CN206189921U - Archaistic building - Google Patents

Archaistic building Download PDF

Info

Publication number
CN206189921U
CN206189921U CN201621257995.0U CN201621257995U CN206189921U CN 206189921 U CN206189921 U CN 206189921U CN 201621257995 U CN201621257995 U CN 201621257995U CN 206189921 U CN206189921 U CN 206189921U
Authority
CN
China
Prior art keywords
antique
modelled
building
style
ancients
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621257995.0U
Other languages
Chinese (zh)
Inventor
刘长山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING JUXING COMPOSITE MATERIAL TECHNOLOGY DEVELOPMENT Co Ltd
Original Assignee
BEIJING JUXING COMPOSITE MATERIAL TECHNOLOGY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING JUXING COMPOSITE MATERIAL TECHNOLOGY DEVELOPMENT Co Ltd filed Critical BEIJING JUXING COMPOSITE MATERIAL TECHNOLOGY DEVELOPMENT Co Ltd
Priority to CN201621257995.0U priority Critical patent/CN206189921U/en
Application granted granted Critical
Publication of CN206189921U publication Critical patent/CN206189921U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides an archaistic building relates to the technical field that the ancient building was made, include: ground basis, main body steel structure, stand modelled after an antique and disjunctor modelled after an antique tile, reinforced concrete structure is adopted on the ground basis, and main body steel structure is including supporting steelframe and a plurality of vertical pipe, stand modelled after an antique with reinforced concrete structure connects, disjunctor tile modelled after an antique is connected in the top of supporting the steelframe, the material that disjunctor modelled after an antique tile and stand modelled after an antique adopted includes modified cement, and disjunctor modelled after an antique is made of baked clay and stand modelled after an antique belongs to mill's prefabrication, and the form is lifelike, has fine assembly and effect modelled after an antique, and have and do not seep water, rain leakage not, utensil feel is true, and the durability is good, and the advantage of outward appearance, proportion and tradition tile unanimity. The problem of the construction cycle of the existence among the prior art long, and the short technique of life is solved for archaistic building's construction just utilize more extensive reasonable more.

Description

Building in the style of the ancients
Technical field
The utility model is related to ancient building manufacturing technology field, more particularly, to a kind of building in the style of the ancients.
Background technology
China is a multi-ethnic ancient civilized country, there is long history and colourful traditional culture.Research and Pass on the ancient architecture art of China, from officially to ancient building among the people, and various nationalities architectural style;From general construction ratio The contract of example enters to construction technology technology, and the wisdom and art of nationality are filled with invariably, is crystallization and the model of Chinese national culture, And turned into exchanged with world various nationalities and friendship important content.
Traditional ancient building using it is special, watt, ash, wood, stone, it is desirable to it is extremely strict to enter material, production brick, watt also to consume a large amount of energy Ecological environment is destroyed in source;It is especially grand brilliant and design requirement is consummate, and construction requirement is tight, careful, exquisite, the cycle is long Ancient building roof is even more so.Building in the style of the ancients of the prior art mainly using steel plate as building lot, install imitative by outside Ancient accessory, can within a certain period of time serve as the function of building in the style of the ancients.
But, building in the style of the ancients in the prior art, mainly by building temporarily, the time limit for generally using is shorter, and existing Construction period in technology is more long, and material is usually on the basis of clay, by increasing dyeing color essence, to reach exterior color The effect similar to ancient building, but to generally use the life-span shorter for the material, and color can come off and shoal over time, it is impossible to It is continuing with.
Utility model content
The purpose of this utility model is to provide a kind of building in the style of the ancients, to solve construction period present in prior art It is long, and the short technical problem of service life.
The utility model provides a kind of building in the style of the ancients, including:Ground base, main body steel construction, column modelled after an antique and company modelled after an antique Body watt;
Ground base uses reinforced concrete structure, and main body steel construction includes supporting steel frame and multiple steel pipes vertically;Vertically Steel pipe one end along its length is connected with supporting steel frame, and the other end is connected to reinforced concrete structure;
Column modelled after an antique is wrapped in the outside of all or part of steel pipe vertically along its length;And column modelled after an antique and the steel Tendon concrete structure is connected;
Conjuncted tile modelled after an antique is connected to the top of supporting steel frame;
The material that Conjuncted tile modelled after an antique and column modelled after an antique are used includes modified cement.
Further, Conjuncted tile modelled after an antique is the solid of modified cement products.
Further, the building in the style of the ancients that the utility model is provided also includes purlin three;
Purlin three is fixedly connected on the one end of column modelled after an antique away from the ground base.
Further, the building in the style of the ancients that the utility model is provided also includes:Baotou beam;
Purlin three is provided with multiple, and baotou beam is interspersed to be arranged between purlin three.
Further, the building in the style of the ancients that the utility model is provided also includes that rafter hopes integral piece;
Rafter hopes that integral piece one end is arranged on purlin three;The other end is arranged on supporting steel frame;
Rafter hopes that integral piece is provided with multiple, and multiple rafters hope that integral piece is arranged in order;
Conjuncted tile modelled after an antique is arranged at the top that rafter hopes integral piece.
Further, the building in the style of the ancients that the utility model is provided also includes wall modelled after an antique;
The part vertical steel pipe is arranged inside the wall modelled after an antique.
Further, the building in the style of the ancients that the utility model is provided also includes door modelled after an antique and antique window;
The quantity of the column modelled after an antique is multiple;Be provided between the adjacent column modelled after an antique in part the door modelled after an antique or The antique window.
Further, main body steel construction and the connected mode of reinforced concrete structure are in height of a house formula or truss-like Kind.
Further, hook-shaped reinforcing bar is provided with reinforced concrete structure, hook-shaped reinforcing bar is embedded in ground base.
Further, Conjuncted tile modelled after an antique is divided into polylith carries out molding shaping;
Polylith Conjuncted tile modelled after an antique is hung by steel or mud is connected in main body steel construction.
A kind of building in the style of the ancients that the utility model is provided, including:Ground base, main body steel construction, column modelled after an antique and modelled after an antique Conjuncted tile;The material that Conjuncted tile modelled after an antique and column modelled after an antique are used includes modified cement, and Conjuncted tile modelled after an antique and column modelled after an antique are Belong to prefabrication product, form is true to nature, with assembling and antique effect well, the building in the style of the ancients that the utility model is provided passes through The column modelled after an antique and Conjuncted tile modelled after an antique suppressed using modified cement material, and most of component modelled after an antique is factory's making, Need to only assemble at the scene, it is convenient and swift;Component modelled after an antique is suppressed by mould and formed, and is not fallen off with stable physical property, safety, The characteristics of wind resistance is strong, solves the long construction period of presence of the prior art, and the short technical problem of service life, makes The construction for obtaining building in the style of the ancients is more reasonable and utilization more extensive.
Brief description of the drawings
In order to illustrate more clearly of the utility model specific embodiment or technical scheme of the prior art, below will be right The accompanying drawing to be used needed for specific embodiment or description of the prior art is briefly described, it should be apparent that, describe below In accompanying drawing be some implementation methods of the present utility model, for those of ordinary skill in the art, do not paying creativeness On the premise of work, other accompanying drawings can also be obtained according to these accompanying drawings.
The overall structure diagram of the building in the style of the ancients that Fig. 1 is provided for the utility model embodiment;
The local-style dwelling houses overall structure diagram of the building in the style of the ancients that Fig. 2 is provided for the utility model embodiment;
The sectional view of the layers of eaves octagonal pavilion of the building in the style of the ancients that Fig. 3 is provided for the utility model embodiment;
The overall structure diagram of the layers of eaves octagonal pavilion of the building in the style of the ancients that Fig. 4 is provided for the utility model embodiment;
The sectional view of the corner booth of the building in the style of the ancients that Fig. 5 is provided for the utility model embodiment;
The overall structure diagram of the corner booth of the building in the style of the ancients that Fig. 6 is provided for the utility model embodiment;
The front view of the gallery of the building in the style of the ancients that Fig. 7 is provided for the utility model embodiment;
The side view of the gallery of the building in the style of the ancients that Fig. 8 is provided for the utility model embodiment;
The front view of the decorated archway of the building in the style of the ancients that Fig. 9 is provided for the utility model embodiment;
The side view of the decorated archway of the building in the style of the ancients that Figure 10 is provided for the utility model embodiment;
The front view of the festoon gate of the building in the style of the ancients that Figure 11 is provided for the utility model embodiment;
The side view of the festoon gate of the building in the style of the ancients that Figure 12 is provided for the utility model embodiment.
Icon:010- Roof systems;020- agent structure systems;030- platforms are bright;040- small bells arrange ridge;050- companies modelled after an antique Body watt;060- rafters hope integral piece;070- sticks together head;The rich seam plates of 080-;090- purlins three;100- columns modelled after an antique;110- antique windows; 120- doors modelled after an antique;130- walls modelled after an antique;The steel columns of 150- first;The steel columns of 160- second;170- floor tiles modelled after an antique;180- stool;200- Bao Ding;210- hangs upside down lintel;220- closes angle kiss;230- spends serratd edge;250- angles cloud;260- covers beast;270- ridge beasts;280- hangs down beast; 290- hangs down ridge;300- hangs down band;The trouble heads of 310- tri-;320- drapes over one's shoulders water tip ridge;330- bargeboards;The steel columns of 340- the 3rd;350- pedestal boulders; 360- month beams;370- melon posts;380- is with beam a tree, used in making timber for boats.
Specific embodiment
The technical solution of the utility model is clearly and completely described below in conjunction with accompanying drawing, it is clear that described Embodiment is a part of embodiment of the utility model, rather than whole embodiments.Based on the embodiment in the utility model, this The every other embodiment that field those of ordinary skill is obtained under the premise of creative work is not made, belongs to this practicality Novel protected scope.
It is term " " center ", " on ", D score, "left", "right", " perpendicular, it is necessary to explanation in description of the present utility model Directly ", the orientation or position relationship of the instruction such as " level ", " interior ", " outward " are, based on orientation shown in the drawings or position relationship, to be only Described with simplified for the ease of description the utility model, must had rather than the device or element for indicating or implying meaning specific Orientation, with specific azimuth configuration and operation, therefore it is not intended that to limitation of the present utility model.Additionally, term " the One ", " second ", " the 3rd " are only used for describing purpose, and it is not intended that indicating or implying relative importance.
, it is necessary to explanation, unless otherwise clearly defined and limited, term " is pacified in description of the present utility model Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected, or be detachably connected, or integratedly Connection;Can mechanically connect, or electrically connect;Can be joined directly together, it is also possible to be indirectly connected to by intermediary, Can be two connections of element internal.For the ordinary skill in the art, above-mentioned art can be understood with concrete condition Concrete meaning of the language in the utility model.
The overall structure diagram of the building in the style of the ancients that Fig. 1 is provided for the present embodiment;Fig. 2 modelled after an antique builds for what the present embodiment was provided The local-style dwelling houses overall structure diagram built;Such as Fig. 1, shown in Fig. 2, a kind of building in the style of the ancients that the present embodiment is provided, including:Ground base Plinth, main body steel construction, column modelled after an antique 100 and Conjuncted tile modelled after an antique 050;Ground base uses reinforced concrete structure, main body steel knot Structure includes supporting steel frame and multiple steel pipes vertically;Vertical steel pipe one end along its length is connected with the supporting steel frame, another End is connected to reinforced concrete structure;Column modelled after an antique 100 is wrapped in the outside of all or part of steel pipe vertically along its length; And column 100 modelled after an antique is connected with reinforced concrete structure;Conjuncted tile modelled after an antique 050 is connected to the top of supporting steel frame;Disjunctor modelled after an antique Watt 050 and the material that uses of column modelled after an antique 100 include modified cement.
It is preferred that modified be set to sulphate aluminium cement.Sulphate aluminium cement is current material.
The material of Conjuncted tile modelled after an antique 050 includes sulphate aluminium cement, bluestone particle, iron oxide black and water;Aluminium sulfate water Mud, bluestone particle, iron oxide black and water form mixed slurry;Conjuncted tile modelled after an antique 050 compacting in mould is put into by mixed slurry and Into;Conjuncted tile modelled after an antique is the solid of sulphate aluminium cement product.
And the material of Conjuncted tile 050 modelled after an antique also includes defoamer and reduces agent;Defoamer and reduction agent are arranged at mixing slurry In material.
In addition, the building in the style of the ancients that the present embodiment is provided also includes that purlin three 090 and rafter hope integral piece 060;Purlin is consolidated for three 090 Surely it is connected to the one end of column modelled after an antique 100 away from ground base;Rafter hopes that integral piece 060 one end is arranged on purlin three 090;Separately One end is arranged on supporting steel frame;Rafter hopes that integral piece 060 is provided with multiple, and multiple rafters hope that integral piece 060 is arranged in order;It is modelled after an antique Conjuncted tile 050 is arranged at the top that rafter hopes integral piece 060.
Wherein, purlin three 090 is the main supporting member in Chinese ancient architecture, including purlin, backing plate, a long thick piece of timber shaped like a square pillar.Rafter hopes one Part 060 includes rafter, roof boarding, even flying-rafter, eaves, watt mouth etc..
Further, the building in the style of the ancients that the present embodiment is provided also includes wall modelled after an antique 130 and door modelled after an antique 120 and antique window 110;Straightened portion steel pipe is arranged inside wall modelled after an antique 130;The quantity of column modelled after an antique 100 is multiple;Part is adjacent modelled after an antique vertical Door modelled after an antique 120 or antique window 110 are provided between post 100.
Wherein, the local-style dwelling houses of building in the style of the ancients generally speaking, including Roof system, agent structure system 020 and Tai Ming 030.
In the local-style dwelling houses of building in the style of the ancients, Roof system 010 includes:Small bell row ridge 040, Conjuncted tile modelled after an antique 050, rafter hope one Body part 060, stick together first 070, rich seam plate 080 and purlin three 090 etc.;Agent structure system 020 includes antique window 110, door modelled after an antique 120 With wall modelled after an antique 130 etc..
It is ground base to be carried out by design requirement, typically using reinforced concrete structure to build a building in the style of the ancients local-style dwelling houses As ground base, the skeleton of main body steel construction is connected on reinforced concrete structure on ground base, then will be various Sample mounting structure overlap joint modelled after an antique is installed, and is wrapped in outside the skeleton of main body steel construction.
In addition, main body steel construction is the one kind in height of a house formula or truss-like with the connected mode of reinforced concrete structure.
Wherein, truss is made up of straight-bar general plane or space structure with triangular element.Under load effect, Truss member is primarily subjected to axial tension or pressure, so as to make full use of the intensity of material, when span is larger than reality abdomen Beam material-saving, mitigates deadweight and increase rigidity, therefore suitable for the load-carrying members and tall and slender structure compared with large span.
The height of a house is the method that Han nationality's traditional architecture determines roof curved surface curvature, and this building is used when roof beam structure stacking is increased Height of a house method calculates the slope of roof, makes the gradient on roof more up steeper, so as to be in concave curved surface, is beneficial under roof drainage and eaves Daylighting, is conducive to reducing roofing wind and snow load.
Main body steel construction has various with the specific connected mode of armored concrete, for example weld, bolt, riveting etc., preferably Ground, main body steel construction is welded with armored concrete.
Purlin is provided between adjacent column modelled after an antique 100 three 090, and baotou beam is provided between principal column and peripheral column Connection, and rafter is installed on purlin three 090 hopes that integral piece 060, purlin three 090 and rafter hope that integral piece 060 is provided with multiple, And hope that integral piece 060 installs Conjuncted tile modelled after an antique 050 in rafter, after assembling roof, positive ridge or ingot top 200 etc. can be added.In addition, Straightened portion steel pipe is arranged inside wall modelled after an antique 130;Door modelled after an antique 120 or imitative is provided between the column 100 modelled after an antique of part Ancient window 110.
Purlin three is provided with multiple, and baotou beam is interspersed to be arranged between purlin three.
Wherein, wall modelled after an antique 130 is set to self-heat conserving wall modelled after an antique, and can be using interior wall grouting exterior wall integrated brick modelled after an antique New-type way is made wall modelled after an antique 130, and the wall modelled after an antique 130 has the wall of combination with decorative surfaces, insulation and load-bearing integration.And The material of the Antique Imitation Tiles of wall, technique is built to be put into mould by mixed slurry with the material technology of Conjuncted tile modelled after an antique 050 and pressed System is formed.
The material of door modelled after an antique 120 and antique window 110 can be for various, such as:Bridge-cut-off aluminum, timber, fiberglass etc., preferably The material of ground, door modelled after an antique 120 and antique window 110 is bridge-cut-off aluminum.
Can increase insulation, waterproof, protective layer in addition, being hoped between integral piece 060 and Conjuncted tile modelled after an antique 050 in rafter.
The building in the style of the ancients that the present embodiment is provided includes:Ground base, main body steel construction, column modelled after an antique 100 and disjunctor modelled after an antique Watt 050;The material that Conjuncted tile modelled after an antique 050 and column modelled after an antique 100 are used includes modified cement, and Conjuncted tile modelled after an antique 050 and modelled after an antique Column 100 is belonging to prefabrication product, and form is true to nature, and with assembling and antique effect well, it is imitative that the present embodiment is provided Column modelled after an antique 100 and Conjuncted tile modelled after an antique 050 that ancient building is suppressed by using modified cement material, and most of structure modelled after an antique Part is factory's making, need to only assemble at the scene, convenient and swift;Component modelled after an antique is suppressed by mould and formed, with physical property Stabilization, safety do not fall off, and the characteristics of wind resistance is strong, solve the long construction period of presence of the prior art, and use the longevity The short technical problem of life so that the construction of building in the style of the ancients is more reasonable and utilization more extensive.
A kind of building in the style of the ancients preparation method that the present embodiment is provided, the method includes:
Step 100, the ground base that building in the style of the ancients is made using reinforced concrete structure;
Step 200, in ground base main body steel construction is assembled by design requirement, main body steel construction includes multiple steel vertically Pipe and supporting steel frame;
Step 300, column modelled after an antique 100 is made on the basis of reinforced concrete structure, and column modelled after an antique 100 is wrapped in main body The all or part of vertical steel pipe of steel construction;
Step 400, making wall 130 modelled after an antique, straightened portion steel pipe are arranged inside wall modelled after an antique 130;
Step 500, between the adjacent column modelled after an antique 100 in part make door modelled after an antique 120 or antique window 110;
Step 600, Conjuncted tile modelled after an antique 050 is set on the supporting steel frame of main body steel construction;
The mounting structure modelled after an antique being made for the cement slurry that is modified is added by design requirement, with reference to the wall modelled after an antique 130, it is made building in the style of the ancients;
Wherein, Conjuncted tile modelled after an antique 050 uses the clay work of modified water, Conjuncted tile modelled after an antique 050 to be made up of following raw materials:
The mould of Conjuncted tile 050 modelled after an antique is made by design requirement, by above-mentioned percent by weight by sulphate aluminium cement, green stone Particle stirs, and adds the cement mortar being configured to by the iron oxide black and water of above-mentioned percent by weight in advance, and compacting is de- Conjuncted tile modelled after an antique 050 is made after being conserved through the cycle after mould.
The specific manufacture craft of Conjuncted tile modelled after an antique 050 is, the first step:The control of raw material:Including (1) sulphate aluminium cement It is current material, and sulphate aluminium cement is most important raw material in mixed slurry, has significant impact to the intensity of product. (2) bluestone particle:Between mesh~40 mesh of particle diameter 20.(3) iron oxide black:Main Function feedwater mud dyeing, reaches product needed Color, appropriate adjustment can be done according to service condition.(4) defoamer:For eliminating the bubble in cement slurry. (5) agent is reduced:For adjusting slurry performance, increase mobility.(6) flyash:For adjusting product properties, increase mobility.
In addition, the formwork of mould:A formwork, No. two formworks and No. three formworks can be divided into, can be fixed according to use ratio The formwork of varying number processed, meets production needs.
Second step:Stirring slurry:(1) blower fan is opened before stirring, all personnel has worn anti-dust respirator and personal protection is used Product, equipment shakedown.(2) it is preferred that water temperature control is more than 18 DEG C.(3) sulphate aluminium cement, water, bluestone particle, froth breaking Agent, flyash and various additive meterings are accurate.(4) mixer requirement mixing effect is good, and various materials are well mixed, preferably Ground, rotating speed is with about 200 revs/min.(5) sequence of operation is stirred:Plus bluestone particle, coloring agent (stirring 2 minutes) → mud that adds water (are stirred Mix) → add water, water reducer (stirring 10-15 minute) → add defoamer → entrucking stand-by.Work is finished will clean dry inside and outside tank body Only, electric equipment is covered before rinsing, material is cleaned out around place, and instrument is piled up neatly, power-off of operating a switch.
3rd step:Pressing process:(1) operating personnel put on insulation water shoes, with good apron and mouth mask;Inspection equipment and mixing The viscosity of slurry, and start Weighing;Weighed by different tile-type meterings before suppressing Conjuncted tile modelled after an antique 050, wet feed weight ± 50 grams.(2) during cloth by the uniform cloth of mixed slurry putamina eminence;Pressure when dripping with scuppit will drip head wipe it is mixed Close slurry;Mould cloth cleaned, is wrung out, unfolded and be opened on putamina, slurry covered completely, it is ensured that the open and flat aptychus of cloth.(3) press After head is lifted, putamina is gently removed and is placed on platform, two hands are parallel to open release cloth, smoothly by Conjuncted tile modelled after an antique 050 It is put into watt unwheeling.
Wherein, Conjuncted tile modelled after an antique 050 being suppressed every time and suppressing 30 pieces, rinse a pressure head, every 5,000 pieces are pulled down pressure head Clear and coherent steam vent, it is ensured that pressure head draining gas sky is unimpeded;When rinsing pressure head and equipment, electric equipment is covered, will after finally completing Ground flushing is clean, and instrument is piled up neatly, power-off of operating a switch.
4th step:Maintenance releasing process:(1) after full watt of watt unwheeling code, gently car is shifted onto in the range of 2 meters (prevent from shattering) Solidification;Rest 2 as a child again by watt unwheeling shifted onto appointed place by compacting disjunctor modelled after an antique sequentially pile up, it is small every 2 When watering maintenance once.(2) demoulding (can be suitable according to temperature after the demoulding after the solidification that band drips 48 hours, other solidifications 24 hours When regulation).(3) demoulding is carried out in demoulding platform, and first light compression molding material putamina surrounding, then turns over and gently knock putamina one end, two hands Four fingers hold tiling, and Conjuncted tile modelled after an antique 050 is gently put down on table top.(4) a watt surrounding burr is struck off with scraper plate, founds code It is put into appointed place.(5) code good the lid straw screen or mat of Conjuncted tile modelled after an antique 050 or plastic cloth, twice, watering maintenance is or not watering sooner or later daily Less than 7 days.
The above system of following watt technological process, the Conjuncted tile modelled after an antique 050 produced all is either from color or quality Really up to the mark, can directly use, without painting again, greatly save the engineering time.Again will by design by other accessories modelled after an antique Ask and be fixedly mounted on main body steel construction, by technique hands such as junction staking, socket joint, welding, the bolts of all parts Duan Jinhang treatment, finally carries out overall colour painting modification, you can whole local-style dwelling houses ancient architecture is completed, so as to reach assembled type imitation antique building Purpose.
Using the method for the making Conjuncted tile 050 modelled after an antique of the present embodiment, i.e., make Conjuncted tile modelled after an antique 050 using modified water is clay Method, can be carried out in new building main body roof installation modification, it is also possible to existing structure roof is carried out modelled after an antique Transformation decoration, this kind of assembled has construction fast, and effect is good, free of contamination advantage, more promotes industry restructuring upgrading, tightly The great development of energy-conserving and environment-protective NPD projects is chased after, the various advantages of assembled architecture are spread far and wide.
In addition, being provided with hook-shaped reinforcing bar in step 100, on reinforced concrete structure, hook-shaped reinforcing bar is embedded in ground In basis.Step 600, Conjuncted tile modelled after an antique 050 is divided into polylith carries out molding shaping;In step 600, by disjunctor modelled after an antique described in polylith Watt 050 is hung or mud is connected in main body steel construction by steel.
Wherein, steel extension is a kind of technique of exterior wall finishing, is to do skeleton with angle steel or other metal, then using card Button, screw hang on skeleton material, are also dry-hang stone.Mud is made to represent traditional plastering.
The manufacture method of the building in the style of the ancients that this implementation is provided, method and step is simple, and the Conjuncted tile modelled after an antique 050 for manufacturing Physical dimension design science, overlap joint is reasonable, and with impermeable, rain-tight, tool texture is true, good endurance, and outward appearance, ratio with The consistent advantage of traditional tile.And because most assembling component modelled after an antique belongs to integrated property so that the construction cycle Short, form of construction work can be with flexible and changeable;The long construction period of the construction of building in the style of the ancients of the prior art is solved, and uses the longevity The short technical problem of life so that building in the style of the ancients can preferably be used and spread.
The sectional view of the layers of eaves octagonal pavilion of the building in the style of the ancients that Fig. 3 is provided for the present embodiment;Fig. 4 is imitating that the present embodiment is provided The overall structure diagram of the layers of eaves octagonal pavilion of ancient building;As shown in Figure 3, Figure 4, the layers of eaves eight of the building in the style of the ancients that this implementation is provided Angle booth includes:Conjuncted tile modelled after an antique 050, rafter hopes integral piece 060, the first steel column 150, the second steel column 160, floor tile modelled after an antique 170, seat stool 180th, treasured pushes up 200, hangs upside down lintel 210, close angle kiss 220, spend serratd edge 230, angle cloud 250, cover beast 260, ridge beast 270, the vertical and of beast 280 Hang down ridge 290 etc..The layers of eaves octagonal pavilion of the building in the style of the ancients that the present embodiment is provided builds the building in the style of the ancients provided using above-described embodiment Technique;First on the ground, vertical band 300, step and Tai Ming 030 are made respectively;Ground base is by armored concrete Structure is embedded in the concrete of the table top of platform bright 030 on the table top of platform bright 030 by hook-shaped reinforcing bar.
Wherein, the first steel column 150 is the steel column of a diameter of 300mm, and the second steel column 160 is the steel column of a diameter of 245mm.
As shown in figure 3, eight first steel columns 150 are respectively perpendicular being connected on the Ji Chu of ground.Then the room for assembling Frame supporter is integrally lifted, on eight first steel columns 150 after, be respectively fixedly connected with;Eight purlins three 090 respectively with eight The first steel column of root 150 is fixedly connected.Then eight second steel columns 160 are respectively perpendicular again and are connected on roof truss supporter, repeated Operation.
In addition, with producing wood purlin three 090, three troubles first 310 and angle clouds 250, main body steel knot is separately mounted to after being made On structure;With between the steel column of producing wood Chinese cabbage head, flower serratd edge 230, projecting lintel 210 below purlin three 090;With wood Material is made between bench, eight steel columns on the table top of platform bright 030.Again by the junction staking of all parts, Socket joint, overlap joint, gluing etc. carry out encapsulation process, then polish, clear up each position junction;Then by purlin three 090, trident Head, angle cloud 250, Chinese cabbage head, flower serratd edge 230, projecting lintel 210, bench and pedestal boulder 350 paint red respectively.Finally carry out Overall modification, you can complete overall building in the style of the ancients.
Eight faces of layers of eaves octagonal pavilion are divided into 16 pieces and are made, i.e., each face is divided into two pieces and is made, each face It is divided into peripheral portion and inner core, wherein, peripheral portion includes outer edge part, the ridge 290 that hangs down, the set beast 260 of angle booth tiling plate With angle cloud 250;The angle booth tiling plate in addition to outer edge part that inner core is folded by two vertical ridges 290.
In the building in the style of the ancients that above-described embodiment is provided, the ridge 290 that hangs down closes angle kiss 220 and can be integrally formed;Can also individually into Type.And, the accessory modelled after an antique of above-mentioned building in the style of the ancients is formed using the injection mould compacting of sulphate aluminium cement mixed slurry.Cause This, building in the style of the ancients can be molded by molding and be entirely capable of reaching effect true to nature, modelled after an antique.
In addition, the sectional view of the corner booth of the building in the style of the ancients that Fig. 5 is provided for the present embodiment;Fig. 6 is provided for the present embodiment The overall structure diagram of the corner booth of building in the style of the ancients;As shown in Figure 5, Figure 6, the corner booth of the building in the style of the ancients that the present embodiment is provided Including Conjuncted tile modelled after an antique 050, three the 090, second steel columns 160 of purlin, floor tile modelled after an antique 170, seat stool 180, precious top 200, flower serratd edge 230th, angle cloud 250, set beast 260, the trouble of band 300, three first 310 etc. of hanging down;The corner booth of the building in the style of the ancients that the present embodiment is provided builds same The layers of eaves octagonal pavilion building technology of the building in the style of the ancients that above-described embodiment is provided is similar to, and here is omitted.
The front view of the gallery of the building in the style of the ancients that Fig. 7 is provided for the present embodiment;The building in the style of the ancients that Fig. 8 is provided for the present embodiment Gallery side view;As shown in Figure 7, Figure 8, the gallery of the building in the style of the ancients that the present embodiment is provided includes Conjuncted tile modelled after an antique 050, rafter Hope integral piece 060, seat stool 180, projecting lintel 210, drape over one's shoulders water tip ridge 320, bargeboard 330, the 3rd steel column 340, pedestal boulder 350, Month beam 360, melon post 370, with beam a tree, used in making timber for boats 380.
Wherein, the 3rd steel column 340 is the steel column of a diameter of 160mm.
Four the 3rd steel columns 340 are respectively perpendicular and are connected on the Ji Chu of ground.Then it is the roof truss supporter for assembling is whole Body lifted, on four first steel columns 150 after, be respectively fixedly connected with;Four pedestal boulders 350 are respectively fitted over four the 3rd again On steel column 340.Gallery is provided with multiple, and multiple galleries are fixedly connected.
In addition, with producing wood purlin three 090, three troubles first 310 and angle clouds 250, main body steel knot is separately mounted to after being made On structure;With between the steel column of producing wood Chinese cabbage head, flower serratd edge 230, projecting lintel 210 below purlin three 090;With wood Material is made between bench, four steel columns on the table top of platform bright 030.Again by the junction staking of all parts, Socket joint, overlap joint, gluing etc. carry out encapsulation process, then polish, clear up each position junction;Then by purlin three 090, trident Head, angle cloud 250, Chinese cabbage head, flower serratd edge 230, projecting lintel 210, bench and pedestal boulder 350 paint red respectively.Finally carry out Overall modification, you can complete overall building in the style of the ancients.
The Conjuncted tile modelled after an antique that the building in the style of the ancients that the present embodiment is provided is suppressed by using sulphate aluminium cement material 050, and most of component modelled after an antique is factory's making, need to only assemble at the scene, it is convenient and swift;Component modelled after an antique is suppressed by mould Form, do not fallen off with stable physical property, safety, the characteristics of wind resistance is strong, solve applying for presence of the prior art The work cycle is long, and the short technical problem of service life so that the construction of building in the style of the ancients is more reasonable and utilization more extensive.
The front view of the decorated archway of the building in the style of the ancients that Fig. 9 is provided for the present embodiment;Figure 10 modelled after an antique builds for what the present embodiment was provided The side view of the decorated archway built;Such as Fig. 9, shown in Figure 10, the decorated archway of the building in the style of the ancients that the present embodiment is provided, including Conjuncted tile modelled after an antique 050th, rafter hopes that 410, sansan 420, sets of brackets on top of the columns 430, big frontal plate are shouted in integral piece 060, rich seam plate 080, wenshou 390, positive ridge 400, prestige day 440th, card 450, architrave 460, vertical post 470,480, decorated bracket 490 of hanging one's head, decorated bracket 500 of riding, clamping bar stone 510.
The front view of the festoon gate of the building in the style of the ancients that Figure 11 is provided for the present embodiment;Figure 12 for the present embodiment provide it is modelled after an antique The side view of the festoon gate of building;Such as Figure 11, shown in Figure 12, the decorated archway of the building in the style of the ancients that the present embodiment is provided, including small bell is arranged Ridge 040, Conjuncted tile modelled after an antique 050, rafter hope integral piece 060, rich seam plate 080, purlin three 090, the trouble of angle cloud 250, three first 310, just Ridge 400, card 450,480, decorated bracket 490 of hanging one's head, just kissing 520, Swallow Tail Fang 530, baotou beam 540.
The decorated archway and festoon gate of the building in the style of the ancients that the present embodiment is provided are the common buildings in building in the style of the ancients;And this The technique of the building in the style of the ancients that the construction of the decorated archway and festoon gate of the building in the style of the ancients that embodiment is provided is provided using above-described embodiment; The annexation and position relationship all same of each part, here is omitted.
The decorated archway of building in the style of the ancients and the component most of modelled after an antique of festoon gate that the present embodiment is provided are factory's making, pass through It is completed at the scene, it is convenient and swift, solve the long construction period of presence of the prior art, and the short technology of service life Problem so that the construction of building in the style of the ancients is more reasonable and utilization more extensive.
The assembled type imitation antique building that the present embodiment is provided has construction fast, and effect is good, free of contamination advantage, more promotes and produces Adjustment of agricultural stracture is upgraded, and clings to the great development of energy-conserving and environment-protective NPD projects on one's trail, spreads the various advantages of assembled architecture far and wide.
Finally it should be noted that:Various embodiments above is only used to illustrate the technical solution of the utility model, rather than it is limited System;Although being described in detail to the utility model with reference to foregoing embodiments, one of ordinary skill in the art should Understand:It can still modify to the technical scheme described in foregoing embodiments, or to which part or whole Technical characteristic carries out equivalent;And these modifications or replacement, the essence of appropriate technical solution is departed from this practicality newly The scope of each embodiment technical scheme of type.

Claims (10)

1. a kind of building in the style of the ancients, it is characterised in that including:Ground base, main body steel construction, column modelled after an antique and Conjuncted tile modelled after an antique;
The ground base uses reinforced concrete structure, and the main body steel construction includes supporting steel frame and multiple steel pipes vertically; Vertical steel pipe one end along its length is connected with the supporting steel frame, and the other end is connected to the armored concrete knot Structure;
The column modelled after an antique is wrapped in the outside of all or part of vertical steel pipe along its length;And the column modelled after an antique It is connected with the reinforced concrete structure;
The Conjuncted tile modelled after an antique is connected to the top of the supporting steel frame;
The material that the Conjuncted tile modelled after an antique and the column modelled after an antique are used includes modified cement.
2. building in the style of the ancients according to claim 1, it is characterised in that described Conjuncted tile modelled after an antique is modified cement products Solid.
3. building in the style of the ancients according to claim 1, it is characterised in that also including purlin three;
The purlin three is fixedly connected on the one end of the column modelled after an antique away from the ground base.
4. building in the style of the ancients according to claim 3, it is characterised in that also include:Baotou beam;
The purlin three is provided with multiple, and the baotou beam is interspersed to be arranged between the purlin three.
5. building in the style of the ancients according to claim 4, it is characterised in that also hope integral piece including rafter;
The rafter hopes that integral piece one end is arranged on the purlin three;The other end is arranged on the supporting steel frame;
The rafter hopes that integral piece is provided with multiple, and multiple rafters hope that integral piece is arranged in order;
The Conjuncted tile modelled after an antique is arranged at the top that the rafter hopes integral piece.
6. the building in the style of the ancients according to claim any one of 1-5, it is characterised in that also including wall modelled after an antique;
The part vertical steel pipe is arranged inside the wall modelled after an antique.
7. building in the style of the ancients according to claim 6, it is characterised in that also including door modelled after an antique and antique window;
The quantity of the column modelled after an antique is multiple;The door modelled after an antique or described is provided between the adjacent column modelled after an antique in part Antique window.
8. building in the style of the ancients according to claim 1, it is characterised in that the main body steel construction and the armored concrete knot The connected mode of structure is the one kind in height of a house formula or truss-like.
9. building in the style of the ancients according to claim 8, it is characterised in that be provided with the reinforced concrete structure hook-shaped Reinforcing bar, hook-shaped reinforcing bar is embedded in ground base.
10. building in the style of the ancients according to claim 1, it is characterised in that the Conjuncted tile modelled after an antique is divided into polylith carries out molding Shaping;
Conjuncted tile modelled after an antique described in polylith is hung by steel or mud is connected in the main body steel construction.
CN201621257995.0U 2016-11-23 2016-11-23 Archaistic building Active CN206189921U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621257995.0U CN206189921U (en) 2016-11-23 2016-11-23 Archaistic building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621257995.0U CN206189921U (en) 2016-11-23 2016-11-23 Archaistic building

Publications (1)

Publication Number Publication Date
CN206189921U true CN206189921U (en) 2017-05-24

Family

ID=58723639

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621257995.0U Active CN206189921U (en) 2016-11-23 2016-11-23 Archaistic building

Country Status (1)

Country Link
CN (1) CN206189921U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106382023A (en) * 2016-11-23 2017-02-08 北京聚星复合材料技术发展有限公司 Archaistic building and manufacturing method thereof
CN109025390A (en) * 2018-08-17 2018-12-18 苏州园林发展股份有限公司 A kind of roof truss primary structure member system
CN109779008A (en) * 2019-03-19 2019-05-21 浙江万峰装配式房屋工程有限公司 A kind of seismic crack steel house and its method of construction

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106382023A (en) * 2016-11-23 2017-02-08 北京聚星复合材料技术发展有限公司 Archaistic building and manufacturing method thereof
CN109025390A (en) * 2018-08-17 2018-12-18 苏州园林发展股份有限公司 A kind of roof truss primary structure member system
CN109779008A (en) * 2019-03-19 2019-05-21 浙江万峰装配式房屋工程有限公司 A kind of seismic crack steel house and its method of construction
CN109779008B (en) * 2019-03-19 2021-07-09 浙江长兴万峰钢结构科技股份有限公司 Anti-seismic anti-cracking steel structure house and construction method thereof

Similar Documents

Publication Publication Date Title
CN106382023B (en) Pseudo-classic architecture and its manufacturing method
CN101307629B (en) Fastener type self-decoration composite heat insulation high layer dwelling building module and its construction method
CN103470067B (en) Transformation and construction method used for facing bare concrete of existing building outer wall
CN101818527B (en) Assembled integral shear wall structure system and construction method thereof
CN201687102U (en) Assembled integral type shear wall structure system
CN101457546A (en) Novel energy-conserving emission reduction pseudo-classic architecture and construction method thereof
CN206189921U (en) Archaistic building
CN102535846A (en) One-step forming construction process for integrally pouring housing construction
CN100472015C (en) Light archaized architecture production method and product
CN105672664A (en) Integral heat insulation wallboard building system
CN110469138B (en) Traditional rammed earth building repairing method and structure
CN102747807A (en) Novel building wallboard, building wall body structure and manufacturing method thereof
CN101858143B (en) Mold pipe building construction technology
CN103806655A (en) construction method for glass brick wall
CN204774343U (en) Barricade adheres to close net of formula steelframe and moulds GRC artificial hillock at present
CN102220810B (en) Method for connecting wooden members with concrete members of eaves of antique buildings
CN207420088U (en) A kind of detachable combination cornice for facade rebuilding construction
CN107747378A (en) The body composite board processing method of Fast Installation heat insulation decorative load-bearing one
CN202017292U (en) Connecting structure for wooden element and concrete element of pseudo-classic building eave
CN101475344B (en) Building heat preserving exterior wall decorating tile
CN207063141U (en) A kind of thermal-insulating waterproof building structure
CN203412312U (en) Thermal-insulating integrated template wallboard construction building
CN202023317U (en) Cement base insulation waterproof sheet material with decorative cover layer
CN211229618U (en) Traditional rammed earth building repair structure
CN207812740U (en) One body composite board linear type wall of Fast Installation heat insulation decorative load-bearing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant