CN206174356U - Assembled ceramic tile wall surface and wall face mould piece - Google Patents

Assembled ceramic tile wall surface and wall face mould piece Download PDF

Info

Publication number
CN206174356U
CN206174356U CN201621252009.2U CN201621252009U CN206174356U CN 206174356 U CN206174356 U CN 206174356U CN 201621252009 U CN201621252009 U CN 201621252009U CN 206174356 U CN206174356 U CN 206174356U
Authority
CN
China
Prior art keywords
wall
metope
ceramic tile
main joist
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621252009.2U
Other languages
Chinese (zh)
Inventor
秦涛
朱燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
DONGYI RISHENG DECORATION CORP
Original Assignee
DONGYI RISHENG DECORATION CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by DONGYI RISHENG DECORATION CORP filed Critical DONGYI RISHENG DECORATION CORP
Priority to CN201621252009.2U priority Critical patent/CN206174356U/en
Application granted granted Critical
Publication of CN206174356U publication Critical patent/CN206174356U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Floor Finish (AREA)

Abstract

The utility model discloses an assembled ceramic tile wall surface and wall face mould piece. This ceramic tile wall surface includes: the wall body, install main joist on the wall body, and through with the connection of main joist joint is installed wall face mould piece on the wall body, wherein, wall face mould piece via cement pressure plate inner face installation bear fossil fragments with the joint connection of main joist is installed on the wall body. Through the utility model discloses an assembled ceramic tile wall surface and wall face mould piece can realize the fitment through reliable assembly methods, adoption dry construction's mode with the wall face mould piece of batch production production fast, shortens construction period, improves the efficiency of fitment, guarantees the quality level of wall, and the while reduces on -the -spot building rubbish and construction pollution.

Description

Assembled ceramic tile metope and metope module
Technical field
The utility model is related to building field, more particularly to a kind of assembled ceramic tile metope and metope module.
Background technology
Assembled finishing be a kind of component part by factorial praluction by reliable assembling mode, pressed by industrial worker Sighting target quasi-ordering uses the fitment process of dry construction.Assembled is fitted up because its construction period is short, pollution few, while can save About resource, lifting labor productivity and quality safety level, have obtained greatly developing for country in recent years.Interior assembling at present Formula decoration construction technology mainly have fast-assembling light partition wall, fast keel furred ceiling, modular fast-assembling warming ground, house integrated form to Four subdivisional works such as waterpipe, cement mortar paving or plaster application wet method are still used for common ceramic tile metope engineering Form of construction work.
Existing ceramic tile metope paving technology (such as wet construction such as cement mortar paving mode) is still present and much asks Topic.For example, relying on higher to construction operation workman professional quality, the temperature dependent that dries of metope (is such as dried slow when temperature is low Slowly, there is crack in temperature Gao Shiyi), long construction period, site operation is also easy to produce more building waste, causes job site dirty Dye etc..Cement is directly laid on wall by existing ceramic tile metope paving technology, the thickness of cement layer also cannot be accurately held Degree.Need integrally to fit up metope again when ceramic tile metope goes wrong, change relatively costly.
In view of this, the utility model proposes a kind of new assembled ceramic tile metope, it is used to solve above-mentioned at least one Problem.
Utility model content
The technical problems to be solved in the utility model there is provided a kind of assembled ceramic tile metope and metope module, using dry The fitment process of method construction, it is easy for installation, the finishing to wall is quickly realized with less labour, shorten the construction period, improve The efficiency of finishing.Meanwhile, metope is firm to be readily disassembled, it is ensured that the quality level of assembled ceramic tile metope.
According to one side of the present utility model, there is provided a kind of assembled ceramic tile metope, the assembled ceramic tile wall bread Include:Wall;Main joist on the wall;And be connected on the wall by with the main joist clamping Metope module;Wherein, the card of the bearing keel that the metope module is installed via cement pressure plate inner face and the main joist Connect in succession on the wall.
Thus, it is connected with the clamping of main joist by bearing keel and metope module is fixed on wall, can be quickly real Now fit up, substantially reduce the construction period of finishing, while reducing rubbish and the pollution of job site so that construction is more just Victory, improves decoration efficiency.
Preferably, the main joist is laterally or vertically arranged on the wall;The bearing keel is vertical or horizontal To the inner face installed in the cement pressure plate;And the bearing keel and the main joist are perpendicular to each other at card contact Clamping each other.
Thus, main joist perpendiculars to one another clamping with bearing keel so that metope module can be firmly secured on wall. Meanwhile, easily directly metope module can be unloaded when being necessary, and main joist is not changed, and is reduced secondary The cost of change.
Preferably, the main joist is spaced with identical with the bearing keel and laid, and each described metope module It is fixed on the wall via multiple card contacts.
Thus, it is possible to be further ensured that the stabilization fixation of whole metope module, it is ensured that the quality peace of assembled ceramic tile metope Full level.
Preferably, the main joist is arranged on the wall by expansion bolt, and the bearing keel is by certainly Tapping is arranged on the inner face.
Thus, it is possible to the screw and bolt of appropriate length or rugosity are selected according to actual conditions, by bearing keel and main dragon Bone stabilization is fixed, it is ensured that the quality level of assembled ceramic tile metope.
Preferably, the bearing keel and the main joist are lightgage steel joists.
Thus, from the steel material of high rigidity, it is ensured that the load-bearing scope of keel is larger, while more prolonged resistance to With.
According to other side of the present utility model, there is provided a kind of assembled ceramic tile wall face mould block, the ceramic tile wall bread Include:Inner face is in face of wall and the cement pressure plate of outside paving ceramic tile;Multiple ceramic tiles of the paving on the outside;And install Bearing keel on the inner face, the bearing keel is connected with the mutual clamping of main joist on the wall.
Preferably, the bearing keel perpendiculars to one another laying, and the clamping each other at card contact with the main joist.
Preferably, the main joist is spaced with identical with the bearing keel and laid, and each described metope module It is fixed on the wall via multiple card contacts.
Preferably, the installation interval of main joist, the installation interval of bearing keel, the thickness of metope module, size and porcelain Predefined according to the wall size for one or more in the size of brick.
Preferably, the gap width identical seam between ceramic tile is left between the metope module on the wall Gap, and jointing treatment is carried out to the gap between metope module using tile pointing agent.
Thus, jointing treatment is carried out to ceramic tile gap and metope module gap so that whole assembled ceramic tile metope is whole Body is smooth attractive in appearance, it is easy to arranges, clean.
By assembled ceramic tile metope of the present utility model and metope module, using the fitment process of dry construction, in advance Metope module is prepared, is installed rapidly with fastener after transporting to job site, the dress to wall can be quickly realized with less labour Repair, it is easy for installation, the construction period is substantially reduced, improve the efficiency of finishing.Meanwhile, metope is firm to be readily disassembled, it is ensured that dress Quality level with formula ceramic tile metope.
Brief description of the drawings
Disclosure illustrative embodiments are described in more detail by with reference to accompanying drawing, the disclosure above-mentioned and its Its purpose, feature and advantage will be apparent, wherein, in disclosure illustrative embodiments, identical reference number Typically represent same parts.
Fig. 1 shows the schematic diagram of the assembled ceramic tile metope according to the utility model one embodiment.
Fig. 2 shows the construction method schematic diagram of the assembled ceramic tile metope according to the utility model one embodiment.
Fig. 3 shows the sectional view of the assembled ceramic tile metope according to this clearly demarcated one embodiment.
Fig. 4 shows the main joist and bearing keel clamping schematic diagram according to the utility model one embodiment.
Fig. 5 shows the front view of the assembled ceramic tile metope according to the utility model one embodiment.
Specific embodiment
The following preferred embodiment that the disclosure is more fully described with reference to the accompanying drawings.Although showing the disclosure in accompanying drawing Preferred embodiment, however, it is to be appreciated that may be realized in various forms the disclosure without the embodiment party that should be illustrated here Formula is limited.Conversely, these embodiments are provided so that the disclosure is more thorough and complete, and can be by the disclosure Scope intactly conveys to those skilled in the art.
In recent years, people purchase house, the demand lived and worked in peace and contentment significantly increases, and have correspondingly driven interior decoration market Flourish.Used as a kind of common finishing mode, ceramic tile metope receives everybody welcome.Existing ceramic tile metope engineering is also It is, using cement mortar paving or plaster application, to rely on operating worker professional quality high, construction and take time and effort, while existing The problems such as wasting of resources, construction pollution.
Therefore, the utility model proposes a kind of new assembled ceramic tile metope scheme.Fig. 1 shows new according to this practicality The schematic diagram of the assembled ceramic tile metope of type one embodiment.
As shown in figure 1, assembled ceramic tile metope of the present utility model can include metope module 100, main joist 200 and wall Body 300.Wherein, the metope module 100 can include cement pressure plate 110, ceramic tile 120 and bearing keel 130.Metope module 100 are connected by main joist 200 with wall 300, and main joist 200 is arranged separately on wall 300, are assembled ceramic tile metopes Main force structure.The bearing keel 130 of metope module 100 is connected with the clamping of main joist 200 and is fixed on metope module 100 On wall 300, wall 300 is the wall that decoration design surface layer is tile decorative surface.
For main joist 200, according to keel layout viewing and bolt (for example, expansion bolt) can be passed through by main joist 200 Laterally or vertically it is arranged on wall 300.The arrangement of bolt can be by various implementations.In one embodiment, can be by Vertically arrangement is arranged on wall main joist 200, and the arranging rule of bolt can be for typically on the one end of main joist 200 distance ground First bolt is laid at the 50mm of face, follow-up to lay a bolt per spacing 600mm, last bolt is apart from main joist top 50mm.When main joist 200 is laterally arranged, it is also possible to reference to the arrangement mode of bolt in above-described embodiment.The installation of main joist 200 Mode not limited to this, it is also possible to take other manner that main joist 200 is fixed on wall 300, such as strong bond makes Obtain other heavy burdens that main joist 200 can be born in the weight even metope module 100 of the assembled ceramic tile metope.
For metope module 100, cement pressure plate 110 is that ceramic tile 120 carries basic unit, and cement pressure plate 110 can be with inner face In face of wall 300 and installation bearing keel 130, outside paving ceramic tile 120.Bearing keel 130 is metope module 100 and main joist Connection and force structure between 200, are arranged on cement pressure plate 110 according to keel layout viewing.Ceramic tile 120 be metope most Whole architectural surface.
Wherein, workman can be in plant produced cement pressure plate 110, it is to avoid mud watt is carried out in indoor range to be fitted up Work, reduces live rubbish and scene is polluted.And the thickness of cement pressure plate 100 in process of production, can be accurately held, The difficult control of cement layer thickness for avoiding traditional wall construction from causing, reduces the problem of the interior space.For the water of same size Mud pressure plare 110 can also be produced in batches, so can significantly shorten the construction period.In one embodiment, cement pressure plate 110 thickness typically can be 15mm.The cement pressure plate of 15mm can meet firm after the completion of whole metope module 100 Degree, and indoor too many space will not be taken.
Cement pressure plate 110 as metope module 100 carrying basic unit, can be by it in width and/or the size of height The size of metope module 100 is determined, the size can be according to concrete condition customized in practice.The chi of metope module 100 It is very little to have limited.In one embodiment, can be for installation and transport and the consideration of intensity, by metope module 100 Width dimensions be limited to maximum 1200mm, height degree size is limited to maximum 2800mm.Height dimension such as module should not surpass Cross the height of daily residential building.Meanwhile, the size of module is also unsuitable too small.It is too small to cause to need to install more for a face wall Individual metope module, the increase construction volume that the coordination between the connection and module between module and main joist all can be unnecessary, with Original intention of the present utility model is runed counter to.
Furthermore it is possible to according to module packet diagram in one or more ceramic tiles of the outside paving of cement pressure plate 110.It is selected Multiple ceramic tiles can have solid color or pattern, proper alignment is laid in metope module;Can also respectively have difference Picture, the mutual splicing composition complete picture of one width;There can also be irregular shape, be connected with each other paving in cement pressure The outside of power plate 110.In one embodiment, the picture of multiple ceramic tiles constitutes a width complete picture, it is necessary to according to complete group Metope module is grouped, is numbered, to avoid the confusion of metope module, it is ensured that the assembled ceramic tile metope after finishing is complete Picture.Preferably, jointing treatment equably paving ceramic tile and can be carried out using tile pointing agent using tile binding material, is made Ceramic tile wall surface levelling, solid.
Correspondingly, inner face (towards the one side of wall) that can be according to keel layout viewing in cement pressure plate 110 can be erected To or be transversely mounted bearing keel 130, it is fastened on wall 300 with the mutual clamping of main joist.Can be by screw Be arranged on bearing keel 130 on the inner face of cement pressure plate 110 by (for example, self-tapping screw), and the specification of self-tapping screw can foundation The growth of cement pressure plate thickness is selected.The master for keeping bearing keel 130 corresponding is should be noted in this installation process Keel 200 are perpendicular to one another, and the position of card contact mutually corresponds to.
Bearing keel 130 and the clamping each other at card contact perpendicular to each other of main joist 200, simply and easily by metope mould Block 100 is arranged on wall 300, without connecting accessory or welding, and is connected firmly.In one embodiment, can adopt Laterally laid with main joist, the mode that bearing keel is vertically laid, main joist is connected with bearing keel using plug-in.Another In individual embodiment, can vertically be laid using main joist, the mode that bearing keel is laterally laid, main joist is used with bearing keel Plug-in is connected.
Clamping connection can be accomplished in several ways.For example, being transversely mounted main joist vertically installs bearing keel, main dragon Bone has prominent structure at card contact, can realize main joist with the mutual clamping of the cavernous structure at the card contact of bearing keel It is connected with the clamping of bearing keel.In one embodiment, main joist can set one with the clamping position of bearing keel Or multiple has the pad of certain thickness and cavernous structure, when metope module is installed with the pad of main joist under, bearing keel Pad in upper mode, the cavernous structure of two keel Upper gaskets is connected by two ends rugosity inconsistent bolt, with protect Card main joist carries the weight of metope module.In another embodiment, can main joist clamping position set one or Multiple column structures perpendicular or parallel to main joist, it is perpendicular with column structure in the clamping position setting one of bearing keel The cavernous structure of matching, when metope module is installed, indoor top is pointed to the column structure of main joist, directly carries this The cavernous structure of keel is inserted in the column structure of main joist, realizes the clamping connection of keel.Keel clamping connection implementation is not It is required that.
According to keel layout viewing, main joist 200 can be spaced with identical with bearing keel 130 and be laid, and each wall Face mould block 100 is fixed on wall 300 via multiple card contacts, to ensure that metope module stability is fixed on wall 300.
For the material of keel, main joist and bearing keel can be steel keel.Steel material has high rigidity, weight Relatively light the advantages of, the load-bearing scope of keel can be made as big as possible, so that user is hanged in addition on assembled ceramic tile metope When hanging the weight of constant weight, keel can have certain amount of bearing.Workman can be surface-treated (for example to steel keel Spray epoxy etc. after electrogalvanizing, electrostatic powder spraying, phosphorating treatment), make it have not fugitive color, be unlikely to deform, it is moisture resistance, The advantages of high temperature resistant, extend the service life of keel.The production processing procedure of steel keel avoids generation from being unfavorable for health simultaneously Pernicious gas, allow the safer environmental protection of use of user.Preferably, lightgage steel joist can be used, keel weight in itself is reduced Amount, in this way, can also bear keel weight in itself while bolt is connected with wall, alleviates the load-bearing of wall.
In the installation process of main joist 200, the vertical of main joist 200 can also be adjusted by way of increasing pad Degree, flatness, to ensure the vertical smooth of assembled ceramic tile metope.In one embodiment, by main joist 200 vertically arranging Mode be arranged on wall on, can the one end of main joist 200 at ground and/or its other end top end increase pad, to the greatest extent Amount causes that main joist 200 is perpendicular to the ground, to ensure the vertical smooth of assembled ceramic tile metope.To the perpendicularity of main joist 200, put down The adjustment mode not limited to this of whole degree, it is also possible to realize otherwise.
Foregoing detailed description according to assembled ceramic tile metope of the present utility model, by main joist 200 and bearing keel Be arranged on metope module 100 on wall 300 by 130 clamping connection, can quickly realize the finishing to wall 300, installation side Just, the construction period is substantially reduced, the efficiency of finishing is improve.Meanwhile, metope is firm to be readily disassembled, it is ensured that assembled ceramic tile wall The quality level in face.Simultaneously, it is possible to reduce the bricklayer muddy water of job site is lived, live building waste and construction pollution are reduced.
The assembled ceramic tile metope can be realized by a kind of construction method of assembled ceramic tile metope.Fig. 2 shows root According to the construction method schematic diagram of the assembled ceramic tile metope of the utility model one embodiment.As shown in Fig. 2 in step S510 In, main joist installation steps are carried out, main joist is installed on wall 300.Main joist 200 can be installed according to keel layout viewing On wall 300, mounting means is same or similar with the description in Fig. 1, will not be repeated here.
In step S520, metope module preparation process is carried out, bearing keel is installed in the inner face of cement pressure plate 110, And in the outside paving multiple ceramic tile of cement pressure plate.Preparation method will not be repeated here referring to associated description in Fig. 1.
It is worth noting that, the order between step S510 and step S520 is not required, user can voluntarily select head First install main joist 200 carries out the preparation of metope module 100 again, and the preparation for still first carrying out metope module 100 carries out main dragon again The installation of bone 200.In one embodiment, the design and preparation of metope module 100 can be in advance carried out, metope module is being carried out On 100 same day installed, while completing the installation of main joist 200 and the installation of metope module 100, before this, user still may be used With in the indoor inhabitation, the daily life without influenceing user.
In step S530, metope module installation step is carried out, be connected with the clamping of main joist 200 via bearing keel 130 Metope module 100 is arranged on wall 300.
Construction method of the present utility model can use the module of prefabricated uniform sizes, and in practical set according to tool Body metope situation cuts to the carrying out for being for example located at corner.For example, width can be unified to prepare no more than 1200mm, height does not surpass 2800mm is crossed, and main joist and bearing keel interval are all the metope module of 600mm.
In other embodiments, it may be preferred to which the actual conditions of the specific metope constructed as needed, customization is needed to use Module and determine corresponding main joist installation position.For example, before being fitted up to interior, some beam workers can be carried out Make, for example, need to study the original wall decorated, structure, wall size and selected ceramic tile for wall The suitable finishing drawing (such as module packet diagram, metope module row brick figure and keel layout viewing) of the design such as specification, and based on upper Each item data and drawing is stated to be grouped metope module, number that (numbering is used to recognize the metope corresponding to wall diverse location Module), prepare, with ensure the metope module that is installed to after construction on original wall body structure mutually agree with original wall, Match somebody with somebody.Therefore, in a preferred embodiment, construction method of the present utility model can also include being pre-designed step, in the step In rapid, installation interval, the installation interval of bearing keel, the metope mould of main joist according to the wall size to be constructed, can be determined One or more in the size of the thickness, size and ceramic tile of block.It is, of course, also possible to specifically combine interior decoration style and The ceramic tile of size, selection suitable material and color.
After metope module 100 is installed, perpendicularity, the seam between flatness and ceramic tile of the ceramic tile metope after assembling can be checked Gap etc., left between the metope module 100 on wall 300 with ceramic tile gap width identical gap, can also now increase Jointing filling step, jointing treatment is carried out using tile pointing agent to the gap between metope module 100.So, each metope Module 100 it is relatively independent and be seamlessly connected, it is ensured that ceramic tile metope it is smooth, while it is seamless spliced cause to the clear of ceramic tile metope It is clean more convenient, when metope module 100 is changed, jointing agent can be simply wiped off, without influence metope module 100 itself.
So, it is possible to complete the preparation of metope module 100 in factory, and quickly complete installation at the construction field (site), reduce Live bricklayer muddy water is lived and significantly shortens the construction period of interior decoration while construction,
Reach and reduce simultaneously cement consumption, reduce live building waste and construction pollution.Meanwhile, in assembled ceramic tile metope Certain position need change when, the metope module 100 where can directly changing the position, without entering to whole metope Row is changed, and reduces the workload of change and the cost of change.
Also, assembled ceramic tile metope of the present utility model will not produce larger in manufacture and installation process to human body The material of infringement, people can continue to live on the day of finishing completion, it is not required that give more times to clear away interior Finishing pollution thing, makes resident trust inhabitation.
After technique effect of the present utility model is realized, the technical solution of the utility model can also be extended.Example Such as, in dry environments, cement pressure plate of the present utility model can be using materials, Blockboard phase such as core-board, OSB plates Than in the more light cleaning of cement pressure plate, operation is more simple, can also reduce the input of workmen.For example, in ceramic tile rule When lattice are larger, ceramic tile bond can work as material using polyurethane adhesive, to ensure that the larger ceramic tile of specification can be firmly bonded.This The technical scheme of utility model can also have various implementations, and this is not particularly limited.
Assembled ceramic tile metope of the present utility model is described below in conjunction with an embodiment.
Fig. 3 is the schematic diagram of the sectional view of the assembled ceramic tile metope of the embodiment of the utility model one.As shown in figure 3, should Assembled ceramic tile wall face includes metope module 100, main joist 200 and wall 300, and metope module 100 includes cement pressure plate 110th, ceramic tile 120 and bearing keel 130.Wherein, the ceramic tile 120 of the outside paving decoration of cement pressure plate 110, inner face faces wall Body 300 and bearing keel 130 is vertically installed by self-tapping screw.Main joist 200 is transversely mounted on wall 300 by expansion bolt On, bearing keel 130 is perpendicular to one another with main joist 200 and is vertically connected with main joist 200, can use side as shown in Figure 4 Formula clamping is connected, to ensure the firm stable of assembled ceramic tile metope.Although for clear signal clamping principle in clamping in figure Place leaves gap, but it is understood that, main joist and bearing keel can be than more closely carrying out clamping shown in Fig. 4.
Fig. 5 shows the schematic diagram of the front view of the assembled ceramic tile metope of the present embodiment, it can be seen that the porcelain Brick wall includes metope module 1 and metope module 2, there is the ceramic tile of multiple proper alignments in each module respectively, and module it Between gap carry out jointing treatment using tile pointing agent, whole ceramic tile wall surface levelling is vertical.
Above describe in detail according to assembled ceramic tile wall face mould block of the present utility model and its apply by reference to accompanying drawing Work method.By assembled metope of the present utility model and its construction method, shift to an earlier date according to tile laying figure in cement in factory Sub-module is pasted on pressure plare, is installed rapidly with fastener after transporting to scene, can significantly shorten the construction week of interior decoration Phase, improve decoration efficiency.Ceramic tile metope firm stable is readily disassembled, it is ensured that the quality level of metope.Simultaneously, it is to avoid applying The bricklayer muddy water at work scene is lived, and reduces cement consumption, building waste and construction pollution.
It is described above each embodiment of the present utility model, described above is exemplary, and non-exclusive, and And it is also not necessarily limited to disclosed each embodiment.In the case of without departing from the scope and spirit of illustrated each embodiment, for Many modifications and changes will be apparent from for those skilled in the art.The choosing of term used herein Select, it is intended to best explain principle, practical application or the improvement to the technology in market of each embodiment, or lead this technology Other those of ordinary skill in domain are understood that each embodiment disclosed herein.

Claims (10)

1. a kind of assembled ceramic tile metope, it is characterised in that including:
Wall;
Main joist on the wall;And
By being connected the metope module on the wall with the main joist clamping;
Wherein, the metope module is connected peace via the bearing keel that cement pressure plate inner face is installed with the clamping of the main joist On the wall.
2. ceramic tile metope as claimed in claim 1, it is characterised in that
The main joist is laterally or vertically arranged on the wall;
The bearing keel is vertical or is transversely mounted on the inner face of the cement pressure plate;And
The bearing keel and the main joist clamping each other at card contact perpendicular to each other.
3. ceramic tile metope as claimed in claim 2, it is characterised in that
The main joist is spaced with identical with the bearing keel and laid, and each described metope module is via multiple clampings Point is fixed on the wall.
4. ceramic tile metope as claimed in claim 1, it is characterised in that
The main joist is arranged on the wall by expansion bolt, and the bearing keel is arranged on by self-tapping screw On the inner face.
5. the ceramic tile metope as any one of claim 1-4, it is characterised in that
The bearing keel is lightgage steel joist with the main joist.
6. a kind of assembled ceramic tile wall face mould block, it is characterised in that including:
Inner face is in face of wall and the cement pressure plate of outside paving ceramic tile;
Multiple ceramic tiles of the paving on the outside;And
Bearing keel on the inner face, the bearing keel and the mutual clamping of main joist being arranged on the wall Connection.
7. metope module as claimed in claim 6, it is characterised in that
The bearing keel perpendiculars to one another laying, and the clamping each other at card contact with the main joist.
8. metope module as claimed in claim 7, it is characterised in that
The main joist is spaced with identical with the bearing keel and laid, and each described metope module is via multiple clampings Point is fixed on the wall.
9. metope module as claimed in claim 6, it is characterised in that the installation interval of main joist, the clipping room of bearing keel Predefined according to the wall size every one or more in, the size of the thickness of metope module, size and ceramic tile.
10. metope module as claimed in claim 6, it is characterised in that the metope module on the wall it Between leave the gap width identical gap between ceramic tile, and the gap between metope module is entered using tile pointing agent Row jointing is processed.
CN201621252009.2U 2016-11-16 2016-11-16 Assembled ceramic tile wall surface and wall face mould piece Active CN206174356U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621252009.2U CN206174356U (en) 2016-11-16 2016-11-16 Assembled ceramic tile wall surface and wall face mould piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621252009.2U CN206174356U (en) 2016-11-16 2016-11-16 Assembled ceramic tile wall surface and wall face mould piece

Publications (1)

Publication Number Publication Date
CN206174356U true CN206174356U (en) 2017-05-17

Family

ID=58685803

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621252009.2U Active CN206174356U (en) 2016-11-16 2016-11-16 Assembled ceramic tile wall surface and wall face mould piece

Country Status (1)

Country Link
CN (1) CN206174356U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760295A (en) * 2016-11-16 2017-05-31 东易日盛家居装饰集团股份有限公司 Assembled ceramic tile metope and its construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760295A (en) * 2016-11-16 2017-05-31 东易日盛家居装饰集团股份有限公司 Assembled ceramic tile metope and its construction method

Similar Documents

Publication Publication Date Title
CN106760295A (en) Assembled ceramic tile metope and its construction method
US7204060B2 (en) System for manufacturing structures of cementitious materials
CN208792663U (en) A kind of room finishing system
CN109898774A (en) A kind of assembled ceramic tile metope and its construction method
CN101831963A (en) Novel multipurpose composite insulation board and construction method and processing device thereof
CN201502164U (en) Tool for paving floor tile
CN106049766B (en) The combination eaves system and its construction method of large span steel structure and sets of brackets on top of the columns timber structure
CN106836718A (en) Precast floor system and its assembly method
CN101476361B (en) Inner partition plate system and its construction method
CN106760146A (en) A kind of assembled porcelain earthenware brick for building and the construction process using the porcelain earthenware brick
CN206512966U (en) Precast floor system
CN210658664U (en) Assembled energy-saving new residential structure
CN206174356U (en) Assembled ceramic tile wall surface and wall face mould piece
CN110387954A (en) A kind of assembled energy-saving New Residence structure and preparation method thereof
CN102839805A (en) Dry-hanging resin plate wall surface decoration system and construction method thereof
CN102535807B (en) Modular wall tile pre-bonding structure and construction method thereof
CN208792669U (en) Concealed frame type wall brick system in a kind of assembled room
CN204475767U (en) Wall decoration building materials hang special part
CN105421656A (en) External wall board installation structure of embedded type steel structure assembled house
CN116464282A (en) Construction method of special-shaped metal composite roof
CN206554360U (en) A kind of assembled porcelain earthenware brick for building and the house built using the porcelain earthenware brick
CN205171752U (en) Prefabricated light steel partition wall and mounting structure thereof
CN210659110U (en) Assembly type overhead ground installation system of ceramic tile concrete composite board
CN210947543U (en) Assembled height-adjustable floor heating paving system
CN210659109U (en) Ground veneer leveling supporting device and ground veneer mounting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant