A kind of steel post deviation correcting device Download PDF

Info

Publication number
CN204491613U
CN204491613U CN201520155816.1U CN201520155816U CN204491613U CN 204491613 U CN204491613 U CN 204491613U CN 201520155816 U CN201520155816 U CN 201520155816U CN 204491613 U CN204491613 U CN 204491613U
Authority
CN
China
Prior art keywords
semicircular ring
correcting device
steel
deviation correcting
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520155816.1U
Other languages
Chinese (zh)
Inventor
管中建
徐忠民
张家春
桂加升
张福军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Academy of building Limited by Share Ltd
Original Assignee
Jiangsu Jianyuan Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Jianyuan Construction Co Ltd filed Critical Jiangsu Jianyuan Construction Co Ltd
Priority to CN201520155816.1U priority Critical patent/CN204491613U/en
Application granted granted Critical
Publication of CN204491613U publication Critical patent/CN204491613U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model discloses a kind of steel post deviation correcting device, comprise: pile foundation frame, steel post and deviation correcting device, described deviation correcting device comprises: semicircular ring, jack, push pedal and steel clamp sheet, the two ends of described semicircular ring are respectively arranged with an otic placode, the center of described otic placode offers screwed hole, described semicircular ring adopts two symmetrical semicircular ring, this semicircular ring is used for outside jack being fixed on pile foundation frame, one end of described jack is secured by bolts in semicircular ring, the other end of jack is fixed on the side of push pedal by hinge means, described steel clamp sheet is secured by bolts in the opposite side of push pedal, the quantity of described steel clamp sheet is two panels, two panels steel clamp sheet is arranged at the two ends of push pedal.By the way, the utility model can be rectified a deviation to steel post, facilitates the later stage to support and wears reinforcing bar, improve the construction quality of steel post.

Description

A kind of steel post deviation correcting device
Technical field
The utility model relates to building field, particularly relates to a kind of steel post deviation correcting device.
Background technology
For traditional construction stand column pile, steel post is sling by general employing castinplace pile pile foundation suspension hook, then righting, alignment is carried out by the range estimation of two to three workmans, but when steel post drops to below ground, steel post often rotates, and causes the reserving hole of steel post not have and supports parallel, during construction in later period concrete support, reinforcing bar cannot pass from steel post, thus reduces construction quality.The technical requirements of conventional construction method to construction worker is high; drop to below ground once steel post to deflect; just be difficult to realize to steel post correction; even if steel post is promoted to correction position, ground to issue again; probably still rotate in decline process; it is obviously unrealistic for repeatedly promoting correction steel post position, therefore engineering usually there will be steel post and causes reinforcing bar to pass steel post with support oblique.
Utility model content
The technical problem that the utility model mainly solves is to provide a kind of steel post deviation correcting device, can rectify a deviation to steel post, facilitates the later stage to support and wears reinforcing bar, improve the construction quality of steel post.
For solving the problems of the technologies described above, the technical scheme that the utility model adopts is: provide a kind of steel post deviation correcting device, comprise: pile foundation frame, steel post and deviation correcting device, described deviation correcting device comprises: semicircular ring, jack, push pedal and steel clamp sheet, the two ends of described semicircular ring are respectively arranged with an otic placode, the center of described otic placode offers screwed hole, described semicircular ring adopts two symmetrical semicircular ring, this semicircular ring is used for outside jack being fixed on pile foundation frame, one end of described jack is secured by bolts in semicircular ring, the other end of jack is fixed on the side of push pedal by hinge means, described steel clamp sheet is secured by bolts in the opposite side of push pedal, the quantity of described steel clamp sheet is two panels, two panels steel clamp sheet is arranged at the two ends of push pedal.
Preferably, described two semicircular ring are symmetrically secured by bolts in the outside of pile foundation frame, and jack through the screwed hole at otic placode center, semicircular ring two ends, thus is fixed on the outside of pile foundation frame by described bolt.
Preferably, the jack quantity of each deviation correcting device is two, and these two jack are symmetrically fixed on the center line of semicircular ring, adopts two symmetrically arranged jack, ensure that the stability be connected between push pedal with semicircular ring.
Preferably, described push pedal evenly offers several locating holes, can according to the different cross section size of steel post, the distance between unrestricted choice steel clamp sheet.
Preferably, described steel clamp sheet is made up of at least two telescopic expansion plates.
The beneficial effects of the utility model are: 1, when steel post is more than ground, without the need to the expansion plate of flexible steel clamp sheet, directly blocked by steel post by steel clamp sheet, then by controlling, jack is flexible rectifies a deviation to steel post, controls simply, convenient, efficiency is high; 2, when steel post drops to below ground, the expansion plate of steel clamp sheet is launched, then by expansion plate, steel post is blocked, then steel post is rectified a deviation, facilitate the later stage to support and wear reinforcing bar, improve the construction quality of steel post.
Accompanying drawing explanation
Fig. 1 is the top view of a kind of steel post deviation correcting device one of the utility model preferred embodiment;
Fig. 2 is the front view of shown Fig. 1;
Fig. 3 is the connection diagram of described push pedal and steel clamp sheet;
Fig. 4 is the left view of shown Fig. 3;
Fig. 5 is the top view of shown Fig. 3;
Fig. 6 is the structural representation of described steel clamp sheet;
Fig. 7 is the left view of shown Fig. 6;
Fig. 8 is the assembling original state schematic diagram of described deviation correcting device and steel post;
Fig. 9 is described deviation correcting device and steel post working state schematic representation;
In accompanying drawing, the mark of each parts is as follows: 1, semicircular ring, and 2, jack, 3, push pedal, 4, steel clamp sheet, 5, bolt, 6, hinge means, 7, locating hole, 8, pile foundation frame, 9, steel post, 11, otic placode, 12, screwed hole, 41, expansion plate.
Detailed description of the invention
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described in detail, to make advantage of the present utility model and feature can be easier to be readily appreciated by one skilled in the art, thus more explicit defining is made to protection domain of the present utility model.
Refer to Fig. 1 to Fig. 9, the utility model embodiment comprises:
A kind of steel post deviation correcting device, comprise: pile foundation frame 8, steel post 9 and deviation correcting device, described deviation correcting device comprises: semicircular ring 1, jack 2, push pedal 3 and steel clamp sheet 4, the two ends of described semicircular ring 1 are respectively arranged with an otic placode 11, the center of described otic placode 11 offers screwed hole 12, described semicircular ring 1 adopts two symmetrical semicircular ring, this semicircular ring 1 is for being fixed on the outside of pile foundation frame 8 by jack 2, semicircular ring 1 is fixed on by bolt 5 in one end of described jack 2, the other end of jack 2 is fixed on the side of push pedal 3 by hinge means 6, described steel clamp sheet 4 is fixed on the opposite side of push pedal 3 by bolt 5, the quantity of described steel clamp sheet 4 is two panels, two panels steel clamp sheet 4 is arranged at the two ends of push pedal 3.
As Fig. 5, described push pedal 3 evenly offers several locating holes 7, can according to the different cross section size of steel post 9, the distance between unrestricted choice steel clamp sheet 4.
As shown in Figure 6, Figure 7, in the present embodiment, the quantity of expansion plate 41 is 3, by controlling the flexible length controlling steel clamp sheet 4 of expansion plate 41.
In the utility model, the quantity of deviation correcting device is two, and these two deviation correcting devices are arranged at the symmetrical two ends of steel post 9 respectively, are adjusted by the angle of jack 3 pairs of steel posts 9, makes steel post 9 hole parallel with the main muscle direction of support.
Work progress of the present utility model is as follows: 1, be arranged on the lateral surface of pile foundation frame 8 by bolt 5 by deviation correcting device, exceeds board pile foundation frame 8 about 30 centimeters, and adjustment position is fixed; 2, transferring steel post 9 to pile foundation frame 8 position, by regulating jack 2 to stretch, tentatively determining the orientation of steel post 9; 3, continue to transfer steel post 9 to design elevation, if deflection appears in steel post 9 in decentralization process, just steel clamp sheet 4 is extended and block steel post 9, and it is finely tuned, make the hole of steel post 9 parallel with the main muscle direction of support.
The foregoing is only embodiment of the present utility model; not thereby the scope of the claims of the present utility model is limited; every utilize the utility model manual and accompanying drawing content to do equivalent structure or equivalent flow process conversion; or be directly or indirectly used in other relevant technical fields, be all in like manner included in scope of patent protection of the present utility model.

Claims (5)

1. a steel post deviation correcting device, comprise: pile foundation frame, steel post and deviation correcting device, it is characterized in that, described deviation correcting device comprises: semicircular ring, jack, push pedal and steel clamp sheet, the two ends of described semicircular ring are respectively arranged with an otic placode, the center of described otic placode offers screwed hole, described semicircular ring adopts two symmetrical semicircular ring, this semicircular ring is used for outside jack being fixed on pile foundation frame, one end of described jack is secured by bolts in semicircular ring, the other end of jack is fixed on the side of push pedal by hinge means, described steel clamp sheet is secured by bolts in the opposite side of push pedal, the quantity of described steel clamp sheet is two panels, two panels steel clamp sheet is arranged at the two ends of push pedal.
2. a kind of steel post deviation correcting device according to claim 1, is characterized in that, described two semicircular ring are symmetrically secured by bolts in the outside of pile foundation frame, and described bolt is through the screwed hole at otic placode center, semicircular ring two ends.
3. a kind of steel post deviation correcting device according to claim 1, is characterized in that, the jack quantity of each deviation correcting device is two, and these two jack are symmetrically fixed on the center line of semicircular ring.
4. a kind of steel post deviation correcting device according to claim 1, is characterized in that, described push pedal evenly offers several locating holes.
5. a kind of steel post deviation correcting device according to claim 1, is characterized in that, described steel clamp sheet is made up of at least two telescopic expansion plates.
CN201520155816.1U 2015-03-19 2015-03-19 A kind of steel post deviation correcting device Active CN204491613U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520155816.1U CN204491613U (en) 2015-03-19 2015-03-19 A kind of steel post deviation correcting device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520155816.1U CN204491613U (en) 2015-03-19 2015-03-19 A kind of steel post deviation correcting device

Publications (1)

Publication Number Publication Date
CN204491613U true CN204491613U (en) 2015-07-22

Family

ID=53570914

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520155816.1U Active CN204491613U (en) 2015-03-19 2015-03-19 A kind of steel post deviation correcting device

Country Status (1)

Country Link
CN (1) CN204491613U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108914999A (en) * 2018-07-28 2018-11-30 江苏地基工程有限公司 Structure is repaired in correction for tilting pile foundation
CN109386000A (en) * 2018-11-29 2019-02-26 中交路桥华南工程有限公司 Steel pile casting decentralization installation deviation correcting device and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108914999A (en) * 2018-07-28 2018-11-30 江苏地基工程有限公司 Structure is repaired in correction for tilting pile foundation
CN108914999B (en) * 2018-07-28 2020-07-24 江苏地基工程有限公司 Deviation rectifying and repairing structure for inclined pile foundation
CN109386000A (en) * 2018-11-29 2019-02-26 中交路桥华南工程有限公司 Steel pile casting decentralization installation deviation correcting device and construction method

Similar Documents

Publication Publication Date Title
CN203821867U (en) Shear wall body assembling and aligning device
CN204252284U (en) Built-in fitting bracing means
CN204491613U (en) A kind of steel post deviation correcting device
CN103982049B (en) Shear wall body assembling machine straightening device
CN204126077U (en) A kind of temporary fastening device for prefabricated panel and steel column connection
CN206468030U (en) A kind of isolated beam combined type faces bound defence rail
CN205046843U (en) Reinforcing apparatus's stair template of marking time in middle of installation
CN204753374U (en) Equipment bridge railing
CN212078774U (en) Load-bearing tripod
CN203361607U (en) Adjustable oblique jacking
CN204510814U (en) Beam for building jacking
CN205935720U (en) Steel truss frame that slides
CN207277830U (en) The jacking structure of formwork erection
CN202148494U (en) Formwork support for bridge
CN206233539U (en) A kind of cantilever for tall building construction
CN105586830A (en) Bridge template support
CN207079615U (en) A kind of roller-coaster built-in fitting support system
CN206053310U (en) A kind of adjustable falsework
CN206233540U (en) Regulation hoisting type elevator job platform
CN205558256U (en) Two concrete construction die carrier systems that prop separation
CN205476444U (en) Light -duty support post based on low level jacking die carrier system
CN205531257U (en) Installing support for building site
CN204826220U (en) Location built -in fitting with U type groove
CN204418439U (en) Adjusting part bottom a kind of out-hung panel
CN109457874A (en) Bar-spacing set control device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: Suzhou District South East Suzhou city Jiangsu province 215000 New Building No. 10

Patentee after: Jiangsu Academy of building Limited by Share Ltd

Address before: Suzhou District South East Suzhou city Jiangsu province 215000 No. 10 (new building)

Patentee before: Jiangsu Jianyuan Construction Co., Ltd.

CP03 Change of name, title or address