CN206310919U - A kind of ceramic metallization atmosphere sintering furnace - Google Patents

A kind of ceramic metallization atmosphere sintering furnace Download PDF

Info

Publication number
CN206310919U
CN206310919U CN201621384016.8U CN201621384016U CN206310919U CN 206310919 U CN206310919 U CN 206310919U CN 201621384016 U CN201621384016 U CN 201621384016U CN 206310919 U CN206310919 U CN 206310919U
Authority
CN
China
Prior art keywords
controller
hydrogen
ceramic metallization
heater
curtain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621384016.8U
Other languages
Chinese (zh)
Inventor
毛桂生
康丁华
康文涛
颜勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Loudi City An Diyasi electronic ceramics company limited
Original Assignee
康文涛
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 康文涛 filed Critical 康文涛
Priority to CN201621384016.8U priority Critical patent/CN206310919U/en
Application granted granted Critical
Publication of CN206310919U publication Critical patent/CN206310919U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Furnace Details (AREA)

Abstract

The utility model provides a kind of ceramic metallization atmosphere sintering furnace, using the multiple air inlets in body of heater, so that the flow and spacing of air inlet have been controlled in body of heater, effectively solve the problems, such as ceramic metallization atmosphere skewness and cause ceramic metallized layer engaging force uneven;Fiery curtain curtain is set in charging aperture and discharging opening, the entrance of air is prevented, the oxidation of metal stratification is effectively prevented;Multiple air inlets, moreover it is possible to solve the problems, such as that product useful load is excessively that the quality for causing is bad in body of heater;Dry hydrogen import is set at plug for outlet, prevents ceramics from collecting the oxidation of metal layer in temperature-fall period.Using ceramic metallization atmosphere sintering furnace of the present utility model so that the quality of the product of sintering is improved to more than 95% by 80%.

Description

A kind of ceramic metallization atmosphere sintering furnace
Technical field
The utility model belongs to electrovacuum special equipment technical field, and in particular to a kind of ceramic metallization atmosphere sintering Stove.
Background technology
High-temperature hydrogen sintering furnace is mainly used in agglomerated material, is widely used in new energy development, heat treatment, powder metallurgy, pottery The fields such as porcelain metal words, realize vacuum seal ceramic metallization, have good application to act on to high-sintering process.Current city On field with high-temperature hydrogen sintering furnace there is furnace atmosphere skewness, ceramic metallized layer engaging force is uneven, engaging force Fluctuated between 60~100MPa, and after coming out of the stove, the oxidized phenomenon of product is more, and product percent of pass is low.
CN201510945532.7 discloses a kind of ceramic sintering furnace, and it includes cabinet and horizontal-extending along cabinet length direction The boiler tube of the cabinet inside is arranged on, the boiler tube is fixed on the cabinet inside and by the fixation by fixed support Support is divided into ceramic post sintering pipeline section, transitional pipe segment and cooling pipeline section, the two ends of the boiler tube be respectively arranged with charging aperture with And discharging opening, the transmission crawler belt positioned at cabinet inside, the ceramic post sintering are provided between the charging aperture and the discharging opening Pipeline section outside is arranged with furnace wall, and is fixed on furnace wall inside by support and is divided into multiple bringing-up sections, outside each bringing-up section At least one heater is provided with wall, the heater of each bringing-up section is connected at least one temperature control equipment, used Temperature inside to bringing-up section is detected and is adjusted control.It becomes ceramics drying, Ceramic brazing and ceramic metallization Integrally, the constructed and differentiation requirement of ceramic post sintering, Ceramic brazing, three sets of techniques of ceramic metallization is combined, is saved excellent Change apparatus and process flow, saved material, reduce disposal of pollutants.But the ceramic sintering furnace does not solve existing high temperature sintering work still During skill, the oxidized situation of product does not solve furnace atmosphere phenomenon pockety yet.
Utility model content
In view of the shortcomings of the prior art, the utility model provides a kind of ceramic metallization atmosphere sintering furnace, can be effective Avoid causing the bad problem of product quality because gas load amount is excessive, it is effective to solve that furnace atmosphere is pockety to ask Topic, the problem for effectively preventing product oxidized.
In order to solve the above technical problems, the utility model provides following technical scheme:A kind of ceramic metallization atmosphere sintering Stove, including body of heater, controller and gas output device;
The body of heater includes pre-burning section, sintering stage, changeover portion and cooling section;The pre-burning section includes charging aperture, feed furnace Door, steam vent and the first dry hydrogen fiery curtain curtain;The first dry hydrogen fiery curtain curtain is arranged at charging fire door;
The sintering stage is provided with some hydrogen inlets, and the hydrogen inlet is evenly distributed on the surrounding of sintering stage;
The changeover portion is provided with wet hydrogen import near one end of cooling section;
The cooling section includes discharging opening, the second dry hydrogen fiery curtain curtain, dry hydrogen import and discharging door, the second dry hydrogen fire Curtain is arranged on discharging opening inner side, and the dry hydrogen import is arranged on cooling section near one end of changeover portion;
The hydrogen inlet, wet hydrogen import, dry hydrogen import, the second dry hydrogen fiery curtain curtain and the first dry hydrogen fiery curtain curtain pass through gas Body flow controller is connected with gas output device;
The gas flow controller is connected with controller.
Further, boiler tube is provided with the body of heater, the outside of the boiler tube is provided with sintering stage slightly in sintering stage Furnace wall long, the furnace wall includes inner and outer wall, and insulation material is provided between the inwall and outer wall;The inwall and stove Hydrogen circulation passage is provided between pipe.
Further, electric heater unit is provided with the furnace tube outer wall, the electric heating coil is spirally wrapped in On boiler tube, according to the region of pre-burning section and sintering stage in body of heater, electric heater unit is divided into two sections, and every section has its independent temperature control Device processed, the temperature control equipment is connected with controller.
Further, the gas flow controller is connected by hydrogen gas detector with gas output device, the hydrogen Gas detection means is connected with controller.
Further, the wet hydrogen import is connected by humidity controller with humidification device;The humidity controller and control Device processed is connected.
Further, the steam vent is communicated by air bleeding valve with air, and the air bleeding valve is connected with controller.
Further, the pre-burning section, sintering stage, changeover portion and cooling section are provided with temperature detector, the temperature Detector is connected with controller.
Further, the ceramic metallization atmosphere sintering furnace is additionally provided with alarm, the controller and alarm phase Even.
Further, some small-sized fans are uniformly arranged in the body of heater, the blower fan is connected with controller.
Further, the gas output device is connected with pressure gauge.
Further, the hydrogen inlet is 3.
The beneficial effects of the utility model:
The utility model provides a kind of ceramic metallization atmosphere sintering furnace, 1) using the multiple air inlets in body of heater so that The flow and spacing of air inlet have been controlled in body of heater, are effectively solved ceramic metallization atmosphere skewness and are caused ceramic metallization The uneven problem of layer engaging force;2) fiery curtain curtain is set in charging aperture and discharging opening, prevents the entrance of air, effectively prevent metal level The oxidation of change;3) multiple air inlets, moreover it is possible to solve the problems, such as that product useful load is excessively that the quality for causing is bad in body of heater;4) exist Dry hydrogen import is set at plug for outlet, the oxidation of ceramics metal layer in temperature-fall period is prevented;5) gas flow controller is set The gas flow of each position can be rationally controlled, rationally the technique of effective control ceramic metallization;6) the pre-burning section row of being provided with Air valve, can scavenge in time, it is ensured that technique is normally carried out;7) ceramic metallization atmosphere sintering of the present utility model is used Stove so that the quality of the product of sintering is improved to more than 95% by 80%.
The ceramic metallization atmosphere sintering furnace that the utility model is provided not only effectively solves the problems, such as atmosphere skewness, and And can cost-effective and energy consumption, improve sintering product quality, reduce ceramic material production procedure, save material, subtract Few discharge, is adapted to industrial production.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model embodiment;
Fig. 2 is the controller schematic diagram of the utility model embodiment.
Specific embodiment
The utility model is further described with specific embodiment below, but the utility model does not receive following embodiments Restriction.
Embodiment 1
As shown in Fig. 1~2, the utility model provides a kind of ceramic metallization atmosphere sintering furnace, including body of heater 1, controller And gas output device;
The body of heater 1 includes pre-burning section 11, sintering stage 12, changeover portion 13 and cooling section 14;Pre-burning section 11 include into Material mouth 111, charging fire door 112, the dry hydrogen fiery curtain curtain 114 of steam vent 113 and first;The first dry hydrogen fiery curtain curtain 114 is arranged on At charging fire door 112, when opening charging fire door 112, the first dry hydrogen fiery curtain curtain 114 is opened, and the ceramics entered from charging aperture 111 are needed Will be by the hydrogen of the first dry hydrogen fiery curtain curtain 114 fire, it is to avoid air enters, and increases the protection of ceramic metallized layer;Ceramics enter pre- After burning section 11, the waste gas that hydrogen fire pre-burning is produced is discharged by steam vent 113, it is to avoid exhaust residual;
The sintering stage 12 is provided with some hydrogen inlets 121, and the hydrogen inlet 121 is evenly distributed on sintering stage 12 Surrounding, it is ensured that the temperature equalization of sintering stage 12, even if in the case that useful load is more in the body of heater 1, the flowing of hydrogen, it is ensured that burn Temperature equalization in knot section 12, so that it is guaranteed that the uniformity of product, the chamber inner height of the body of heater sintering stage 12 sets and exceedes 30mm, controls in 240mm, can effectively ensure the effective flowing of gas in sintering stage 12;Further, the hydrogen inlet It is 3;The sintering stage 12 is used to be sintered ceramic material;
The changeover portion 13 is provided with wet hydrogen import 131 near one end of cooling section 14, it is ensured that the condensation effect of changeover portion 13 Really;The changeover portion 13 is used to carry out wet hydrogen cooling to the ceramic material after sintering;
The cooling section 14 includes discharging opening 141, the second dry hydrogen fiery curtain curtain 142, dry hydrogen import 143 and discharging door 144, The second dry hydrogen fiery curtain curtain 142 is arranged on the inner side of discharging opening 141, and the dry hydrogen import 143 is arranged on cooling section 14 and was close to Cross one end of section 13;The dry hydrogen import 143 can effectively prevent ceramics metal layer in temperature-fall period from aoxidizing;Described second Dry hydrogen fiery curtain curtain 142 is arranged on the inner side of discharging opening 141, is prevented effectively from air entrance;The cooling section 14 is used for natural cooling Ceramic material afterwards carries out natural cooling.
Further, the hydrogen inlet 121, wet hydrogen import 131, dry hydrogen import 143, the and of the second dry hydrogen fiery curtain curtain 142 First dry hydrogen fiery curtain curtain 114 is connected by gas flow controller 2 with gas output device.
Further, the gas flow controller 2 is connected by hydrogen gas detector with gas output device.Further Ground, the wet hydrogen import 131 is connected by humidity controller 3 with humidification device;The humidity controller 3 is connected with controller 8. Humidification device described in the utility model can realize automatic humidification, and water level can be automatically controlled.The humidity controller 3 passes through The humidity of wet hydrogen is detected, regulates and controls the size of humidification device, the humidity condition of wet hydrogen is transferred to control by humidity controller 3 in real time Device 8, controller 8 is according to the humidity threshold for setting, timely regulating and controlling humidity situation, while the record of controller 8 enters wet in body of heater 1 The humidity change of hydrogen.
Further, the steam vent 113 is communicated by air bleeding valve 4 with air;The air bleeding valve 4 by controller 8 with Pressure-detecting device (being not drawn into figure) is connected.The steam vent 133 discharges the waste gas in body of heater 1 in real time, it is ensured that sintering The carrying out of normal safe.
Further, boiler tube 5 is provided with the body of heater 1, the outside of the boiler tube 5 is provided with and sintering in sintering stage 12 12 furnace walls 6 slightly long of section, the furnace wall 6 includes inner and outer wall, insulation material is provided between the inwall and outer wall, is used for Boiler tube 5 is incubated;Hydrogen circulation passage is provided between the inwall and boiler tube 5, for the gas in sintering process Protection and the equilibrium of temperature.The transmission crawler belt inside boiler tube 5 is provided between described charging aperture 111 and discharging opening 141 (not shown);The transmission crawler belt is used to convey ceramic material in boiler tube 5.
Further, the pre-burning section 11, sintering stage 12, changeover portion 13 and cooling section 14 are provided with temperature detector 7, Temperature conditions in real-time monitoring body of heater.The data of detection are timely transferred to controller 8 by the temperature detector 7, control Device 8 according to setting temperature threshold, it is determined that and regulation electric heater unit work, to ensure the normal work of sintering furnace.
Further, the hydrogen gas detector, gas flow controller 2, air bleeding valve 4, temperature detector 7 with control Device 8 is connected.
Further, the controller 8 is connected with alarm, when hydrogen detectable concentration is not inconsistent standardization or gas flow control When device processed breaks down or air bleeding valve breaks down or temperature occurs abnormal, alarm is alarmed, and points out operator's equipment to enter The corresponding operation of row.
Further, the gas output device is connected with pressure gauge, the gas flow in monitor in real time gas output device, Ensure the normal operation of ceramic post sintering.
Further, electric heater unit (not shown), i.e. electric heating coil are provided with spirally on the outer wall of the boiler tube 5 It is wrapped on boiler tube 5, according to the region of pre-burning section 11 and sintering stage 12 in body of heater, electric heater unit is divided into two sections, and every section has it Independent temperature control equipment, the temperature control equipment is connected with controller 8.
Further, some small-sized fans 9 are uniformly arranged in the body of heater 1, for the gas in body of heater 1 to be flowed rapidly It is dynamic so that the equilibrium of temperature in sintering process;The blower fan 9 is connected with controller 8.
The ceramic metallization atmosphere sintering furnace that the utility model is provided, uses dry by charging aperture 111 and discharging opening 141 Hydrogen fiery curtain curtain is protected, and prevents the entrance of air;Steam vent 113 is set in pre-burning section 11, the discharge of waste gas is effectively solved; Some hydrogen inlets 121 are set in body of heater 1, and effective reduction the situation of defect ware occurs because ceramics load excessive; Discharging opening 141 sets dry hydrogen import 143 increases hydrogen shield, effectively prevents the oxidation of temperature-fall period metal layer;In body of heater 1 Interior setting blower fan 9, is effectively ensured the flowing of gas in body of heater 1, it is ensured that the uniformity of sintering;Sintering furnace is controlled by controller 8 Parameters, monitor in real time and effectively treatment.When temperature detector 7 detects certain section of ceramic metallization atmosphere sintering furnace When temperature is higher or lower than design temperature, by signal transmission to controller 8, controller 8 is by signal transmission to electric heater unit, electricity Heater is heated up or cooling treatment according to the program of former setting;When humidity controller 3 detection periphery humidity be less than or During higher than setting humidity, by signal transmission to controller, controller 8 carries out different signal transmissions according to presetting scope, Controller control humidification device is processed accordingly;The density of hydrogen that hydrogen gas detector is detected in sintering furnace does not meet will When asking, controller 8 is transmitted a signal to, controller 8 will be transferred to gas output device, gas output device root after signal transacting According to the size of particular situation adjusting gas flow controller 2;The atmosphere pressures in sintering furnace are detected when pressure-detecting device Certain value is reached, the control air bleeding valve 4 of controller 8 is opened, and gas is discharged from steam vent 113.In addition, sintering stage 12, changeover portion 13 and cooling section 14 be respectively provided with different hydrogen inlets, according to the demand of different phase, the amount and kind of hydrogen are completely not yet Together, the temperature interference of different zones can be not only avoided, and disclosure satisfy that the sintering process demand in body of heater;Ensure agglomerant The uniformity of skill.
Preferred embodiment of the present utility model is the foregoing is only, the utility model is not limited to, for this For the technical staff in field, the utility model can have various modifications and variations.It is all it is of the present utility model spirit and principle Within, any modification, equivalent substitution and improvements made etc. should be included within protection domain of the present utility model.

Claims (10)

1. a kind of ceramic metallization atmosphere sintering furnace, it is characterised in that including body of heater, controller and gas output device;
The body of heater includes pre-burning section, sintering stage, changeover portion and cooling section;The pre-burning section includes charging aperture, charging fire door, row Stomata and the first dry hydrogen fiery curtain curtain;The first dry hydrogen fiery curtain curtain is arranged at charging fire door;
The sintering stage is provided with some hydrogen inlets, and the hydrogen inlet is evenly distributed on the surrounding of sintering stage;
The changeover portion is provided with wet hydrogen import near one end of cooling section;
The cooling section includes discharging opening, the second dry hydrogen fiery curtain curtain, dry hydrogen import and discharging door, the second dry hydrogen fiery curtain curtain Discharging opening inner side is arranged on, the dry hydrogen import is arranged on cooling section near one end of changeover portion;
The hydrogen inlet, wet hydrogen import, dry hydrogen import, the second dry hydrogen fiery curtain curtain and the first dry hydrogen fiery curtain curtain pass through gas stream Amount controller is connected with gas output device;
The gas flow controller is connected with controller.
2. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that be provided with stove in the body of heater Pipe, the outside of the boiler tube is provided with the furnace wall slightly long with sintering stage in sintering stage, and the furnace wall includes inner and outer wall, described Insulation material is provided between inwall and outer wall;Hydrogen circulation passage is provided between the inwall and boiler tube.
3. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that the gas flow controller leads to Cross hydrogen gas detector to be connected with gas output device, the hydrogen gas detector is connected with controller.
4. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that the wet hydrogen import passes through humidity Controller is connected with humidification device;The humidity controller is connected with controller.
5. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that the steam vent passes through air bleeding valve Communicated with air, the air bleeding valve is connected by controller with pressure-detecting device.
6. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that the pre-burning section, sintering stage, mistake Cross section and cooling section is provided with temperature detector, the temperature detector is connected with controller.
7. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that be provided with the furnace tube outer wall Electric heater unit, the electric heating coil is spirally wrapped on boiler tube, according to the region of pre-burning section and sintering stage in body of heater, Electric heater unit is divided into two sections, and every section has its independent temperature control equipment, and the temperature control equipment is connected with controller.
8. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that if being uniformly arranged in the body of heater Dry small-sized fan, the blower fan is connected with controller.
9. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that the ceramic metallization atmosphere is burnt Freezing of a furnace is additionally provided with alarm, and the controller is connected with alarm.
10. ceramic metallization atmosphere sintering furnace according to claim 1, it is characterised in that the gas output device with Pressure gauge is connected.
CN201621384016.8U 2016-12-16 2016-12-16 A kind of ceramic metallization atmosphere sintering furnace Active CN206310919U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621384016.8U CN206310919U (en) 2016-12-16 2016-12-16 A kind of ceramic metallization atmosphere sintering furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621384016.8U CN206310919U (en) 2016-12-16 2016-12-16 A kind of ceramic metallization atmosphere sintering furnace

Publications (1)

Publication Number Publication Date
CN206310919U true CN206310919U (en) 2017-07-07

Family

ID=59251710

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621384016.8U Active CN206310919U (en) 2016-12-16 2016-12-16 A kind of ceramic metallization atmosphere sintering furnace

Country Status (1)

Country Link
CN (1) CN206310919U (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107314669A (en) * 2017-08-16 2017-11-03 肇庆市宏华电子科技有限公司 Hydrogen continuous tunnel furnace and ceramic circuit elements process equipment
CN107906948A (en) * 2017-10-25 2018-04-13 北京北方华创真空技术有限公司 A kind of horizontal-type high temperature hydrogen resistance furnace
CN108685197A (en) * 2018-07-30 2018-10-23 福建闽航电子有限公司 A kind of fever piece making method and electronic smoking set for electronic smoking set
CN108981180A (en) * 2018-07-30 2018-12-11 福建闽航电子有限公司 A kind of manufacturing method of the heat generating device of warm-air drier
CN109114983A (en) * 2018-08-14 2019-01-01 通威太阳能(成都)有限公司 A kind of sintering furnace and its application method
CN109141036A (en) * 2018-09-17 2019-01-04 湖南湘瓷科艺有限公司 A kind of continous way metallization furnace atmosphere stable regulation method and device
CN109539782A (en) * 2018-11-12 2019-03-29 上海申和热磁电子有限公司 The method of top and the sintering of bottom two-way oxygen formula high temperature sintering furnace and its oxygenation
CN109539774A (en) * 2018-11-24 2019-03-29 泰州市华诚钨钼制品有限公司 A kind of safety anti-explosive Muffle furnace of automatic control
CN111170764A (en) * 2019-12-31 2020-05-19 娄底市安地亚斯电子陶瓷有限公司 Wet hydrogen system and working method thereof
CN113606935A (en) * 2021-07-30 2021-11-05 合肥圣达电子科技实业有限公司 Oxidation furnace for improving uniformity of copper sheet oxidation layer
CN114199033A (en) * 2021-11-19 2022-03-18 湖南新华源科技有限公司 Support transferring device for ceramic metallization and using method thereof

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107314669A (en) * 2017-08-16 2017-11-03 肇庆市宏华电子科技有限公司 Hydrogen continuous tunnel furnace and ceramic circuit elements process equipment
CN107314669B (en) * 2017-08-16 2023-09-08 肇庆市宏华电子科技有限公司 Hydrogen tunnel furnace and ceramic circuit element processing equipment
CN107906948B (en) * 2017-10-25 2019-04-30 北京北方华创真空技术有限公司 A kind of horizontal-type high temperature hydrogen resistance furnace
CN107906948A (en) * 2017-10-25 2018-04-13 北京北方华创真空技术有限公司 A kind of horizontal-type high temperature hydrogen resistance furnace
CN108981180A (en) * 2018-07-30 2018-12-11 福建闽航电子有限公司 A kind of manufacturing method of the heat generating device of warm-air drier
CN108685197A (en) * 2018-07-30 2018-10-23 福建闽航电子有限公司 A kind of fever piece making method and electronic smoking set for electronic smoking set
CN109114983A (en) * 2018-08-14 2019-01-01 通威太阳能(成都)有限公司 A kind of sintering furnace and its application method
CN109114983B (en) * 2018-08-14 2024-04-26 通威太阳能(成都)有限公司 Sintering furnace and use method thereof
CN109141036A (en) * 2018-09-17 2019-01-04 湖南湘瓷科艺有限公司 A kind of continous way metallization furnace atmosphere stable regulation method and device
CN109141036B (en) * 2018-09-17 2023-12-19 湖南湘瓷科艺有限公司 Continuous metallization furnace atmosphere stable adjustment method
CN109539782A (en) * 2018-11-12 2019-03-29 上海申和热磁电子有限公司 The method of top and the sintering of bottom two-way oxygen formula high temperature sintering furnace and its oxygenation
CN109539774A (en) * 2018-11-24 2019-03-29 泰州市华诚钨钼制品有限公司 A kind of safety anti-explosive Muffle furnace of automatic control
CN111170764A (en) * 2019-12-31 2020-05-19 娄底市安地亚斯电子陶瓷有限公司 Wet hydrogen system and working method thereof
CN113606935A (en) * 2021-07-30 2021-11-05 合肥圣达电子科技实业有限公司 Oxidation furnace for improving uniformity of copper sheet oxidation layer
CN114199033A (en) * 2021-11-19 2022-03-18 湖南新华源科技有限公司 Support transferring device for ceramic metallization and using method thereof
CN114199033B (en) * 2021-11-19 2023-10-31 湖南省新化县鑫星电子陶瓷有限责任公司 Support transfer device for ceramic metallization and application method thereof

Similar Documents

Publication Publication Date Title
CN206310919U (en) A kind of ceramic metallization atmosphere sintering furnace
CN209124820U (en) A kind of antiquated sand roasting system
CN103954144A (en) Sintering annular cooler cooling process monitoring system and control method
CN102278879A (en) Micro-wave roller kiln
CN106705442A (en) Gas water heater with self-adaption function
CN101718502B (en) Electric furnace flue gas waste heat recovering and temperature regulating device
CN201600037U (en) Electric furnace flue gas waste heat recovery temperature control device
CN206478620U (en) Control the robot control system(RCS) of exhaust gas temperature
CN105858649B (en) Graphite high temperature puffing stove
CN210569930U (en) Energy-saving electric furnace for smelting scrap iron
CN104819450B (en) A kind of boiler controls the method for drum wall temperature difference after determining the normal blowing out of parameter
CN204880201U (en) Humidity elimination equipment discharges fume
CN207975996U (en) A kind of smelting residual heat generating device
CN207871785U (en) A kind of simple flue gas cool-down and desulfurizer
CN110860378A (en) Hot air blowing system for electric dust remover
CN207159275U (en) A kind of meshbeltfurnace quickly burns carbon system
CN204324899U (en) Active carbon production equipment process furnace
CN208357187U (en) Copper wire enameling machine baker
CN207527598U (en) A kind of dangerous waste incineration system dual firing chamber bottom steam retracting device
CN207316939U (en) Organic exhaust gas aoxidizes the urgent cooling system of incinerator
CN209679524U (en) A kind of spray-drying installation
CN202204281U (en) Microwave roller kiln
CN209268493U (en) A kind of automatically controlled bakery of temperature automatic control
CN203083328U (en) Wood drying kiln
CN206356138U (en) A kind of hot blast protection device for wet electrical dust precipitator

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20170818

Address after: 417000 Loudi City, Hunan province Loudi economic and Technological Development Zone two Park Road North and South Qianyuan International Building D7-1

Patentee after: Loudi City An Diyasi electronic ceramics company limited

Address before: 417000 Xinhua County, Loudi Province on the town of workers and peasants on the River Road, No. 54, No.

Patentee before: Kang Wentao

TR01 Transfer of patent right
CB03 Change of inventor or designer information

Inventor after: Kang Dinghua

Inventor after: Kang Wentao

Inventor after: Yan Yong

Inventor before: Mao Guisheng

Inventor before: Kang Dinghua

Inventor before: Kang Wentao

Inventor before: Yan Yong

CB03 Change of inventor or designer information