A kind of hoistable platform for building a wall
Technical field
The utility model is related to building trade technical field, more particularly to a kind of hoistable platform for building a wall.
Background technology
In building trade, the article carrying platform of wall building equipment is rationally set with operating platform is favorably improved operating efficiency,
Employee work amount is reduced, employee's burden is reduced.However, many wall building equipments are during operation at present, due to operating platform
With article carrying platform set it is unreasonable, cause personnel to be operated in work progress relatively painstaking, increase employee's burden, simultaneously
Also reduce operating efficiency.Even, some wall building equipments are not provided with workbench or article carrying platform so that personnel are in production
It is relatively painstaking when to add fragment of brick or paving ash on wall during of a relatively high wall, while adding employee's burden, also drop
Low production efficiency.
Utility model content
In order to solve the above technical problems, the utility model provides a kind of hoistable platform for building a wall.
The utility model is achieved by the following technical programs.
A kind of hoistable platform for building a wall that the utility model is provided, including operating platform and article carrying platform, the behaviour
Make between platform and article carrying platform be provided with step, step upper end connection article carrying platform, lower end attended operation platform, operating platform with
Article carrying platform two ends are respectively equipped with support column A, and support column A tops are provided with crossbeam B, and crossbeam B is provided with motor, motor
Power supply is connected with, motor is connected with chain matching, and the gear that operating platform, article carrying platform two ends are additionally provided with, chain is remote
One end of motor is connected respectively on gear.
Using welding between the operating platform, article carrying platform and step.
Some support column B are respectively equipped with the operating platform, article carrying platform.
Pull bar, track and crossbeam are welded with the support column B.
The pull bar and track are installed each parallel to the side of operating platform or article carrying platform.
The crossbeam A is installed perpendicular to the side of operating platform or article carrying platform.
The beneficial effects of the utility model are:
The utility model is during use, by the setting of operating platform, article carrying platform and step, can take personnel
Brick more facilitates when operating, more laborsaving, so as to reduce the work load of employee, and further improves operating efficiency.Together
When, because operating platform and article carrying platform two ends are respectively equipped with support column A, support column A tops are provided with motor, motor
Power supply is connected with, motor is connected with chain matching, and the one end of chain away from motor is connected respectively flat in operation
On platform, the gear at article carrying platform two ends, in production, operating platform and article carrying platform can also be driven using motor,
And by chain and the gear and the gear at article carrying platform two ends at operating platform two ends, make operating platform and article carrying platform while entering
Row rises or falls regulation, so as to meet the demand that different height is built a wall in production.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
In figure:1- operating platforms, 2- article carrying platforms, 3- support columns A, 4- gear, 5- chains, 6- motors, 7- pull bars,
8- tracks, 9- crossbeams A, 10- step, 11- support columns B, 12- crossbeam B.
Embodiment
Be described further below the technical solution of the utility model, but claimed scope be not limited to it is described.
As shown in figure 1, a kind of hoistable platform for building a wall, including operating platform 1 and article carrying platform 2, the operation is flat
Step 10 is provided between platform 1 and article carrying platform 2, the upper end of step 10 connection article carrying platform 2, lower end attended operation platform 1, operation is flat
Platform 1 is respectively equipped with support column A3 with the two ends of article carrying platform 2, and support column A3 tops are provided with crossbeam B12, and crossbeam B12 is provided with driving
Motor 6, motor 6 is connected with power supply, and motor 6 is connected with the matching of chain 5, and operating platform 1, the two ends of article carrying platform 2 are also
The gear 4 being provided with, the one end of chain 5 away from motor 6 is connected respectively on gear 4., first will branch in actual installation
Dagger A3 and motor 6, which are installed, to be fixed, while installing the master controller of motor 6.Then, using with motor
6 chains 5 that connect of matching are connected to operating platform 1, on the gear 4 that the two ends of article carrying platform 2 are provided with.Afterwards, support column is passed through
A3 fixed support, and motor 6 is adjusted using master controller, make the drive chain 5 of motor 6, and chain 5 acts on tooth
On wheel 4, so that operating platform 1 and article carrying platform 2 be mentioned, and hoisting depth is adjusted using master controller according to demand, from
And it is satisfied the production requirement of building a wall of different height.In operation, fragment of brick etc. needed for first passing through correlative transporting equipment and building a wall
Transport of materials is deposited on article carrying platform, and then operating personnel adjust the height of operating platform 1, article carrying platform 2 by master controller
Degree is so as to meet the production requirement of different height.When building a wall, because operating platform 1 is separated with article carrying platform 2 by step 10,
The materials such as the fragment of brick on article carrying platform 2 are avoided operating platform 1 is caused in stacking to hinder to influence.Meanwhile, in operating platform 1
And in the manufacturing process of article carrying platform 2, the height of step 10 should suitably make according to actual conditions, make personnel take brick to operate as far as possible
Shi Gengjia is convenient, more laborsaving, so as to reduce the work load of employee, and further improves operating efficiency.
It is attached by welding using welding between the operating platform 1, article carrying platform 2 and step 10, makes operation
Connected between platform 1, article carrying platform 2 more firmly, allow operating platform 1, the entirety of article carrying platform 2 and synchronism more preferably, while
Avoid and mutually split in operation between operating platform 1, article carrying platform 2, influence operation, influence production.
Some support column B11 are respectively equipped with the operating platform 1, article carrying platform 2.
Pull bar 7, track 8 and crossbeam A9 are welded with the support column B11.
The pull bar 7 and track 8 are installed each parallel to the side of operating platform 1 or article carrying platform 2.
The crossbeam A9 is installed perpendicular to the side of operating platform 1 or article carrying platform 2.
Support column B11 setting, mainly tie-strut 7, track 8 and crossbeam A9, make pull bar 7, track 8 and crossbeam A9 with
Operating platform 1 or the synchronization lifting of article carrying platform 2, and then it is satisfied with the demand of production.The setting of track 8, is mainly convenient to life
Production process middle cross beam A9's is movable, and then is satisfied with when being built a wall in production and slings transport to fragment of brick front and back position.And it is horizontal
Beam A9 setting, when mainly making to sling fragment of brick in production, can allow fragment of brick to be moved left and right on crossbeam A9, so as to meet
Demand of the diverse location to fragment of brick when building a wall or so.And the setting of pull bar 7, the mainly support to support column B11, prevent support
Post B11 because track 8 and crossbeam A9 hang oneself weight when there is tilt phenomenon, influence operation and produce.