CN206313364U - Automatic power construction supervision system - Google Patents
Automatic power construction supervision system Download PDFInfo
- Publication number
- CN206313364U CN206313364U CN201621348201.1U CN201621348201U CN206313364U CN 206313364 U CN206313364 U CN 206313364U CN 201621348201 U CN201621348201 U CN 201621348201U CN 206313364 U CN206313364 U CN 206313364U
- Authority
- CN
- China
- Prior art keywords
- ball
- unmanned plane
- support tube
- automatic power
- supervision system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Accessories Of Cameras (AREA)
Abstract
The utility model discloses a kind of automatic power construction supervision system, including unmanned plane, measurement camera is installed on unmanned plane, measurement camera is arranged on unmanned plane by angular adjustment frame, and the angular adjustment frame includes mounting plate(1), lower clamp(2)And governor motion;The governor motion includes support tube(3), in support tube(3)Upper end is provided with annular necking(4), in support tube(3)On be arranged with ball(5), in ball(5)Bottom is provided with the annular groove being engaged with annular necking.The utility model passes through " unmanned plane+management " method of work, automation degree of holding is high, and the method patrolled and examined in the past is instead of using automation means, has been obviously improved management efficiency, conventional management security risk is reduced, power transmission engineering work high above the ground management new model has been started.
Description
Technical field
The utility model is related to a kind of supervision system, especially automatic power construction supervision system.
Background technology
Global energy Internet Construction ambitious goal is carried out by country, and extra-high voltage project enters builds peak period, engineering construction
It is multi-point and wide-ranging, there is a large amount of tower erections, lead wire and earth wire and set up(Crimping)With annex install etc. work high above the ground project, operation quality and
Security risk is difficult to control, and the work such as management side station, parallel testing, tour and quality examination is, it is necessary to put into a large amount of manpower and materials.
At present, relative to substantial amounts of transmission line high-altitude events in operation, management work high above the ground personnel's relative deficiency, by age composition, specially
The factor influence such as industry technical ability and detection Work tool, it is impossible to quick to the work high above the ground project implementation, accurate and comprehensive effective prison
Superintend and direct and process management and control, and have that falling from high altitude security risk, quality examination operating efficiency be not high, cost of labor is larger etc. and ask
Topic, does not meet lean management and requires.
Utility model content
The purpose of this utility model is, for above-mentioned the deficiencies in the prior art, there is provided a kind of automatic power construction supervision
System, the system adopts the disadvantage solved in an automated fashion to live manpower to ascend a height and patrol and examine by " unmanned plane+management " method of work
End.
To reach above-mentioned technique effect, the technical scheme that the utility model is used is as follows:
The utility model automatic power construction supervision system, including unmanned plane, are provided with measurement camera on unmanned plane,
Measurement camera is arranged on unmanned plane by angular adjustment frame, and the angular adjustment frame includes mounting plate, lower clamp and tune
Section mechanism, lower clamp is stuck in unmanned plane top, and mounting plate is fixed on measurement bottom of camera, by adjusting between mounting plate and lower clamp
Section mechanism is attached;The governor motion includes support tube, and support tube upper end is provided with annular necking, blocks on support tube
Ball is provided with, the annular groove being engaged with annular necking is provided with ball bottom, annular necking is snapped onto in annular groove,
Lower clamp lower surface is provided with suspension bracket, micro machine is installed in suspension bracket, the output shaft of micro machine passes through lower clamp and ball
It is connected, ball top is provided with vertical cut (V. cut), the swing arm that can be swung up and down is hinged with vertical cut (V. cut), on swing arm
End is connected with mounting plate.
As preferred scheme of the present utility model, zig-zagging rib is provided with vertical cut (V. cut), behind swing arm lower end
Portion is provided with the card article being engaged with zig-zagging rib.
Used as preferred scheme of the present utility model, the card article is plastics spring.
As preferred scheme of the present utility model, oil filler point is provided with the annular necking of support tube upper end.
Used as preferred scheme of the present utility model, the ball is ceramic material ball.
In sum, the utility model has the advantages that, the system by " unmanned plane+management " method of work, hold by automation
Degree is high, and the method patrolled and examined in the past is instead of using automation means, has been obviously improved management efficiency, reduces conventional management
Security risk, has started power transmission engineering work high above the ground management new model.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model automatic power construction supervision system.
Specific embodiment
As illustrated, a kind of automatic power construction supervision system of the utility model, including unmanned plane, pacify on unmanned plane
Equipped with measurement camera, measurement camera is arranged on unmanned plane by angular adjustment frame.By installing measurement phase on unmanned plane
The pattern of machine, after unmanned plane takes off during operation, reaches the hovering position of photographic subjects design, when hovering point is risen to, alignment
Photographic subjects are taken pictures and are recorded a video, and are landed after completion task, system solves the problem with management duration, the security risk of firmly ascending a height
Big problem.Conventional management steel tower of ascending a height checks average used time 150min;Wire quality checks average time(The phase 1km of 1 people 1)
52.4 min /km;Labour intensity is big, and inefficiency has security risk.
Angular adjustment frame includes mounting plate 1, lower clamp 2 and governor motion, and lower clamp 2 is stuck in unmanned plane top, pop-up
Plate 1 is fixed on measurement bottom of camera, is attached by governor motion between mounting plate 1 and lower clamp 2.Angular adjustment frame can
With adjust measurement camera shooting angle, the situation excessive to solve existing camera shooting blind angle amount,
The governor motion includes support tube 3, and the upper end of support tube 3 is provided with annular necking 4, blocks on support tube 3 and sets
There is ball 5, the annular groove being engaged with annular necking is provided with the bottom of ball 5, annular necking 4 snaps onto annular groove
It is interior, the lower surface of lower clamp 2 is provided with suspension bracket 6, micro machine 7 is installed in suspension bracket 6, the output shaft of micro machine 7 passes through lower card
Plate 2 is connected with ball 5, and the top of ball 5 is provided with vertical cut (V. cut) 8, and the pendulum that can be swung up and down is hinged with vertical cut (V. cut)
Lever 9, the upper end of swing arm 9 is connected with mounting plate 1.By being arranged to governor motion to include support tube 3, on support tube 3
The frame mode of ball 5 is arranged with so that ball can be rotated relative to support tube, so as to rotate the bat of regulation measurement camera
Angle is taken the photograph, by being arranged to ball to be connected with micro machine, drives ball to rotate regulation when micro machine starts.The ball
5 are preferably ceramic material ball, to strengthen the service life of ball.The swing arm 9 that can be swung up and down swings in vertical cut (V. cut)
When, the upper lower angle of measurement camera is can adjust, adjusted with the direction up and down for reaching measurement camera.
Zig-zagging rib 10 preferably is provided with vertical cut (V. cut) 8 as a kind of, is provided with the lower-end rear portion of swing arm 9
The card article being engaged with zig-zagging rib.The card article is plastics spring.Each zigzag of zig-zagging rib 10 is raised
Play a part of a regulation stall, card article plays a part of fixed gear, so as to the regulation angle of swing arm be positioned.
Further, it is provided with oil filler point in the annular necking of the upper end of support tube 3.By can be with toward oiling in oil filler point
Play the lubrication of support tube and ball.
Claims (5)
1. a kind of automatic power construction supervision system, including unmanned plane, it is characterised in that:Measurement phase is installed on unmanned plane
Machine, measurement camera is arranged on unmanned plane by angular adjustment frame, and the angular adjustment frame includes mounting plate(1), lower card
Plate(2)And governor motion, lower clamp(2)It is stuck in unmanned plane top, mounting plate(1)It is fixed on measurement bottom of camera, mounting plate(1)
With lower clamp(2)Between be attached by governor motion;The governor motion includes support tube(3), in support tube(3)Upper end
It is provided with annular necking(4), in support tube(3)On be arranged with ball(5), in ball(5)Bottom is provided with and annular necking phase
The annular groove of cooperation, annular necking(4)Snap onto in annular groove, in lower clamp(2)Lower surface is provided with suspension bracket(6),
Suspension bracket(6)Micro machine is inside installed(7), micro machine(7)Output shaft pass through lower clamp(2)With ball(5)It is connected, in ball
(5)Top is provided with vertical cut (V. cut)(8), the swing arm that can be swung up and down is hinged with vertical cut (V. cut)(9), swing arm(9)On
End and mounting plate(1)It is connected.
2. automatic power construction supervision system according to claim 1, it is characterised in that:In vertical cut (V. cut)(8)Inside set
It is equipped with zig-zagging rib(10), in swing arm(9)Lower-end rear portion is provided with the card article being engaged with zig-zagging rib.
3. automatic power construction supervision system according to claim 2, it is characterised in that:The card article is plastics bullet
Bar.
4. automatic power construction supervision system according to claim 1, it is characterised in that:In support tube(3)Upper end
Oil filler point is provided with annular necking.
5. automatic power construction supervision system according to claim 1, it is characterised in that:The ball(5)It is ceramics
Material ball.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621348201.1U CN206313364U (en) | 2016-12-09 | 2016-12-09 | Automatic power construction supervision system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621348201.1U CN206313364U (en) | 2016-12-09 | 2016-12-09 | Automatic power construction supervision system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206313364U true CN206313364U (en) | 2017-07-07 |
Family
ID=59251026
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621348201.1U Expired - Fee Related CN206313364U (en) | 2016-12-09 | 2016-12-09 | Automatic power construction supervision system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206313364U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110751081A (en) * | 2019-10-17 | 2020-02-04 | 河南四建工程有限公司 | Construction safety monitoring method and device based on machine vision |
-
2016
- 2016-12-09 CN CN201621348201.1U patent/CN206313364U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110751081A (en) * | 2019-10-17 | 2020-02-04 | 河南四建工程有限公司 | Construction safety monitoring method and device based on machine vision |
CN110751081B (en) * | 2019-10-17 | 2022-01-28 | 河南四建工程有限公司 | Construction safety monitoring method and device based on machine vision |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106886225B (en) | Multifunctional unmanned aerial vehicle intelligent landing station system | |
CN103658052B (en) | A kind of automation steel ball sorting equipment | |
CN101881598B (en) | Automatic corn ear character parameter detecting device based on machine vision | |
CN108868169B (en) | Wall building robot | |
CN105651782A (en) | Engine cylinder cover defect automatic detection equipment based on machine vision | |
CN204197989U (en) | Glass shifting apparatus | |
CN112590822B (en) | Modular robot system is patrolled and examined to track | |
CN206313364U (en) | Automatic power construction supervision system | |
CN109089923A (en) | A kind of animal husbandry automatic charging device | |
CN114136364A (en) | River hydrology automatic monitoring system | |
CN209064371U (en) | It is a kind of can the unmanned plane photographic device that is shot of multi-angle | |
CN203654172U (en) | Bridge health detection device | |
CN111103218A (en) | Concrete aggregate particle diameter on-line monitoring device | |
CN204831093U (en) | Meadow height monitoring device | |
CN206210136U (en) | A kind of auto repair on-the-spot teaching equipment | |
CN110454657B (en) | Project supervision and supervision system | |
CN210479030U (en) | Coal mine vertical shaft well wall crack inspection aircraft system capable of flying autonomously | |
CN205695185U (en) | Worm monitoring system | |
CN208873746U (en) | Full automatic solar cell piece, which is drawn, splits machine | |
CN111804602A (en) | Part grabbing, rotating and removing integrated device and using method thereof | |
CN206313363U (en) | Transmission line high-altitude operation supervision system | |
CN216622214U (en) | Bridge bottom surface crack detection device | |
CN207366471U (en) | Paster resistance end face automatic detection device | |
CN203615898U (en) | Automatic change through-hole size detection device | |
CN207464638U (en) | A kind of spinning head automatic assembling device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170707 Termination date: 20171209 |