CN205558256U CN201620359811.5U CN201620359811U CN205558256U CN 205558256 U CN205558256 U CN 205558256U CN 201620359811 U CN201620359811 U CN 201620359811U CN 205558256 U CN205558256 U CN 205558256U
Authority
CN
China
Prior art keywords
support
maintenance
vertical rod
frame
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620359811.5U
Other languages
Chinese (zh)
Inventor
马荣全
苗冬梅
胡成佑
秦聪伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201620359811.5U priority Critical patent/CN205558256U/en
Application granted granted Critical
Publication of CN205558256U publication Critical patent/CN205558256U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model relates to a two concrete construction die carrier systems that prop separation, include: the maintenance of supporting under the frame template is propped, the maintenance is propped and is established stabilizer blade, the edge of being fixed in the holding surface including immediately regulation pole setting that the stabilizer blade can be adjusted from top to bottom and locate support frame on the holding surface, and support in operation under the frame template is propped, the operation is propped to establish immediately and is fixed in the holding surface and with the crisscross setting is propped in the maintenance. On the frame template behind the concreting, get into the concrete maintenance during stage, prop the operation to demolish and carry out the cyclic utilization that is under construction, only stay the maintenance to prop the support as frame template and concrete, the one side can satisfy the requirement of the support intensity of concrete maintenance, and on the other hand is still quick to carry out cyclic utilization with the pole setting, has effectively reduced the use amount of job site pole setting, the further construction cost that has saved.

Description

The concrete construction formwork system that two supports separate
Technical field
This utility model relates to the realm of building construction, refers in particular to the concrete construction mould bases that a kind of two supports separate System.
Background technology
Template is a large amount of important tool used in construction.China's traditional handicraft uses plywood to do Template, flitch is decided, secondary beam, and low bearing capacity is fragile, and lumber consumption is big, and operating efficiency is low, Artificial consuming is many, it is impossible to early tear open, and security incident takes place frequently, and is increasingly denounced by industry.
Owing to conventional template exists above-mentioned various problem, frame template is adopted in work progress Ratio increasing.The structure of frame template is to arrange frame knot in the back side surrounding of stencil body Structure, it is simple to the splicing between template connects, and template also serves the effect of reinforcing.
In work progress, for guaranteeing the stability of strutting system of frame template, need under frame template Support substantial amounts of vertical rod, provide support force by vertical rod for frame template.Substantial amounts of vertical rod is supported in limit Need under frame template could remove when concrete setting reaches form removal requirement so that vertical rod recycles Cycle is long, and job site needs to be equipped with substantial amounts of vertical rod building materials could meet use, adds and is constructed into This.
Utility model content
The purpose of this utility model is to overcome the defect of prior art, it is provided that it is mixed that a kind of two supports separate Solidifying soil construction formwork system, solves job site vertical rod and recycles cycle length and need to be equipped with substantial amounts of vertical Bar building materials and bring increase construction cost problem.
The technical scheme realizing above-mentioned purpose is:
The concrete construction formwork system that a kind of two supports of this utility model separate, including:
Being supported in the maintenance support under frame template, described maintenance support includes erecting is fixed on supporting surface Leg, can the regulation vertical rod of up-down adjustment and be located at the support on described supporting surface along described leg Frame, frame template described in described regulation vertical rod top braces, support frame as described above is sheathed on described regulation and stands On bar, by screw togather wear support frame as described above and against described regulation vertical rod top bracing member realize with described Being fastenedly connected of regulation vertical rod;And
Being supported in the operation support under described frame template, described operation support erects is fixed on described support Face and with described maintenance support be crisscross arranged.
Use operation support and maintenance to support the bottom support as frame template, and friendship is supportted in operation support and maintenance Wrong setting, on frame template after casting concrete, when entering the concrete curing stage, will operation Recycling of carrying out constructing is removed in support, only stays maintenance to support as frame template and the support of concrete, On the one hand disclosure satisfy that the requirement of the support strength of concrete curing, the most quickly by vertical rod It is circulated utilization, effectively reduces the usage amount of job site vertical rod, further save construction Cost.
Further improvement is that of the concrete construction formwork system that this utility model two support separates, described Leg includes base and the support bar being erected on base, and described base is fixing with described supporting surface even Connect.
Further improvement is that of the concrete construction formwork system that this utility model two support separates, described Bracing frame include being sheathed on the sleeve pipe in described regulation vertical rod and with described telescopic joint multiple diagonal braces Bar, described hound skewed horizontal load is on described supporting surface.
Further improvement is that of the concrete construction formwork system that this utility model two support separates, described The top end of described leg is located at by sleeve pipe.
Further improvement is that of the concrete construction formwork system that this utility model two support separates, described The screw of the described top bracing member of multiple connection is offered on sleeve pipe.
Further improvement is that of the concrete construction formwork system that this utility model two support separates, described Top bracing member is flat foot bolt.
Accompanying drawing explanation
Fig. 1 is that the concrete construction formwork system that this utility model two support separates is supported in frame template Structural representation.
Fig. 2 is that the concrete construction formwork system that this utility model two support separates waters on frame template Build the structural representation after concrete.
Fig. 3 is that in the concrete construction formwork system that this utility model two support separates, the structure of maintenance support is shown It is intended to.
Fig. 4 is the decomposition knot of maintenance support in the concrete construction formwork system that this utility model two support separates Structure schematic diagram.
Detailed description of the invention
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
This utility model provides the concrete construction formwork system that a kind of two supports separate, and is supported in frame The bottom of template, opposite side frame template is played a supporting role.Refering to Fig. 1 and Fig. 2, of the present utility model The concrete construction formwork system that two supports separate includes maintenance support and the operation support of supporting frame template, Before concreting, now walk about on template owing to having workmen so that frame template Have the phenomenon of movement, so the stability requirement to template is higher, supportted and operate support by maintenance altogether With carrying out supporting frame template, it can be ensured that the stability of strutting system of frame template.Pour mixed in frame template After solidifying soil, being put into the concrete curing stage, now concrete and frame template are in standing shape State, no one person walks about on template, so the support force required by the vertical rod bottom template is relatively Little, now operation support dismounting is circulated use, retains maintenance support supporting frame template and concrete, Be enough to supporting frame template until concrete setting by maintenance support, more together rest care-supporting during form removal and tear open Except.This utility model improves the cyclic utilization rate of operation support, decreases job site and is equipped with vertical The consumption of bar, reduces construction cost.The coagulation below in conjunction with the accompanying drawings this utility model two support separated Soil construction formwork system illustrates.
Refering to Fig. 1, it is shown that the concrete construction formwork system that this utility model two support separates is supported in The structural representation of frame template.Below in conjunction with Fig. 1, the concrete that this utility model two support is separated Construction formwork system illustrates.
As it is shown in figure 1, the concrete construction formwork system that this utility model two support separates includes that maintenance is supportted 20 are supported under frame template 12 with operation support 30, maintenance support 20, and are erected on supporting surface 11 On, operation support 30 is also supported on frame template 12, and erects and be fixed on supporting surface 11, Operation support 30 and maintenance support 20 are crisscross arranged.It is crisscross arranged by maintenance support 20 and operation support 30, On frame template 12 after casting concrete, operation support 30 dismounting can be made to continue cycling through With, as in figure 2 it is shown, after concrete 13 pours, stay maintenance to support on frame template 12 20 are supported frame template 12 and concrete 13, until after concrete 13 reaches some strength, When removing frame template 12, another with removing maintenance support 20.
Shown in Fig. 3 and Fig. 4, maintenance support 20 includes leg 21, regulation vertical rod 23 and supports Frame 22, this leg 21 erects and is fixed on supporting surface 11, and regulation vertical rod 23 can be upper and lower along leg 21 Regulation, to adjust bearing height, the top braces frame template of this regulation vertical rod 23, bracing frame 22 Propping up and be located on supporting surface 11, bracing frame 22 is set in regulation vertical rod 23, props up by screwing togather to wear Support 22 top bracing member against regulation vertical rod 23 realize and regulate being fastenedly connected of vertical rod 23.
By arranging a bracing frame 22 being located on supporting surface 11, the structure increasing maintenance support 20 is strong Degree and steadiness, to meet the requirement of the support strength of frame template.Regulation vertical rod 23 is designed as Can move up and down to regulate height along leg 21 so that the adjusting position of regulation vertical rod 23 is positioned at regulation The bottom of vertical rod 23, this adjusting position, near supporting surface 11, can facilitate operator to be adjusted Operation, it is to avoid adjusting position is positioned at the regulation inconvenience of eminence and needs by step ladder isostructural existing As.Maintenance support 20 has regulatory function, and easy to adjust, the advantage that structural stability is good.
Leg 21 includes base 211 and support bar 212, and base 211 is fixedly connected on supporting surface On 11, supporting surface 11 can be ground, it is also possible to be flooring.Support bar 212 erects at base 211 On, support bar 212 is the basis that regulation vertical rod 23 provides regulation.Regulation vertical rod 23 and support bar Regulative mode between 212, can be any one in existing regulative mode, both can make spiral shell The regulative mode of stricture of vagina, is i.e. provided with, on regulation stock 21 and leg 21, the screw thread matched, passes through spiral shell The incompatible regulation realizing height.The mode of sheathed connection can also be made, as shown in Figure 4, at Fig. 4 In shown structure, regulation vertical rod 23 through bracing frame 22 and is set on support bar 212, regulation Vertical rod 23 can move up and down along leg 21, is fixed by bracing frame 22 when fixing.
The support bar 212 of leg 21 can be short steel pipes, and length is less than one meter, regulates vertical rod 212 For long steel pipe, length can select according to the needs of bearing height.
As shown in Figure 3 and Figure 4, bracing frame 22 includes sleeve pipe 221, hound 222 and shores Part 223, sleeve pipe 221 is set in regulation vertical rod 23, and hound 222 is connected with sleeve pipe 221, and Hound 222 is multiple, and hound 222 skewed horizontal load is on supporting surface 11, by hound 222 Installing fixing by sleeve pipe 221, sleeve pipe 221 has again certain restriction effect to regulation vertical rod 23, anti- Stop toppling of regulation vertical rod 23.
Further, top bracing member 223 screws togather and wears sleeve pipe 221, and top bracing member 223 wears sleeve pipe 221 End against regulation vertical rod 23, by top bracing member 223 lean fasten regulation vertical rod 23, right Regulation vertical rod 23 also acts fixing effect.
The sleeve pipe 221 of bracing frame 22 is set in the top end of corresponding support bar 211 in regulation vertical rod 23, Support bar 211 and the firm of regulation vertical rod 23 are all played certain reinforcement effect.
Sleeve pipe 221 offers the screw of multiple connection top bracing member 223, multiple top bracing member is set 223, the stability of regulation vertical rod 23 can be strengthened.This top bracing member 223 preferably flat foot bolt.
It is preferred that the operation support 30 in this utility model is also height-adjustable structure, such as grasp Making support 30 is two sleeve pipes that are setting up and down and that mutually screw togather, realizes height by being screwed together Regulation, to adapt to the support of the frame template 12 of differing heights.As it is shown in figure 1, this utility model The concrete construction formwork systems that separate of two supports be supported in the bottom of frame template 12, frame template 12 splicings are arranged, and have installed multiple adjustable support structure in the bottom of frame template 12, including behaviour Make support 30 and maintenance support 20, operation support 30 and maintenance support 20 and be adjustable for height support bar, energy Enough adapt to the frame template 12 of differing heights.After having poured concrete on frame template 12, as Shown in Fig. 2, dismantling operation becomes 30, retains maintenance and supports 20 supporting frame templates 12 and concrete 13, 20 stabilized structures are supportted in maintenance, it is possible to meet the support maintenance demand of concrete, this utility model one side Face improves the cyclic utilization rate of operation support, on the other hand also ensure that the firm supporting that maintenance is supportted, real Show solid and reliable supporting construction.
Having the beneficial effect that of the concrete construction formwork system that this utility model two support separates
Use operation support and maintenance to support the bottom support as frame template, and friendship is supportted in operation support and maintenance Wrong setting, on frame template after casting concrete, when entering the concrete curing stage, will operation Recycling of carrying out constructing is removed in support, only stays maintenance to support as frame template and the support of concrete, On the one hand disclosure satisfy that the requirement of the support strength of concrete curing, the most quickly by vertical rod It is circulated utilization, effectively reduces the usage amount of job site vertical rod, further save construction Cost.
Scalable regulates vertical rod sleeve be located on leg, adjusting position is provided close at supporting surface, side Just regulating operation, the regulation for supporting construction brings facility.For guaranteeing to regulate the stability of vertical rod, Sheathed bracing frame in regulation vertical rod, improves the steadiness of supported rod erecting by bracing frame.
Above in association with accompanying drawing embodiment, this utility model is described in detail, ordinary skill in this area This utility model can be made many variations example by personnel according to the above description.Thus, some in embodiment Details should not constitute restriction of the present utility model, and this utility model will define with appended claims Scope is as protection domain of the present utility model.

Claims (6)

1. the concrete construction formwork system that a support separates, it is characterised in that including:
Being supported in the maintenance support under frame template, described maintenance support includes erecting is fixed on supporting surface Leg, can the regulation vertical rod of up-down adjustment and be located at the support on described supporting surface along described leg Frame, frame template described in described regulation vertical rod top braces, support frame as described above is sheathed on described regulation and stands On bar, by screw togather wear support frame as described above and against described regulation vertical rod top bracing member realize with described Being fastenedly connected of regulation vertical rod;And
Being supported in the operation support under described frame template, described operation support erects is fixed on described support Face and with described maintenance support be crisscross arranged.
The concrete construction formwork system that two supports the most as claimed in claim 1 separate, its feature exists In, described leg includes base and the support bar being erected on described base, described base and described Support face is fixing to be connected.
The concrete construction formwork system that two supports the most as claimed in claim 1 separate, its feature exists Include being sheathed on the sleeve pipe in described regulation vertical rod and telescopic joint many with described in, support frame as described above Individual hound, described hound skewed horizontal load is on described supporting surface.
The concrete construction formwork system that two supports the most as claimed in claim 3 separate, its feature exists In, the top end of described leg is located at by described sleeve pipe.
The concrete construction formwork system that two supports the most as claimed in claim 3 separate, its feature exists In, described sleeve pipe offers the screw of the described top bracing member of multiple connection.
6. the concrete construction formwork system that two supports as described in claim 1 or 5 separate, its feature Being, described top bracing member is flat foot bolt.
CN201620359811.5U 2016-04-26 2016-04-26 Two concrete construction die carrier systems that prop separation Expired - Fee Related CN205558256U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620359811.5U CN205558256U (en) 2016-04-26 2016-04-26 Two concrete construction die carrier systems that prop separation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620359811.5U CN205558256U (en) 2016-04-26 2016-04-26 Two concrete construction die carrier systems that prop separation

Publications (1)

Publication Number Publication Date
CN205558256U true CN205558256U (en) 2016-09-07

Family

ID=56807691

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620359811.5U Expired - Fee Related CN205558256U (en) 2016-04-26 2016-04-26 Two concrete construction die carrier systems that prop separation

Country Status (1)

Country Link
CN (1) CN205558256U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113266401A (en) * 2021-05-17 2021-08-17 中交一公局集团有限公司 Waterproof board operation trolley for tunnel construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113266401A (en) * 2021-05-17 2021-08-17 中交一公局集团有限公司 Waterproof board operation trolley for tunnel construction

Similar Documents

Publication Publication Date Title
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN105888236B (en) frame template system
CN106088587A (en) A kind of Combined formwork support system
CN106337559B (en) The morning of formwork-support tears support system and its application method open
CN108756241A (en) Overhanging slab form installs device on the outside of a kind of shear wall
CN105781100A (en) Template component for sidewall of subway station
CN204001731U (en) A kind of shuttering supporting vertical rod base fixing device
CN209723607U (en) Adjustable entirety stair tread formwork
CN203296379U (en) Formwork beam supporting device convenient to clamp and adjustable in height
CN205558256U (en) Two concrete construction die carrier systems that prop separation
CN202055517U (en) Thin-walled cylinder pouring formwork supporting and lifting device
CN206888904U (en) A kind of cat ladder for bridge pier column construction
CN208379847U (en) A kind of building prefabrication wallboard concrete pouring structure
CN209338999U (en) A kind of telescopic overhanging support
CN205558259U (en) A adjustable bearing structure for frame template
CN205421971U (en) Assembly type structure outer wall bearing structure
CN104563515A (en) Template bracing structure for ultrahigh shear wall and construction method thereof
CN103321406B (en) A kind of support system of tall and big floor template
CN213710354U (en) Be used for independent support frame body of steel bar truss building carrier plate
CN205314539U (en) Large -scale cantilever type combination steel form
CN215254596U (en) Wall column template device capable of being spliced
CN209323685U (en) Girder steel concrete column connected node
CN107724672A (en) A kind of steel construction skyscraper cast-in-situ floor formwork support structure
CN203640313U (en) Floor beam installing support
CN208949829U (en) A kind of truss-like cantilever form

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907