CN206095201U - Subway station main part structural support system construction process monitoring system - Google Patents
Subway station main part structural support system construction process monitoring system Download PDFInfo
- Publication number
- CN206095201U CN206095201U CN201621057980.XU CN201621057980U CN206095201U CN 206095201 U CN206095201 U CN 206095201U CN 201621057980 U CN201621057980 U CN 201621057980U CN 206095201 U CN206095201 U CN 206095201U
- Authority
- CN
- China
- Prior art keywords
- monitoring system
- input
- computer
- subway station
- outfan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Testing Or Calibration Of Command Recording Devices (AREA)
Abstract
The utility model provides a subway station main part structural support system construction process monitoring system relates to the intelligent monitoring field. Subway station main part structural support system construction process monitoring system, including strain monitoring system, support deformation monitoring system and on -the -spot monitoring system, the strain monitoring system includes a plurality of strain sensor, support deformation monitoring system includes a plurality of total powerstations, the output of total powerstation passes through the shielded wire and is connected with the input of computer, on -the -spot monitoring system includes a plurality of cameras, the output of camera passes through the shielded wire and is connected with the input of computer, the computer is connected with RAM memory, MRAM memory, database and data analysis module, the utility model discloses a strain monitoring system, support deformation monitoring system and on -the -spot monitoring system carry out real time monitoring to atress, the deformation condition and the job site of construction among the forming process to make corresponding adjustment, guarantee the security and the shaping accuracy of construction of work progress.
Description
Technical field
This utility model is related to intellectual monitoring field, and in particular to a kind of main structure of subway station mounting system was constructed
Journey monitoring system.
Background technology
In the work progress of Practical Project, as made by template, design theory is not mature enough, part when setting up
Construction technical staff is often too dependent on traditional construction experience, does not have enough attention to construction environment and construction featuress
Deng, be so difficult to hold support system working condition.The especially more special system of those structures, if these are special
The stress and deformation of structure can not be grasped in time, be difficult to take the key position of structure effectively adjustment to arrange
Apply.
Subway work scale is big, have after cycle length and structural mechanical property in work progress and structure formation significance difference away from,
Thus the lot of essential factors in taking into full account work progress and being monitored to work progress is very important.
Utility model content
(1) technical problem for solving
For the deficiencies in the prior art, this utility model was constructed there is provided a kind of main structure of subway station mounting system
Journey monitoring system, the stress and deformation for solving special construction can not be unable to monitor in real time by grasp, job site in time
Problem.
(2) technical scheme
To realize object above, this utility model is achieved by the following technical programs:
A kind of main structure of subway station mounting system work progress monitoring system, including the change of strain monitoring system, support
Shape monitoring system and site monitoring system, the strain monitoring system include multiple strain transducers, the strain transducer
Outfan is connected with the input of signal processor by data acquisition controller, the outfan and signal of the signal processor
The input connection of transducer, the outfan of the signal adapter are connected with the input of computer by shielding line, described
Frame DEFORMATION MONITORING SYSTEM includes multiple total powerstations, and the outfan of the total powerstation is connected with the input of computer by shielding line,
The site monitoring system includes multiple photographic head, and the outfan of the photographic head is connected by the input of shielding line and computer
Connect, the computer is connected with RAM memory, mram memory, data base and data analysis module.
The strain transducer is specially vibrating string type sensor.
The total powerstation is specially TOCON OS101 total powerstations.
The photographic head is specially 360 ° of fish-eye cameras.
The outfan of the computer is connected with the input of printer.
(3) beneficial effect
This utility model embodiment provides a kind of main structure of subway station mounting system work progress monitoring system.Tool
Standby following beneficial effect:1st, by strain monitoring system in multiple strain sensings and deformation of timbering monitoring system in it is multiple complete
Instrument of standing carries out monitor in real time to the component of job site, makes the stress of component in work progress comparatively safe steady all in one
State, it is ensured that completion of works rear part be not in than larger stress, while can grasp in time the stress of structure, strain
Situation, it is ensured that component does not have too big deformation in work progress, it is ensured that structure reaches the effect of expected shaping and prevents construction
During there is collapse phenomenon;
2nd, by site monitoring system in multiple photographic head monitor in real time carried out to job site ensure job site
Safety, while emergency case can be understood in time, is conducive to managing job site;
3rd, seven big analysis methods in data analysis module:Affinity diagram method, associated diagram method, System Diagram, matrix diagram method,
The data for monitoring preferably can be analyzed by PDPC methods, arrow diagram method and factor analysis;
4th, the data for monitoring are stored, compared and is inquired about using RAM memory, mram memory and data base.
Description of the drawings
In order to be illustrated more clearly that this utility model embodiment or technical scheme of the prior art, below will be to embodiment
Or accompanying drawing to be used is briefly described needed for description of the prior art, it should be apparent that, drawings in the following description are only
It is some embodiments of the present utility model, for those of ordinary skill in the art, in the premise for not paying creative work
Under, can be with according to these other accompanying drawings of accompanying drawings acquisition.
Fig. 1 this utility model theory diagrams.
Strain monitoring system 1, strain transducer 2, data acquisition controller 3, signal processor 4, signal adapter 5, screen
Cover line 6, computer 7, deformation of timbering monitoring system 8, total powerstation 9, site monitoring system 10, photographic head 11, RAM memory 12,
Mram memory 13, data base 14, data analysis module 15, printer 16
Specific embodiment
It is to make purpose, technical scheme and the advantage of this utility model embodiment clearer, new below in conjunction with this practicality
Accompanying drawing in type embodiment, is clearly and completely described to the technical scheme in this utility model embodiment, it is clear that retouched
The embodiment stated is a part of embodiment of this utility model, rather than the embodiment of whole.Based on the enforcement in this utility model
Example, the every other embodiment obtained under the premise of creative work is not made by those of ordinary skill in the art are belonged to
The scope of this utility model protection.
A kind of main structure of subway station mounting system work progress monitoring system, including the change of strain monitoring system 1, support
Shape monitoring system 8 and site monitoring system 10, the strain monitoring system 1 include multiple strain transducers 2, the strain sensing
The outfan of device 2 is connected with the input of signal processor 4 by data acquisition controller 3, the output of the signal processor 4
End is connected with the input of signal adapter 5, and the outfan of the signal adapter 5 is by shielding line 6 and the input of computer 7
Connection, the deformation of timbering monitoring system 8 include multiple total powerstations 9, and the outfan of the total powerstation 9 is by shielding line 6 and electricity
The input connection of brain 7, the site monitoring system 10 include multiple photographic head 11, and the outfan of the photographic head 11 is by screen
The input for covering line 6 with computer 7 is connected, and the computer 7 is divided with RAM memory 12, mram memory 13, data base 14 and data
Analysis module 15 connects, and the strain transducer 2 is specially vibrating string type sensor, and it is complete that the total powerstation 9 is specially TOCON OS101
Stand instrument, the photographic head 11 is specially 360 ° of fish-eye cameras, the outfan of the computer 7 is connected with the input of printer 16
Connect.
Operation principle:It is many in multiple strain sensings 2 and deformation of timbering monitoring system 8 in using strain monitoring system 1
Individual total powerstation 9 carries out real-time monitoring to the component of job site, makes the stress of component in work progress all in a relative peace
Complete smoothly state, it is ensured that completion of works rear part is not in than larger stress, it is ensured that component is without too in work progress
Big deformation, it is ensured that structure reaches the effect of expected shaping and collapse phenomenon occurs in preventing work progress, by existing
Multiple photographic head 11 in the monitoring system 10 of field carry out monitor in real time to job site, it is ensured that the safety of job site, data
Seven big analysis methods in analysis module 15:Affinity diagram method, associated diagram method, System Diagram, matrix diagram method, PDPC methods, Arrow Diagram
The data for monitoring preferably can be analyzed by solution and factor analysis, and be printed by printer 16, profit
The data for monitoring are stored, compared and inquired about with RAM memory 12, mram memory 13 and data base 14.
Above example only to illustrate the technical solution of the utility model, rather than a limitation;Although with reference to aforementioned reality
Apply example to be described in detail this utility model, it will be understood by those within the art that:Which still can be to front
State the technical scheme described in each embodiment to modify, or equivalent is carried out to which part technical characteristic;And these
Modification is replaced, and does not make the essence of appropriate technical solution depart from the spirit and model of each embodiment technical scheme of this utility model
Enclose.
Claims (5)
1. a kind of main structure of subway station mounting system work progress monitoring system, including strain monitoring system (1), support change
Shape monitoring system (8) and site monitoring system (10), it is characterised in that:The strain monitoring system (1) is passed including multiple strains
Sensor (2), the outfan of the strain transducer (2) is by data acquisition controller (3) and the input of signal processor (4)
Connection, the outfan of the signal processor (4) are connected with the input of signal adapter (5), the signal adapter (5)
Outfan is connected with the input of computer (7) by shielding line (6), and the deformation of timbering monitoring system (8) is including multiple whole stations
Instrument (9), the outfan of the total powerstation (9) are connected with the input of computer (7) by shielding line (6), the field monitoring system
System (10) includes multiple photographic head (11), and the outfan of the photographic head (11) is by shielding line (6) and the input of computer (7)
Connection, the computer (7) is with RAM memory (12), mram memory (13), data base (14) and data analysis module (15) even
Connect.
2. main structure of subway station mounting system work progress monitoring system as claimed in claim 1, it is characterised in that institute
State strain transducer (2) and be specially vibrating string type sensor.
3. main structure of subway station mounting system work progress monitoring system as claimed in claim 1, it is characterised in that institute
State total powerstation (9) and be specially TOCON OS101 total powerstations.
4. main structure of subway station mounting system work progress monitoring system as claimed in claim 1, it is characterised in that institute
State photographic head (11) and be specially 360 ° of fish-eye cameras.
5. main structure of subway station mounting system work progress monitoring system as claimed in claim 1, it is characterised in that institute
The outfan for stating computer (7) is connected with the input of printer (16).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621057980.XU CN206095201U (en) | 2016-09-14 | 2016-09-14 | Subway station main part structural support system construction process monitoring system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621057980.XU CN206095201U (en) | 2016-09-14 | 2016-09-14 | Subway station main part structural support system construction process monitoring system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206095201U true CN206095201U (en) | 2017-04-12 |
Family
ID=58476875
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621057980.XU Active CN206095201U (en) | 2016-09-14 | 2016-09-14 | Subway station main part structural support system construction process monitoring system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206095201U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106370154A (en) * | 2016-09-14 | 2017-02-01 | 安徽省建筑科学研究设计院 | Subway station main body structure support system construction process monitoring system |
-
2016
- 2016-09-14 CN CN201621057980.XU patent/CN206095201U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106370154A (en) * | 2016-09-14 | 2017-02-01 | 安徽省建筑科学研究设计院 | Subway station main body structure support system construction process monitoring system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105869066B (en) | The system and method for grid switching operation based on Digital Image Processing identification | |
CN106227977A (en) | A kind of method of steel structure net rack hydraulic pressure lift time-varying finite element analysis based on BIM | |
CN104008465A (en) | Switching operation ticket safety execution system | |
CN206095201U (en) | Subway station main part structural support system construction process monitoring system | |
CN207068067U (en) | A kind of more people of integrated WiFi probes check card attendance recorder automatically simultaneously | |
CN103196373A (en) | Automatic detection method of battery positive-negative electrode lug terminal length | |
CN208903300U (en) | A kind of construction risk automatic monitoring system based on BIM technology | |
CN203882342U (en) | Back brake operation order safe execution system | |
CN205049450U (en) | Dust monitored control system suitable for mill workshop | |
CN207964779U (en) | A kind of electric power tunnel based on tunnel ceiling track is automatic to make an inspection tour and monitors system | |
CN106683219A (en) | Power equipment indicating label and power equipment inspecting device | |
CN203164745U (en) | Building engineering safety construction informatization monitoring system | |
CN205861127U (en) | A kind of big data effluent flow rate monitoring pipeline | |
CN108226402A (en) | A kind of electric power tunnel based on tunnel ceiling track is maked an inspection tour automatically and monitoring system | |
CN106370154A (en) | Subway station main body structure support system construction process monitoring system | |
CN205302374U (en) | Enterprise safe production's 3D training system | |
CN206399436U (en) | A kind of engineering template verticality measuring tool | |
CN206181056U (en) | WIFI module test data management system based on high in clouds | |
CN108756962A (en) | A kind of hydraulic support monitoring method and system based on MVC design pattern | |
CN205049162U (en) | System for monitoring and record digitalizer table data | |
CN101211170A (en) | FPGA based automatic safe monitoring system for tower crane | |
CN203908531U (en) | Photovoltaic calendering glass on-line automatic thickness measuring apparatus | |
CN113095461A (en) | Pull-up counter based on machine vision | |
CN205405622U (en) | Personnel management attendance machine | |
CN102981073B (en) | Portable fault detector for electronic information system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |