CN206401862U - Assembled prefabricated cable duct - Google Patents
Assembled prefabricated cable duct Download PDFInfo
- Publication number
- CN206401862U CN206401862U CN201720006048.2U CN201720006048U CN206401862U CN 206401862 U CN206401862 U CN 206401862U CN 201720006048 U CN201720006048 U CN 201720006048U CN 206401862 U CN206401862 U CN 206401862U
- Authority
- CN
- China
- Prior art keywords
- ditch body
- dovetail
- cable duct
- dovetail groove
- ditch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model patent is related to cable work technical field of construction, and in particular to a kind of Assembled prefabricated cable duct.The cable shaft includes the prefabricated ditch body and cover plate of some armored concrete, and ditch body takes the shape of the letter U, and ditch body one end is provided with dovetail groove, and the other end is provided with the dovetail matched, and each ditch body is mutually permanently connected by dovetail groove and dovetail.The utility model can carry out batch production batch production, then in construction site Assembling.Ditch body two ends are respectively arranged with the dovetail groove matched, tenon.Connected by the tongue-and-groove of the dovetail groove of adjacent ditch body, dovetail, some sections of ditch bodies are connected into an entirety.Using above-mentioned technical proposal, the Assembled prefabricated cable duct can carry out batch production, modularized production, be easy to unified mass standard and effectively control construction quality;Modular prefabricated components are transported to building site and assembled, and installation rate is fast, are conducive to accelerating the speed of application shortening duration, so as to improve efficiency.
Description
Technical field
The utility model patent is related to cable work technical field of construction, and in particular to a kind of Assembled prefabricated cable duct.
Background technology
In traditional cable work construction, cable duct is typically cast using the artificial brick or on-site concrete in scene, by
In civil engineering team, level of skill is uneven, is not easy to management and control construction quality.In addition, using artificial brick or on-site concrete
Cast quantities big, speed is long in time limit slowly, seriously constrains project progress.
Utility model content
The utility model there is provided a kind of Assembled prefabricated cable duct of dependable performance, can be pressed in view of the shortcomings of the prior art
Unified mass standard, accelerates speed of application, so as to improve production efficiency.
What the technical solution of the utility model was realized in:The Assembled prefabricated cable duct includes some by reinforced concrete
Soil prefabricated ditch body and cover plate, it is characterised in that the ditch body takes the shape of the letter U, and described ditch body one end is provided with dovetail groove, another
End is provided with the dovetail matched, and each ditch body is mutually permanently connected by the dovetail groove and dovetail.
The dovetail groove and dovetail are fixedly connected with precast reinforced in ditch body.
Wall is provided with some cable clips or cable bearer in the ditch body, and the ditch body bottom is provided with for the heavy of draining
Water hole.
The ditch body is provided with the top of the drop handle for being easy to carry, the ditch body and is provided with the chute for being used for placing cover plate, described
Chute uses angle steel bound edge.
The cover plate uses angle steel bound edge.
The Assembled prefabricated cable duct is connected by dovetail groove and dovetail with cable shaft, ring main unit basis.
The utility model solves defect present in background technology, has the advantages that:
The utility model can carry out batch production batch production, then in construction site Assembling.Ditch body two ends are set respectively
It is equipped with the dovetail groove matched, tenon.Connected, i.e., inserted dovetail vertically by the tongue-and-groove of the dovetail groove of adjacent ditch body 1, dovetail
Enter in dovetail groove and fix, some sections of ditch bodies are connected into an entirety.Using above-mentioned technical proposal, the Assembled prefabricated cable duct
Batch production, modularized production can be carried out, is easy to unified mass standard and effectively controls construction quality;Modular prefabricated components fortune
Assembled to building site, installation rate is fast, be conducive to accelerating the speed of application shortening duration, so as to improve efficiency.
Brief description of the drawings
Fig. 1 is dimensional structure diagram of the present utility model;
Fig. 2 is schematic front view of the present utility model;
Fig. 3 is Fig. 2 schematic rear view;
Fig. 4 is schematic cross-sectional views of the Fig. 3 along A-A directions;
In figure:1- ditch bodies, 2- dovetail grooves, 3- dovetails, 4- cable clips, 5- cable beareves, 6- sinks water hole, 7- drop handles,
8- is precast reinforced.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belongs to the scope of the utility model protection.
Assembled prefabricated cable duct as shown in Figure 1, Figure 2, Figure 3 and Figure 4, including some formed by armored concrete is prefabricated
Ditch body 1 and cover plate, ditch body 1 takes the shape of the letter U, and the one end of ditch body 1 is provided with dovetail groove 2, and the other end is provided with the dovetail 3 matched,
Each ditch body 1 is mutually permanently connected by dovetail groove 2 and dovetail 3.Dovetail groove 2 and dovetail 3 and precast reinforced 8 in ditch body 1
It is fixedly connected, to increase bonding strength.The inwall of ditch body 1 is provided with some cable clips 4 or cable bearer 5, and the bottom of ditch body 1 is provided with
Heavy water hole 6 for draining.Ditch body 1 is provided with the drop handle 7 for being easy to carry, and the top of ditch body 1 is provided with the chute for being used for placing cover plate,
Chute uses angle steel bound edge.Cover plate uses angle steel bound edge, so that closer when cover plate is installed on cable duct.Assembled prefabricated electricity
Cable ditch is connected by dovetail groove 2 and dovetail 3 with cable shaft, ring main unit basis.
The utility model implementation process is:The cable duct by some sections the prefabricated ditch body 1 of monolithic reinforced-concrete and lid
Plate is constituted, depending on the length of every section of ditch body 1 can be according to project situation.The utility model can carry out batch production batch production, then
In construction site Assembling.The two ends of ditch body 1 are respectively arranged with the dovetail groove matched, tenon.Pass through the dovetail groove of adjacent ditch body 1
2nd, dovetail 3, i.e., be inserted vertically into dovetail groove 2 and fix, cover plate is then installed, according to actual (tube) length by the tongue-and-groove connection of dovetail 3
Some sections of ditch bodies 1 are connected into an entirety by degree.Using above-mentioned technical proposal, the Assembled prefabricated cable duct can carry out factory
Change, modularized production, are easy to unified mass standard and effectively control construction quality;Modular prefabricated components transport to building site progress
Assembling, installation rate is fast, is conducive to accelerating the speed of application shortening duration, so as to improve efficiency.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model
Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc. should be included in the utility model
Protection domain within.
Claims (6)
1. a kind of Assembled prefabricated cable duct, including some the ditch bodies (1) and cover plate prefabricated by armored concrete, its feature
It is, the ditch body (1) takes the shape of the letter U, described ditch body (1) one end is provided with dovetail groove (2), and the other end is provided with the dovetail matched
Tenon (3), each ditch body (1) is mutually permanently connected by the dovetail groove (2) and dovetail (3).
2. Assembled prefabricated cable duct according to claim 1, it is characterised in that:The dovetail groove (2) and dovetail (3)
It is fixedly connected with precast reinforced (8) in ditch body (1).
3. Assembled prefabricated cable duct according to claim 1 or 2, it is characterised in that:Ditch body (1) inwall is provided with
Some cable clips (4) or cable bearer (5), ditch body (1) bottom are provided with the heavy water hole (6) for draining.
4. Assembled prefabricated cable duct according to claim 3, it is characterised in that:The ditch body (1), which is provided with, to be easy to remove
The chute for being used for placing cover plate is provided with the top of the drop handle (7) of fortune, the ditch body (1), the chute uses angle steel bound edge.
5. Assembled prefabricated cable duct according to claim 4, it is characterised in that:The cover plate uses angle steel bound edge.
6. Assembled prefabricated cable duct according to claim 3, it is characterised in that:The Assembled prefabricated cable duct passes through
Dovetail groove (2) and dovetail (3) are connected with cable shaft, ring main unit basis.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720006048.2U CN206401862U (en) | 2017-01-04 | 2017-01-04 | Assembled prefabricated cable duct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720006048.2U CN206401862U (en) | 2017-01-04 | 2017-01-04 | Assembled prefabricated cable duct |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206401862U true CN206401862U (en) | 2017-08-11 |
Family
ID=59516956
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720006048.2U Expired - Fee Related CN206401862U (en) | 2017-01-04 | 2017-01-04 | Assembled prefabricated cable duct |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206401862U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107516866A (en) * | 2017-08-30 | 2017-12-26 | 国家电网公司 | A kind of Prefabricated cable duct |
CN110943420A (en) * | 2019-11-27 | 2020-03-31 | 国网山东省电力公司经济技术研究院 | Protection device for cable laying |
CN111779028A (en) * | 2020-07-04 | 2020-10-16 | 四川航天建筑工程有限公司 | Finished prefabricated electric shallow trench and construction method thereof |
CN112152179A (en) * | 2020-08-06 | 2020-12-29 | 广东电网有限责任公司广州供电局 | Prefabricated cable trench and construction method thereof |
-
2017
- 2017-01-04 CN CN201720006048.2U patent/CN206401862U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107516866A (en) * | 2017-08-30 | 2017-12-26 | 国家电网公司 | A kind of Prefabricated cable duct |
CN110943420A (en) * | 2019-11-27 | 2020-03-31 | 国网山东省电力公司经济技术研究院 | Protection device for cable laying |
CN110943420B (en) * | 2019-11-27 | 2021-04-06 | 国网山东省电力公司经济技术研究院 | Protection device for cable laying |
CN111779028A (en) * | 2020-07-04 | 2020-10-16 | 四川航天建筑工程有限公司 | Finished prefabricated electric shallow trench and construction method thereof |
CN112152179A (en) * | 2020-08-06 | 2020-12-29 | 广东电网有限责任公司广州供电局 | Prefabricated cable trench and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206401862U (en) | Assembled prefabricated cable duct | |
CN203080517U (en) | Steel formwork for combination of manual hole digging piles | |
CN102817375A (en) | Assembly type precast reinforced concrete inspection well system | |
CN206396783U (en) | Assembled prefabricated ring main unit basis | |
CN103590486B (en) | Anti-seismic energy saving three-dimensional mortise and tenon joint net fixing one-piece cast building structure and construction method | |
CN106088318A (en) | The overlapping assembled integral basement that flat slab system is combined with post and lintel system | |
CN107443550A (en) | Prefabricated cushion cap template and its installation method | |
CN106088317A (en) | The overlapping assembled integral basement that post and lintel system is combined with flat slab system | |
CN106088316A (en) | A kind of overlapping assembled integral basement of hollow building cover post and lintel system | |
CN101666085B (en) | Prefabricated part composite cement soil wall and construction method thereof | |
CN106088320A (en) | A kind of overlapping assembled integral basement of superstructure post and lintel system | |
CN210684922U (en) | Post-cast strip centralized drainage pipeline component | |
CN204475529U (en) | The syndeton of a kind of assembling type outer wall and beam | |
CN203846660U (en) | Prefabricated assembled type open-web net rack for reinforced concrete | |
CN206396800U (en) | Assembled prefabricated cable shaft | |
CN203755423U (en) | Novel drainage ditch shaping device | |
CN205445125U (en) | Execute i -shaped assembled enclosure fast | |
CN202187330U (en) | Concrete hardened prefabricated spliced trapezoidal channel | |
CN205894278U (en) | Solid superstructure beam -columns system's integral basement of coincide assembly | |
CN101666086B (en) | Cement cast-in-situ pile of prefabricated part and construction method thereof | |
CN204282528U (en) | A kind of prefabricated balcony structure | |
CN205152973U (en) | Root stake | |
CN209399990U (en) | A kind of field surface observation pier structure | |
CN103498512B (en) | A kind of assembled architecture wall beam stablizes syndeton | |
CN207348081U (en) | Prefabricated cushion cap template |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170811 Termination date: 20220104 |