CN206428583U - It is a kind of to be used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence - Google Patents
It is a kind of to be used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence Download PDFInfo
- Publication number
- CN206428583U CN206428583U CN201621199311.6U CN201621199311U CN206428583U CN 206428583 U CN206428583 U CN 206428583U CN 201621199311 U CN201621199311 U CN 201621199311U CN 206428583 U CN206428583 U CN 206428583U
- Authority
- CN
- China
- Prior art keywords
- guardrail
- reinforcing bar
- concrete board
- hanging plate
- prefabricated concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
It is used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence the utility model discloses a kind of, it is characterised in that:The guardrail prefabricated concrete board bottom, which is set, drips, side joint place of dripping sets hanging plate pedestal in guardrail prefabricated concrete board, pre-buried stretching reinforcing bar is extend out to outside guardrail prefabricated concrete board on the inside of guardrail prefabricated concrete board, the guardrail part on the guardrail prefabricated concrete board top is that reinforcing bar in hanging plate is set inside the inclined concrete thin plates in the inside side in top, guardrail prefabricated concrete board.The utility model devises a kind of guardrail prefabricated concrete board, so that the cast-in-place work of part field of armored concrete wall guardrail switchs to prefabrication completion, outside is used as template by the use of hanging plate when guardrail is constructed, eliminate substantial amounts of template, eliminate falsework, only cast-in-place part concrete, shortens on-site construction time.
Description
Technical field
The utility model is related to bridge structure field, more particularly to a kind of bridge new accessory structure construction technique, specifically
For a kind of guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence.
Background technology
Current bridge reinforcement concrete wall type guard rail is generally cast-in-place using template, i.e., choose and set on the outside of arm in superstructure beam
Colligation anti-collision wall reinforcing bar after shuttering cantilever supporting frame, fixed form, completes concrete cast and conserves.Its drawback is that high-altitude is made
Industry influences big to surrounding enviroment, and security is poor, seriously polluted, and on-site concrete casting quality is unstable, the linear quality of anti-collision wall
It is unstable.
By improving, also there are the whole prefabrications of complete prefabricated wall fence technique, i.e. guardrail, in-site installation is general to use
Bolt connection, it is to avoid the drawbacks of complete cast-in-place method, but in, easy leak slightly worse with the durability of the coupling part of beam-ends structure.
Utility model content
The purpose of this utility model is to provide a kind of guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence, can
Armored concrete wall guardrail template and falsework are set up in reduction scene, can reduce shadow of the anti-collision wall construction to surrounding enviroment again
Ring.
To achieve these goals, the technical solution of the utility model is:A kind of half prefabricated reinforced concrete wall fence
Guardrail prefabricated concrete board, it is characterised in that:The guardrail prefabricated concrete board bottom, which is set, drips, and side joint drips in guardrail prefabricated concrete board
Place sets pre-buried stretching reinforcing bar on the inside of hanging plate pedestal, guardrail prefabricated concrete board and extend out to outside guardrail prefabricated concrete board.
According to preferred embodiment of the present utility model, the guardrail part on the guardrail prefabricated concrete board top is top to inner side
Reinforcing bar in hanging plate is set inside inclined concrete thin plates, guardrail prefabricated concrete board.
According to preferred embodiment of the present utility model, the guardrail segment thickness on the guardrail prefabricated concrete board top for 50 ~
80mm, is highly 1000 ~ 1200mm, and angle of inclination is 80 ~ 85 °.
According to preferred embodiment of the present utility model, the plane for dripping inner side to be vertically arranged, outside is flat to tilt
Face, the lower edge width that drips is 90 ~ 110mm, and upper limb width is 140 ~ 160mm, is highly 250 ~ 350mm.
According to preferred embodiment of the present utility model, the height of the hanging plate pedestal is 140 ~ 160mm, the hanging plate pedestal
Width be 170 ~ 180mm.
According to preferred embodiment of the present utility model, pre-buried stretching reinforcing bar includes one group of suspension ring on the inside of guardrail prefabricated concrete board
Reinforcing bar.
According to preferred embodiment of the present utility model, four groups of steel are stretched out under upper in the top of the guardrail prefabricated concrete board
Muscle, first group of reinforcing bar includes a hollow reinforcing bar, and the hollow reinforcing bar side is provided with opening, opening outwardly, in terms of outside
Two L-shaped reinforcing bars being oppositely arranged are presented, and form small gap between the two, hollow reinforcing bar opposite side is embedded in hanging plate in advance,
And with bar connecting in hanging plate;Second group of reinforcing bar includes an arch door shape Ω steel bar, and outside is in arch door shape, the two of Ω steel bars
Pin is embedded in hanging plate in advance, and with bar connecting in hanging plate;3rd group of reinforcing bar also includes a hollow reinforcing bar, the hollow reinforcing bar
Side is provided with opening, at opening outwardly, and hollow reinforcing bar opposite side is embedded in hanging plate in advance, and with bar connecting in hanging plate;4th group
Reinforcing bar includes square frame-shaped reinforcing bar, and side is embedded in hanging plate in advance, and with bar connecting in hanging plate, second group of reinforcing bar be used as suspension ring steel
Muscle.
According to preferred embodiment of the present utility model, four groups of reinforcing bars are diameter 16mm spiral.
The utility model has the advantage of:
1. the utility model devises a kind of guardrail prefabricated concrete board so that the part field of armored concrete wall guardrail
Cast-in-place work switchs to prefabrication completion, and outside eliminates substantial amounts of template and mould by the use of hanging plate as template when guardrail is constructed
Board mount, only cast-in-place part concrete, shortens on-site construction time.
2. prefabricated concrete board is in plant produced, quality of finished product good easily-controllable with maintenance quality is poured into a mould, batch making is convenient, component
Dimensional accuracy is high, live freely adjustable line style.
3. because member-retaining portion is cast-in-place, it is ensured that guardrail and choose being reliably connected for arm, stress performance good, good endurance, phase
Than complete prefabricated anti-collision wall, seam closure will not leak.
4. eliminating workmen scene sets up the workload of falsework, thus reduces the live high-altitude of workmen
The risk of operation, reduces the influence to periphery such as risk and on-site noise, dust of falling object from high altitude.
Brief description of the drawings:
Fig. 1 is that half prefabricated wall fence completes figure.
Fig. 2 is prefabricated concrete board structural map.
Fig. 3 is Fig. 2 inner side view.
Fig. 4 is prefabricated concrete board reinforcement drawing.
Fig. 5 is Fig. 4 lateral plan.
Fig. 6 is one of guardrail construction process figure.
Fig. 7 is the two of guardrail construction process figure.
Fig. 8 is the three of guardrail construction process figure.
Embodiment
Accompanying drawing is the utility model schematic diagram, by taking SS grades of guardrails of certain engineering as an example.
It is a kind of half prefabricated reinforced concrete wall fence as shown in Figure 1, it is characterised in that a part is to protect on the outside of guardrail
The form of column prefabricated concrete board 1 is prefabricated, the pre-buried stretching reinforcing bar in the inner side of guardrail prefabricated concrete board 1, chooses pre-buried in arm 2 with superstructure beam
Reinforcing bar part is welded or colligation, and hanging plate in place is required according to anti-collision wall line style, and link position is smeared and sets up internal model on the inside of slurry, guardrail
Plate, carries out concrete 3 on the inside of the cast of inner side concrete, prefabricated concrete board and cast-in-place guardrail and is collectively forming entirety.
Schematic diagram is by taking SS grades of reinforced guardrails as an example.
Installation site chooses arm sideline to inner side 350mm, outside 150mm, or other sizes.
SS grades of guardrail hanging plates are illustrated as Fig. 2 ~ 5 are shown in prefabricated concrete board structural map and hanging plate in steel bar arrangement figure, figure
Structure principle.
The outside profile of guardrail prefabricated concrete board 1 is consistent with guardrail profile, and thickness can be 65mm, or other sizes are located at
On the outside of guardrail, can as cast-in-place part outboard template;Side joint, which drips, in guardrail prefabricated concrete board sets hanging plate pedestal 4, pedestal chi at 5
Very little is 150mmx173mm(High x is wide), or other sizes, the bottom of hanging plate pedestal 4 chooses arm top with beam and flushes, hanging plate pedestal 4
It act as making hanging plate be fixed on beam choosing on arm;Hanging plate bottom is drips 5, and 5 height of dripping are that outside chooses arm and highly adds 50mm, also may be used
For other sizes, the 5 width lower edges that drip are 100, and upper limb is 150mm, or other sizes, the lateral surface dripped be bottom to
The inclined inclined-plane in inner side, act as making rainwater flow out along lower end herein, without flowing to beam body.
Guardrail height is pave-load layer top surface level above, can be the armored concrete wall guardrail and group of specification defined
Any height of box-like guardrail concrete parts.
Hanging plate is highly:Guardrail height+pave-load layer thickness+drips highly
Hanging plate width is 1495mm, plate stitch 5mm, or other sizes are defined by easy construction.
It is illustrated in figure 3 the reinforcement drawing that SS grades of prefabricated concrete boards are illustrated in prefabricated concrete board reinforcement drawing, figure.11,12,14 in figure
Reinforcing bar is reinforcing bar in hanging plate, and four groups of reinforcing bars are stretched out under upper in the top of the guardrail prefabricated concrete board, wherein first group of reinforcing bar 13a
Including a less hollow reinforcing bar, hollow reinforcing bar side is provided with opening, opening outwardly, and two phases are presented in terms of outside
To the L-shaped reinforcing bar of setting, and form small gap between the two, hollow reinforcing bar opposite side is embedded in hanging plate in advance, and with hanging plate
Bar connecting;Second group of reinforcing bar 13b includes an arched door shape Ω steel bar, and outside is in arch door shape(Or referred to as circular arc), Ω
The bipod of steel bar is embedded in hanging plate in advance, and with bar connecting in hanging plate, it is ensured that the anchorage length of reinforcing bar;3rd group of reinforcing bar
13c also includes a large mouth font reinforcing bar, and hollow reinforcing bar side is provided with opening, opening outwardly, presentation two in terms of outside
The L-shaped reinforcing bar that root is oppositely arranged, and form small gap between the two, hollow reinforcing bar opposite side is embedded in hanging plate in advance, and with extension
Bar connecting in plate;4th group of reinforcing bar 15 then includes a square frame-shaped reinforcing bar, and side is embedded in hanging plate in advance, and connects with reinforcing bar in hanging plate
Connect, second group of reinforcing bar 13b can be used as suspension ring reinforcing bar, embedded bar in arm is chosen by interim reinforcing bar 16 and superstructure beam and welded
Connect to form interim connection, embedded bar is welded in interim one end of reinforcing bar 16 and mat formation reinforcing bar or beam, the other end and second group of reinforcing bar
13b or other reinforcement weldings, the interim connection of composition, play a part of fixed hanging plate, the 4th group of reinforcing bar 15 is arranged at hanging plate pedestal
Top, and set close to hanging plate pedestal, the 4th group of reinforcing bar 15 chooses the welding of embedded bar 17 in arm with superstructure beam and forms permanent
Connection.
Such as Fig. 6 ~ 8 show guardrail construction process figure,
Step one:The construction of prefabricated concrete board is first completed, hanging plate is placed on superstructure beam and chosen on arm, by the 4th group of hanging plate
Reinforcing bar 15 chooses arm embedded bar with superstructure beam and welds to form permanently connected, separately by interim one end of reinforcing bar 16 and mat formation reinforcing bar or
Embedded bar is welded in beam, the other end and second group of reinforcing bar 13b or other reinforcement weldings, the interim connection of composition, and in hanging plate base
Seat bottom smears that cement mortar 6 is levelling, while playing and choosing arm cementation, a few road measures reliably connect hanging plate with choosing arm and being formed
Connect, fixed hanging plate.
Step 2:Side rail reinforcing bar in colligation, sets up concrete on the inside of inner side template 7, cast guardrail.
Step 3:After the concrete curing phase terminates, inner side template is removed, interim reinforcing bar 16 is removed, guardrail construction is completed.
The advantage of the prefabricated reinforced concrete wall fence construction technology of the utility model half is to change traditional guardrail
Form of construction work, the cast-in-place work of part field switchs to prefabrication completion, and outside is saved by the use of hanging plate as template when guardrail is constructed
Substantial amounts of template, only cast-in-place part concrete, shortens on-site construction time.Prefabricated concrete board plant produced, presentation quality is good,
Batch making is convenient, and scantling precision is guaranteed.Because member-retaining portion is cast-in-place, it is ensured that guardrail with choosing being reliably connected for arm,
Stress performance is good, good endurance.The risk of the live work high above the ground of workmen is reduced, on-site noise and dust pair is reduced
The influence on periphery.
Claims (6)
1. a kind of guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence, it is characterised in that:The guardrail prefabricated concrete board
Bottom, which is set, drips, and side joint place of dripping sets hanging plate pedestal in guardrail prefabricated concrete board, pre-buried stretching reinforcing bar on the inside of guardrail prefabricated concrete board
It extend out to outside guardrail prefabricated concrete board, the guardrail part on the guardrail prefabricated concrete board top is thin for the inclined concrete in the inside side in top
Reinforcing bar in hanging plate is set inside plate, guardrail prefabricated concrete board.
2. the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence as claimed in claim 1, it is characterised in that:Guardrail
Pre-buried stretching reinforcing bar at least includes one group of suspension ring reinforcing bar on the inside of prefabricated concrete board.
3. the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence as claimed in claim 1, it is characterised in that:It is described
The guardrail segment thickness on guardrail prefabricated concrete board top is 50 ~ 80mm, is highly 1000 ~ 1200mm, and angle of inclination is 80 ~ 85 °.
4. the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence as claimed in claim 1, it is characterised in that:It is described
It is the plane being vertically arranged on the inside of dripping, outside is clinoplain, the lower edge width that drips is 90 ~ 110mm, and upper limb width is
140 ~ 160mm, is highly 250 ~ 350mm.
5. the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence as claimed in claim 1, it is characterised in that:It is described
The height of hanging plate pedestal is 140 ~ 160mm, and the width of the hanging plate pedestal is 170 ~ 180mm.
6. the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence as claimed in claim 1, it is characterised in that:It is described
Four groups of reinforcing bars are stretched out on the top of guardrail prefabricated concrete board under upper, and first group of reinforcing bar includes a hollow reinforcing bar, the hollow
Reinforcing bar side is provided with opening, opening outwardly, two L-shaped reinforcing bars being oppositely arranged is presented in terms of outside, and formed between the two
Small gap, hollow reinforcing bar opposite side is embedded in hanging plate in advance, and with bar connecting in hanging plate;Second group of reinforcing bar includes an arched door
Shape Ω steel bars, outside is in arch door shape, and the bipod of Ω steel bars is embedded in hanging plate in advance, and with bar connecting in hanging plate;3rd group
Reinforcing bar also includes a hollow reinforcing bar, and the hollow reinforcing bar side is provided with opening, opening outwardly, hollow reinforcing bar opposite side
It is pre- to be embedded in hanging plate, and with bar connecting in hanging plate;4th group of reinforcing bar includes a square frame-shaped reinforcing bar, and side is embedded in hanging plate in advance, and
With bar connecting in hanging plate, second group of reinforcing bar is used as suspension ring reinforcing bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621199311.6U CN206428583U (en) | 2016-11-07 | 2016-11-07 | It is a kind of to be used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621199311.6U CN206428583U (en) | 2016-11-07 | 2016-11-07 | It is a kind of to be used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206428583U true CN206428583U (en) | 2017-08-22 |
Family
ID=59589807
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621199311.6U Active CN206428583U (en) | 2016-11-07 | 2016-11-07 | It is a kind of to be used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206428583U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700094A (en) * | 2019-11-12 | 2020-01-17 | 中国建筑土木建设有限公司 | Viaduct wall-mounted guardrail structure and construction method thereof |
-
2016
- 2016-11-07 CN CN201621199311.6U patent/CN206428583U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700094A (en) * | 2019-11-12 | 2020-01-17 | 中国建筑土木建设有限公司 | Viaduct wall-mounted guardrail structure and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100476142C (en) | Construction method for combined V-shape steel pipe concrete pile | |
CN104963289B (en) | A kind of abnormity pier stud mass concrete overall time pouring construction method | |
CN107190983B (en) | A kind of construction method of prefabricated assembled cornice | |
CN104088461A (en) | Y-type cast-in-place concrete column formwork system and construction method thereof | |
CN105350777A (en) | Device and method for one-time pouring molding of ultra-high concrete column | |
CN106121236B (en) | Floor bar protective layer and structural elevation integrated control method | |
CN108265885A (en) | The construction method of tall and big nonopiate high inclination-angle abnormal shape concrete batter post | |
CN106012851B (en) | Steel box-girder and performance of concrete column confined method for synchronously constructing | |
CN108517869A (en) | A kind of control method of large area concrete surface of base flatness | |
CN105089184B (en) | Multi-curved concrete hollow modelling wall construction method and rhombic hollow structure formwork | |
CN105804110A (en) | Construction method of foundation bolts of railway contact net and mounting bracket | |
CN107476567A (en) | It is a kind of to control the pitched roof gradient and the construction method and track-type facilities of thickness | |
CN106702907A (en) | Bridge guardrail base adjustable flange plate construction method | |
CN207363251U (en) | A kind of track-type facilities for being used to control the pitched roof gradient and thickness | |
CN113202222A (en) | Construction method for assembled type superposed beam slab | |
CN106567328A (en) | Half-prefabricated reinforced concrete wall-type guardrail construction process | |
CN106567329A (en) | Semi-prefabricated reinforced concrete wall type guardrail | |
CN106400686A (en) | Embedded part suspension bracket and construction method thereof | |
CN206428583U (en) | It is a kind of to be used for the guardrail prefabricated concrete board of half prefabricated reinforced concrete wall fence | |
CN106906747A (en) | A kind of column and bent cap splicing structure | |
CN109968522A (en) | The mounting device and installation method of prefabricated case beam bottom web reinforcement skeleton | |
CN109267493A (en) | A kind of construction method installed across river steel lid beam | |
CN104846745A (en) | Urban high-pier support-free formwork turnover construction method | |
CN106401276A (en) | Construction method for wall column binding bars of frame type building block enclosing wall | |
CN206189607U (en) | Rag bolt location structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |