CN201567787U - Form-traveler steel formwork - Google Patents
Form-traveler steel formwork Download PDFInfo
- Publication number
- CN201567787U CN201567787U CN200920216459XU CN200920216459U CN201567787U CN 201567787 U CN201567787 U CN 201567787U CN 200920216459X U CN200920216459X U CN 200920216459XU CN 200920216459 U CN200920216459 U CN 200920216459U CN 201567787 U CN201567787 U CN 201567787U
- Authority
- CN
- China
- Prior art keywords
- template
- interior
- formwork
- hanging basket
- exterior sheathing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model relates to the technical field of railway or highway bridge construction, in particular to a form-traveler steel formwork which is used along with a form traveler when cantilever type construction is adopted to cast continuous beams. The form-traveler steel formwork comprises an outer formwork, an inner top formwork, an inner formwork support and a bottom formwork, the inner top formwork and the inner formwork support are arranged in the middle of the outer formwork, the bottom formwork is arranged on the bottom of the outer formwork, split bolts are arranged on the top of the outer formwork, and the inner top formwork is mounted upon the inner formwork support. Compared with the prior art, the utility model has the advantages of simple structure, convenient mounting, construction saving, wide application range and low cost.
Description
Technical field
The utility model relates to the technical field of construction of railway or highway bridge, during particularly a kind of employing cantilevered construction casting continuous beam and the matching used Hanging Basket steel form of Hanging Basket.
Background technology
The Hanging Basket steel form is the railway of large span and a kind of indispensable equipment that highway cantilevered continuous placing bridge is used, when adopting Hanging Basket to build Longspan Bridge, be not subjected to the influence of factors such as bridge pier height, river be dark, directly extend construction to striding the footpath direction piecemeal from the bridge pier top of having built up.This pouring construction process has not only been simplified the difficulty of construction of Longspan Bridge, and can save duration and the expense of setting up full framing etc. greatly, and extremely unit in charge of construction welcomes.And in the prior art, the structure of Hanging Basket steel form is more complicated all generally, admittedly be difficult to satisfy the requirement that the disconnected cross section of bridge Continuous beam design constantly changes.Present domestic different kinds of roads are in the construction of continuous beam, when rectangle hole width size changes gradually in beam face, beam bottom width degree and the beam, mostly adopt wooden form or take between two steel forms down to go into the way of concentric reducer plank, not only the presentation quality to bridge has certain influence, and the wave given up a large amount of timber and the preparation man-hour.Retrieved a large amount of interrelated datas, do not seen so far at home and utilize direct solution to this problem of steel form or relevant patent.
Summary of the invention
The purpose of this utility model is to overcome deficiency of the prior art, by a kind of and simple in structure, easy for installation, construction saving, wide accommodation and lower-cost novel Hanging Basket steel form are provided.
To achieve these goals, the utility model is by the following technical solutions:
It comprises exterior sheathing, interior top template, interior mould holder, soffit formwork, and interior top template, interior mould holder are located at the middle part of exterior sheathing, and soffit formwork is located at the bottom of exterior sheathing, and Screw arbor with nut at both-ends is located at the top of exterior sheathing, interior top template be installed in mould holder above.
Described exterior sheathing comprises the adjusting device of normal reach master module, 0# section template, secondary template, flank template, flank template; Secondary template is mounted in the bottom of master module, and the flank template is installed in the top of described master module, and the adjusting device of described flank template is fixed on the top of the fixed mount of master module.
Described secondary template can be a joint, also can be divided into more piece, and after being poured into the height of beam section depth of section less than described master module, the secondary template of described exterior sheathing can be separated with described master module dismounting.Secondary template can be removed according to the actual merogenesis that requires of Construction of continuous beam environment, the purpose one of this structure setting is to alleviate the phenomenon of template deadweight because of increasing exponentially with cantilever lengthening gravity, the 2nd, strengthened the spatial altitude under the construction beam section, the vehicle of having guaranteed not influence in work progress below the bridge is normally current, this point at trans-city main line, stride railway, stride in the middle of the bridge construction of speedway by for important.
Described flank template realizes regulating the adjustment that greatly facilitates the two-way butt joint of continuous beam.
In described top template comprise in top template, a pair of the right on symmetrical a pair of left side in push up in top template and one pair in template.
Mould holder in described whenever is with 4~8 pairs, two body frames of described interior every pair of left and right symmetry of branch of mould holder, and middle connection batten and the adjusting screw(rod) used connects; The two ends of described adjusting screw(rod) are left and right hand thread, and described left and right two body frames are respectively equipped with the left-handed nut and the nut of dextrorotation, are provided with some fastening bolts on interior mould holder.After having unscrewed fastening bolt,, can require to regulate the width of described interior top template according to the thickness of abdominal wall of institute's casting beams section by rotating described adjusting screw(rod).
In described in the interior top of top template the width of the panel of template form both wings greater than its collet, its wing limit have part ride on the left side in top template in the top template and the right above, on the described interior top template support bar is set.The width on its wing limit should be greater than the required maximal regulated distance of beam inside ceiling panel, top template also is included as the wing limit that prevents panel and causes diastrophic support bar because of pressurized is excessive in described, the material of described support bar is a batten, also with the left side in the shaped steel of the contour size of top template in top template and the left side.
Described soffit formwork comprises template at the end, the right template of the end left side template and the end; The width of the panel of template forms both wings greater than its pallet at described the end, in the described soffit formwork support bar is set.The width on its wing limit should be greater than maximal regulated distance required at the bottom of the beam.Described soffit formwork also is included as distortion is caused on the wing limit that prevents panel because of pressurized is excessive support bar, and the material of described support bar is a batten, also with the shaped steel of the contour size of the right template of the end left side template and the end.
Described Hanging Basket steel form is to cooperate Hanging Basket to carry out the construction of continuous beam, and the front beam of described Hanging Basket and hang and draw assembly to hang the front and back ends that hauls outer slippage beam is respectively hung the exterior sheathing of both sides; Top template and interior mould holder are hung by the interior slippage beam of described Hanging Basket and draw in described; Described soffit formwork is then being held in the palm by the end indigo plant of described Hanging Basket, hangs the described soffit formwork that highly raises of hanging that draws assembly by regulating.
The 0# section template of described exterior sheathing is promptly removed after having built 0# beam section, by the normal reach master module of described exterior sheathing, secondary template and described in top template, interior mould holder, soffit formwork, Screw arbor with nut at both-ends etc. hanging of Hanging Basket draw carry out the building of 1# beam section under the effect after, only need unclamp the Screw arbor with nut at both-ends of steel form and the anchoring piece of Hanging Basket, steel form and Hanging Basket just can be whole on sliding rail by spurring slippage together and arrive next beam fragment position with pulling Hu Lu, anchoring piece and Screw arbor with nut at both-ends are installed the back just can carry out building the cycle of another beam section, close up until full beam.
The utility model compared with prior art has following advantage: the utility model is simple in structure, easy for installation, construct saving, wide accommodation and cost are lower.
Description of drawings
Fig. 1 is the front view of first kind of embodiment of the utility model, the assembly relation of each component of the utility model shown in the figure, right one side of something of view illustrates the utility model and is building 1# beam section and the cross section working condition when the highest, and left one side of something of view is the utility model to be shown in the working condition of building when connecing the beam section;
Fig. 2 is the front view of the exterior sheathing among first kind of embodiment of the utility model, the assembly relation of the exterior sheathing of the utility model shown in the figure each component when building 0# beam section;
Fig. 3 is the left view of the exterior sheathing among first kind of embodiment of the utility model;
Fig. 4 is the interior top template among first kind of embodiment of the utility model and the front view of interior top template support, the assembly relation of top template and interior top template support in the utility model shown in the figure;
The working condition that Fig. 5 is interior top template among first kind of embodiment of the utility model and interior top template bracket adjustment when the wideest;
Fig. 6 be in the interior top among first kind of embodiment of the utility model template section amplification figure;
Fig. 7 is the front view of the soffit formwork among first kind of embodiment of the utility model, the assembly relation of the soffit formwork of the utility model shown in the figure;
Fig. 8 is that the soffit formwork among first kind of embodiment of the utility model is adjusted to the working condition when the wideest;
Fig. 9 is the section amplification figure of template among first kind of embodiment of the utility model the end;
Figure 10 be among the another kind of embodiment of the utility model front view, the assembly relation of each component of the another kind of steel form of the utility model shown in the figure.It is to build 1# beam section and the cross section working condition when the highest that right half of view illustrates the another kind of steel form of utility model, and the half of view in a left side is illustrated in the working condition of building when connecing the beam section;
Figure 11 is the master map of exterior sheathing among the another kind of embodiment of the utility model, the installation relation of another kind of each component of exterior sheathing of the utility model shown in the figure;
Figure 12 is the left view in A-A cross section among Figure 11 among the another kind of embodiment of the utility model, the installation relation of each component of the another kind of 0# section of the utility model shown in figure exterior sheathing;
Figure 13 is the left view in B-B cross section among Figure 11 among the another kind of embodiment of the utility model, the installation relation of each component of the another kind of normal reach exterior sheathing of the utility model shown in the figure.
The specific embodiment
Below in conjunction with embodiment and contrast 1 to 9 pair of the utility model of accompanying drawing and be described in further detail: it comprises exterior sheathing 1, interior top template 2, interior mould holder 3, soffit formwork 4, interior top template 2, interior mould holder 3 are located at the middle part of exterior sheathing 1, soffit formwork 4 is located at the bottom of exterior sheathing 1, Screw arbor with nut at both-ends 5 is located at the top of exterior sheathing 1, interior top template 2 be installed in mould holder 3 above.
Described exterior sheathing 1 comprises the adjusting device 13 of normal reach master module 11,0# section template 12, secondary template 15, flank template 14, flank template; Secondary template 15 is mounted in the bottom of master module 11, and flank template 14 is installed in the top of described master module 11, and the adjusting device 13 of described flank template 14 is fixed on the top of the fixed mount 111 of master module 11.
In described top template 2 comprise in top template 21, a pair of the right on symmetrical a pair of left side in push up in top template 23 and one pair in template 22.
In described in the interior top of top template 2 width of the panel 221 of template 22 form both wings greater than its collet 212, its wing limit have part ride on the left side in top template 23 in the top template 21 and the right above, on the described interior top template 2 support bar 37 is set.
Described soffit formwork 4 comprises template 41 at the end, the right template 43 of the end left side template 42 and the end; The width of the panel 411 of template 41 forms both wings greater than its pallet 412 at described the end, in the described soffit formwork 4 support bar 44 is set.
To Figure 13, among the another kind of embodiment that provides according to the utility model, the primary structure of steel form and last embodiment are basic identical referring to Figure 10, but the shape in its disconnected cross section is inequality again, and this determines according to this bridge design working drawing.Described exterior sheathing 1 also is the adjusting device 13 that includes normal reach master module 11,0# section template 12, secondary template 15, flank template 14 and flank template, but has increased the secondary template 16 of 2#.Again because the stomach wall of beam and base plate at right angles are the exterior sheathing 1 of both sides is parallel, soffit formwork 4 so also just there is no need to be designed to adjustable.
Claims (6)
1. Hanging Basket steel form, it comprises exterior sheathing (1), interior top template (2), interior mould holder (3), soffit formwork (4), it is characterized in that: interior top template (2), interior mould holder (3) are located at the middle part of exterior sheathing (1), soffit formwork (4) is located at the bottom of exterior sheathing (1), Screw arbor with nut at both-ends (5) is located at the top of exterior sheathing (1), interior top template (2) be installed in interior mould holder (3) above.
2. Hanging Basket steel form according to claim 1 is characterized in that: described exterior sheathing (1) comprises the adjusting device (13) of normal reach master module (11), 0# section template (12), secondary template (15), flank template (14), flank template; Secondary template (15) is mounted in the bottom of master module (11), and flank template (14) is installed in the top of described master module (11), and the adjusting device (13) of described flank template (14) is fixed on the top of the fixed mount (111) of master module (11).
3. Hanging Basket steel form according to claim 1 is characterized in that: in described top template (2) comprise in top template (21), a pair of the right on symmetrical a pair of left side in push up in top template (23) and one pair in template (22).
4. Hanging Basket steel form according to claim 1, it is characterized in that: mould holder (3) in described, whenever be with 4~8 pairs, two body frames (31) of described interior every pair of left and right symmetry of branch of mould holder (3), middle with connecting the connection of batten (36) and adjusting screw(rod) (34); The two ends of described adjusting screw(rod) (34) are left and right hand thread, and described left and right two body frames (31) are respectively equipped with the nut (33) of left-handed nut (32) and dextrorotation, are provided with some fastening bolts (35) on interior mould holder (3).
5. Hanging Basket steel form according to claim 1, it is characterized in that: the width of the panel (221) of template (22) is greater than its collet (212) in the interior top of described interior top template (2), form both wings, its wing limit have part ride over top template (23) in the top template left side in (21) and the right above, on the described interior top template (2) support bar (37) is set.
6. Hanging Basket steel form according to claim 1 is characterized in that: described soffit formwork (4) comprises template at the end (41), the right template (43) of the end left side template (42) and the end; The width of the panel (411) of template at the described end (41) forms both wings greater than its pallet (412), and support bar (44) is set in the described soffit formwork (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200920216459XU CN201567787U (en) | 2009-09-17 | 2009-09-17 | Form-traveler steel formwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200920216459XU CN201567787U (en) | 2009-09-17 | 2009-09-17 | Form-traveler steel formwork |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201567787U true CN201567787U (en) | 2010-09-01 |
Family
ID=42660074
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN200920216459XU Expired - Fee Related CN201567787U (en) | 2009-09-17 | 2009-09-17 | Form-traveler steel formwork |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201567787U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535338A (en) * | 2010-12-23 | 2012-07-04 | 上海市基础工程有限公司 | Hanging side formwork of cradle |
WO2013079747A1 (en) | 2011-11-30 | 2013-06-06 | Rúbrica Ingeniería Y Arquitectura, S.L. | Traveller for the construction of engineering works |
CN103711065A (en) * | 2013-12-30 | 2014-04-09 | 江苏省交通科学研究院股份有限公司 | Cantilever construction steel-concrete combined bridge and construction method thereof |
CN103911954A (en) * | 2014-04-18 | 2014-07-09 | 浙江省衢州市交通建设集团有限公司 | Inside ceiling panel formwork of bridge box girder and method for pouring ceiling plate of box girder by using formwork |
CN107447669A (en) * | 2017-08-27 | 2017-12-08 | 贵州新联爆破工程集团有限公司 | A kind of hanging basket formwork positioner |
CN111749139A (en) * | 2020-07-20 | 2020-10-09 | 中交二公局第三工程有限公司 | Inner mold structure of telescopic adjustable continuous beam bridge |
-
2009
- 2009-09-17 CN CN200920216459XU patent/CN201567787U/en not_active Expired - Fee Related
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535338A (en) * | 2010-12-23 | 2012-07-04 | 上海市基础工程有限公司 | Hanging side formwork of cradle |
WO2013079747A1 (en) | 2011-11-30 | 2013-06-06 | Rúbrica Ingeniería Y Arquitectura, S.L. | Traveller for the construction of engineering works |
CN103711065A (en) * | 2013-12-30 | 2014-04-09 | 江苏省交通科学研究院股份有限公司 | Cantilever construction steel-concrete combined bridge and construction method thereof |
CN103911954A (en) * | 2014-04-18 | 2014-07-09 | 浙江省衢州市交通建设集团有限公司 | Inside ceiling panel formwork of bridge box girder and method for pouring ceiling plate of box girder by using formwork |
CN107447669A (en) * | 2017-08-27 | 2017-12-08 | 贵州新联爆破工程集团有限公司 | A kind of hanging basket formwork positioner |
CN107447669B (en) * | 2017-08-27 | 2023-06-27 | 保利新联爆破工程集团有限公司 | Hanging basket template positioning device |
CN111749139A (en) * | 2020-07-20 | 2020-10-09 | 中交二公局第三工程有限公司 | Inner mold structure of telescopic adjustable continuous beam bridge |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201567787U (en) | Form-traveler steel formwork | |
CN202017346U (en) | Late poured band hanging formwork structure | |
CN203903834U (en) | Internal-climbing tower crane | |
CN108532968A (en) | A kind of assembled support device of steel bar truss floor support plate composite floor system | |
CN210659228U (en) | Movable single-side formwork system for subway construction | |
CN201901964U (en) | Three-dimensional adjustable and disconnectable curtain wall | |
CN201963316U (en) | Template system for tunnel wall construction | |
CN208950300U (en) | Using the beam beam support system of independent support column | |
CN205171782U (en) | Frame curtain system between stone material edge list | |
CN206521939U (en) | A kind of overhanging down-stayed scaffold | |
CN102102437A (en) | Combined U-shaped elevation hanging work platform | |
CN204919356U (en) | Mould platform is hung in construction of steel longeron concrete bridge panel | |
CN202023353U (en) | Integral lifting scaffold for building operations | |
CN206530077U (en) | A kind of support frame | |
CN201981728U (en) | Stainless steel composite covered column structure | |
CN215055300U (en) | Upward-pulling assembly type post-pouring belt template | |
CN201850751U (en) | Combined U-shaped high-altitude suspension operation platform | |
CN211006352U (en) | Pier stud template reinforced structure | |
CN205314539U (en) | Large -scale cantilever type combination steel form | |
CN209539398U (en) | A kind of evacuation platform of Fast Installation | |
CN204356658U (en) | Bridge floor tapping pipe bush mould | |
CN209307867U (en) | Framed bent and bracket | |
CN203807946U (en) | Track beam erecting device | |
CN208455941U (en) | A kind of building precast beam | |
CN208545831U (en) | A kind of dismountable steel structure and dismountable steel structure house |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20100901 Termination date: 20120917 |