CN206090610U - Utility tunnel system - Google Patents

Utility tunnel system Download PDF

Info

Publication number
CN206090610U
CN206090610U CN201621133901.9U CN201621133901U CN206090610U CN 206090610 U CN206090610 U CN 206090610U CN 201621133901 U CN201621133901 U CN 201621133901U CN 206090610 U CN206090610 U CN 206090610U
Authority
CN
China
Prior art keywords
piping lane
sides
crane span
span structure
pipe gallery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621133901.9U
Other languages
Chinese (zh)
Inventor
卓如斌
佟斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Foreshore Electroplating Enterprise Management Co Ltd
Original Assignee
Tianjin Foreshore Electroplating Enterprise Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Foreshore Electroplating Enterprise Management Co Ltd filed Critical Tianjin Foreshore Electroplating Enterprise Management Co Ltd
Priority to CN201621133901.9U priority Critical patent/CN206090610U/en
Application granted granted Critical
Publication of CN206090610U publication Critical patent/CN206090610U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model belongs to pipeline engineering field, the utility model relates to an utility tunnel system, by the piping lane, the sewage gathering station, the sewage treatment station, lighting system, ventilation system, the forceful electric power crane span structure, the light current crane span structure, lateral wall pipe road bridge frame, bottom pipeline support bracket, the maintenance passageway is formed, the sewage gathering station sets up in the piping lane initiating terminal, the sewage treatment station sets up in the piping lane terminally, lighting system, ventilation system sets up top in the piping lane, the forceful electric power crane span structure, the light current crane span structure sets up respectively in piping lane top both sides, lateral wall pipe road bridge erects and arranges piping lane lower part both sides in, bottom pipeline support bracket sets up bottom both sides in the piping lane, the maintenance passageway sets up in piping lane bottom centre, the piping lane, by be responsible for the corridor, mainly connect the piping lane, a piping lane is formed, the main piping lane of connecting is connected in each and is responsible for between the corridor, a piping lane sets up in being responsible for the corridor both sides, one end with be responsible for corridor upper portion and feed through, the other end is connected with the sewage gathering station. The utility model discloses comprehensive function is powerful, the operation is reliable, the maintenance is convenient, the energy can be saved, has the novelty.

Description

A kind of underground pipe gallery system
Technical field
The utility model belongs to municipal pipeline field of engineering technology, more particularly to a kind of underground pipe gallery system.
Background technology
Municipal pipeline engineering includes the engineering such as feedwater, draining, power supply, communication, underground pipe gallery be exactly can feed water, The engineering construction unified planning such as draining, power supply, communication, Uniting, the unified one kind municipal administration basis work built, be managed collectively Journey.The raising that requires with municipal administration and become more meticulous, the particularly appearance of large scale industry garden, supply, Drainage feature has Greatly change, requirements at the higher level are proposed to supply and drain facility, and conventional underground pipe gallery is mostly single piping lane or culvert, Lack globality, systematicness, function is not perfect enough, check, keep in repair inconvenient, lack organic connections with other urban operating mechanisms, Much can not meet the needs that modern urban construction is particularly park building.Such as chemical engineering industry garden, Treatment of Industrial Park of Plating garden, its Waste discharge species will carry out innoxious, recycling treatment up to tens of kinds to sewage, in the urgent need to a kind of function more Powerful, operation is more reliable, management more easily underground pipe gallery.Also it is exactly, the waste water conveying of conventional industrial park pipe culvert, All it is mostly power conveying, not only needs many with equipment, also to consume the energy, long-play causes evaporating, emitting, dripping or leaking of liquid or gas situation serious; Realize the gravity flow discharge of industrial wastewater, the even more hope of numerous enterprises man.My company Jing development tests in many years, independent research one Underground pipe gallery system is planted, the system is not only suitable for cities and towns urban construction, the gardens such as chemical industry, Treatment of Industrial Park of Plating are particularly well-suited to again Area builds;The architecture design science is various pipes such as sewage disposal, water supply, power supply, fire-fighting, communication, heating, combustion gas rationally Line engineering is provided builds platform, and comprehensive function is powerful, and comprehensive benefit is good, is extensively praised by various circles of society.
The content of the invention
The purpose of this utility model is to overcome the deficiencies in the prior art, there is provided one kind is not only suitable for cities and towns urban construction, The with better function of the park building such as chemical industry, Treatment of Industrial Park of Plating is particularly well-suited to again, operation is more reliable, it is more convenient to manage and it He builds the underground pipe gallery system of organic linking, save energy.
The utility model solves its technical problem and is achieved through the following technical solutions:
A kind of underground pipe gallery system, it is characterised in that:By piping lane, sewage collecting station, Sewage Disposal, illumination system System, ventilating system, forceful electric power crane span structure, light current crane span structure, side wall pipeline crane span structure, bottom pipe support bracket, maintenance channel composition, sewage is received Collection station is arranged at piping lane initiating terminal, and Sewage Disposal is arranged at piping lane end, and illuminator, ventilating system are arranged at top in piping lane Portion, forceful electric power crane span structure, light current crane span structure are respectively arranged at piping lane top both sides, and side wall conduit bridge sets up and is placed in piping lane bottom both sides, bottom Portion's pipeline support bracket is arranged at piping lane inner bottom part both sides, and maintenance channel is arranged in the middle of piping lane bottom, the piping lane, by being responsible for Corridor, main connection piping lane, a piping lane composition, main connection piping lane is connected between each supervisor corridor, and a piping lane is arranged at supervisor corridor both sides, One end connects with supervisor corridor top, and the other end is connected with sewage collecting station.
And, the supervisor corridor, main connection piping lane, a piping lane are one or more, are integrated slurry molding and have The Square Reinforced Concrete tubular member of hollow cavity, is made up of piping lane top board, piping lane base plate, piping lane sidewall paneling, and piping lane top board exists Upper, piping lane base plate is under, piping lane sidewall paneling connects in two side rings and is made as one, and wherein cavity road section specification is two meters to ten of width Rice, two meters to five meters of height, its outside bottom surface and both sides are formed with " U " type waterproof layer, its internal two sides, bottom surface scribble anti-corrosion Layer, thereon delocalization is formed with multiple access holes, turnover stair, equipment hoisting mouth, and longitudinal direction is formed with collecting gutter in the middle of its inner bottom part, its Outer bottom both sides are symmetrically formed with anti-settling protuberance, and top side or both sides are formed with anti-roadbed subsidence flange, and its piping lane top board can For horizontal plane piping lane top board or slope piping lane top board.
And, the slope piping lane top board, its gradient is consistent with road gradient.
And, the piping lane base plate, its longitudinal direction gradually sinks in ramp shaped from initiating terminal to end, the gradient be 2/1000ths to 15/1000ths, its horizontal upper surface is high outside and low outside domatic state.
And, the bottom pipe support bracket is two groups, piping lane inner bottom part both sides is respectively arranged at, by multiple precast beams Plate is constituted, and multiple precast beams are uniformly arranged in piping lane inner bottom part both sides.
And, the side wall pipeline crane span structure is two groups, is respectively arranged in piping lane on the piping lane sidewall paneling of bottom both sides, per group It is one to five, one to five side wall pipeline crane span structure is side by side up and down to be installed on piping lane sidewall paneling.
And, the maintenance channel is multigroup composite gridding cover plate.
And, the sewage collecting station is one or more, multiple sewage collecting stations be respectively arranged at piping lane both sides with Factory building adjacent.
And, the ventilating system is made up of air intake tower, exhaust chimney, ventilating fan, and air intake tower, exhaust chimney are arranged at piping lane On, ventilating fan is provided with exhaust chimney lower section on piping lane.
And, the forceful electric power crane span structure, light current crane span structure, its bottom is provided with bracing frame.
Advantage of the present utility model and have the beneficial effect that:
1. the piping lane of the utility model underground pipe gallery system has large volume, be sewage disposal, water supply, power supply, Various pipe engineerings such as fire-fighting, communication, heating, combustion gas are provided builds platform, and comprehensive function is powerful.Various pipelines are concentrated on Underground pipe gallery, can resist impact load, improve Disaster Defense Capability, it is to avoid the harm that the disaster such as wind, rain, fire is caused.
2. the utility model underground pipe gallery system, its piping lane, supervisor corridor, the piping lane base plate of connection supervisor corridor are from dirt Waterpipe starting point, in state of gradually sinking, can will pass through nothing to pipeline flow-direction direction after the sewage categorised collection of workshop Power gravity flow mode is fed directly to Sewage Disposal and is processed, save energy.
3. its piping lane top board of the utility model underground pipe gallery system can be planar top surface or slope top surface, in slope top Its gradient is consistent with road gradient during face, is easy to be connected with pavement of road;The outer top side of its piping lane or both sides are formed with anti-road surface Sedimentation flange, can effectively prevent roadbed subsidence with road surface organic linking.
4. its piping lane outer wall of the utility model underground pipe gallery system is formed with " U " type waterproof layer, inwall bottom surface, two sides Waterproof, anticorrosive coat are formed with, external water source seepage can be effectively prevented, effectively prevent inside and outside harmful object from corroding.
5. the utility model underground pipe gallery system is provided with ventilating system, drainage system, it is ensured that piping lane has good Good running environment, effectively strengthens the operational reliability of equipment and pipeline, extension device and pipeline service life.
6. the utility model underground pipe gallery system is provided with illuminator, turnover stair, maintenance channel, equipment hoisting Mouthful, the daily management operation such as it is convenient for checking, keeps in repair;And it is provided with the emergency power supply with automatic charging function, it is to avoid Accident power-off is caused in maintenance process illuminator and ventilating system failure, effective protection personal security.
7. the utility model underground pipe gallery system structure design is scientific and reasonable, with comprehensive function it is powerful, operation can By, management service convenience, save energy, be easy to the advantages of being connected with other urban operating mechanisms, be a kind of with higher innovation Underground pipe gallery system.
Description of the drawings
Fig. 1 is that underground pipe gallery System planes arrange schematic diagram;
Fig. 2 is Pipe rack schematic diagram of the present utility model;
Fig. 3 is of the present utility model piping lane and supervisor's corridor joint portion sectional schematic diagram.
Accompanying drawing marks explanation:
1- light current crane span structures, 2- sides wall pipeline crane span structure, 3- bottom pipe support brackets, 4- illuminators, 5- maintenance channels, 6- leads to Wind system, 7- collecting gutters, 8- piping lane top boards, 9- forceful electric power crane span structures, 10- bracing frames, the anti-roadbed subsidence flanges of 11-, 12- piping lanes bottom Plate, 13- piping lane sidewall panelings, 14- anti-settling protuberances, 15- sewage collectings station, 16- piping lane, 17- supervisors corridor.
Specific embodiment
Below by specific embodiment, the utility model is described in further detail, following examples be it is descriptive, no It is determinate, it is impossible to which protection domain of the present utility model is limited with this.
A kind of underground pipe gallery system, by piping lane, sewage collecting station 15, Sewage Disposal, illuminator 4, ventage System 6, forceful electric power crane span structure 9, light current crane span structure 1, side wall pipeline crane span structure 2, bottom pipe support bracket 3, maintenance channel 5 are constituted, sewage collecting Station is arranged at piping lane initiating terminal, and Sewage Disposal is arranged at piping lane end, and illuminator, ventilating system are arranged at top in piping lane Portion, forceful electric power crane span structure, light current crane span structure are respectively arranged at piping lane top both sides, and side wall conduit bridge sets up and is placed in piping lane bottom both sides, bottom Portion's pipeline support bracket is arranged at piping lane inner bottom part both sides, and maintenance channel is arranged in the middle of piping lane bottom, the piping lane, by supervisor corridor 17th, main connection piping lane, a piping lane 16 are constituted, and main connection piping lane is connected between each supervisor corridor, and a piping lane is arranged at supervisor corridor two Side, one end connects with supervisor corridor top, and the other end is connected with sewage collecting station.
Propping up piping lane is used to arrange the pipeline for being directly entered factory building, connection wastewater collection station;It is each that supervisor corridor is used for arrangement connection The pipeline of individual piping lane;Main connection piping lane is used to connect each piping lane;Sewage collecting station is used for the collection of workshop waste water With classification;Illuminator is used for piping lane intraoral illumination, is easy to safeguard;Ventilating system is used for ventilation drying in piping lane, keeps drying, protects Piping lane good environment is held, is beneficial to extend various pipelines and piping lane service life itself;Forceful electric power crane span structure is used to arrange low-voltage power supply Circuit;Light current crane span structure is used for the light current cables such as arrangement communication;Side wall pipeline crane span structure is used to arrange all kinds of with bottom pipe support bracket Water supply, fire-fighting, blow-off line;Maintenance channel is used for personnel's same sex, is easy to operating repairs.
Supervisor corridor, main connection piping lane, a piping lane, are one or more, and the present embodiment supervisor corridor is two, main connecting tube It is multiple that corridor is two, piping lanes.Supervisor corridor, main connection piping lane, a piping lane are one slurry molding and have hollow cavity Square Reinforced Concrete tubular member, is made up of piping lane top board 8, piping lane base plate 12, piping lane sidewall paneling 13, and piping lane top board is in upper, pipe Corridor base plate is under, piping lane sidewall paneling connects in two side rings and is made as one.Supervisor corridor, main connection piping lane, a piping lane wherein cavity road cut Face specification be two meters to ten meters of width, height two meters to five meters.Its outside bottom surface and two of supervisor corridor, main connection piping lane, a piping lane Side is formed with " U " type waterproof layer, its internal two sides, bottom surface scribble anticorrosive coat.Supervisor corridor, main connection piping lane, a piping lane are thereon Delocalization is formed with multiple access holes, turnover stair, equipment hoisting mouth, and longitudinal direction is formed with collecting gutter 7 in the middle of its inner bottom part, its outer bottom Both sides are symmetrically formed with anti-settling protuberance 14, and top side or both sides are formed with anti-roadbed subsidence flange 11, and its piping lane top board can be Horizontal plane piping lane top board or slope piping lane top board.Slope piping lane top board, its gradient is consistent with road gradient.Piping lane top board is The slope piping lane top board and gradient is consistent with road gradient, top side or both sides are formed with anti-roadbed subsidence flange, are easy to piping lane With road surface organic linking.
Piping lane base plate, its longitudinal direction gradually sinks in ramp shaped from initiating terminal to end, and the gradient is 10/2000ths to thousand/1000ths Five, its horizontal upper surface is high outside and low outside domatic state.Piping lane base plate is in ramp shaped, can make the unpowered self-flowing pastefill of sewage conduct, Save energy;Laterally upper surface is for high outside and low outside domatic state and piping lane bottom is formed with collecting gutter, is easy to gather accidental leak Collection and exclusion.
Bottom pipe support bracket is two groups, is respectively arranged at piping lane inner bottom part both sides, many by multiple precast beams composition Individual precast beam is uniformly arranged in piping lane inner bottom part both sides.
Wall pipeline crane span structure in side is two groups, is respectively arranged in piping lane on the piping lane sidewall paneling of bottom both sides, be per group one to Five, one to five side wall pipeline crane span structure is side by side up and down to be installed on piping lane sidewall paneling;The present embodiment is three.
Maintenance channel, is multigroup composite gridding cover plate.
Sewage collecting station is one or more, and the present embodiment is multiple, and multiple sewage collecting stations are respectively arranged at a piping lane Both sides and factory building adjacent.
Ventilating system, is made up of air intake tower, exhaust chimney, ventilating fan, and air intake tower, exhaust chimney are arranged on piping lane, ventilating fan It is provided with exhaust chimney lower section on piping lane.Air intake tower, exhaust chimney are set, it is more preferable than general air inlet, floss hole ventilation effect.
Forceful electric power crane span structure, light current crane span structure, its bottom is provided with bracing frame 10.The bracing frame can make crane span structure more firm, hold Weight is bigger.
Operation principle of the present utility model:
A kind of underground pipe gallery system of the utility model, using unified planning, design, builds and operation management, its handle Dispersion is independently embedded in more than the ten of underground and plants various underground utilities and is partly or entirely pooled to a common underground pipe gallery In, various pipelines are laid in an orderly manner in the limited underground space, implement common maintenance, centralized management, can more effectively utilize base The ground underground space, is avoided that the roundabout arrangement of pipeline, so as to save land used, has saved resource;Road can be also avoided to repeat " to cut open the chest Broken tripe ", reduces accident and occurs, and extends the pipeline life-span;Meanwhile, various pipelines being concentrated on underground pipe gallery, can improve anti- Calamity ability, it is to avoid the harm that the disaster such as wind, rain, fire is caused, resists impact load, with performance of taking precautions against natural calamities.
The utility model underground pipe gallery system, its piping lane, supervisor corridor, the piping lane base plate of connection supervisor corridor are from sewage Pipeline starting point, in state of gradually sinking, can be moved after the sewage categorised collection of workshop to pipeline flow-direction direction by nothing Power gravity flow mode is fed directly to Sewage Disposal and is processed, save energy.
The utility model underground pipe gallery system its piping lane top board can be planar top surface or slope top surface, in slope top surface When its gradient it is consistent with road gradient, be easy to be connected with pavement of road;The outer top side of its piping lane or both sides are formed with anti-road surface and sink Drop flange, can effectively prevent roadbed subsidence with road surface organic linking.
The utility model underground pipe gallery system its piping lane outer wall is formed with " U " type waterproof layer, inwall bottom surface, two sides system There are waterproof, anticorrosive coat, can effectively prevent external water source seepage, effectively prevent inside and outside harmful object from corroding.
The utility model underground pipe gallery system is provided with ventilating system, drainage system, it is ensured that piping lane has good Running environment, effectively strengthen the operational reliability of equipment and pipeline, extension device and pipeline service life.
Although disclosing embodiment of the present utility model and accompanying drawing for the purpose of illustration, those skilled in the art can be with Understand:In without departing from the utility model and spirit and scope of the appended claims, various replacements, change and modifications all be can Can, therefore, scope of the present utility model is not limited to embodiment and accompanying drawing disclosure of that.

Claims (10)

1. a kind of underground pipe gallery system, it is characterised in that:By piping lane, sewage collecting station, Sewage Disposal, illuminator, Ventilating system, forceful electric power crane span structure, light current crane span structure, side wall pipeline crane span structure, bottom pipe support bracket, maintenance channel composition, sewage collecting Station is arranged at piping lane initiating terminal, and Sewage Disposal is arranged at piping lane end, and illuminator, ventilating system are arranged at top in piping lane Portion, forceful electric power crane span structure, light current crane span structure are respectively arranged at piping lane top both sides, and side wall conduit bridge sets up and is placed in piping lane bottom both sides, bottom Portion's pipeline support bracket is arranged at piping lane inner bottom part both sides, and maintenance channel is arranged in the middle of piping lane bottom, the piping lane, by being responsible for Corridor, main connection piping lane, a piping lane composition, main connection piping lane is connected between each supervisor corridor, and a piping lane is arranged at supervisor corridor both sides, One end connects with supervisor corridor top, and the other end is connected with sewage collecting station.
2. underground pipe gallery system according to claim 1, it is characterised in that:The supervisor corridor, main connection piping lane, Piping lane, is one or more, the Square Reinforced Concrete tubular member that slurry molding has hollow cavity is integrated, by piping lane Top board, piping lane base plate, piping lane sidewall paneling composition, piping lane top board upper, piping lane base plate under, piping lane sidewall paneling connect system in two side rings It is integrated, wherein cavity road section specification is two meters to ten meters of width, two meters to five meters of height, its outside bottom surface and both sides system Have " U " type waterproof layer, two sides, bottom surface scribble anticorrosive coat inside it, and delocalization thereon is formed with multiple access holes, turnover building Ladder, equipment hoisting mouth, longitudinal direction is formed with collecting gutter in the middle of its inner bottom part, and its outer bottom both sides is symmetrically formed with anti-settling protuberance, top Portion one or both sides are formed with anti-roadbed subsidence flange, and its piping lane top board can be horizontal plane piping lane top board or slope piping lane top board.
3. underground pipe gallery system according to claim 2, it is characterised in that:The slope piping lane top board, its slope Degree is consistent with road gradient.
4. underground pipe gallery system according to claim 2, it is characterised in that:The piping lane base plate, its longitudinal direction is from Top to end gradually sinks in ramp shaped, and the gradient is 15/2000ths to thousand/1000ths, and its horizontal upper surface is high outside and low outside slope Shape state.
5. underground pipe gallery system according to claim 1, it is characterised in that:The bottom pipe support bracket is two Group, is respectively arranged at piping lane inner bottom part both sides, and by multiple precast beams composition, multiple precast beams are uniformly arranged in piping lane Two bottom sides.
6. underground pipe gallery system according to claim 1, it is characterised in that:The side wall pipeline crane span structure is two groups, It is respectively arranged in piping lane on the piping lane sidewall paneling of bottom both sides, one to five, on one to five side wall pipeline crane span structure is per group Under be installed in side by side on piping lane sidewall paneling.
7. underground pipe gallery system according to claim 1, it is characterised in that:The maintenance channel, is multigroup compound Grid cover plate.
8. underground pipe gallery system according to claim 1, it is characterised in that:The sewage collecting station is one or many Individual, multiple sewage collecting stations are respectively arranged at a piping lane both sides and factory building adjacent.
9. underground pipe gallery system according to claim 1, it is characterised in that:The ventilating system, by air intake tower, row Wind tower, ventilating fan composition, air intake tower, exhaust chimney are arranged on piping lane, and ventilating fan is provided with exhaust chimney lower section on piping lane.
10. underground pipe gallery system according to claim 1, it is characterised in that:The forceful electric power crane span structure, light current crane span structure, Its bottom is provided with bracing frame.
CN201621133901.9U 2016-10-17 2016-10-17 Utility tunnel system Active CN206090610U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621133901.9U CN206090610U (en) 2016-10-17 2016-10-17 Utility tunnel system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621133901.9U CN206090610U (en) 2016-10-17 2016-10-17 Utility tunnel system

Publications (1)

Publication Number Publication Date
CN206090610U true CN206090610U (en) 2017-04-12

Family

ID=59976279

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621133901.9U Active CN206090610U (en) 2016-10-17 2016-10-17 Utility tunnel system

Country Status (1)

Country Link
CN (1) CN206090610U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320370A (en) * 2016-10-17 2017-01-11 天津滨港电镀企业管理有限公司 Underground comprehensive pipe rack system
CN107726525A (en) * 2017-10-10 2018-02-23 上海市政工程设计研究总院(集团)有限公司 A kind of pipe gallery Moistureproof dehumidification ventilating system and its implementation
CN107725090A (en) * 2017-10-10 2018-02-23 上海市政工程设计研究总院(集团)有限公司 A kind of subterranean tunnel ventilating system and its implementation
CN107842038A (en) * 2017-10-31 2018-03-27 上海市政工程设计研究总院(集团)有限公司 A kind of pipe gallery node location road subtracts sink device
CN110258367A (en) * 2019-06-24 2019-09-20 中铁第四勘察设计院集团有限公司 Transition structure is contained on a kind of culvert and road

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106320370A (en) * 2016-10-17 2017-01-11 天津滨港电镀企业管理有限公司 Underground comprehensive pipe rack system
CN107726525A (en) * 2017-10-10 2018-02-23 上海市政工程设计研究总院(集团)有限公司 A kind of pipe gallery Moistureproof dehumidification ventilating system and its implementation
CN107725090A (en) * 2017-10-10 2018-02-23 上海市政工程设计研究总院(集团)有限公司 A kind of subterranean tunnel ventilating system and its implementation
CN107725090B (en) * 2017-10-10 2024-04-05 上海市政工程设计研究总院(集团)有限公司 Underground tunnel ventilation system and implementation method thereof
CN107842038A (en) * 2017-10-31 2018-03-27 上海市政工程设计研究总院(集团)有限公司 A kind of pipe gallery node location road subtracts sink device
CN110258367A (en) * 2019-06-24 2019-09-20 中铁第四勘察设计院集团有限公司 Transition structure is contained on a kind of culvert and road

Similar Documents

Publication Publication Date Title
CN206090610U (en) Utility tunnel system
CN106320370A (en) Underground comprehensive pipe rack system
CN205296224U (en) Air intake, hoist and mount mouthful and mouthful combined layout's utility tunnel node structure of fleing
CN103775099B (en) 3+X city main pipeline network system
CN106381885B (en) A kind of Underground Steel pipe gallery with skeleton
CN104746531A (en) Stainless steel composite steel comprehensive pipe gallery
CN205557584U (en) Steel pipe corridor and large -scale utility tunnel system
CN110924509A (en) Turn-back type ultra-deep inspection well
CN212358372U (en) City utility tunnel
CN205296229U (en) Sewer manhole in utility tunnel
CN205742273U (en) A kind of fiberglass pipe gallery
CN205077513U (en) Utility tunnel and underpass uncovered formula structure of building together
CN211057848U (en) Circular utility tunnel extensible structure of individual layer
CN203296162U (en) Buried prefabricated pump station
CN207760873U (en) Assembled steel system utility tunnel sewage conduit overhauls structure
CN102562153A (en) Setting method for auxiliary system of electric power tunnel
CN206616592U (en) Lighting device is penetrated at a kind of bottom constructed for pipe gallery
CN109881709A (en) A kind of assembled rectangle pipe gallery and round pipe gallery T-section point
CN205742466U (en) Prestressing force is to adding series rain dirt shunting underground pipe gallery
CN220747096U (en) Integrated buried irrigation pump station
CN205557571U (en) Prestressing force divides and adds series side storehouse drainage type underground pipe gallery
CN205776353U (en) Supporting type pipe gallery structure
CN205662944U (en) Public underground box culvert of electroplating industry garden integrated form
CN205480643U (en) Have cable well exhausting function's street lamp device concurrently
CN208996090U (en) A kind of piping lane sewage inspection system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant