CN206173956U - A cast -in -place dado structure for manual hole digging pile - Google Patents

A cast -in -place dado structure for manual hole digging pile Download PDF

Info

Publication number
CN206173956U
CN206173956U CN201621210929.8U CN201621210929U CN206173956U CN 206173956 U CN206173956 U CN 206173956U CN 201621210929 U CN201621210929 U CN 201621210929U CN 206173956 U CN206173956 U CN 206173956U
Authority
CN
China
Prior art keywords
retaining wall
linkage section
place
dado
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621210929.8U
Other languages
Chinese (zh)
Inventor
孙淼军
单治钢
汪明元
徐学勇
狄圣杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Electric Power Construction Group Aviation Port Construction Co Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201621210929.8U priority Critical patent/CN206173956U/en
Application granted granted Critical
Publication of CN206173956U publication Critical patent/CN206173956U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses at first provide a cast -in -place dado structure for manual hole digging pile, dado on fore shaft roof beam on the soil body horizontal plane of drill way and stake lateral wall, dado include drill way linkage segment dado and downthehole section dado. The utility model discloses an on -the -spot binding reinforcement cage and concreting method form manual hole digging pile's dado system, can overcome the difficulty of mountain area transportation and the prefabricated dado of hoist and mount, can adjust dado system size in a flexible way according to the pile body size, and dado intensity and stability are higher than prefabricated dado.

Description

A kind of cast-in-place dado structure for artificial digging pile
Technical field
This utility model belongs to Geotechnical Engineering pile foundation engineering design and construction field, and in particular to one kind is used for excavated by manual work The cast-in-place dado structure of hole stake.
Background technology
Artificial digging pile is referred to and is excavated to form circular or square stake holes by manpower, to be laid and pour into a mould coagulation after steel reinforcement cage Soil and formed pile body.Application of the artificial digging pile in China's foundation engineering, slope project is quite varied.Currently for artificial Soil body stability evaluation methodology in caisson does not form corresponding codes and standards, often empirically determined construction skill during construction The minimum requirements of art, the unstability accident of the stake holes soil body happens occasionally.Artificial digging pile hole wall unstability can not only cause the weight of stake holes New excavation, the construction again of retaining wall, make construction costs increase and construction delay, and to the personal safety of workmen in stake holes Formed and greatly threatened.
Man-made digging pile mould-pipe is the unique engineering support structure of pile peripheral earth, the stability pair of retaining wall before filling concrete Soil body stability has vital effect.Currently for prefabricated reinforced concrete, steel retaining wall design and construction technique compared with For maturation, for above-mentioned material retaining wall patent application also show it is all in relevant report.However, above-mentioned material is to transporting and lifting Requirement it is higher, traffic of mountain area and construction equipment shortcoming under conditions of be difficult to complete the construction of retaining wall, in such area often Using the cast-in-situ steel reinforced concrete retaining wall relatively low to traffic and equipment requirements.Because dado thickness is relatively thin compared to stake footpath, and receive Retaining wall is easier to tensile failure when acting on to flowing concrete pressure, and pouring quality is relatively difficult to ensure card.As fully visible, cast-in-place retaining wall Design and construct the urgently design of reasonable standard and construction method, and there is no at present and be specifically designed for manually digging hole cast in place reinforced bar and mix The Patents of solidifying soil retaining wall.
Utility model content
For the deficiency of prior art, this utility model aims to provide a kind of cast-in-place retaining wall for artificial digging pile and ties Structure, construction method skimble-scamble problem more random to solve existing cast-in-situ steel reinforced concrete bracing work, while can be effective Improve retaining wall stability and reduce construction cost.
For achieving the above object, this utility model is adopted the following technical scheme that:A kind of cast-in-place shield for artificial digging pile Wall construction, it includes the retaining wall on the fore shaft beam in the soil mass water plane of aperture and stake side wall, and retaining wall includes aperture linkage section retaining wall With hole inner segment retaining wall.
Further, the fore shaft beam, aperture linkage section retaining wall and hole inner segment retaining wall material are armored concrete, adopt Reinforcing bar is Ι level reinforcing bars, and casting concrete is C25 concrete.
Further, the fore shaft soffit is closely agreed with soil mass water plane, and upper surface is parallel with bottom surface, fore shaft deck-molding Degree, aperture linkage section retaining wall width are identical with hole inner segment retaining wall upper end width, on fore shaft beam upper surface and aperture linkage section retaining wall Surface flushes.
Further, the vertical section of the aperture linkage section retaining wall is shaped as rectangle, the vertical section shape of hole inner segment retaining wall Shape is wide at the top and narrow at the bottom trapezoidal, and medial wall and the stake holes side wall of retaining wall closely agree with, and vertical with fore shaft beam upper and lower surface.
Further, the fore shaft beam and aperture linkage section retaining wall Pouring concrete at the same time, fore shaft beam steel bar stress and hole The vertical long reinforcing bar of mouth linkage section is connected by crotch.
Further, the reinforcing bar in the fore shaft beam includes cableway and steel bar stress, and the steel bar stress is bent Rectangular, the frame reinforced bar adopts building tied silk colligation at each turning position of steel bar stress, and adopts at turning position Spot welding is fixed, and is linked using oblique pull reinforcing bar at the level up and down of the steel bar stress, and the vertical reinforcement of aperture linkage section is by curved Link the upper surface in steel bar stress.
Further, bar splicing adopts building tied silk colligation in the retaining wall, in the orthogonal both sides retaining wall of pile body Vertical long reinforcing bar lacing wire is set, and is mutually linked between different plates, vertical reinforcement short lacing wire is set in the other both sides retaining wall of pile body, And separate between different plates, it is 100mm that thickness of concrete cover is arranged inside and outside pile body reinforcing bar.
Further, multiple tracks aperture linkage section retaining wall stirrup is provided with along its short transverse in the aperture linkage section retaining wall, Per pass aperture linkage section retaining wall stirrup is bent into rectangle, and place two ends of remaining silent bend again and mutually link, aperture linkage section shield Armlet muscle is connected with the vertical long reinforcing bar of aperture linkage section and vertical bar dowel using building tied silk colligation.
Further, multiple tracks hole inner segment retaining wall stirrup is provided with along its short transverse in the hole inner segment retaining wall, in per pass hole Section retaining wall stirrup is bent into rectangle, and place two ends of remaining silent bend again and mutually link, hole inner segment retaining wall stirrup with hole inner segment Vertical long reinforcing bar and vertical bar dowel are using the colligation connection of building tied silk.
The beneficial effects of the utility model are:This utility model is using live banding steel cage and casting concrete method shape Into the retaining wall system of artificial digging pile, the difficulty of mountain area transport and hoisting prefabricated retaining wall can be overcome, can be flexible according to pile body size Adjustment retaining wall system dimension, and retaining wall strength and stability is higher than prefabricated bulkhead.
Description of the drawings
The cast-in-place dado structure elevation for artificial digging pile that Fig. 1 is related to for this utility model.
Fig. 2 is the A-A ' profiles of Fig. 1.
The fore shaft beam corner structure of the cast-in-place dado structure for artificial digging pile that Fig. 3 is related to for this utility model is detailed Figure.
Fig. 4 is the Ι-Ι ' profiles of Fig. 3.
Wherein:1- fore shaft beams, 2- apertures linkage section retaining wall, 3- holes inner segment retaining wall, the 4- soil bodys, 101- fore shaft beams erect steel Muscle, 102- fore shaft beam steel bar stresses, 103- fore shaft beam oblique pull reinforcing bars, 104- fore shaft beam concrete, 105- fore shaft beam bent-up bars, 201- apertures linkage section retaining wall vertical long reinforcing bar, the vertical bar dowel of 202- apertures linkage section retaining wall, 203- apertures linkage section retaining wall Stirrup, 204- apertures linkage section breast wall concrete, the vertical long reinforcing bar of 301- holes inner segment retaining wall, the vertical short steel of 302- holes inner segment retaining wall Muscle, 303- holes inner segment retaining wall stirrup, 304- holes inner segment breast wall concrete.
Specific embodiment
It is wide 1.1m, as a example by the artificial digging pile of long 1.6m, with reference to accompanying drawing this reality is set forth in by horizontal cross-section below With new particular content.
Retaining wall system includes the retaining wall on fore shaft beam 1 and stake side wall on the horizontal plane of the aperture soil body 4, and retaining wall connects including aperture Connect section retaining wall 2 and hole inner segment retaining wall 3.
The fore shaft beam 1, aperture linkage section retaining wall 2 and the material of hole inner segment retaining wall 3 are armored concrete, equal using reinforcing bar For Ι level reinforcing bars, casting concrete is C25 concrete.
The bottom surface of the fore shaft beam 1 is closely agreed with the horizontal plane of the soil body 4, and upper surface is parallel with bottom surface, the height of fore shaft beam 1, hole Mouthful linkage section 3 width of retaining wall are identical with hole inner segment 4 upper end widths of retaining wall, the upper surface of fore shaft beam 1 and the upper table of aperture linkage section retaining wall 3 Face flushes.
The vertical section of the aperture linkage section retaining wall 2 is shaped as rectangle, and the vertical section of hole inner segment retaining wall 3 is shaped as width Under it is narrow trapezoidal, medial wall and the stake holes side wall of retaining wall closely agree with, and vertical with the upper and lower surface of fore shaft beam 1.
The fore shaft beam 1 connects with the Pouring concrete at the same time of aperture linkage section retaining wall 2, fore shaft beam steel bar stress 102 and aperture Connect the vertical long reinforcing bar 201 of section to connect by crotch.
Reinforcing bar includes cableway 101 and steel bar stress 102 in the fore shaft beam 1, and the steel bar stress 102 is bent into Rectangle, the frame reinforced bar 101 adopts building tied silk colligation at each turning position of steel bar stress 102, and at turning position Fixed using spot welding, linked using oblique pull reinforcing bar 103 at the level up and down of the steel bar stress 102, aperture linkage section it is vertical Reinforcing bar links the upper surface in steel bar stress 102 by hook.Bar splicing is using building tied silk colligation, pile body in the retaining wall Vertical long reinforcing bar 201 is set in orthogonal both sides retaining wall, and is mutually linked between different plates, in the other both sides retaining wall of pile body Vertical bar dowel 202 is set, and it is separate between different plates, concrete cover, thickness are set inside and outside pile body reinforcing bar For 100mm.
Multiple tracks aperture linkage section retaining wall stirrup 203, per pass hole are provided with along its short transverse in the aperture linkage section retaining wall 2 Mouth linkage section retaining wall stirrup 203 is bent into rectangle, and place two ends of remaining silent bend again and mutually link, aperture linkage section retaining wall hoop Muscle 203 is connected with the vertical long reinforcing bar 201 of aperture linkage section and vertical bar dowel 202 using building tied silk colligation.
Multiple tracks hole inner segment retaining wall stirrup, per pass hole inner segment retaining wall hoop are provided with the hole inner segment retaining wall 3 along its short transverse Muscle is bent into rectangle, and place two ends of remaining silent bend again and mutually link, hole inner segment retaining wall stirrup with the vertical long steel of hole inner segment Muscle and vertical bar dowel are using the colligation connection of building tied silk.
The above-mentioned cast-in-place dado structure for artificial digging pile, implementation step is as follows:
(1), the coordinate points at pile body center are determined according to design requirement, by the soil in the range of stake planar dimension and its periphery 1m The surface evening of body 4.Fore shaft beam steel bar stress 102 is bent using angle bender rectangular and curved again at place two ends of remaining silent Folding is mutually linked, and is arranged along aperture with uniform distances;Using building tied silk by fore shaft beam cableway 101 and fore shaft beam stress steel , in four corner point colligations, in the mutual junction in turning using welding, corner is using lock for fore shaft beam cableway 101 for muscle 102 Mouth beam bent-up bar 105 is connected by colligation with fore shaft beam steel bar stress 102, cableway 101;Using 2 fore shaft beam oblique pulls Reinforcing bar 103 links fore shaft beam steel bar stress about 102 at level.
(2), by the design pile body size hand excavation soil body 4 to subsurface 1m, by the vertical long reinforcing bar of aperture linkage section retaining wall 201st, the two ends of vertical bar dowel 202 bend up, and link with fore shaft beam steel bar stress 102 in upper end;By aperture linkage section retaining wall stirrup 203 bendings are rectangular, and remaining silent, place two ends bend mutually link again, aperture linkage section retaining wall stirrup 203 and vertical long reinforcing bar 201st, vertical bar dowel 202 is using the colligation connection of building tied silk.
(3), in fore shaft beam steel bar stress 102 times, high 25mm cushion blocks are set, erect steel die plate with steel pipe support, use C25 Concrete is poured into closely knit, and fore shaft beam concrete 104 is poured simultaneously with aperture linkage section breast wall concrete 204, concrete curing 7 Form removal after it.
(4), continue after the completion of concrete curing to excavate 1.2m downwards, by the vertical long reinforcing bar 301 of hole inner segment retaining wall, vertical short The two ends of reinforcing bar 302 bend up, and link with the vertical long reinforcing bar 201 of aperture linkage section retaining wall, vertical bar dowel 202 respectively in upper end;Will Hole inner segment retaining wall stirrup 303 bends rectangular, bends again at place two ends of remaining silent and mutually links, hole inner segment retaining wall stirrup 303 with Vertical long reinforcing bar 301, vertical bar dowel 302 are using the colligation connection of building tied silk.
(5), erect steel template and with hole inner segment breast wall concrete 304 is poured to closely knit, concrete curing is torn open after 7 days Template.Often excavating 1.2m carries out a retaining wall, and specific implementation is same(4)、(5)It is described, until being excavated to a bottom elevation, bottom Less than pressing actual grade assembling reinforcement and casting concrete at 1.2m.
This utility model forms the retaining wall system of artificial digging pile using live banding steel cage and casting concrete method, The difficulty of mountain area transport and hoisting prefabricated retaining wall can be overcome, retaining wall system dimension, and retaining wall can be adjusted flexibly according to pile body size Strength and stability is higher than prefabricated bulkhead.
It is illustrated above only to pass through a kind of base of the cast-in-place dado structure for artificial digging pile of graphic extension this utility model Present principles, rather than by this utility model be only limitted to shown in and described concrete structure and the scope of application within, therefore it is all it is all can The corresponding modification that can be utilized and equivalent, belong to the apllied the scope of the claims of this utility model.

Claims (9)

1. a kind of cast-in-place dado structure for artificial digging pile, it is characterised in that it includes the fore shaft in the soil mass water plane of aperture Retaining wall on beam and stake side wall, retaining wall includes aperture linkage section retaining wall and hole inner segment retaining wall.
2. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 1, it is characterised in that fore shaft beam, aperture Linkage section retaining wall and hole inner segment retaining wall material are armored concrete.
3. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 1, it is characterised in that fore shaft soffit Closely agree with soil mass water plane, upper surface is parallel with bottom surface, fore shaft depth of beam, aperture linkage section retaining wall width and hole inner segment shield Wall upper end width is identical, fore shaft beam upper surface and aperture linkage section retaining wall upper surface flush.
4. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 1, it is characterised in that aperture linkage section The vertical section of retaining wall is shaped as rectangle, and the vertical section of hole inner segment retaining wall is shaped as trapezoidal, the medial wall of retaining wall wide at the top and narrow at the bottom Closely agree with stake holes side wall, and it is vertical with fore shaft beam upper and lower surface.
5. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 2, it is characterised in that fore shaft beam and hole The vertical long reinforcing bar of mouth linkage section retaining wall Pouring concrete at the same time, fore shaft beam steel bar stress and aperture linkage section is connected by crotch Connect.
6. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 5, it is characterised in that the steel of fore shaft beam Muscle includes cableway and steel bar stress, and the steel bar stress is bent into rectangle, and the cableway is tied up using building tied silk Prick at each turning position of steel bar stress, and fixed using spot welding at turning position, at the level up and down of the steel bar stress Linked using oblique pull reinforcing bar, the vertical reinforcement of aperture linkage section links the upper surface in steel bar stress by hook.
7. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 5, it is characterised in that reinforcing bar in retaining wall Overlap joint adopts building tied silk colligation, and vertical long reinforcing bar is arranged in the orthogonal both sides retaining wall of pile body, and mutual between different plates Link, setting vertical reinforcement is short and separate between different plates in the other both sides retaining wall of pile body, sets inside and outside pile body reinforcing bar Put concrete cover.
8. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 7, it is characterised in that the aperture connects Connect in section retaining wall and be provided with multiple tracks aperture linkage section retaining wall stirrup along its short transverse, per pass aperture linkage section retaining wall stirrup is bent Rectangular, place two ends of remaining silent bend again and mutually link, aperture linkage section retaining wall stirrup with the vertical long steel of aperture linkage section Muscle and vertical bar dowel are using the colligation connection of building tied silk.
9. a kind of cast-in-place dado structure for artificial digging pile as claimed in claim 7, it is characterised in that the hole inner segment Multiple tracks hole inner segment retaining wall stirrup is provided with along its short transverse in retaining wall, per pass hole inner segment retaining wall stirrup is bent into rectangle, remains silent Place two ends bend again and mutually link, and hole inner segment retaining wall stirrup is adopted with the vertical long reinforcing bar of hole inner segment and vertical bar dowel to be built Build tied silk colligation connection.
CN201621210929.8U 2016-11-10 2016-11-10 A cast -in -place dado structure for manual hole digging pile Active CN206173956U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621210929.8U CN206173956U (en) 2016-11-10 2016-11-10 A cast -in -place dado structure for manual hole digging pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621210929.8U CN206173956U (en) 2016-11-10 2016-11-10 A cast -in -place dado structure for manual hole digging pile

Publications (1)

Publication Number Publication Date
CN206173956U true CN206173956U (en) 2017-05-17

Family

ID=58684245

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621210929.8U Active CN206173956U (en) 2016-11-10 2016-11-10 A cast -in -place dado structure for manual hole digging pile

Country Status (1)

Country Link
CN (1) CN206173956U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400799A (en) * 2016-11-10 2017-02-15 中国电建集团华东勘测设计研究院有限公司 Cast-in-situ dado structure for manually excavated pile and construction method
CN110241817A (en) * 2019-06-28 2019-09-17 重庆渝高科技产业(集团)股份有限公司 A kind of impaired after-construction method of the friction pile stake holes of emergency repair engineering

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106400799A (en) * 2016-11-10 2017-02-15 中国电建集团华东勘测设计研究院有限公司 Cast-in-situ dado structure for manually excavated pile and construction method
CN106400799B (en) * 2016-11-10 2019-06-18 中国电建集团华东勘测设计研究院有限公司 A kind of cast-in-place dado structure and construction method for artificial digging pile
CN110241817A (en) * 2019-06-28 2019-09-17 重庆渝高科技产业(集团)股份有限公司 A kind of impaired after-construction method of the friction pile stake holes of emergency repair engineering

Similar Documents

Publication Publication Date Title
CN106400799B (en) A kind of cast-in-place dado structure and construction method for artificial digging pile
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN101787701B (en) Construction method for supporting pine pile in elevator shaft foundation pit
CN104532754B (en) A kind of prestressed concrete box girder end-blocking template construction method
CN201943086U (en) Underground building wall body
CN206173956U (en) A cast -in -place dado structure for manual hole digging pile
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN106436732A (en) Reinforcing method and reinforcing structure for replacing strip foundations by raft foundations
CN108301425A (en) Prefabricated quick mounting type lattice girder system and its construction method
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN209339171U (en) A kind of transmission line of electricity assembled sheet pile composite foundation
CN111305182A (en) Soft foundation reinforcement construction method
CN106545071A (en) Inspection shaft, roof drain and cement concrete pavement one-time cast-forming construction method
CN211690389U (en) Inter-pile retaining plate structure for adjacent anti-slide piles
CN109137986A (en) Urban road inspection shaft walling crib green promotes reinforced construction method
CN105464128B (en) Prestress anchorage cable assembled pile plate wall protection construction method
CN106930307A (en) The foundation beam prefabricated board and its assembly construction method of a kind of replacement brick fetal membrane
CN212176547U (en) Building floor bathroom falls board construction template device in building
CN208685617U (en) A kind of foundation underpinning system of old brick foundation building
CN106120690A (en) A kind of inverter box flattens platform and preparation method thereof
CN207143993U (en) Steel Wall for subway station shield hole side
CN206956738U (en) A kind of super-sized foundation pit subregion adds inner supporting structure after excavating
CN206736789U (en) Ready-package reusable edible railway protective fence
CN217580128U (en) Supporting side mold structure and manual hole digging pile wall supporting mold
CN215948247U (en) Pile foundation structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180423

Address after: No. 82, Hudong Road, Gulou District, Fuzhou, Fujian Province

Patentee after: China Electric Power Construction Group aviation Port Construction Co., Ltd.

Address before: 310014 Hangzhou city in the lower reaches of the city of Zhejiang Wang Road, No. 22

Patentee before: Co., Ltd of East China Investigation and Design Institute of electricity Jian group of China

TR01 Transfer of patent right