CN205557571U - Prestressing force divides and adds series side storehouse drainage type underground pipe gallery - Google Patents

Prestressing force divides and adds series side storehouse drainage type underground pipe gallery Download PDF

Info

Publication number
CN205557571U
CN205557571U CN201620182804.2U CN201620182804U CN205557571U CN 205557571 U CN205557571 U CN 205557571U CN 201620182804 U CN201620182804 U CN 201620182804U CN 205557571 U CN205557571 U CN 205557571U
Authority
CN
China
Prior art keywords
storehouse
prestressing force
piping lane
pipe
lane body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620182804.2U
Other languages
Chinese (zh)
Inventor
张楸长
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620182804.2U priority Critical patent/CN205557571U/en
Application granted granted Critical
Publication of CN205557571U publication Critical patent/CN205557571U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model discloses a prestressing force divides and adds series side storehouse drainage type underground pipe gallery, include the stress tube corridor body and outer skeleton and inner skeleton in advance, be provided with horizontal bobbin and vertical bobbin between the two -layer skeleton, wherein horizontal bobbin setting is in the roof and bottom plate that personally experienced sth. Part of the body in the stress tube corridor in advance, be provided with steel strand wires in the horizontal bobbin, the anchor is in the both sides of the stress tube corridor body in advance after stretch -draw produces prestressing force, the internal hole in stress tube corridor is provided with four piece at least compartment backup pads in advance, become five at least piping lane storehouses with piping lane hole separated, be provided with prefabricated drain pipe bottom the piping lane storehouse of the piping lane zhong cang left and right sides. The utility model discloses can further reduce the engineering valence of underground pipe gallery engineering, the all right more effective water discharge ability who improves underground pipe gallery can be for carrying out the more reliable condition of carrying on of PPP mode.

Description

Prestressing force divides and adds series storehouse, side drainage type underground pipe gallery
Technical field
This utility model relates to a kind of prestressing force and divides and add series storehouse, side drainage type underground pipe gallery.
Background technology
The process of China's Urbanization Construction is constantly being accelerated, and the level that arranges also constantly is improving, and this is to build smart city to create the big good opportunity of development.Affected by new trend, " design " majority of smart city is confined to the aspects such as the Internet, cloud computing, big data, it is essentially all the design concept of management and service, in terms of urban planning or traditional plane general layout, underground infrastructure also should the lifting manipulation of wisdom, the most do not cause the concern of people.
The urban disease that people comment on from many aspects, and " bad phenomenon " caused because of underground pipe network, it has also become the topic of " widely known, known by everybody ".Thus may certify that, building smart city should be improving the public environment of people, and the quality of the life improving people is classified as the aims of systems of the first level.
New city underground pipe gallery, is the requisite underground infrastructure of Urbanization Construction, is again that municipal administration common line lays networking, informationization, intelligentized new support, and therefore Urban Underground pipe gallery should be the important set composition building smart city overall planning.The a series of principles and policies issued according to country for this, it is very important " technical task " that development is suitable for the underground pipe gallery of smart city.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of prestressing force and divides and add series storehouse, side drainage type underground pipe gallery, use five storehouses side by side, two-tube prefabricated structural models, manufacture the underground pipe gallery of super-section, can solve to build at metropolis major trunk roads " especially big technology ' difficult problem ' " of multi-chamber underground pipe gallery, according to local geological conditions, according to the urban planning that local urban district is new, can be with the sectional space optimizing many storehouses underground pipe gallery of science, can reach that " cross-sectional distribution is reasonable, Mechanical Builds is unique, Technology is advanced, construction costs is minimum, long perfomance life, operation value is reliable " target.
Specifically, this utility model adopts the following technical scheme that
nullA kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery,The outer layer skeleton including prestressing force piping lane body and being arranged in prestressing force piping lane body and nexine skeleton,The inboard of described outer layer skeleton is provided with horizontal bobbin,Longitudinal bobbin it is provided with between horizontal bobbin and nexine skeleton,Laterally bobbin is separately positioned in top board and the base plate of prestressing force piping lane body,The steel strand wires being anchored at prestressing force piping lane body both sides through stretch-draw generation prestressing force anchorage it are provided with in horizontal bobbin,The steel strand wires being anchored at prestressing force piping lane body two ends through stretch-draw generation prestressing force anchorage it are provided with in longitudinal bobbin,At least two pieces of compartment gripper shoes it are provided with in prestressing force piping lane body opening,It is respectively storehouse, left side and storehouse, right side in middle two pieces of compartment gripper shoe left and right sides,The bottom in storehouse, left side and storehouse, right side is provided with prefabricated drain pipe,The bottom of prestressing force piping lane body is provided with discharge casing,The end of prestressing force piping lane body is provided with connecting box,The middle part of prestressing force piping lane body is provided with construction joint,Water-swellable adhesive tape it is provided with in construction joint.
Described outer layer skeleton is indulged muscle by outer layer horizontal bar and outer layer and is constituted, described nexine skeleton is indulged muscle by nexine horizontal bar and nexine and is constituted, the both sides indulging muscle intersection at outer layer horizontal bar and outer layer are provided with U-shaped positioning bar, laterally bobbin is arranged in the U-shaped mouth of U-shaped positioning bar, being provided with longitudinal bobbin in compartment gripper shoe, bottom prestressing force piping lane body, the left and right sides is provided with precast support angle.
Four pieces of compartment gripper shoes it are provided with in prestressing force piping lane body opening, piping lane hole is separated into storehouse, the left side, storekeeper corridor, left side Zhong Cang, storehouse, right side and storehouse, the right by the most successively, precast support angle is separately positioned on storehouse, left side bottom left and storehouse, the right bottom right, it is provided with in precast support angle bottom ventilation duct, storehouse, left side and storehouse, right side and is provided with prefabricated drain pipe.
Running water pipe, regeneration water pipe, thermal pipe, refuse conveying pipe, communication pipe and cable tube it is provided with in storehouse in described piping lane, it is respectively arranged with sewage pipe in storehouse, left side and storehouse, right side, the left side is provided with Gas Pipe in storehouse, being provided with power pipe on the right in storehouse, above-mentioned each pipeline is fixed in corresponding piping lane storehouse by bracing frame.
Storehouse, the described left side, storekeeper corridor, left side Zhong Cang, storehouse, right side is provided with rhone with bottom storehouse, the right, rhone is connected with discharge casing by osculum, be provided with drain pipe in the both sides of discharge casing, regulation and control boiled water room and drain sump that described drain pipe is external with being arranged on prestressing force piping lane connect.
Edge on road surface, city is provided with rainwater import, is provided with row's rain pipe and lower row's raintank, described discharge casing and lower row's raintank, water storehouse and purification sump in the bottom of greenery patches plane and is connected.
It is provided with dilatation seam in the junction of described connecting box Yu prestressing force piping lane body, is provided with rubber fastening band in dilatation seam, the middle part of prestressing force piping lane body is provided with construction joint, in construction joint, is provided with water-swellable adhesive tape.
Sidepiece at described connecting box is provided with passage, and connecting box is connected with function room, Surveillance center, ventilating house, service centre, special room, underground parking and the ecommerce supermarket of being connected respectively by passage.
Good effect of the present utility model is as follows:
This utility model uses the five the most two-tube prefabricated frame modes in storehouse to belong to " structure innovation " and " function innovation ", prestressing force is utilized to divide the new technology added, new technique, horizontal bobbin is designed in the lower shoe and upper cover plate of prestressing force piping lane body, in horizontal bobbin, steel strand wires are set, both sides sidepiece anchorage at piping lane body anchors, piping lane body can be promoted to form especially big stretching resistance, use longitudinally connected new technology, new technique, whole piping lane can be formed a prestressing force piping lane body, the prestressing force underground pipe gallery of heavy in section cast in situs can be brought up to a new height, can solve to build at shallow soil layer the especially big technical barrier of anti-weight structure thoroughly, standardized demonstration project can be developed into.
This utility model arranges storehouse, left side in the left side of piping lane body, storehouse, right side is set in right side, lower bottom part row's rain pipe in storehouse, left side and storehouse, right side, and sewage pipe is set in storehouse, left side and right side, on row's rainwater and blowdown moisture, lower setting is very science, not only reduce the width of piping lane body, and in terms of the docking of each pipeline, provide more convenient, more reliable condition, thus can further prove can the construction costs of substantial amounts of reduction underground pipe gallery engineering, can also more effectively improve the drainability of underground pipe gallery, can be to carry out the advantage that PPP pattern provides more reliable.
This utility model arranges discharge casing at the lower bottom part of heavy in section piping lane body, can be because of assembling or maintenance and wash away the hydrops of generation and be discharged to header tank in time, can guarantee that the cleaning in piping lane body, the ventilation duct arranged in utilizing each storehouse carries out cold air cooling, the conversion that hot blast is heated, promote heavy in section piping lane endoporus, form an air resource treasure-house cleaned very much, the most not only can increase the on-road efficiency of heavy in section underground pipe gallery, but also each dedicated pipeline and the life of auxiliary facility in gallery can be extended in various degree, " joint money can be really achieved, energy-conservation, green, environmental protection " high standard requirement.
Accompanying drawing explanation
Accompanying drawing 1 is this utility model agent structure schematic diagram;
Accompanying drawing 2 is this utility model section structure schematic diagram;
Accompanying drawing 3 is this utility model planar structure schematic diagram;
Accompanying drawing 4 is this utility model side elevation structural representation;
Accompanying drawing 5 is this utility model function room structural representation;
Accompanying drawing 6 is this utility model ventilating house structural representation;
Accompanying drawing 7 is this utility model water flowing room structural representation;
Accompanying drawing 8 is this utility model special connection room structural representation.
nullIn the accompanying drawings: 1 prestressing force piping lane body、2 outer layer skeletons、3 nexine skeletons、4 outer layer horizontal bars、5 outer layers indulge muscle、6 U-shaped positioning bars、7 horizontal bobbins、8 longitudinal bobbins、9 nexine horizontal bars、10 nexines indulge muscle、11 steel strand wires、12 compartment gripper shoes、13 precast support angles、14 storehouse, the left sides、Storehouse on the right of in the of 15、Storehouse on the left of in the of 16、Storehouse on the right side of in the of 17、Storehouse in 18 piping lanes、19 rhones、20 prefabricated drain pipies、21 ventilation ducts、22 bed courses、23 anchorages、24 bracing frames、25 osculums、26 discharge casings、27 drain pipies、28 running water pipes、29 regeneration water pipes、30 thermal pipes、31 refuse conveying pipes、32 communication pipes、33 cable tubes、34 light controlling devices、35 sewage pipes、36 Gas Pipe、37 power pipes、38 water-swellable adhesive tape、39 connecting boxs、40 dilatation seams、41 function rooms、42 passages、43 Surveillance center、44 special drain pipies、45 regulation and control boiled water rooms、46 drain sumps、47 rainwater imports、48 row's rain pipes、49 times row's raintank、50 water flowing rooms、51 water storehouses、52 purify sump、53 Pressure water discharging pipes、54 special connection rooms、55 ventilating houses、56 repair and maintenance centers、57 service centres、58 underground parkings、59 ecommerce supermarkets、60 rubber fastening bands、61 construction joints、62 road surface, cities、63 greenery patches planes、64 air-intake devices、65 air exhausting devices、66 water supply installations、67 self-con-tained units.
Detailed description of the invention
As shown in Figure 1, this utility model includes that cross section is rectangular prestressing force piping lane body 1 and is arranged on the outer layer skeleton 2 in prestressing force piping lane body 1 and nexine skeleton 3, horizontal bobbin 7 it is provided with inside outer layer skeleton 2, longitudinal bobbin 8 it is provided with between horizontal bobbin 7 and nexine skeleton 3, outer layer skeleton 2 is indulged muscle 5 by outer layer horizontal bar 4 and outer layer and is constituted, nexine skeleton 3 is indulged muscle 10 by nexine horizontal bar 9 and nexine and is constituted, the both sides indulging muscle 5 intersection at outer layer horizontal bar 4 and outer layer are provided with U-shaped positioning bar 6, and horizontal bobbin 7 is in the U-shaped mouth arranging U-shaped positioning bar 6.
As shown in Figure 2, laterally bobbin 7 is separately positioned in top board and the base plate of prestressing force piping lane body 1, the top board of prestressing force piping lane body 1 can be that plane can also be for arch, in horizontal bobbin 7, it is provided with the steel strand wires 11 being anchored at prestressing force piping lane body 1 both sides through stretch-draw generation prestressing force anchorage 23, in longitudinal bobbin 8, is provided with the steel strand wires 11 being anchored at prestressing force piping lane body 1 two ends through stretch-draw generation prestressing force anchorage 23.At prestressing force piping lane body 1) it is provided with four pieces of compartment gripper shoes 12 in hole, piping lane hole is separated into storehouse 18, storehouse, right side 17 and storehouse, the right 15 in storehouse, the left side 14, storehouse, left side 16 piping lane by the most successively, precast support angle 13 is separately positioned on storehouse, the left side 14 bottom left and storehouse, the right 15 bottom right, it is provided with in precast support angle 13 bottom ventilation duct 21, storehouse, left side 16 and storehouse, right side 17 and is provided with prefabricated drain pipe 20.Storehouse, the described left side 14, storehouse 18 in the piping lane of storehouse 16, left side, it is provided with rhone 19 bottom storehouse 17, right side and storehouse, the right 15, rhone 19 is connected with discharge casing 26 by osculum 25, discharge casing arranges one every a segment distance as required, piping lane body bottom does not has at discharge casing i.e. to arrange bed course 22, running water pipe 28 it is provided with in storehouse 18 in described piping lane, regeneration water pipe 29, thermal pipe 30, refuse conveying pipe 31, communication pipe 32 and cable tube 33, it is respectively arranged with sewage pipe 35 in storehouse 16, left side and storehouse, right side 17, Gas Pipe 36 it is provided with in storehouse, the left side 14, it is provided with power pipe 37 on the right in storehouse 15.
As shown in Figure 3, connected by passage 42 in the both sides of connecting box 39 and have function room 41, ventilating house 55 and Surveillance center 43, two upper lateral parts at prestressing force piping lane body 1 are provided with rainwater import 47, row's rain pipe 48 and lower row's raintank 49, sidepiece at prestressing force piping lane body 1 is provided with water flowing room 50, water storehouse 51, purify sump 52 and special drain pipe 44, sidepiece at prestressing force piping lane body 1 is additionally provided with regulation and control boiled water room 45, drain sump 46, special connection room 54, underground parking 56 and ecommerce supermarket 57, described drain sump 46 is connected with sewage pipe 35 by Pressure water discharging pipe 53.
As shown in Figure 4, the end of prestressing force piping lane body 1 is provided with connecting box 39, the junction of connecting box 39 and prestressing force piping lane body 1 is provided with dilatation seam 40, it is provided with rubber fastening band 60 in described dilatation seam 40, described lower row's raintank 49 is in vertical, it is connected with discharge casing 26 by drain pipe, then is entered in prefabricated drain pipe 20 by discharge casing 26.The middle part of described prestressing force piping lane body 1 is provided with construction joint 61, in construction joint 61, is provided with water-swellable adhesive tape 38.
As shown in Figure 5, function room 41 described in the utility model is arranged on the upper and lower of greenery patches plane 61, described rainwater import 47 is arranged on the avris portion on road surface, city 62, described row's rain pipe 48 is connected with prefabricated drain pipe 20 by discharge casing 26, function room 41 is connected with connecting box 39 by passage 42, and the osculum 27 between connecting box 39 and discharge casing 26 is provided around water-swellable adhesive tape 38.
As shown in Figure 6, ventilating house 55 described in the utility model is provided with air-intake device 64 and air exhausting device 65, is connected with ventilation duct 21 by passage 42, and the avris at passage is provided with lower row's raintank 49, is connected with row's rain pipe 48.
As shown in Figure 7, water flowing room 50 described in the utility model is arranged on the bottom of greenery patches plane 63, water supply installation 66 it is provided with in water flowing room 50, rainwater in drain pipe 27 is discharged to water flowing room 50 and water storehouse 51 by discharge casing 26, it is discharged to after precipitation purify sump 52, is returned in prestressing force piping lane body 1 by regeneration water pipe 29 again by purifying sump 52.
As shown in Figure 8, special connection room 54 described in the utility model is provided with self-con-tained unit 67, is arranged on the running water pipe 28 in prestressing force piping lane body 1, regeneration water pipe 29, thermal pipe 30, ventilation duct 21, cable tube 33, Gas Pipe 36, power pipe 37 and refuse conveying pipe 31 and is docked by the dedicated pipeline of special connection room 54 and community.
This utility model uses the plan of establishment of combined type, Gas Pipe and power pipe are optimized, and the diameter of pipe is diminished, with two pieces points of upper and lower compound settings, storehouse, the left side and the width in storehouse, the right can be reduced, reaching space, the target of reduction construction costs in Appropriate application storehouse, the support height Gas Pipe and power pipe that can also be suitable under the effect of prefabricated orientation angle brings up to reasonable altitudes, moreover it is possible to more effectively extend Gas Pipe and the service life of power pipe.
This utility model is owing to reasonably optimizing the space in piping lane hole, being arranged on the special cable of the upper space in storehouse in piping lane can be by smart city needs, it is optimized setting, the target of " worth, must use up its with " can be reached, in the case of conditions permit, in available piping lane, e-commerce channels is set up in storehouse, not only can increase the running income of underground pipe gallery, but also can be that electricity business creates a new model.
This utility model arranges function room, ventilating house, water flowing room, special docking room in the both sides of prestressing force piping lane body.The facilities such as Surveillance center have actually been carried out " system innovation ", the design that the design of piping lane agent structure should break traditions, underground pipe gallery should be regarded as a big system engineering, finally just can there is big technological break-through, could fundamentally solve " the especially big technical barrier " of square underground pipe gallery " worth and not to the utmost its with ", could be for the good condition of heavy in section underground pipe gallery creation implementation PPP pattern.

Claims (8)

  1. null1. a prestressing force divides and adds series storehouse, side drainage type underground pipe gallery,It is characterized in that: include prestressing force piping lane body (1) and the outer layer skeleton (2) being arranged in prestressing force piping lane body (1) and nexine skeleton (3),The inboard of described outer layer skeleton (2) is provided with horizontal bobbin (7),Longitudinal bobbin (8) it is provided with between horizontal bobbin (7) and nexine skeleton (3),Laterally bobbin (7) is separately positioned in top board and the base plate of prestressing force piping lane body (1),The steel strand wires (11) being anchored at prestressing force piping lane body (1) both sides through stretch-draw generation prestressing force anchorage (23) it are provided with in horizontal bobbin (7),The steel strand wires (11) being anchored at prestressing force piping lane body (1) two ends through stretch-draw generation prestressing force anchorage (23) it are provided with in longitudinal bobbin (8),At least two pieces of compartment gripper shoes (12) it are provided with in prestressing force piping lane body (1) hole,It is respectively storehouse, left side (16) and storehouse, right side (17) in middle two pieces of compartment gripper shoe (12) left and right sides,The bottom of storehouse, left side (16) and storehouse, right side (17) is provided with prefabricated drain pipe (20),The bottom of prestressing force piping lane body (1) is provided with discharge casing (26),The end of prestressing force piping lane body (1) is provided with connecting box (39),The middle part of prestressing force piping lane body (1) is provided with construction joint (61),Water-swellable adhesive tape (38) it is provided with in construction joint (61).
  2. The most according to claim 1, a kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: described outer layer skeleton (2) is indulged muscle (5) by outer layer horizontal bar (4) and outer layer and constituted, described nexine skeleton (3) is indulged muscle (10) by nexine horizontal bar (9) and nexine and is constituted, indulge, at outer layer horizontal bar (4) and outer layer, the both sides that muscle (5) intersects and be provided with U-shaped positioning bar (6), laterally bobbin (7) is arranged in the U-shaped mouth of U-shaped positioning bar (6), longitudinal bobbin (8) it is provided with in compartment gripper shoe (12), the left and right sides, prestressing force piping lane body (1) bottom is provided with precast support angle (13).
  3. A kind of prestressing force the most according to claim 1 or claim 2 divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: in prestressing force piping lane body (1) hole, be provided with four pieces of compartment gripper shoes (12), piping lane hole is separated into storehouse, the left side (14) by the most successively, storehouse (18) in storehouse (16) piping lane of left side, storehouse, right side (17) and storehouse, the right (15), precast support angle (13) is separately positioned on storehouse, the left side (14) bottom left and storehouse, the right (15) bottom right, ventilation duct (21) it is provided with in precast support angle (13), bottom, storehouse, left side (16) and storehouse, right side (17) is provided with prefabricated drain pipe (20).
  4. The most according to claim 3, a kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: in described piping lane, in storehouse (18), be provided with running water pipe (28), regeneration water pipe (29), thermal pipe (30), refuse conveying pipe (31), communication pipe (32) and cable tube (33), it is respectively arranged with sewage pipe (35) in storehouse, left side (16) and storehouse, right side (17), Gas Pipe (36) it is provided with in storehouse, the left side (14), it is provided with power pipe (37) on the right in storehouse (15), above-mentioned each pipeline is fixed in corresponding piping lane storehouse by bracing frame (24).
  5. The most according to claim 3, a kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: be provided with rhone (19) bottom storehouse (18), storehouse, right side (17) and storehouse, the right (15) in storehouse, the described left side (14), storehouse, left side (16) piping lane, rhone (19) passes through osculum (25) and connects with discharge casing (26), be provided with drain pipe (27) in the both sides of discharge casing (26), described drain pipe (27) be arranged on the outer regulation and control boiled water room (45) of prestressing force piping lane body (1) and drain sump (46) connects.
  6. The most according to claim 3, a kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: the edge in road surface, city (62) is provided with rainwater import (47), it is provided with row's rain pipe (48) and lower row's raintank (49), described discharge casing (26) and lower row's raintank (49), water storehouse (51) and purification sump (52) to be connected in the bottom of greenery patches plane (63).
  7. The most according to claim 3, a kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: be provided with dilatation seam (40) in the junction of described connecting box (39) Yu prestressing force piping lane body (1), it is provided with rubber fastening band (60) in dilatation seam (40), it is provided with construction joint (61) at the middle part of prestressing force piping lane body (1), in construction joint (61), is provided with water-swellable adhesive tape (38).
  8. The most according to claim 3, a kind of prestressing force divides and adds series storehouse, side drainage type underground pipe gallery, it is characterized in that: the sidepiece at described connecting box (39) is provided with passage (42), connecting box (39) by passage (42) respectively with function room (41), Surveillance center (43), ventilating house (55), service centre (57), special be connected room (54), underground parking (58) and ecommerce supermarket (59) connection.
CN201620182804.2U 2016-03-10 2016-03-10 Prestressing force divides and adds series side storehouse drainage type underground pipe gallery Expired - Fee Related CN205557571U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620182804.2U CN205557571U (en) 2016-03-10 2016-03-10 Prestressing force divides and adds series side storehouse drainage type underground pipe gallery

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620182804.2U CN205557571U (en) 2016-03-10 2016-03-10 Prestressing force divides and adds series side storehouse drainage type underground pipe gallery

Publications (1)

Publication Number Publication Date
CN205557571U true CN205557571U (en) 2016-09-07

Family

ID=56816909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620182804.2U Expired - Fee Related CN205557571U (en) 2016-03-10 2016-03-10 Prestressing force divides and adds series side storehouse drainage type underground pipe gallery

Country Status (1)

Country Link
CN (1) CN205557571U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115977149A (en) * 2022-12-29 2023-04-18 重庆大学 Assembled energy pipe gallery and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115977149A (en) * 2022-12-29 2023-04-18 重庆大学 Assembled energy pipe gallery and construction method thereof

Similar Documents

Publication Publication Date Title
CN102995660B (en) Multifunctional arched combined prestress underground pipe gallery for cisty and preparation process thereof
CN202227749U (en) Underground automatic parking area for track traffic
CN204151825U (en) Super-section prestressing force Urban Underground pipe gallery
CN205557571U (en) Prestressing force divides and adds series side storehouse drainage type underground pipe gallery
CN203256772U (en) Multifunctional arched combination pre-stress urban underground pipe gallery
CN202324155U (en) Adjustable corrugated prestress anti-pollution drainage culvert
CN203007978U (en) Multifunctional net-shaped combined prestressed underground pipe gallery
CN205557579U (en) Well controllable formula underground pipe gallery in storehouse is assembled to adding to prestressing force
CN205557574U (en) Underground pipe gallery with adjustable prestressing force divides to add assembles well storehouse
CN106677207A (en) Staggered type underground traffic pipe gallery car entrance and exit structure
CN202252422U (en) Multifunctional pre-stress underground draining integrated pipeline of city
CN205557563U (en) Prestressing force list adds series pipe storehouse and share formula underground pipe gallery
CN205557561U (en) Formula underground pipe gallery is chooseed for use to adding serial many storehouses to prestressing force
CN205557570U (en) Prestressing force divides and adds series pipe storehouse formula underground pipe gallery side by side
CN109469099A (en) Assembled underground pipe gallery
CN109296006A (en) The double-deck assembly concrete pipe gallery
CN205557580U (en) Well storehouse cellular -type underground pipe gallery is assembled to adding to prestressing force
CN205742466U (en) Prestressing force is to adding series rain dirt shunting underground pipe gallery
CN205557569U (en) Prestressing force divides and adds special formula underground pipe gallery in serial limit storehouse
CN204080859U (en) High-strength resistance to compression centripetal-stress Urban Underground pipe gallery
CN205557568U (en) Prestressing force divides and adds serial single storehouse drainage type underground pipe gallery
CN204491663U (en) Prestressed structure function formula underground pipe gallery combined system
CN205557572U (en) Prestressing force divides with storehouse passageway formula underground pipe gallery in series
CN204491661U (en) Upper arch prestressed structure pin-connected panel underground pipe gallery
CN209816915U (en) Double-circular shield construction comprehensive pipe gallery

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907