CN206091259U - Adjustable steel configuration operation hanging flower basket - Google Patents

Adjustable steel configuration operation hanging flower basket Download PDF

Info

Publication number
CN206091259U
CN206091259U CN201621101231.2U CN201621101231U CN206091259U CN 206091259 U CN206091259 U CN 206091259U CN 201621101231 U CN201621101231 U CN 201621101231U CN 206091259 U CN206091259 U CN 206091259U
Authority
CN
China
Prior art keywords
supporting steel
steel plate
bolt hole
plate
hanging basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621101231.2U
Other languages
Chinese (zh)
Inventor
王希河
胡朝兵
董玉坤
朱井学
赵科森
王东宛
翟文明
唐太
朱贺龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Original Assignee
First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd filed Critical First Construction Co Ltd of China Construction Eighth Engineering Division Co Ltd
Priority to CN201621101231.2U priority Critical patent/CN206091259U/en
Application granted granted Critical
Publication of CN206091259U publication Critical patent/CN206091259U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to an adjustable steel configuration operation hanging flower basket, including operation hanging flower basket main part, operation hanging flower basket main part includes the side lever of hanging flower basket and vertical setting, and one side of hanging flower basket is located to the side lever, be equipped with a first supporting steel plate on the top of side lever, be equipped with a second supporting steel plate in the place ahead of first supporting steel plate, be equipped with two rows of parallel arrangement's first bolt hole and second bolt hole on first supporting steel plate, be equipped with two rows of parallel arrangement's third bolt hole and fourth bolt hole on the second supporting steel plate, first bolt hole and third bolt hole looks parallel and level, second bolt hole and fourth bolt hole looks parallel and level, first supporting steel plate and second supporting steel plate pass through the bolt and link to each other, at the vertical baffle that is equipped with of the left end of second supporting steel plate. The utility model discloses can adjust the length of couple, make a string basket be connected with the elevating system of different models, the risk has been avoidd to the expense of having saved.

Description

A kind of adjustable steel construction operates hanging basket
Technical field
This utility model is related to a kind of high-altitude constructing device, and more particularly to a kind of adjustable steel construction operates hanging basket.
Background technology
During engineering construction, there is substantial amounts of high-altitude safety check operation, existing frequently-used method will be applied with hanging basket Workman person and instrument take to needs the height constructed to be constructed, so carry out operation not only save time, saving of labor, and be work Cheng Fang saves substantial amounts of expense, also makes the safety of workmen obtain effective guarantee.But the existing mechanical hanging basket for using, Its complex structure, generally uses hook and whole hanging basket is hung on the girder of elevating mechanism, it is impossible to entered according to the width of girder steel Row is adjusted.Which results in when the width of girder steel is less, hanging basket farther out, makes workmen's operation inconvenience and exists apart from girder steel Larger danger;When the width of girder steel is larger, then hanging basket cannot be used, the hanging basket for needing welding bigger.This is made to hanging basket With causing inconvenience, and cause certain waste.
The content of the invention
The technical problems to be solved in the utility model is to provide a kind of adjustable steel construction behaviour of adjustable hook length Make hanging basket.
In order to solve above-mentioned technical problem, the technical solution adopted in the utility model is:
A kind of adjustable steel construction operates hanging basket, including operation basket body, described operation basket body to include hanging Basket and the side lever being vertically arranged, side lever is located at the side of hanging basket;One first supporting steel is provided with the upper horizontal of described side lever Plate, is provided with one second supporting steel plate in the front horizontal of the first supporting steel plate;It is provided with the first described supporting steel plate up and down The first bolt hole and the second bolt hole that two rows be arranged in parallel, are provided with the second described supporting steel plate that two rows are parallel to be set The 3rd bolt hole put and the 4th bolt hole;The first described bolt hole and the 3rd bolt hole flush, the second described bolt Tetra- bolt hole flushes of Kong Yu;First supporting steel plate and the second supporting steel plate are connected by bolt;In the second supporting steel plate Left end is vertically provided with a baffle plate.
Above-described adjustable steel construction operates hanging basket, the second described bolt hole and the 4th bolt hole to be strip Shape through hole;The length direction of the second described bolt hole is identical with the length direction of the first supporting steel plate, the 4th described bolt The length direction in hole is identical with the length direction of the second supporting steel plate.
Preferably, the front side horizontal in the first described supporting steel plate is provided with one and sets along the length direction of the first supporting steel plate The first level plate put, the length of first level plate are identical with the length of the first supporting steel plate;In the second described supporting steel plate Rear side level be provided with one along the second supporting steel plate length direction and the second horizontal plate of setting is engaged with first level plate, The length of the second horizontal plate is identical with the length of the second supporting steel plate, and the second described horizontal plate is under first level plate Side.
Preferably, the length direction along first level plate on the downside of described first level plate is provided with some first Limited block;Length direction along the second horizontal plate on the upper side of the second described horizontal plate is provided with some and the first limited block It is engaged the second limited block that clamping is connected.
Preferably, the first described limited block and the second limited block are in dentation.
This utility model adopts said structure, with advantages below:
The length linked up with can be adjusted, enable Hanging Basket to be connected with the elevating mechanism of different model, save Expense, has evaded risk.
Description of the drawings
Below in conjunction with the accompanying drawings this utility model is further described.
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the front view of embodiment 1 in Fig. 1;
Fig. 3 is the close-up schematic view in A portions in Fig. 2;
Fig. 4 is B-B direction cross section structure diagram in Fig. 3;
Fig. 5 is the front view of embodiment 2;
Fig. 6 is the close-up schematic view in C portions in Fig. 5;
Fig. 7 is D-D in Fig. 6 to cross section structure diagram;
Fig. 8 is the close-up schematic view in E portions in Fig. 7;
Fig. 9 be in Fig. 8 F-F to cross section structure diagram.
In figure, 1, operation basket body, 2, side lever, the 3, first supporting steel plate, the 4, second supporting steel plate, the 5, first bolt Hole, the 6, second bolt hole, the 7, the 3rd bolt hole, the 8, the 4th bolt hole, 9, bolt, 10, baffle plate, 11, first level plate, 12, Two horizontal plates, the 13, first limited block, the 14, second limited block.
Specific embodiment
Clearly to illustrate the technical characterstic of this programme, below by specific embodiment, and its accompanying drawing is combined, to this reality It is described in detail with new.
Embodiment 1:
As shown in Fig. 1-Fig. 4, the adjustable steel construction operation hanging basket includes operating basket body 1, described operation Basket body 1 includes hanging basket and the side lever 2 being vertically arranged, and side lever 2 is located at the side of hanging basket;In the top water of described side lever 2 It is flat to be provided with one first supporting steel plate 3, one second supporting steel plate 4 is provided with the front horizontal of the first supporting steel plate 3;Described One supporting steel plate 3 is provided with the first bolt hole 5 and the second bolt hole 6 being set in two parallel rows up and down, in the second described support Steel plate 4 is provided with the 3rd bolt hole 7 and the 4th bolt hole 8 being set in two parallel rows up and down;The first described bolt hole 5 and the 3rd 7 flush of bolt hole, the second described bolt hole 6 and 8 flush of the 4th bolt hole;First supporting steel plate 3 and the second supporting steel Plate 4 is connected by bolt 9;A baffle plate 10 is provided with vertically in the left end of the second supporting steel plate 4.
Above-described adjustable steel construction operation hanging basket, the second described bolt hole 6 and the 4th bolt hole 8 are Strip through hole;The length direction of the second described bolt hole 6 is identical with the length direction of the first supporting steel plate 3, and described The length direction of four bolts hole 8 is identical with the length direction of the second supporting steel plate 4.
The use process of the present embodiment is as follows:
When the installation of hanging basket is carried out, the size of hook needed for first determining, further according to the size for needing to use to second The position of support steel plate 4 is adjusted, it is determined that after good position, with first bolt of the bolt 9 on the first supporting steel plate 3 The 3rd bolt hole 7 on hole 5 and the second supporting steel plate 4, then the second bolt with a bolt 9 on the first supporting steel plate 3 Bolt 9 is fixed by the 4th bolt hole 8 on hole 6 and the second supporting steel plate 4 with nut, be this completes to linking up with length Preliminary regulation;Hanging basket is positioned over to be needed behind position to be mounted, further according to the size of installation site, using the second bolt hole 6 It is the characteristic of strip through hole with the 4th bolt hole 8, its length is finely adjusted, after regulating, nut is tightened, is completed hanging basket The installation of the length adjustment and hanging basket of hook.
Embodiment 2:
As shown in Fig. 5-Fig. 9, the adjustable steel construction operation hanging basket includes operating basket body 1, described operation Basket body 1 includes hanging basket and the side lever 2 being vertically arranged, and side lever 2 is located at the side of hanging basket;In the top water of described side lever 2 It is flat to be provided with one first supporting steel plate 3, one second supporting steel plate 4 is provided with the dead ahead level of the first supporting steel plate 3;Described First supporting steel plate 3 is provided with the first bolt hole 5 and the second bolt hole 6 being set in two parallel rows up and down, at described second Support steel plate 4 is provided with the 3rd bolt hole 7 and the 4th bolt hole 8 being set in two parallel rows up and down;The first described bolt hole 5 and Three bolts hole, 7 flush, the second described bolt hole 6 and 8 flush of the 4th bolt hole;First supporting steel plate 3 and second is supported Steel plate 4 is connected by bolt 9;A baffle plate 10 is provided with vertically in the left end of the second supporting steel plate 4.
It is long that above-described adjustable steel construction operates hanging basket, the second described bolt hole 6 and the 4th bolt hole 8 Strip through-hole;The length direction of the second described bolt hole 6 is identical with the length direction of the first supporting steel plate 3, and the described the 4th The length direction of bolt hole 8 is identical with the length direction of the second supporting steel plate 4.
Preferably, the front side horizontal in the first described supporting steel plate 3 be provided with one along the first supporting steel plate 3 length direction The first level plate 11 of setting, the length of first level plate 11 are identical with the length of the first supporting steel plate 3;At described second The rear side level of support steel plate 4 be provided with one along the second supporting steel plate 4 length direction and be engaged setting with first level plate 11 Second horizontal plate 12, the length of the second horizontal plate 12 are identical with the length of the second supporting steel plate 4, and the second described horizontal plate 12 sets In the lower section of first level plate 11.
Preferably, the length direction along first level plate 11 on the downside of described first level plate 11 is provided with some First limited block 13;Length direction along the second horizontal plate 12 on the upper side of the second described horizontal plate 12 be provided with it is some with First limited block 13 is engaged the second limited block 14 that clamping is connected.
Preferably, the first described limited block 13 and the second limited block 14 are in dentation.
The use process of the present embodiment is as follows:
When the installation of hanging basket is carried out, the size of hook needed for first determining, further according to the size for needing to use to second The position of support steel plate 4 is adjusted, it is determined that after good position, with first bolt of the bolt 9 on the first supporting steel plate 3 The 3rd bolt hole 7 on hole 5 and the second supporting steel plate 4, then the second bolt with a bolt 9 on the first supporting steel plate 3 Bolt 9 is fixed by the 4th bolt hole 8 on hole 6 and the second supporting steel plate 4 with nut, be this completes to linking up with length Preliminary regulation;Hanging basket is positioned over to be needed behind position to be mounted, further according to the size of installation site, using the second bolt hole 6 It is the characteristic of strip through hole with the 4th bolt hole 8, its length is finely adjusted;After regulating, make on the first supporting steel plate 3 The first level plate 11 of setting is abutted with the second horizontal plate 12 arranged on the second supporting steel plate 4, is made located at first level plate 11 First limited block 13 of the dentation of lower section and 14 clamping of the second limited block of the dentation above the second horizontal plate 12, thus The movement and deformation of the first supporting steel plate 3 and the second supporting steel plate 4 in horizontal and vertical both direction can further be prevented;Twist Tight nut, completes the installation of the length adjustment and hanging basket of hanging basket hook.
The above, only this utility model preferably specific embodiment, but protection domain of the present utility model is not Be confined to this, any those familiar with the art in the technical scope that this utility model is disclosed, according to this practicality New technical scheme and its inventive concept equivalent or change in addition, should all cover protection domain of the present utility model it It is interior.This utility model does not describe part in detail, is the known technology of those skilled in the art of the present technique.

Claims (5)

1. a kind of adjustable steel construction operates hanging basket, including operation basket body, described operation basket body to include hanging basket With the side lever being vertically arranged, side lever is located at the side of hanging basket, it is characterised in that be provided with one the in the upper horizontal of described side lever One supporting steel plate, is provided with one second supporting steel plate in the front horizontal of the first supporting steel plate;On the first described supporting steel plate The first bolt hole and the second bolt hole being set in two parallel rows up and down is provided with, and upper and lower two is provided with the second described supporting steel plate The 3rd bolt hole and the 4th bolt hole that row be arranged in parallel;The first described bolt hole and the 3rd bolt hole flush, it is described Second bolt hole and the 4th bolt hole flush;First supporting steel plate and the second supporting steel plate are connected by bolt;At second The left end of support steel plate is vertically provided with a baffle plate.
2. adjustable steel construction according to claim 1 operates hanging basket, it is characterised in that the second described bolt hole and 4th bolt hole is strip through hole;The length direction of the second described bolt hole and the length direction phase of the first supporting steel plate Together, the length direction of the 4th described bolt hole is identical with the length direction of the second supporting steel plate.
3. the adjustable steel construction according to any one in claim 1 or 2 operates hanging basket, it is characterised in that in institute The front side horizontal of the first supporting steel plate stated be provided with one along the first supporting steel plate length direction arrange first level plate, first The length of horizontal plate is identical with the length of the first supporting steel plate;One is provided with along in the rear side level of the second described supporting steel plate The length direction of two supporting steel plates and the second horizontal plate of setting is engaged with first level plate, the length of the second horizontal plate and the The length of two supporting steel plates is identical, and the second described horizontal plate is located at the lower section of first level plate.
4. adjustable steel construction according to claim 3 operates hanging basket, it is characterised in that in described first level plate Downside on be provided with some first limited blocks along the length direction of first level plate;In the upper side of the second described horizontal plate On be provided with and some the second limited block that clamping is connected be engaged with the first limited block along the length direction of the second horizontal plate.
5. adjustable steel construction according to claim 4 operates hanging basket, it is characterised in that the first described limited block and Second limited block is in dentation.
CN201621101231.2U 2016-09-30 2016-09-30 Adjustable steel configuration operation hanging flower basket Expired - Fee Related CN206091259U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621101231.2U CN206091259U (en) 2016-09-30 2016-09-30 Adjustable steel configuration operation hanging flower basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621101231.2U CN206091259U (en) 2016-09-30 2016-09-30 Adjustable steel configuration operation hanging flower basket

Publications (1)

Publication Number Publication Date
CN206091259U true CN206091259U (en) 2017-04-12

Family

ID=58482421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621101231.2U Expired - Fee Related CN206091259U (en) 2016-09-30 2016-09-30 Adjustable steel configuration operation hanging flower basket

Country Status (1)

Country Link
CN (1) CN206091259U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107127486A (en) * 2017-05-12 2017-09-05 五冶集团上海有限公司 Weld job bogey
CN108729355A (en) * 2018-06-01 2018-11-02 江北建设有限公司 Platform is fitted up on a kind of bridge-collision-avoidance column for municipal science of bridge building
CN108775016A (en) * 2018-07-11 2018-11-09 安徽三建工程有限公司 A kind of concrete support moves horizontally adjustable Hanging Basket
CN111005545A (en) * 2019-12-31 2020-04-14 上海市机械施工集团有限公司 Construction device and method for steel structure
CN111764626A (en) * 2020-06-05 2020-10-13 中船澄西船舶修造有限公司 Cantilever type scaffold

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107127486A (en) * 2017-05-12 2017-09-05 五冶集团上海有限公司 Weld job bogey
CN108729355A (en) * 2018-06-01 2018-11-02 江北建设有限公司 Platform is fitted up on a kind of bridge-collision-avoidance column for municipal science of bridge building
CN108775016A (en) * 2018-07-11 2018-11-09 安徽三建工程有限公司 A kind of concrete support moves horizontally adjustable Hanging Basket
CN108775016B (en) * 2018-07-11 2024-02-23 安徽建工三建集团有限公司 Concrete support horizontal movement adjustable hanging basket
CN111005545A (en) * 2019-12-31 2020-04-14 上海市机械施工集团有限公司 Construction device and method for steel structure
CN111764626A (en) * 2020-06-05 2020-10-13 中船澄西船舶修造有限公司 Cantilever type scaffold

Similar Documents

Publication Publication Date Title
CN206091259U (en) Adjustable steel configuration operation hanging flower basket
CN207079724U (en) A kind of steel construction primary and secondary beam connecting node
CN203923914U (en) Solely stub bent cap support
CN103362069B (en) Steel and concrete combined box girder concrete wing plate formwork and construction method
CN205171782U (en) Frame curtain system between stone material edge list
CN214498388U (en) Assembled overhanging formwork support bent
CN103089010A (en) Cradle construction device replacing reinforced concrete beam bottom protection layer and cradle construction method
CN206667042U (en) Bridge expanssion joint installation and adjustment instrument
CN205781433U (en) Central air-conditioning novel pipeline suspension and support device
CN206052554U (en) A kind of Construction Supporting System for square twin columns great cantilever bent cap
CN208934394U (en) One kind can turnover type hydraulic climbing formwork wall-attaching equipment
CN201367730Y (en) A die plate supporting device convenient for dismounting die plates
CN205061244U (en) Extension formula elevator guide rail support
CN204826714U (en) Novel steel constructs a tire supporting frame
CN208310204U (en) A kind of pedestal for elevator coupling beam formwork erection
CN105648918A (en) Deviation device and construction method thereof
CN106522531B (en) The support system of one discharge plate buckle type scaffold door opening position bracket
CN201335397Y (en) Vertical enclosure framework of furnace top
CN205064389U (en) Air cooling fan crane span structure installation base
CN208868124U (en) A kind of lower mounting bracket based on electric steering column
CN208668921U (en) A kind of pre-buried wall attaching parts of postposition
CN207761274U (en) Easily assembly and disassembly recycling formula cantilever tripod
CN204754225U (en) Can have enough to meet need a support
CN206667784U (en) The erecting device of glass curtain wall outer visor
CN207073118U (en) Dam hangs the concrete prefabricated formwork structure of body by the feet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170412