CN206317989U - Floating dolphin landing stage - Google Patents

Floating dolphin landing stage Download PDF

Info

Publication number
CN206317989U
CN206317989U CN201621455631.3U CN201621455631U CN206317989U CN 206317989 U CN206317989 U CN 206317989U CN 201621455631 U CN201621455631 U CN 201621455631U CN 206317989 U CN206317989 U CN 206317989U
Authority
CN
China
Prior art keywords
main hull
landing stage
drinking water
anchor
floating
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621455631.3U
Other languages
Chinese (zh)
Inventor
姚智衡
姚奉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yichang Dongjiang Shipyard Co Ltd
Original Assignee
Yichang Dongjiang Shipyard Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yichang Dongjiang Shipyard Co Ltd filed Critical Yichang Dongjiang Shipyard Co Ltd
Priority to CN201621455631.3U priority Critical patent/CN206317989U/en
Application granted granted Critical
Publication of CN206317989U publication Critical patent/CN206317989U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of floating dolphin landing stage includes main hull, and the main hull bottom is provided with multiple drinking water bodies being parallel to each other, and drinking water is provided with ballast tank in vivo;It is connected in main hull front at least provided with the anchor chain that a pair are symmetrical arranged in anchor capstan, anchor capstan connection through the hawse-pipe on main hull with being located at the anchor of main hull bottom.The utility model has the advantages that, improve the utility of coastline of port and pier, particularly original old harbour is renovated, the solution for anchor of exempting to cast anchor can be provided for substantial amounts of harbour anchorage by using the arrangement form of multiple rows of row combination, bank electricity is inputted into this floating dolphin landing stage using very simple technique to realize come port berthing ship lay day " oil changes electricity ", positive booster action is played to build green harbour.

Description

Floating dolphin landing stage
Technical field
This project is related to a kind of floating dolphin landing stage, and its structure type is simple, cheap, deep with enough drinking water The drinking water of degree and anchor chain exit point is more than the extreme draft for mooring waters ship.
Background technology
Existing port and pier have jetty type wharf, quay by horizontal layout form, dig into formula harbour, island-type pier With formula harbour in dike;This kind of Wharf Construction investment is huge, and the construction period is long, and the big-and-middle-sized harbour in generally harbour and inland is adopted With;Most of inland rivers and the port and pier in reservoir waters are influenceed typically to use special landing stage by the seasonal water level swell that disappears Form, water level phase of rising that disappears wants frequent shifting berth, causes to be unable to the actual conditions of operation during its shifting berth, to normal production and operation order Impact, and the old anchoring in landing stage and the formation of mooring form can only moor a boat by waters center side, utility of coastline It is extremely low, and being exposed to the anchor chain and mooring cable of the water surface and being had the wet season more wound by a large amount of floating refuses, but can not be with very Convenient method cleaning, has uglified harbour water area environment, has a ship waters wide, there is large number of different types of anchor Ground, but be all the form of single secure anchoring up to now, and this anchoring approach wastes a large amount of water surface areas.Before setting sail Necessarily unmoor, build fixed anchorage and carry out the mode of anchorage ship and also there is no precedent.Due to being independent anchoring, ship is in anchoring Harbor generator is at least also used in period, substantial amounts of ship is generated electricity using subsidiary engine in anchorage causes substantial amounts of waste gas row again Put, severe contamination harbour environment.
With the fast development of economic society, China faces resource environment constraint, communications and transportation development and faces soil, water front The rigid constraint of resource scarcity will be further exacerbated by, and more urgent requirement is proposed to communications and transportation Green Development.Therefore, build If green harbour is the important measures for promoting transportation Green Development.Now, limited harbour coastline resource is non-renewable, Old terminal facilities, equipment and very low utilization rate hinders the fast development of port construction.
The content of the invention
The technical problems to be solved in the utility model is to provide a kind of floating dolphin landing stage to improve the bank of port and pier Line use ratio, particularly renovates to original old harbour, uses the arrangement form of multiple rows of multiple row chain of rings combination can be with The solution for anchor of exempting to cast anchor is provided for substantial amounts of harbour anchorage, bank electricity is inputted by ship by this floating using very simple technique Pier landing stage, which is realized, carrys out port berthing ship lay day " oil changes electricity ", and positive booster action is played to build green harbour.
In order to solve the above technical problems, the technical solution adopted in the utility model, which is a kind of floating dolphin landing stage, includes master Hull, the main hull bottom is provided with ballast tank in vivo provided with drinking water body, drinking water;
In main hull front main ship is passed through at least provided with the anchor chain that a pair are symmetrical arranged in anchor capstan, anchor capstan connection Hawse-pipe on body is connected with being located at the anchor of main hull bottom.
Further, the hawse-pipe is penetrated from main hull front and passed from drinking water body bottom, the master in hawse-pipe exit Hull base plate is set and hawse-pipe central axis.
Further, four drinking water bodies set up separately at four angles of main hull bottom.
Further, main hull bottom is provided with a drinking water body, and drinking water body forms a Back Word along main hull bottom margin Type closed shape.
Further, main hull bottom symmetrical absorbs water provided with two and is not connected between bodies, two described drinking water bodies.
Further, the ballast tank of each drinking water body carries out ballast or off-load using portable pump.
Further, the drinking water of the drinking water body, which is more than, moors most gobbling for waters berthing this floating dolphin landing stage ship Water.
Further, bank electricity can be inputted this floating dolphin by the floating dolphin landing stage using very simple technique Landing stage, realizes and carrys out port berthing ship lay day " oil changes electricity ".
The utility model has the advantages that:
1st, the floating dolphin landing stage after anchorage is appropriate, because of its anchor chain exit point(Hawse-pipe is exported)With enough depth, Using when the water-area navigation or berthing operation ship are heavily loaded extreme draft deeply plus rich d -trans- allethrin as its draft.When carrying out ship berthing Without producing anchor chain touching carry out ship and hindered because its anchor chain exit point is relatively deep, forming peripheral direction all around can moor The floating dolphin of ship, economic and practical, operation technique is simple, construction cost is cheap, is efficiently to utilize non-renewable harbour bank Line resource provides a solution.
2nd, floating dolphin landing stage only set anchor and anchor chain it is supporting come anchorage landing stage, exempt to set to bank base mooring hawser be set, it is excellent In conventional landing stage as fine as a spider's web cable lead around defect, can create whole in the waters collar of its berthing inward ship operation Clean, safe water environment.
3rd, with two this landing stages and any pierhead pontoon as dried food and nuts pierhead pontoon, wharf for bulk cargo landing stage, container The a chain of landing stage of pierhead pontoon, roll-on berth is combined, and applicability is extensive.
4th, can also constitute jointly pontoon bridge type harbour using a plurality of floating dolphin landing stage, this combining form be suitable for from The shallower water environment of bank and reach deeper water, deeper water is arranged in using this landing stage of supporting relatively deep drinking water, it is supporting compared with This light-draft landing stage, which to be arranged in, gone directly compared with shallow water area on the bank, supporting between this landing stage of pontoon bridge type harbour scope two of which Using landing stage connection is jumped, anchor arrangement need not be configured by jumping landing stage, and such combination can be utilized extends compared with shallow water area to profundal zone Carry out wharf.
5th, this landing stage can as floating dock dolphin, the sinking at floating dock and lift what the special process of ship operation needed Maximum is heavy deep larger, general river ship dock >=3m, the drinking water of seagoing vessel floating dock is bigger, if made using itself mooring system Industry, cumbersome, labor intensity are big, add and are frequently adjusted using high-power windlass, energy consumption is big;It is fixed using pile foundation Harbour configuration guide pillar can solve above-mentioned problem, but pile foundation fixed quay is built by harbour addressing, all many conditions of fluctuation in stage Limitation and it is difficult, and invest huge, unsuitable popularity.This project only needs to configure two floating dolphin landing stages, A side of a ship shipboard only on this landing stage, which is set, to sink with floating dock and the attachment means of lift ship floating linkage can just solve to float The above-mentioned problem of dock, and economic, applicable, safety, energy-conservation.
6th, common pierhead pontoon general at this stage be using anchoring and mooring two ways is come fixed quay landing stage, its Middle anchoring form is because anchor chain exit point surfaces mostly and causes berthing ship from the initial and tail sections close to landing stage, wherein mooring Form be to guide mooring rope on the bank earth anchor facility from landing stage bollard, be substantially all exposed to landing stage and pull in shore the water of side On face, it is also as fine as a spider's web that What is more, and such landing stage offshore side is just unable to berthing ship completely.Form dock barge only Can be by the middle of the river(Or waters center)A side of a ship berthing carry out ship.Harbour utility of coastline is extremely low, the protrusion on floating dolphin landing stage Advantage can be achieved on four direction all around and harbour utility of coastline can be substantially increased with berthing ship, be precious The rational exploitation and utilization of expensive coastline resource, there is provided a solution for beautification harbour environment.Further use this practicality New any combination form, can easily be realized using the technique being simply connected with bank base very much the harbour itself and come Port berthing operation ship uses bank electricity, reaches the purpose of " oil changes electricity ", and a kind of solution is provided to create the green harbour of energy-saving and emission-reduction Certainly scheme.
Brief description of the drawings
Below in conjunction with drawings and Examples, the utility model is described in further detail:
Fig. 1 is the utility model front view.
Fig. 2 is the utility model side view.
Fig. 3 is A-A sectional schematic diagrams in Fig. 1.
Fig. 4 is that main hull bottom sets three-back-shaped drinking water body schematic diagram.
Fig. 5 is that main hull bottom sets symmetrical two drinking water body schematic diagram.
Fig. 6 is that main hull bottom sets four drinking water body arrangement schematic diagrames.
Fig. 7 is using floating dolphin of the present utility model wholesale and container loading and unloading ship combination diagram.
Fig. 8 is B-B sectional schematic diagrams in Fig. 7.
Fig. 9 is using a chain of combination diagram of the multiple rows of multiple row of floating dolphin of the present utility model wholesale.
Figure 10 is using floating dolphin of the present utility model wholesale and floating dock combination diagram.
Figure 11 is the unloaded schematic diagram of C-C sections in Figure 12.
Figure 12 is C-C sections loading schematic diagram in Figure 12.
In such as figure, main hull 1, drinking water body 2, ballast tank 3, anchor capstan 4, anchor chain 5, hawse-pipe 6, anchor 7, suction pump 8, electronics Level meter 9, controller 10, container loading and unloading ship 11, container ship 12, ship 13, jump landing stage 14, floating dock 15.
Embodiment
As in Fig. 1,2, a kind of floating dolphin landing stage includes main hull 1(The bound form of main hull 1 use deepbar for Transverse system, stringers longitudinal framing), it is preferred that the drinking water of drinking water body, which is more than, moors waters berthing this floating dolphin landing stage ship The extreme draft of oceangoing ship.The bottom of main hull 1 is provided with multiple drinking water bodies 2 being parallel to each other, drinking water body 2 and is provided with ballast tank 3, preferably , four drinking water bodies set up separately at four angles of main hull bottom, are arranged on the drinking water body 2 on four angles, can make main ship The stability of body 1 is more preferable;
In the front of main hull 1 at least provided with a pair of symmetrically arranged two anchor capstans 4, it is preferred that in main hull 1 just Symmetrically arranged four anchor capstans 4 of two pairs of setting in face, four anchor capstans 4 set up separately at four angles of main hull 1, and anchor capstan 4 connects The anchor chain 5 connected is connected through the hawse-pipe 6 on main hull 1 with being located at the anchor 7 of the bottom of main hull 1, the logical driving anchor 7 of anchor capstan 4 Leave the bottom of main hull 1 or close to the bottom of main hull 1.
As in Fig. 3, hawse-pipe 6 is penetrated from the front of main hull 1 and passed from drinking water body 2 bottom, the main ship in the exit of hawse-pipe 6 The base plate of body 1 into the central axis of hawse-pipe 6.
It is preferred that, the ballast tank 3 of each drinking water body 2 carries out ballast or off-load using portable pump.
In main hull front, the control room of the receiving device inputted for bank electricity and output equipment, the incoming line of bank electricity are set Laid by connecting the floating dolphin landing stage of bank base or jumping landing stage Yan Lu, the technique of its incoming line is simply applicable.
It is preferred that, anchor capstan 4 is multiple twin anchor, the electric mincing anchor of multiple twin cable reel, cable machine, supporting 2 sets of anchors each all around And anchor chain, using ship is cast anchor and this ship windlass operation 4 × 2 directions of casting anchor position this ship, twist anchor, the stranded cable reel of cable machine and aid in Mooring stranded cable is used.
It is preferred that, main deck 1 all around sets bollard, fairlead or fairlead on demand, for inward ship berthing Tying, stem and afterbody and his ship interlink using cable tying or can set the pattern of a chain of tying of heavy hinge.
Structure:This ship is all built using new steel material, is carried out according to existing construction specification, this ship is full electric welding knot Structure, rational welding procedure and flow should be used by building factory, and method of construction is block system.
As in Fig. 4, the bottom of main hull 1 is returned for one provided with a drinking water body 2, drinking water body 2 along the formation of the bottom margin of main hull 1 Font closed shape, the centre of form is hollow in the middle of Back Word type closed shape, can improve the stability of the utility model device, and can mitigate The deadweight of the utility model device.
It is not connected with as in Fig. 6, the bottom symmetrical of main hull 1 absorbs water provided with two between bodies 2, two described drinking water bodies 2.
As in Fig. 5, four drinking water bodies 2 set up separately at four angles of the bottom of main hull 1.
In Fig. 7, the new floating dolphin landing stage of the utility model is set up separately at the end of container loading and unloading ship 11 2, for stable set Vanning changes the outfit ship 11, during work, and the side of container loading and unloading ship 11 2 can respectively stop a container ship 12, and Fig. 8 is that B-B breaks in Fig. 7 Face, the schematic diagram of container loading and unloading ship 11, during work, the packaging on container ship 12 are transported to by the container crane on container ship 12 Case is hoisted to container loading and unloading ship 11, and haulage vehicle is transported on the bank via one of floating dolphin landing stage.
In Fig. 9, multiple the utility model are connected between new floating dolphin landing stage by jumping landing stage 14, and ship is leaned in floating The side of pier landing stage two can respectively stop a ship 13, and transmission of electricity, oil circuit can be arranged along floating dolphin landing stage, jump landing stage 14, be combined into Oil changes electric anchorage.
In Figure 10, the new floating dolphin landing stage of a utility model is respectively set at two ends of the side of floating dock 15, is such as schemed In 11, the ship on floating dock 15 is in service mode, such as Figure 12, and the ship on floating dock 15 is by after the completion of maintenance(The quilt of floating dock 15 Decentralization is easy to ship to drive into or roll away from floating dock 15 to most bottom position), this arrangement is available in various waters(Such as river, lake, marine) Position.

Claims (7)

1. a kind of floating dolphin landing stage, it is characterized in that:The landing stage includes main hull, and the main hull bottom is provided with drinking water Body, drinking water is provided with ballast tank in vivo;
In main hull front at least provided with a pair of symmetrically arranged anchor capstans, the anchor chain that anchor capstan is connected passes through main hull On hawse-pipe be connected with being located at the anchor of main hull bottom.
2. floating dolphin landing stage according to claim 1, it is characterized in that:The hawse-pipe from main hull front penetrate from Drinking water body bottom is passed, floor and the hawse-pipe central axis in hawse-pipe exit.
3. floating dolphin landing stage according to claim 1, it is characterized in that:Four drinking water bodies set up separately at main hull bottom Four angles in portion.
4. floating dolphin landing stage according to claim 1, it is characterized in that:The main hull bottom is provided with a drinking water Body, drinking water body forms a Back Word type closed shape along main hull bottom margin.
5. floating dolphin landing stage according to claim 1, it is characterized in that:The main hull bottom symmetrical is eaten provided with two It is not connected between water body, two described drinking water bodies.
6. floating dolphin landing stage according to claim 1, it is characterized in that:The ballast tank of each drinking water body is using just Take formula water pump and carry out ballast or off-load.
7. floating dolphin landing stage according to claim 1, it is characterized in that:The drinking water of the drinking water body, which is more than, moors waters The extreme draft of berthing this floating dolphin landing stage ship.
CN201621455631.3U 2016-12-28 2016-12-28 Floating dolphin landing stage Expired - Fee Related CN206317989U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621455631.3U CN206317989U (en) 2016-12-28 2016-12-28 Floating dolphin landing stage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621455631.3U CN206317989U (en) 2016-12-28 2016-12-28 Floating dolphin landing stage

Publications (1)

Publication Number Publication Date
CN206317989U true CN206317989U (en) 2017-07-11

Family

ID=59261752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621455631.3U Expired - Fee Related CN206317989U (en) 2016-12-28 2016-12-28 Floating dolphin landing stage

Country Status (1)

Country Link
CN (1) CN206317989U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109110048A (en) * 2018-08-19 2019-01-01 宜昌东江造船有限公司 LNG shipment application method and self-propulsion type LNG tank formula container loading and unloading ship peculiar to vessel
CN109658439A (en) * 2017-10-12 2019-04-19 中电科海洋信息技术研究院有限公司 Ship is overstocked a harbour state identification method, device, equipment and storage medium
CN110104133A (en) * 2019-05-08 2019-08-09 大连辽南船厂 Pontoon docking Multifunctional floating harbour
CN111422306A (en) * 2020-04-08 2020-07-17 中铁第五勘察设计院集团有限公司 Intelligent berthing device, floating dock, intelligent berthing method and storage medium
CN113585163A (en) * 2021-08-11 2021-11-02 重庆交通大学 Double-ship-position berthing method for mountain river
CN117005360A (en) * 2023-08-31 2023-11-07 江苏海洋大学 Multi-row arrangement pontoon and net cage combined floating breakwater

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109658439A (en) * 2017-10-12 2019-04-19 中电科海洋信息技术研究院有限公司 Ship is overstocked a harbour state identification method, device, equipment and storage medium
CN109658439B (en) * 2017-10-12 2023-06-09 中电科海洋信息技术研究院有限公司 Ship harbor state identification method, device, equipment and storage medium
CN109110048A (en) * 2018-08-19 2019-01-01 宜昌东江造船有限公司 LNG shipment application method and self-propulsion type LNG tank formula container loading and unloading ship peculiar to vessel
CN109110048B (en) * 2018-08-19 2024-04-23 宜昌东江造船有限公司 Ship LNG shipping application method and self-propelled LNG tank container reloading ship
CN110104133A (en) * 2019-05-08 2019-08-09 大连辽南船厂 Pontoon docking Multifunctional floating harbour
CN111422306A (en) * 2020-04-08 2020-07-17 中铁第五勘察设计院集团有限公司 Intelligent berthing device, floating dock, intelligent berthing method and storage medium
CN111422306B (en) * 2020-04-08 2024-03-15 中铁第五勘察设计院集团有限公司 Intelligent berthing device, pontoon, intelligent berthing method, and storage medium
CN113585163A (en) * 2021-08-11 2021-11-02 重庆交通大学 Double-ship-position berthing method for mountain river
CN117005360A (en) * 2023-08-31 2023-11-07 江苏海洋大学 Multi-row arrangement pontoon and net cage combined floating breakwater
CN117005360B (en) * 2023-08-31 2024-02-13 江苏海洋大学 Multi-row arrangement pontoon and net cage combined floating breakwater

Similar Documents

Publication Publication Date Title
CN206317989U (en) Floating dolphin landing stage
CN106114762B (en) Shallow water floating platform mooring gear and method
CN101417693B (en) Oceanography engineering module integral hoisting method
CN101774422B (en) Novel offshore installation construction resource-combined type pontoon barge
CN203345167U (en) Movable jack-up artificial island
CN201092380Y (en) Ship mooring facilities of marine oil-gas production platform
EP1150881A1 (en) Working ship
CN101581086B (en) Positioning riprapping method for constructing island breakwater of artificial island
JP2004001750A (en) Special working ship and execution method for offshore structure
CN201268389Y (en) Multifunctional construction platform
CN108407984A (en) A kind of construction method of open seashore transportation system
JP2001507654A (en) Hull structure
CN206634166U (en) A kind of working ship
CN103195039B (en) Artificial island construction method for self-elevating straight-through deck platform
CN110217346A (en) Floating installation and the multiple spot anchoring system and shifting ship's method for moving ship operation
CN202642027U (en) Floating fitting-out device
CN203064175U (en) Artificial island platform
CN104164885A (en) Caisson towing method
CN217227844U (en) Multipurpose floating body anchoring device
CN203601528U (en) Three-boat side-by-side mooring system
CN210529503U (en) Positioning device for beam-transporting ship of suspension bridge
WO2015136086A1 (en) A quay structure, a quay arrangement and a method of installing such structure
CN103074879A (en) Artificial island manufacture method
CN113968311A (en) High-holding-power combined anchor suitable for offshore platform mooring system and operation method
CN202925455U (en) Marine floating bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170711

Termination date: 20211228

CF01 Termination of patent right due to non-payment of annual fee