestressed pipe inner concrete and Guan Liang concreting, I-steel simultaneously vertical foundation pit side wall side placed in the middle is checked To after formwork reinforcement is intact, casting concrete successively as requested should be first in casting prestressed pile tube during concreting Concrete, tubular pile concrete is poured finish after answer stagnation for a period of time, then carry out Guan Liang concreting, should during casting concrete Carry out concrete vibrating work.
After concrete pouring construction is finished, the maintenance work of concrete, particularly winter should be carried out, heat-preserving anti-freezing should be carried out Measure, it is to avoid concrete is endured cold.
In pile for prestressed pipe insert I-steel+Guan Liang supporting construction and its construction method quick construction efficiently, environmental protection, peace Full performance stabilization, economic benefit and duration remarkable benefit, compared to concrete drilling bored concrete pile+Guan Liang cable bolting mode, energy Construction cost is enough saved, with 135.7 meters long from south to north, exemplified by the foundation pit structure that 95.4 meters of thing length, supporting knot of the present utility model Structure saves more than 900,000 yuan of construction cost altogether compared to concrete drilling bored concrete pile+Guan Liang cable bolting mode.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some of embodiment details should not be constituted to this practicality New restriction, the utility model regard the scope defined using appended claims as protection domain of the present utility model.

Claims (6)

1. a kind of foundation pit supporting construction, it is characterised in that including:
It is embedded in the soil body of foundation ditch surrounding and spaced pile for prestressed pipe;
It is inserted in the shaped steel part in the pile for prestressed pipe;And
The Guan Liang being formed at the top of the pile for prestressed pipe is poured, multiple pile for prestressed pipe are connected by the Guan Liang.
2. foundation pit supporting construction as claimed in claim 1, it is characterised in that the top of the shaped steel part is embedded to the Guan Liang It is interior.
3. foundation pit supporting construction as claimed in claim 1 or 2, it is characterised in that pour and be formed with the pile for prestressed pipe Stake cored structure.
4. foundation pit supporting construction as claimed in claim 1, it is characterised in that the shaped steel part is I-steel.
5. foundation pit supporting construction as claimed in claim 1, it is characterised in that also leaned on including being completely hung on the pile for prestressed pipe The geotechnological layer of cloth of the nearly foundation ditch side.
6. foundation pit supporting construction as claimed in claim 5, it is characterised in that the geotechnological layer of cloth passes through in two prestressed pipes U-shaped card between stake in the insertion soil body hangs the side for being fixed on the pile for prestressed pipe.
CN201720047937.3U 2017-01-16 2017-01-16 Foundation pit supporting construction Expired - Fee Related CN206477344U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720047937.3U CN206477344U (en) 2017-01-16 2017-01-16 Foundation pit supporting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720047937.3U CN206477344U (en) 2017-01-16 2017-01-16 Foundation pit supporting construction

Publications (1)

Publication Number Publication Date
CN206477344U true CN206477344U (en) 2017-09-08

Family

ID=59753561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720047937.3U Expired - Fee Related CN206477344U (en) 2017-01-16 2017-01-16 Foundation pit supporting construction

Country Status (1)

Country Link
CN (1) CN206477344U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457706A (en) * 2018-12-28 2019-03-12 北京城建北方集团有限公司 Foundation pit edge protection can be had enough to meet the need
CN111021353A (en) * 2019-12-30 2020-04-17 中国建筑第四工程局有限公司 Reinforcement method and structure for prestressed pipe pile defects
CN113216218A (en) * 2021-03-26 2021-08-06 招商局重庆交通科研设计院有限公司 Cutting slope anti-slip structure and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457706A (en) * 2018-12-28 2019-03-12 北京城建北方集团有限公司 Foundation pit edge protection can be had enough to meet the need
CN109457706B (en) * 2018-12-28 2024-04-02 北京城建北方集团有限公司 Can have enough to meet need foundation ditch face limit protection
CN111021353A (en) * 2019-12-30 2020-04-17 中国建筑第四工程局有限公司 Reinforcement method and structure for prestressed pipe pile defects
CN113216218A (en) * 2021-03-26 2021-08-06 招商局重庆交通科研设计院有限公司 Cutting slope anti-slip structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN103306289B (en) Foundation pit piled anchor dado concrete anchor cable top beam structure and construction method thereof
CN110042716B (en) Widening construction method for high-fill roadbed with foamed light soil
CN101250886B (en) Method for reinforcing masonry structure building base
CN206477344U (en) Foundation pit supporting construction
WO2023213117A1 (en) Widening structure and construction method for existing subgrade embankment wall section near river
CN110777836A (en) Reinforced concrete plate-anchor rod composite foundation and using method thereof
CN107326898B (en) I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof
CN107100160B (en) A kind of construction technology for lower storage reservoir check dam vibro-replacement stone column
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
JP4925267B2 (en) Independent foundation and its construction method
KR100618597B1 (en) Cast in place concrete pile using vibro magnetic shovel hammer, and the construction method of this
CN201649076U (en) Inversed Y-type single-row unidirectional rotary spraying, mixing and reinforcing combined tangent pile
CN201649102U (en) U-shaped double-row unidirectional rotary jet reinforced combination stirring soldier pile
CN105484270B (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
CN112048959A (en) Transverse grouting roadbed reinforcing structure and roadbed repairing method
CN206337566U (en) Foundation ditch vertical prestressing anchor pole supporting construction
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN110820756A (en) Shield well and vertical shaft deep foundation pit excavation safety construction method
KR20120122024A (en) Uniting Method of Temporary earth wall with basement exterior Wall using Couplers and Bolts.
CN216194772U (en) Foundation pit supporting and water stopping system
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
CN108589738A (en) Half gravity dam formula foundation pit enclosure structure and its construction method
CN108914942A (en) A kind of system of deep foundation pit support and its construction method
CN210766868U (en) Reinforcing structure for existing gravity retaining wall
CN201649103U (en) Xi-type single-row multidirectional swing injected agitating reinforced combined supporting pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170908