CN206090328U - Ball formula steel bearing installation device - Google Patents
Ball formula steel bearing installation device Download PDFInfo
- Publication number
- CN206090328U CN206090328U CN201621126776.9U CN201621126776U CN206090328U CN 206090328 U CN206090328 U CN 206090328U CN 201621126776 U CN201621126776 U CN 201621126776U CN 206090328 U CN206090328 U CN 206090328U
- Authority
- CN
- China
- Prior art keywords
- stull
- bridle iron
- ball
- support frame
- adjusting screw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model provides a ball formula steel bearing installation device, belongs to bridge construction field, including support frame and a plurality of regulation lead screw, the projection of support frame is squarely, the support frame top level on non -conterminous a set of limit mutually is provided with a plurality of stulls, mutual parallel arrangement between the stull, each aforementioned regulation lead screw is all through its upper end and stull fixed connection, the lower extreme of adjusting the lead screw is provided with the couple. Through carrying out the analytical study to current mounting process, carry out innovation and creation, through the mode that sets up the stull on the support frame, carry out the regulation of elevation through adjusting the lead screw to ball formula steel bearing, operating method is simple, and simple structure easily builds and demolishs for bearing installation quality and efficiency of construction obtain improving, shorten construction period simultaneously, save the cost, are suitable for popularization and application.
Description
Technical field
This utility model belongs to field of bridge construction, more particularly to a kind of erecting device of ball bridle iron.
Background technology
With China's expanding economy, the special construction of high ferro visitor in recent years is constantly advanced, built road and bridge is carried out
Cheng Zhong, for the positioning of bridge pad makes one of its critical process.Bridge pad is mounted in Bridge Pier or straining beam bearing
On pinner, for the device of supporting bridge superstructure.Ball bridle iron is the one kind in various bearings, in the past in construction to adopt more
Manually installed positioning is used, it is due to ball bridle iron weight greatly, manually installed to be often difficult accurately to be positioned, and the peace of bearing
Dress process is usually what is carried out under the less environment of the scope of operation, is difficult to be operated using main equipment.
The content of the invention
This utility model aims to solve the problem that the problems referred to above, there is provided a kind of easy to operate, simple structure ball bridle iron is installed
Device.
Ball bridle iron erecting device described in the utility model, including bracing frame and several adjusting screws;Described
The projection of support is square;The top horizontal on the mutual non-conterminous one group of side of support frame as described above is provided with some stulls;The horizontal stroke
It is arranged in parallel between support;Each aforementioned adjusting screw is fixedly connected by its upper end with stull, the adjusting screw
Lower end be provided with hook.When using, bracing frame is built on the pinner for installing ball bridle iron, by hanging apparatus by ball
Bridle iron is moved to pre-installed position so that ball bridle iron be located at bracing frame center, be embedded with ball bridle iron for
Lift the link of displacement;On the hook and ball bridle iron that stull above ball bridle iron passes through adjusting screw lower end
Link be connected;The absolute altitude and surface levelness of ball bridle iron are set by adjusting adjusting screw.
Ball bridle iron erecting device described in the utility model, the stull is provided with two;Two stulls set respectively
Put in the both sides of ball bridle iron, when connecting ball bridle iron by adjusting screw, on the premise of guarantee is reliable and stable, at least
The use stull of amount, reduces the deadweight of ball bridle iron erecting device, so as to also save cost.
Ball bridle iron erecting device described in the utility model, the adjusting screw includes four, in every stull
Spaced set has two;Adjusting screw in two stulls is symmetrical arranged.Stull is arranged at directly over ball bridle iron
Both sides, the structure of maximized simplified erecting device, consequently facilitating movement of the hanging apparatus for ball bridle iron;Parallel
Stull on symmetrical position adjusting screw is set, while adjusting screw spaced set in same stull so that adjust silk
Thick stick is fixed more steady for drawing high for ball bridle iron.
Ball bridle iron erecting device described in the utility model, support frame as described above is adopted28 screw-thread steels are built.
Ball bridle iron erecting device described in the utility model, the adjusting screw adopts flower basket bolt, pull bar model
For20, gaily decorated basket model M22.
Ball bridle iron erecting device described in the utility model, through being analyzed research to existing mounting process, enters
Row innovation and creation, by way of arranging stull on bracing frame, adjusted leading screw carries out the regulation of absolute altitude to ball bridle iron,
Operational approach is simple, and simple structure is easy to build and removes so that bearing installation quality and efficiency of construction are improved, while contracting
It is the short construction period, cost-effective, it is suitable to popularization and application.
Description of the drawings
Fig. 1 is the side view of ball bridle iron erecting device described in the utility model;
Fig. 2 is the top view of ball bridle iron erecting device described in the utility model;
Wherein 1- bracing frames, 2- stulls, 3- adjusting screws, 4- ball bridle irons, 5- pinners.
Specific embodiment
Below in conjunction with the accompanying drawings and embodiment is described in detail to the erecting device of ball bridle iron 4 described in the utility model.
The erecting device of ball bridle iron 4 described in the utility model, as shown in Figure 1 and Figure 2, including bracing frame 1 and four tune
Section leading screw 3;The projection of support frame as described above 1 is square, and adopts28 screw-thread steels are built;Mutually non-conterminous one group of support frame as described above 1
The top horizontal on side is provided with two stulls 2;It is arranged in parallel between the stull 2;Each aforementioned adjusting screw 3 leads to
Cross its upper end to be fixedly connected with stull 2, the lower end of the adjusting screw 3 is provided with hook.Two stulls 2 are separately positioned on ball
The both sides of bridle iron 4, in every stull 2 two are equidistantly provided with;Adjusting screw 3 in two stulls 2 is symmetrical arranged.By horizontal stroke
Support 2 is arranged at the both sides directly over ball bridle iron 4, the structure of maximized simplified erecting device, consequently facilitating hanging apparatus
For the movement of ball bridle iron 4;Symmetrical position in parallel stull 2 arranges adjusting screw 3, while adjusting screw 3
The spaced set in same stull 2 so that adjusting screw 3 is fixed more steady for drawing high for ball bridle iron 4.
When using, ball bridle iron 4 is moved to into pre-installed position by hanging apparatus, ball bridle iron 4 is being installed
Bracing frame 1 is built on pinner 5 so that ball bridle iron 4 is located at the center of bracing frame 1;The Jing of stull 2 on erecting device is adjusted
Section leading screw 3 is connected with hook with default link on ball bridle iron 4;Hanging apparatus can withdraw job site;By adjusting
Section adjusting screw 3 is arranged after the absolute altitude and surface levelness of ball bridle iron 4, and then branching standing template carries out ball bridle iron 4
Gravity type grouting, treats that grouting has the dismountable erecting device of ball bridle iron 4 described in the utility model in some strength rear, completes
The installation of ball bridle iron 4.
The installation steps of ball bridle iron 4 described in the utility model are summarised as:Ball bridle iron 4 is put into into pad using crane
In the anchor hole of stone 5 → alignment axis carry out Primary Location → top of 1 → bracing frame of placements bracing frame 1 and lay stull 2 → hang regulation
Leading screw 3 → hang hook → be attached adjusting screw 3 and hook using the bolt eye of ball bridle iron 4(Profit when length is inadequate
Being attached with 2.0mm steel tendons carries out coarse adjustment)→ using level gauge ball bridle iron 4 is adjusted to designed elevation → be adjusted to design
Re-calibrate after absolute altitude be fixed using timber wedge after ball 4 axis of bridle iron → correction → formwork is using gravity type grouting → treat
Grouting agent reaches striking and its template after some strength.
Claims (5)
1. a kind of ball bridle iron erecting device, including bracing frame(1)With several adjusting screws(3);It is characterized in that:It is described
Bracing frame(1)Projection be square;Support frame as described above(1)Mutually the top horizontal on non-conterminous one group of side is provided with some stulls
(2);The stull(2)Between it is arranged in parallel;Each aforementioned adjusting screw(3)By its upper end and stull(2)Gu
Fixed connection, the adjusting screw(3)Lower end be provided with hook.
2. ball bridle iron erecting device according to claim 1, it is characterised in that:The stull(2)It is provided with two.
3. ball bridle iron erecting device according to claim 2, it is characterised in that:The adjusting screw(3)Include
Four, every stull(2)On be equidistantly provided with two;Two stulls(2)On adjusting screw(3)It is symmetrical arranged.
4. ball bridle iron erecting device according to claim 3, it is characterised in that:Support frame as described above(1)Using28
Screw-thread steel is built.
5. ball bridle iron erecting device according to claim 4, it is characterised in that:The adjusting screw(3)Using flower
Basket bolt, pull bar model20, gaily decorated basket model M22.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621126776.9U CN206090328U (en) | 2016-10-17 | 2016-10-17 | Ball formula steel bearing installation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621126776.9U CN206090328U (en) | 2016-10-17 | 2016-10-17 | Ball formula steel bearing installation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206090328U true CN206090328U (en) | 2017-04-12 |
Family
ID=58483445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621126776.9U Expired - Fee Related CN206090328U (en) | 2016-10-17 | 2016-10-17 | Ball formula steel bearing installation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206090328U (en) |
-
2016
- 2016-10-17 CN CN201621126776.9U patent/CN206090328U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207986489U (en) | Hang regulating device in large diameter pile foundation steel reinforcement cage aperture | |
CN101428308B (en) | Horizontal pressure straightener | |
CN105040591B (en) | A kind of positioner of Wavelike steel webplate and its localization method | |
CN208778012U (en) | Tunnel cable ditch formwork hoisting movable type trolley | |
CN208934399U (en) | A kind of rectangular section pier stud constructing device | |
CN201567787U (en) | Form-traveler steel formwork | |
CN206090328U (en) | Ball formula steel bearing installation device | |
CN207847086U (en) | A kind of tall and big beam form support frame | |
CN207375586U (en) | A kind of hanging apparatus of prefabricated assembled concrete Side fascia | |
CN206530077U (en) | A kind of support frame | |
CN206128663U (en) | Adjusting device of steel construction steel column construction installation | |
CN206625585U (en) | A kind of carrying pole device of purlin installation | |
CN204491613U (en) | A kind of steel post deviation correcting device | |
CN203807946U (en) | Track beam erecting device | |
CN211034970U (en) | Down-the-hole drill jack-up hoist and mount auxiliary device | |
CN210917046U (en) | Device for adjusting height and balance of outer side template of guardrail | |
CN210737374U (en) | Bridge deck concrete pavement construction platform | |
CN113309256A (en) | Construction device and construction method for prefabricated shear wall with post-pouring section | |
CN207552941U (en) | Tooth block tensioning equipment mobile formwork on roof box in a kind of cast-in-situ continuous beam | |
CN107034788B (en) | A kind of suspender tension device and its construction method | |
CN206457725U (en) | It is a kind of to be used for the overall device transferred and remove dragging suspension basket | |
CN201318129Y (en) | Headframe adjusting base | |
CN205369921U (en) | Template roof beam strutting arrangement with adjustable | |
CN206142668U (en) | Girder and end beam connection structure of bridge crane crane span structure | |
CN213234327U (en) | Adjustable support for steel structure installation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170412 Termination date: 20201017 |
|
CF01 | Termination of patent right due to non-payment of annual fee |