CN106088320A - A kind of overlapping assembled integral basement of superstructure post and lintel system - Google Patents
A kind of overlapping assembled integral basement of superstructure post and lintel system Download PDFInfo
- Publication number
- CN106088320A CN106088320A CN201610660071.3A CN201610660071A CN106088320A CN 106088320 A CN106088320 A CN 106088320A CN 201610660071 A CN201610660071 A CN 201610660071A CN 106088320 A CN106088320 A CN 106088320A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- basement
- overlapping
- cast
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0007—Base structures; Cellars
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/17—Floor structures partly formed in situ
- E04B5/18—Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly cast between filling members
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Rod-Shaped Construction Members (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
A kind of overlapping assembled integral basement of superstructure post and lintel system, basement bottom board is full cast-in-place concrete base plate or prefabricated overlapping base plate, basement side wall is prefabricated overlapping sandwich wall, some cast-in-place posts it are provided with in the middle of basement, on cast-in-place post, composite beam is installed, basement roof uses prefabricated overlapping solid floor or prefabricated sandwich hollow slab, and basement is born n-layer and used prefabricated sandwich hollow slab or prefabricated overlapping solid floor, and n is natural number;The prefabricated sandwich hollow slab of basement roof or prefabricated overlapping solid floor connect into entirety with the composite beam three on prefabricated overlapping sandwich wall top, cast-in-place post;Basement is born a kind of sandwich hollow slab of n-layer or prefabricated overlapping solid floor and is connected into entirety with the composite beam on cast-in-place post.The present invention gives full play to that prefabrication quality is good, speed is fast, efficiency is high, good environmental protection and cast-in-place good integrity, advantage that structural strength is high, it is achieved on-the-spot without modular construction, earth volume is little, low cost, construction speed is fast, quality controllable, non-environmental-pollution, technical performance is excellent.
Description
Technical field
The invention belongs to construction engineering technical field, be specifically related to the overlapping assembled integral ground of a kind of superstructure post and lintel system
Lower room.
Background technology
It is known that traditional architecture basement engineering all uses cast-in-place concrete structure, this is accomplished by excavating sufficiently large
Subterranean excavation, with ensure on-the-spot raw material stacking, concrete transportation, formwork, pour, vibrate, maintenance, folding mould etc. are executed on a large scale
Work working place, therefore the earthwork amount of digging is big, and backfill amount is the biggest.It is all to complete at the scene due to all working, all wallboards and top
Plate is intended to configuration template, and template could be removed after concrete is fully achieved intensity, therefore, and template, scaffold demand
Greatly, long construction period, the most, all raw material all transports to scene with bulk form, pollutes environment, causes waste of raw materials,
Cost of labor is high, and concrete cast-in-site manually vibrates, operation easier is big, it is desirable to high, slightly vibrates unreal, will stay
Leakage hidden trouble.Additionally, cast-in-place concrete quality is uncontrollable, curing condition is poor, and concrete occurs that the probability of micro-crack is big,
Later stage rainwater can pass through micro-crack seepage, affects construction quality.
Summary of the invention
The technical problem to be solved is: solves the problem that above-mentioned prior art exists, and provides a kind of superstructure
The overlapping assembled integral basement of post and lintel system, gives full play to that prefabrication quality is good, speed is fast, efficiency is high, environmental-protecting performance
Good and cast-in-place good integrity, the advantage that structural strength is high, the shortcoming overcoming both, maximize favourable factors and minimize unfavourable ones, it is achieved on-the-spot execute without modularity
Work, earth volume is little, and cost of labor is with the cost of material is low, and construction speed is fast, and quality controllable, non-environmental-pollution, technical performance is excellent.
The technical solution used in the present invention is: the overlapping assembled integral basement of a kind of superstructure post and lintel system, basement
Base plate is full cast-in-place concrete base plate or prefabricated overlapping base plate, and basement side wall is prefabricated overlapping sandwich wall, sets in the middle of basement
Having some cast-in-place posts, cast-in-place post is provided with composite beam, basement roof uses prefabricated overlapping solid floor or prefabricated overlapping empty
Heart floor, basement bears n-layer and uses prefabricated sandwich hollow slab or prefabricated overlapping solid floor, and n is natural number;Basement roof
Prefabricated sandwich hollow slab or prefabricated overlapping solid floor and prefabricated overlapping sandwich wall top, cast-in-place post on composite beam three
Connect into entirety;Basement bears the prefabricated sandwich hollow slab of n-layer or prefabricated overlapping solid floor and the composite beam on cast-in-place post
Connect into entirety.
In technique scheme, described composite beam includes precast beam part and Cast-in-situ Beam part.
In technique scheme, described prefabricated overlapping solid floor includes that laminated floor slab preformed layer and laminated floor slab are cast-in-place
Layer, the laminated floor slab preformed layer termination of prefabricated overlapping solid floor is overlapped in the precast beam part of composite beam, and connection has spelling
Seam reinforcing bar and/or distributing bar, the laminated floor slab in-situ layer of prefabricated overlapping solid floor is existing together with the cast-in-place part of composite beam
Pouring concrete integrated connection is fixed-type.
In technique scheme, described prefabricated sandwich hollow slab includes that laminated floor slab preformed layer and laminated floor slab are cast-in-place
Layer, is uniformly filled with polylith light filling block or hollow box in laminated floor slab in-situ layer, and laminated floor slab preformed layer termination is taken
It is connected in the precast beam part of composite beam, and connection has piece reinforcing bar and/or distributing bar, the overlapping of prefabricated sandwich hollow slab
Floor in-situ layer cast-in-place concrete integrated connection together with the Cast-in-situ Beam part of composite beam is fixed-type.
In technique scheme, described composite beam uses bright beam and/or dark beam.
In technique scheme, described prefabricated overlapping base plate includes base plate preformed layer and base plate in-situ layer.
In technique scheme, described prefabricated overlapping sandwich wall includes prefabricated siphonal lobe wall, prefabricated internal lobe wall and cast-in-place sandwiched
Layer.
In technique scheme, it is light that described prefabricated sandwich hollow slab is uniformly filled with polylith in laminated floor slab in-situ layer
Matter filling block or hollow box, make to form multiple uniform honeycomb core in laminated floor slab in-situ layer, have wide rib between honeycomb core
Beam.
The overlapping assembled integral basement of the present invention, by a prefabrication part, the cast-in-place part of on-the-spot overlapping, fills
Distribution waves that prefabrication quality is good, speed is fast, efficiency is high and cast-in-site good integrity, advantage that structural strength is high, overcomes two
The shortcoming of person, maximizes favourable factors and minimizes unfavourable ones, change that traditional cast-in-place basement earth volume is big, constructional difficulties, cost height, cycle length, efficiency are low,
The original backward state that waste of raw materials is many, environmental pollution is serious, it is achieved that on-the-spot without templating construction, earth volume is little, manually
Cost is with the cost of material is low, and construction speed is fast, quality controllable, and non-environmental-pollution is high-quality and efficient, and has excellent water proofing property
Energy.
With area as 10431m2Basement as a example by, 40 days conventional art durations, 10 days present invention durations, conventional art
Workman 156 people, the present invention only needs 82 people, template used amount to greatly reduce, and scaffold consumption reduces, and artificial measures reduces, masonry
Plastering minimizing, speed of application improves four times, civilized construction, good environmental protection.As a example by construction costs, form work engineering cost reduces
100 yuan/m2, cast in place reinforced bar, concrete works cost reduce by 127 yuan/m2, waterproofing work cost reduces by 87/ m2, masonry and smearing
Ash construction costs reduces by 29 yuan/m2, scaffolding work expense reduces by 30 yuan/m2, other measure item cost minimizing 25 yuan/
m2.Therefore, the overlapping assembled basement of the present invention reduces 398 yuan/m of construction costs than conventional art construction basement2。
The present invention is produced as flexible intelligent production line operation, and production efficiency is high, low cost, the transporter of the present invention
Just, efficiently, low cost;The construction of the present invention is simple to operation, and construction quality is controlled, and integrated cost is low, flat appearance, water proofing property
Can be good, total quality is excellent.
Accompanying drawing illustrates:
Fig. 1 is overall structure schematic diagram of the present invention;
Fig. 2 is prefabricated sandwich hollow slab mounting structure schematic diagram;
Fig. 3 is prefabricated overlapping solid floor mounting structure schematic diagram.
Accompanying drawing marks:
1 full precast concrete base plate, 2 prefabricated overlapping sandwich walls, 3 cast-in-place posts, 4 composite beams, 5 laminated floor slabs are prefabricated
Layer, 6 laminated floor slab in-situ layers, 7 light filling blocks or hollow box.
Detailed description of the invention:
Seeing Fig. 1, Fig. 2, Fig. 3, the overlapping assembled integral basement of the present invention a kind of superstructure post and lintel system, basement bottom board is
Full cast-in-place concrete base plate or prefabricated overlapping base plate, basement side wall is prefabricated overlapping sandwich wall, is provided with some in the middle of basement
Cast-in-place post, cast-in-place post is provided with composite beam, and basement roof uses prefabricated overlapping solid floor or prefabricated sandwich hollow slab,
Basement is born n-layer and is used prefabricated sandwich hollow slab or prefabricated overlapping solid floor, and n is natural number;Basement roof prefabricated
Sandwich hollow slab or prefabricated overlapping solid floor connect into the composite beam three on prefabricated overlapping sandwich wall top, cast-in-place post
Overall;Basement bears the prefabricated sandwich hollow slab of n-layer or prefabricated overlapping solid floor connects into the composite beam on cast-in-place post
Overall.Described composite beam includes that precast beam part and Cast-in-situ Beam part, described prefabricated overlapping solid floor include laminated floor slab
Preformed layer and laminated floor slab in-situ layer, the laminated floor slab preformed layer termination of prefabricated overlapping solid floor is overlapped on the prefabricated of composite beam
In beam part, and connection has piece reinforcing bar and/or distributing bar, the laminated floor slab in-situ layer of prefabricated overlapping solid floor and overlapping
The cast-in-place part of beam cast-in-place concrete integrated connection together is fixed-type, and described prefabricated sandwich hollow slab includes that laminated floor slab is pre-
Preparative layer and laminated floor slab in-situ layer, be uniformly filled with polylith light filling block or hollow box in laminated floor slab in-situ layer, folded
Close floor preformed layer termination to be overlapped in the precast beam part of composite beam, and connection has piece reinforcing bar and/or distributing bar, prefabricated
The laminated floor slab in-situ layer of sandwich hollow slab cast-in-place concrete integrated connection together with the Cast-in-situ Beam part of composite beam is fixed into
Type, described composite beam uses bright beam and/or dark beam, and described prefabricated overlapping base plate includes that base plate preformed layer and base plate are cast-in-place
Layer, described prefabricated overlapping sandwich wall includes prefabricated siphonal lobe wall, prefabricated internal lobe wall and cast-in-place sandwiched layer, described prefabricated overlapped hollow building
Plate is uniformly filled with polylith light filling block or hollow box in laminated floor slab in-situ layer, makes to be formed in laminated floor slab in-situ layer
Multiple uniform honeycomb cores, have wide girt strip between honeycomb core.
Claims (8)
1. the overlapping assembled integral basement of a superstructure post and lintel system, it is characterised in that: basement bottom board is complete cast-in-place mixed
Solidifying soil base plate or prefabricated overlapping base plate, basement side wall is prefabricated overlapping sandwich wall, is provided with some cast-in-place posts in the middle of basement, existing
Watering and be provided with composite beam on post, basement roof uses prefabricated overlapping solid floor or prefabricated sandwich hollow slab, and basement bears n
Layer uses prefabricated sandwich hollow slab or prefabricated overlapping solid floor, and n is natural number;The prefabricated overlapped hollow building of basement roof
Plate or prefabricated overlapping solid floor connect into entirety with the composite beam three on prefabricated overlapping sandwich wall top, cast-in-place post;Underground
Room is born the prefabricated sandwich hollow slab of n-layer or prefabricated overlapping solid floor and is connected into entirety with the composite beam on cast-in-place post.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described
Composite beam includes precast beam part and Cast-in-situ Beam part.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described pre-
System overlapping solid floor includes laminated floor slab preformed layer and laminated floor slab in-situ layer, and the laminated floor slab of prefabricated overlapping solid floor is pre-
Preparative layer termination is overlapped in the precast beam part of composite beam, and connection has piece reinforcing bar and/or distributing bar, and prefabricated overlapping is solid
The laminated floor slab in-situ layer of floor cast-in-place concrete integrated connection together with the cast-in-place part of composite beam is fixed-type.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described pre-
Sandwich hollow slab processed includes laminated floor slab preformed layer and laminated floor slab in-situ layer, is uniformly filled with in laminated floor slab in-situ layer
Polylith light filling block or hollow box, laminated floor slab preformed layer termination is overlapped in the precast beam part of composite beam, and connects
There are piece reinforcing bar and/or distributing bar, the laminated floor slab in-situ layer of prefabricated sandwich hollow slab and the Cast-in-situ Beam part of composite beam
Cast-in-place concrete integrated connection is fixed-type together.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described
Composite beam uses bright beam and/or dark beam.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described
Prefabricated overlapping base plate includes base plate preformed layer and base plate in-situ layer.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described pre-
System overlapping sandwich wall includes prefabricated siphonal lobe wall, prefabricated internal lobe wall and cast-in-place sandwiched layer.
The overlapping assembled integral basement of superstructure post and lintel system the most according to claim 1, it is characterised in that: described folded
Close in floor in-situ layer and be all filled with polylith light filling block or hollow box, make laminated floor slab in-situ layer is formed multiple all
Even honeycomb core, has wide girt strip between honeycomb core.
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610660071.3A CN106088320A (en) | 2016-08-12 | 2016-08-12 | A kind of overlapping assembled integral basement of superstructure post and lintel system |
PCT/CN2016/101677 WO2018028040A1 (en) | 2016-08-12 | 2016-10-10 | Stacked and assembled integrated basement of multistory post-and-beam system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610660071.3A CN106088320A (en) | 2016-08-12 | 2016-08-12 | A kind of overlapping assembled integral basement of superstructure post and lintel system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106088320A true CN106088320A (en) | 2016-11-09 |
Family
ID=57455685
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610660071.3A Pending CN106088320A (en) | 2016-08-12 | 2016-08-12 | A kind of overlapping assembled integral basement of superstructure post and lintel system |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN106088320A (en) |
WO (1) | WO2018028040A1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108194095A (en) * | 2018-03-20 | 2018-06-22 | 上海市城市建设设计研究总院(集团)有限公司 | The prefabricated superposed type vehicle driving passage structure of subterranean tunnel or gallery |
CN114086455A (en) * | 2021-10-22 | 2022-02-25 | 中铁第四勘察设计院集团有限公司 | Overlength structure of railway passenger station |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN217175989U (en) * | 2022-03-23 | 2022-08-12 | 刘星东 | Garage and building for motor vehicle or non-motor vehicle |
CN114908794B (en) * | 2022-04-12 | 2023-05-16 | 中铁二院工程集团有限责任公司 | Assembled building method of subway station |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2037758U (en) * | 1988-10-14 | 1989-05-17 | 宁波市机电工业研究设计院 | Assembled commodity house |
JPH11247288A (en) * | 1998-03-02 | 1999-09-14 | Okumura Corp | Column-beam main bar pre-assembled hollow precast concrete column unit and column constructing method using this column unit |
CN201627282U (en) * | 2009-12-28 | 2010-11-10 | 张吉华 | Integrated prefabricating thermal insulation wall by pillar, girder and wall |
CN103276839A (en) * | 2013-06-08 | 2013-09-04 | 北京工业大学 | Hollow irregular column multi-layer high-rise assembling steel frame-eccentric support system |
CN103741714A (en) * | 2013-12-09 | 2014-04-23 | 中国建筑第二工程局有限公司 | Construction method for full cover-excavation reverse method of underground engineering |
CN105649360A (en) * | 2015-12-29 | 2016-06-08 | 山东远博建筑科技有限公司 | Integral assembling type building system and installing method |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000303602A (en) * | 1999-04-23 | 2000-10-31 | Fujita Corp | Pc floor slab, and floor slab execution method using the same |
CN101230607B (en) * | 2007-01-28 | 2012-03-28 | 湖南邱则有专利战略策划有限公司 | Structure combination parts for hollow slab |
KR101001208B1 (en) * | 2010-08-30 | 2010-12-15 | 대한이.이엔.씨(주) | A constructing method of structure using sandwich pc-wall |
CN104879144B (en) * | 2015-05-20 | 2016-09-28 | 上海市城市建设设计研究总院 | The excavating construction method of the underground space is built with array push pipe in soft clay area |
CN105178357B (en) * | 2015-07-16 | 2017-01-11 | 中国建筑股份有限公司 | Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition |
CN106088316A (en) * | 2016-08-12 | 2016-11-09 | 长沙远大住宅工业集团股份有限公司 | A kind of overlapping assembled integral basement of hollow building cover post and lintel system |
CN205894278U (en) * | 2016-08-12 | 2017-01-18 | 长沙远大住宅工业集团股份有限公司 | Solid superstructure beam -columns system's integral basement of coincide assembly |
CN205894280U (en) * | 2016-08-12 | 2017-01-18 | 长沙远大住宅工业集团股份有限公司 | Hollow superstructure beam -columns system's integral basement of coincide assembly |
-
2016
- 2016-08-12 CN CN201610660071.3A patent/CN106088320A/en active Pending
- 2016-10-10 WO PCT/CN2016/101677 patent/WO2018028040A1/en active Application Filing
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2037758U (en) * | 1988-10-14 | 1989-05-17 | 宁波市机电工业研究设计院 | Assembled commodity house |
JPH11247288A (en) * | 1998-03-02 | 1999-09-14 | Okumura Corp | Column-beam main bar pre-assembled hollow precast concrete column unit and column constructing method using this column unit |
CN201627282U (en) * | 2009-12-28 | 2010-11-10 | 张吉华 | Integrated prefabricating thermal insulation wall by pillar, girder and wall |
CN103276839A (en) * | 2013-06-08 | 2013-09-04 | 北京工业大学 | Hollow irregular column multi-layer high-rise assembling steel frame-eccentric support system |
CN103741714A (en) * | 2013-12-09 | 2014-04-23 | 中国建筑第二工程局有限公司 | Construction method for full cover-excavation reverse method of underground engineering |
CN105649360A (en) * | 2015-12-29 | 2016-06-08 | 山东远博建筑科技有限公司 | Integral assembling type building system and installing method |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108194095A (en) * | 2018-03-20 | 2018-06-22 | 上海市城市建设设计研究总院(集团)有限公司 | The prefabricated superposed type vehicle driving passage structure of subterranean tunnel or gallery |
CN114086455A (en) * | 2021-10-22 | 2022-02-25 | 中铁第四勘察设计院集团有限公司 | Overlength structure of railway passenger station |
Also Published As
Publication number | Publication date |
---|---|
WO2018028040A1 (en) | 2018-02-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205894281U (en) | Integral basement of coincide assembly of arch without beam system | |
CN105839667B (en) | The construction manufacture craft of complete prefabricated overlapping assembled underground pipe gallery | |
WO2017206411A1 (en) | Full-prefabricated superimposed assembly-type underground pipe gallery and connection node thereof | |
CN206070835U (en) | A kind of assembled architecture bottom composite floor | |
CN107313517B (en) | Connecting node for laminated wall and laminated floor slab in middle layer | |
CN101914925B (en) | Basement by using optimized composite prefabricated arch wall as external wall | |
CN104358341B (en) | Building brickwork and masonry construction method of building brickwork | |
CN205662947U (en) | Coincide assembled underground pipe gallery system | |
CN105862916A (en) | Superimposed assembled type underground pipe gallery system and construction and manufacturing process | |
CN206070562U (en) | Subassembly formula underground structure | |
CN106121035A (en) | A kind of overlapping assembled integral basement of flat slab system | |
CN106088318A (en) | The overlapping assembled integral basement that flat slab system is combined with post and lintel system | |
CN106088320A (en) | A kind of overlapping assembled integral basement of superstructure post and lintel system | |
CN205742265U (en) | Complete prefabricated overlapping assembled underground pipe gallery and connection node thereof | |
CN106088316A (en) | A kind of overlapping assembled integral basement of hollow building cover post and lintel system | |
CN101418569A (en) | Optimization complex arch wall combining prefabricated arch leaf, support and major structure | |
CN106088317A (en) | The overlapping assembled integral basement that post and lintel system is combined with flat slab system | |
CN205894280U (en) | Hollow superstructure beam -columns system's integral basement of coincide assembly | |
CN106088319A (en) | A kind of overlapping assembled integral basement of the system of hollow building cover without beam | |
CN206956949U (en) | Overlap wall and intermediate layer laminated floor slab connecting node | |
CN205894278U (en) | Solid superstructure beam -columns system's integral basement of coincide assembly | |
CN207110214U (en) | A kind of prefabricated interior fill concrete wallboard | |
CN205894279U (en) | Integral basement of coincide assembly of hollow superstructure system of no roof beam | |
CN106121034A (en) | A kind of overlapping assembled integral basement without the solid floor system of beam | |
CN106121033A (en) | A kind of overlapping assembled integral basement of solid superstructure post and lintel system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20161109 |
|
RJ01 | Rejection of invention patent application after publication |