CN206279548U - A kind of base pit dewatering well crosses water pipe safeguard structure - Google Patents
A kind of base pit dewatering well crosses water pipe safeguard structure Download PDFInfo
- Publication number
- CN206279548U CN206279548U CN201621386528.8U CN201621386528U CN206279548U CN 206279548 U CN206279548 U CN 206279548U CN 201621386528 U CN201621386528 U CN 201621386528U CN 206279548 U CN206279548 U CN 206279548U
- Authority
- CN
- China
- Prior art keywords
- well
- water pipe
- channel
- section steel
- safeguard structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Sewage (AREA)
Abstract
The utility model provides a kind of base pit dewatering well and crosses water pipe safeguard structure, cross water pipe along the circumferential direction distributing installation on well, cross the side wall of water pipe insertion well, enclosed on the outside of well and be provided with the channel-section steel that notch is inwards set, it is described to cross the inner side that water pipe may be contained within channel-section steel, and setting is closed between channel-section steel and well outer wall, the bottom land of channel-section steel offers water hole.It is poor to solve existing conventional safeguard structure weight capacity, and the stronger safeguard structure construction cost of load-bearing is high, the cycle is long, and tool has some limitations.The utility model belongs to drainage construction field.
Description
Technical field
The utility model is related to a kind of job site waterproof construction, belongs to drainage construction field.
Background technology
Conventional job site waterproof is based on unimpeded.Draining is usually to build weeper drain or take ground away using pipe well
Lower water.The building of weeper drain needs certain water pressure or manually manufactures drainage grade, is seeped water for large area and existing
The construction method of the larger local weeper drain of field construction surface has certain limitation.Water blockoff(Manufacture water-stop curtain)And pipe well
Precipitation is then needed along well-point pipe is buried around foundation ditch, and the construction method cycle is more long, and is covered by neighbour building for surrounding place
The field construction of lid is more inconvenient.And after substantial amounts of underground water is pumped discharge.The buoyancy force of underground water in the region can decline, surrounding
Building and underground utilities will produce differential settlement, the structure safety of the neighbour building of influence.To solve the above problems, design
A kind of base pit dewatering well, but crossing water pipe periphery and need to cover multiple filtration Rotating fields due to this well, its peripheral load-bearing
Greatly, therefore, need to design that a kind of weight capacity is extremely strong, the water of filtering can be effectively ensured again by what water pipe entered well and cross water pipe
Safeguard structure.
The content of the invention
The purpose of this utility model is:A kind of base pit dewatering well is provided and crosses water pipe safeguard structure, it is existing normal to solve
The safeguard structure weight capacity of rule is poor, and the stronger safeguard structure construction cost of load-bearing is high, the cycle is long, and with certain office
Sex-limited problem.
To solve the above problems, intend crossing water pipe safeguard structure using such a base pit dewatering well, cross water pipe circumferentially
Directional spreding is installed on well, crosses the side wall of water pipe insertion well, is enclosed on the outside of well and is provided with notch and inwards sets
Channel-section steel, the water pipe of crossing may be contained within the inner side of channel-section steel, and closed between channel-section steel and well outer wall and set, and the bottom land of channel-section steel is opened
It is provided with water hole.
It is foregoing to cross in water pipe safeguard structure, the steel sleeve that water pipe is a diameter of 100mm is crossed, water pipe is crossed in well base surface mark
The position of 1m is distributed by spacing 150mm and set on height;
It is foregoing cross water pipe safeguard structure in, well be square hoistway structure, the channel-section steel by set along square arrangement four
Section straight trough steel is welded from beginning to end successively, and the model of every section of straight trough steel is 14b, i.e. height 140mm, leg 60mm wide, and waist is thick
8mm。
Compared with prior art, well described in the utility model crosses water pipe safeguard structure on the premise of weight capacity is ensured
Structure is more simple, easy construction, and short construction period, more practical, does not interfere with the structure safety of neighbour building, effectively protects
Hinder the normal operation of base pit dewatering well.
Brief description of the drawings
Fig. 1 is main view cross-sectional view of the present utility model.
Specific embodiment
To make the purpose of this utility model, technical scheme and advantage clearer, below will be new to this practicality by accompanying drawing
Type is described in further detail.
Embodiment:
Referring to the drawings 1, the present embodiment provides a kind of base pit dewatering well and crosses water pipe safeguard structure, and it is a diameter of to cross water pipe 2
The steel sleeve of 100mm, crosses water pipe 2 and is along the circumferential direction distributed setting by spacing 150mm in the position of 1m on the base surface absolute altitude of well 1
In on well 1, the side wall of the insertion well 1 of water pipe 2 is crossed, the outside of well 1 encloses and is provided with the channel-section steel 3 that notch is inwards set,
It is described to cross the inner side that water pipe 2 may be contained within channel-section steel 3, and setting is closed between channel-section steel 3 and the outer wall of well 1, the bottom land of channel-section steel 3 is opened up
There is water hole 31;
Well 1 is square hoistway structure, and the channel-section steel 3 is welded from beginning to end successively by the four sections of straight trough steel set along square arrangement
Form, the model of every section of straight trough steel is 14b, i.e. height 140mm, leg 60mm wide, waist thickness 8mm.
Geofabrics cloth 4, cobblestone 5, geofabrics cloth 4 and rubble filter layer 6, goose ovum are laid successively in the outside of channel-section steel 3
The laying height of stone 5 is 1m, according to 1:1.5 gradient carries out slope, and the laying depth of rubble filter layer 6 is 0.4m, the well of well 1
Maintenance cat ladder 7 is installed in road.
The construction method of the well is as follows:
Step one:Excavation and precipitation foundation ditch;
Step 2:Well structure is constructed, constructed on the basis of precipitation foundation ditch well 1, the 1m on well base surface absolute altitude
Position distribution clipping room away from a diameter of 100mm of 150mm cross water pipe 2, cross the insertion well 1 of water pipe 2 side wall, meanwhile, in mistake
A row is installed in the periphery of water pipe 2 is used to fix the reinforcing bar of channel-section steel 3;
Step 3:Channel-section steel is installed, channel-section steel 3 is installed in the outside of well 1, the processing method of channel-section steel 3 is:
A. channel-section steel 3 is cut into 4 parts according to tunnel dimension, the two ends of channel-section steel 3 are cut into ramp-like;
B. bring steel plate into permeable hole 31 out into the open using electric welding machine, diameter is less than 40mm, with uneven distribution, but can ensure
Substantial amounts of rubble into well concrete structure is not had while permeable again;
C. channel-section steel 3 is welded with reserved joint bar after well concrete structure construction is finished, while entering in the angle junction of channel-section steel 3
Row groove is welded;
Step 4:Laying filter layer, geofabrics cloth 4 is laid in the outside of channel-section steel 3, and goose ovum is laid on geofabrics cloth 4
Stone 5, lays geofabrics cloth 4 again on the cobblestone 5 for laying, and rubble is re-layed on the geofabrics cloth 4 on cobblestone 5
Filter layer 6, the laying height of cobblestone 5 is 1m, according to 1:1.5 gradient carries out slope, and the laying depth of rubble filter layer 6 is
0.4m;
Step 5:Pumping equipment is installed, the end of drawing water of pumping equipment extends the bottom of well 1, for that will penetrate into well 1
Water be pumped into and cistern or drain into river course.
Claims (3)
1. a kind of base pit dewatering well crosses water pipe safeguard structure, cross water pipe (2) along the circumferential direction distributing installation on well (1),
Cross the side wall of water pipe (2) insertion well (1), it is characterised in that:Enclosed on the outside of well (1) and be provided with what notch was inwards set
Channel-section steel (3), the water pipe (2) of crossing may be contained within the inner side of channel-section steel (3), and closed between channel-section steel (3) and well (1) outer wall and set
Put, the bottom land of channel-section steel (3) offers water hole (31).
2. a kind of base pit dewatering well crosses water pipe safeguard structure according to claim 1, it is characterised in that:Crossing water pipe (2) is
The steel sleeve of a diameter of 100mm, crosses water pipe (2) and is set by spacing 150mm distributions in the position of 1m on well (1) base surface absolute altitude
Put.
3. a kind of base pit dewatering well crosses water pipe safeguard structure according to claim 1, it is characterised in that:The well (1)
It is square hoistway structure, the channel-section steel (3) is welded from beginning to end successively by the four sections of straight trough steel set along square arrangement, every section straight
The model of channel-section steel is 14b, i.e. height 140mm, leg 60mm wide, waist thickness 8mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621386528.8U CN206279548U (en) | 2016-12-16 | 2016-12-16 | A kind of base pit dewatering well crosses water pipe safeguard structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621386528.8U CN206279548U (en) | 2016-12-16 | 2016-12-16 | A kind of base pit dewatering well crosses water pipe safeguard structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206279548U true CN206279548U (en) | 2017-06-27 |
Family
ID=59073580
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621386528.8U Expired - Fee Related CN206279548U (en) | 2016-12-16 | 2016-12-16 | A kind of base pit dewatering well crosses water pipe safeguard structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206279548U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826199A (en) * | 2019-04-09 | 2019-05-31 | 甘肃中建市政工程勘察设计研究院有限公司 | Seep water white-out structure and its construction method outside a kind of foundation pit side-wall |
-
2016
- 2016-12-16 CN CN201621386528.8U patent/CN206279548U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826199A (en) * | 2019-04-09 | 2019-05-31 | 甘肃中建市政工程勘察设计研究院有限公司 | Seep water white-out structure and its construction method outside a kind of foundation pit side-wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103993603B (en) | A kind of anchor pole churning back cover deep foundation ditch reversed construction method without dewatering operation | |
CN203947484U (en) | Foundation pit drainage and circulating water utilization system | |
CN206408655U (en) | The top plate sidewall structure of covered back-digging construction | |
CN105179011A (en) | Tunnel plugging facility and tunnel plugging method | |
CN113464174B (en) | Construction method of tunnel row waterproof comprehensive treatment system | |
CN208105281U (en) | A kind of the Metro station excavation sealing and precipitation system of the sand-pebble layer containing rich water | |
CN206279548U (en) | A kind of base pit dewatering well crosses water pipe safeguard structure | |
CN106638641B (en) | Base pit dewatering well structure and its construction method | |
CN204899978U (en) | Shaft excavation to interface water layer drainage system | |
CN205421303U (en) | High water level silt ground water treatment facilities falls | |
CN206279547U (en) | Base pit dewatering well structure | |
CN111424685A (en) | Deep water falling hole processing structure and method for backfilling foundation in large karst depression | |
CN104328836B (en) | A kind of environment-friendly type prefabricated pair of case deep hole type catch pit and construction method thereof | |
CN107724405B (en) | Dewatering of foundation construction method in a kind of underground pipe construction | |
CN205369281U (en) | Radial precipitation structure | |
CN108755724A (en) | The external water drainage waterproof method of pipe gallery | |
CN207620014U (en) | A kind of Novel underground room seepage treatment structure | |
CN103993609A (en) | Silicon lime sand water guiding, draining and filtering multifunctional rapid and rigid congealing body manual repaired foundation pit water-stopping curtain | |
CN210164024U (en) | Fill husky cable pit drainage system | |
CN204059139U (en) | Infiltration type catchments concrete reinforced pipe | |
CN203741855U (en) | Foundation pit waterproof curtain capable of being repaired manually and with multifunctional coagulation body with quickly hardening silica fume layer and integrating water guiding, discharging and filtering functions | |
CN209368854U (en) | Foundation pit side-wall infiltration current-collecting device | |
CN108625402A (en) | Foundation pit fertilizer slot ponding processing method | |
CN106120655A (en) | The fast repairing method that asphalt concrete core of embankment dams depths leaks | |
CN111851548A (en) | Dewatering inclined shaft in deep foundation pit and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170627 Termination date: 20211216 |
|
CF01 | Termination of patent right due to non-payment of annual fee |