CN206048254U - A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway - Google Patents

A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway Download PDF

Info

Publication number
CN206048254U
CN206048254U CN201620928369.3U CN201620928369U CN206048254U CN 206048254 U CN206048254 U CN 206048254U CN 201620928369 U CN201620928369 U CN 201620928369U CN 206048254 U CN206048254 U CN 206048254U
Authority
CN
China
Prior art keywords
crossbeam
fixed block
screw rod
seamless spliced
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620928369.3U
Other languages
Chinese (zh)
Inventor
张伟
张璐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
New torch Technology Co., Ltd.
Original Assignee
Xiangyang New Torch Science And Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiangyang New Torch Science And Technology Co Ltd filed Critical Xiangyang New Torch Science And Technology Co Ltd
Priority to CN201620928369.3U priority Critical patent/CN206048254U/en
Application granted granted Critical
Publication of CN206048254U publication Critical patent/CN206048254U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway of this utility model, including first crossbeam, second cross beam, first guide rail, second guide rail and uprights vertical adjustment plate, uprights vertical adjustment plate two ends are separately fixed at the side wall of first crossbeam and second cross beam, the both sides of uprights vertical adjustment plate, the first fixed block and the second fixed block are respectively arranged with positioned at the side of first crossbeam and second cross beam, the first motion block and the second motion block are respectively fixed with the first fixed block and the second fixed block on the side wall of first crossbeam and second cross beam, respectively by the first adjustment screw rod and the second adjustment screw rod connection between first motion block and the second motion block and the first fixed block and the second fixed block.The seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model, simple structure are practical, easy to operate, save manpower and materials, are particularly suitable for the seamless spliced installation for needing to carry out the repeatedly multistage large span guide rail of dismounting assembling.

Description

A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway
Technical field
This utility model is related to a kind of seamless spliced installation adjusting device of guide rail, more particularly to a kind of truss robot multistage The seamless spliced installation adjusting device of beam guideway, belongs to truss robot technical field.
Background technology
Truss robot changes traditional logistics mode, effectively improves working environment, there is provided part manufacturing digitally Change, information-based, few peopleization are until unmanned management, makes Modern Manufacturing Technology reach a brand-new level.At the same time, China The sustainable growth of labour force's wage level at present, and persistently there is large area recruitment famine, increasing enterprise selects to use purlin Frame robot, walks the road of automated production.
Truss robot span is big, and beam height is high, and needs arrange column between lathe, with fixed cross beam.Due to crossbeam Height in 2.5m or so, the weight of single crossbeam up to 300kg or so, therefore, truss robot install when, multistage crossbeam it Between splicing and the guide rail being arranged on crossbeam seamless spliced difficulty of construction it is big, it is desirable to it is high.It is in particular in, due to crossbeam Height is high, and the splicing of crossbeam and guide rail needs to realize by hanging car or fork truck, but, due to truss robot high precision, Splicing required precision to crossbeam and guide rail is also high, only cannot complete trickle adjustment only by the said equipment, it is impossible to complete to lead Rail it is seamless spliced.According to workman manually complete crossbeam trickle adjustment and guide rail it is seamless spliced, as crossbeam weight is big, need Multiple workman's compounding practices are wanted, not only operation is wasted time and energy, and there is the potential safety hazard that crossbeam drops.Prior art lacks one Plant and crossbeam position can be finely adjusted, complete the seamless spliced installation adjusting device of guide rail.
Utility model content
To solve problem of the prior art, it is seamless spliced that this utility model provides a kind of truss robot multistage beam guideway Installation adjusting device, based on the uprights vertical adjustment plate on two crossbeams, arranges in uprights vertical adjustment plate and determines block, Motion block is set on crossbeam, and by adjustment bolt completing the splicing of the guide rail on crossbeam, simple structure is easy to operate, saves time It is laborsaving.
This utility model is adopted the following technical scheme that to realize above-mentioned technical purpose.
A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway, including first crossbeam, second cross beam, First guide rail, the second guide rail and uprights vertical adjustment plate, the uprights vertical adjustment plate two ends be separately fixed at first crossbeam and The side wall of second cross beam, the both sides of the uprights vertical adjustment plate, the side positioned at first crossbeam and second cross beam is respectively provided with Have solid near the first fixed block and second on the side wall of the first fixed block and the second fixed block, the first crossbeam and second cross beam Determine at block, to be respectively fixed with the first motion block and the second motion block, first motion block and the second motion block and the first fixed block and second are admittedly Determine between block respectively by the first adjustment screw rod and the second adjustment screw rod connection.
Further, the seamless spliced installation adjusting device of a kind of truss robot multistage beam guideway, first adjustment Screw rod and the second adjustment screw rod are countersunk head screw rod, and the first outer gear is respectively arranged with the inside of first fixed block and the second fixed block Plate and the second outer baffle, the first adjustment screw rod and the second adjustment screw rod are fixed by the first outer baffle and the second outer baffle, The perforate stretched into for screwdriver is respectively equipped with first outer baffle and the second outer baffle.
This utility model obtains following technique effect using above-mentioned technical proposal.
1st, the seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model, is spelled using two crossbeams Connect based on the uprights vertical installing plate at place, block and fixed block are determined by installation then, between completing between crossbeam by adjustment bolt The regulation of gap, so as to complete the seamless spliced of guide rail.Simple structure, it is practical, and can reuse, it is particularly well-suited to Needs carry out the seamless spliced installation adjusting device of truss robot multistage beam guideway of repeatedly dismounting assembling.
2nd, the seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model, it is easy to operate, only Multistage beam guideway is completed by needing a workman seamless spliced, save manpower and materials, and eliminated simple manual operations Potential safety hazard, improve working security.
Description of the drawings
Fig. 1 is the structural representation of the seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model Figure.
Reference lists as follows:Column 1, first crossbeam 2, second cross beam 3, the first guide rail 4, uprights vertical adjustment plate 5, First fixed block 6, the first motion block 7, the first adjustment screw rod 8, the first outer baffle 9, the second fixed block 10, the second motion block 11, second Adjustment screw rod 12, the second outer baffle 13, the second guide rail 14.
Specific embodiment
Below in conjunction with the accompanying drawings, to the seamless spliced installation adjusting device of truss robot multistage beam guideway of utility model Technical scheme is conducted further description, and those skilled in the art is better understood from this utility model and can be given reality Apply.
Referring to Fig. 1, a kind of seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model stands It is respectively provided with first crossbeam 2 and second cross beam 3 on post 1,4 across the crossbeam setting of the first guide rail, it is horizontal that the second guide rail 14 is arranged on second On beam 3, now, being faced with for the first guide rail 4 is repeatedly dismantled.This is because, truss robot carries out installation splicing before dispatching from the factory After debugging, for ease of transport, need to dismantle multistage crossbeam, debugged to after client factory again, therefore, first leads Rail 4 is faced with the problem of repeatedly dismounting splicing.
5 two ends of uprights vertical adjustment plate are separately fixed on the side wall of first crossbeam 2 and second cross beam 3, and the column hangs down The both sides of straight adjustment plate 5, are respectively arranged with the first fixed block 6 and second positioned at the side of first crossbeam 2 and second cross beam 3 and fix Fixed at the first fixed block 6 and the second fixed block 10 respectively on the side wall of block 10, the first crossbeam 2 and second cross beam 3 There are the first motion block 7 and the second motion block 11, first motion block 7 and the second motion block 11 and the first fixed block 6 and the second fixed block 10 Between connected by the first adjustment screw rod 8 and the second adjustment screw rod 12 respectively.
Before dispatching from the factory, need to carry out installation and debugging to truss robot, now, by first crossbeam 2 and the level of second cross beam 3 Vertically all adjust, and when leaving therebetween the space of about 2mm, the second guide rail is first installed in the splicing of the guide rail for proceeding by 14, then the first guide rail 4 is installed, when the first guide rail 4 has enough space mountings, must between the first guide rail 4 and the second guide rail 14 So there is gap, in order that being seamlessly connected therebetween, the first adjustment screw rod 8 and the second adjustment screw rod are tightened to locking direction 12, until gap is minimum therebetween;, whereas if the first guide rail 4 does not have enough spaces to be installed, then to the side unclamped Screw rod 8 and the second adjustment screw rod 12 are adjusted to twisting first, it is ensured that the first guide rail 4 can be put into, and then carry out again seamless spliced. It should be noted that now uprights vertical adjustment plate 5 should should be fixed therein on a crossbeam, and it is horizontal with other one Beam is disconnected, to reach adjustment purpose.
Installation and debugging are completed, and need transport to be spliced to client factory and again debugging, now, by the first motion block 7, the One fixed block 6, first adjusts screw rod 8, and the second motion block 11, the second fixed block 10 and the second adjustment screw rod 12 are disassembled, Transport.And, it is only necessary to the guide rail across truss crossbeam, i.e. the first guide rail 4 are dismantled and numbered.
When client factory carries out splicing debugging again, stop between the expanding with heat and contract with cold of first crossbeam 2 and second cross beam 3 Away from, and after adjusting horizontal vertical, then adjusted by seamless spliced installation of truss robot multistage beam guideway of the present utility model Engagement positions, are installed according to method above.
First guide rail 4 and the second guide rail 14 it is seamless spliced after the completion of, the first motion block 7, the first fixed block 6, first are adjusted Whole screw rod 8, and the second motion block 11, the second fixed block 10 and the second adjustment screw rod 12 disassemble, and does not first interfere with the later stage Drag chain install, second above-mentioned part can also be reused, it is cost-effective.
The seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model, simple structure are practical Property it is strong, and can reuse, be particularly suitable for needing to carry out repeatedly the seamless spliced of the multistage large span guide rail of dismounting assembling Install.
The seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model, it is easy to operate, it is only necessary to Multistage beam guideway is completed by one workman seamless spliced, save manpower and materials, and eliminated simple manual Potential safety hazard, improves working security.
As a kind of preferred scheme, the seamless spliced mounting and adjusting of truss robot multistage beam guideway of the present utility model Device, the first adjustment screw rod 8 and the second adjustment screw rod 12 are countersunk head screw rod, first fixed block 6 and the second fixed block The first outer baffle 9 and the second outer baffle 13 are respectively arranged with the inside of 10, the first adjustment screw rod and the second adjustment screw rod pass through First outer baffle 9 and the second outer baffle 13 are fixed, and be respectively equipped with and supply screwdriver on first outer baffle 9 and the second outer baffle 13 The perforate stretched into.
This scheme need not adopt the adjustment screw rod of big handle, save the seamless spliced peace of truss robot multistage beam guideway The space of engagement positions is debug, is easy to dismount and is deposited, also bigger space is provided for installation and debugging.
The seamless spliced installation adjusting device of truss robot multistage beam guideway of the present utility model, not by above-described embodiment Restriction, it is every using structure of the present utility model and mode, through the formed technical scheme that converts and replace, all in this reality With in new protection domain.

Claims (2)

1. the seamless spliced installation adjusting device of a kind of truss robot multistage beam guideway, including first crossbeam (2), second cross beam (3), the first guide rail (4), the second guide rail (14) and uprights vertical adjustment plate (5), it is characterised in that:The uprights vertical adjustment plate (5) two ends are separately fixed on the side wall of first crossbeam (2) and second cross beam (3), and the two of the uprights vertical adjustment plate (5) Side, is respectively arranged with the first fixed block (6) and the second fixed block (10) positioned at first crossbeam (2) and second cross beam (3) side, described It is respectively fixed near the first fixed block (6) and the second fixed block (10) place on the side wall of first crossbeam (2) and second cross beam (3) First motion block (7) and the second motion block (11), first motion block (7) and the second motion block (11) and the first fixed block (6) and second Respectively by the first adjustment screw rod (8) and the second adjustment screw rod (12) connection between fixed block (10).
2. the seamless spliced installation adjusting device of truss robot multistage beam guideway according to claim 1, its feature exist In:First adjustment screw rod (8) and the second adjustment screw rod (12) are countersunk head screw rod, and first fixed block (6) and second is admittedly Determine on the inside of block (10), to be respectively arranged with the first outer baffle (9) and the second outer baffle (13), first adjustment screw rod (8) and second Adjustment screw rod (12) is fixed by the first outer baffle (9) and the second outer baffle (13), keeps off outside first outer baffle (9) and second Plate is respectively equipped with the perforate stretched into for screwdriver on (13).
CN201620928369.3U 2016-08-24 2016-08-24 A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway Active CN206048254U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620928369.3U CN206048254U (en) 2016-08-24 2016-08-24 A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620928369.3U CN206048254U (en) 2016-08-24 2016-08-24 A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway

Publications (1)

Publication Number Publication Date
CN206048254U true CN206048254U (en) 2017-03-29

Family

ID=58383970

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620928369.3U Active CN206048254U (en) 2016-08-24 2016-08-24 A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway

Country Status (1)

Country Link
CN (1) CN206048254U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107804664A (en) * 2017-09-19 2018-03-16 浙江工贸职业技术学院 The spliced logistic car of E-business supply chain track
CN108908316A (en) * 2018-09-25 2018-11-30 湖南宇环智能装备有限公司 A kind of planer-type truss manipulator
CN109514278A (en) * 2018-12-29 2019-03-26 济南天辰铝机股份有限公司 A kind of lathe bed docking structure of overlength gantry machining center and connection method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107804664A (en) * 2017-09-19 2018-03-16 浙江工贸职业技术学院 The spliced logistic car of E-business supply chain track
CN108908316A (en) * 2018-09-25 2018-11-30 湖南宇环智能装备有限公司 A kind of planer-type truss manipulator
CN109514278A (en) * 2018-12-29 2019-03-26 济南天辰铝机股份有限公司 A kind of lathe bed docking structure of overlength gantry machining center and connection method
CN109514278B (en) * 2018-12-29 2023-07-28 济南天辰智能装备股份有限公司 Lathe bed butt joint structure and connecting method of ultra-long gantry machining center

Similar Documents

Publication Publication Date Title
CN201496669U (en) Pipeline supporting and hanging frame
CN206048254U (en) A kind of seamless spliced installation adjusting device of truss robot multistage beam guideway
CN204934670U (en) A kind of electric drill auxiliary stand
CN201176703Y (en) Tripod for construction of hyperbola cooling tower cylinder
CN204455794U (en) A kind of assembled steel bridge
CN103343639B (en) A kind of sliding mode system of efficient adjustment
CN201458567U (en) Special angle square for profile steel trolley conductor bracket installation
CN204715763U (en) A kind of aluminum alloy mould plate diagonal brace supporting member pre-embedded bolt structure
CN103628692B (en) A kind of floor beam mounting bracket and use it to install the method for floor beam
CN203361735U (en) Sliding mode system with function of efficient adjustment
CN206616765U (en) Large span is without depending on huge bandy truss pull bar
CN203441074U (en) Scaffold connecting device
CN202055146U (en) Connecting structure for screed board accessories
CN203361633U (en) Template regulating system of sliding form system
CN103334584A (en) Template regulating system for sliding form system
CN203403681U (en) Temporary supporting frame of string beam
CN203188612U (en) Beam frame type building template system
CN202925883U (en) Large size wooden formwork surrounding purlin device
CN201274392Y (en) Operating platform on portable adjustable bar
CN206529707U (en) A kind of Hanging Basket for building
CN201722627U (en) Assembled adjustable support for reinforcing bar binding fixture
CN220319180U (en) Shock-resistant roof for stamping factory building
CN206053075U (en) Bolt-type aluminum alloy glass curtain wall crossbeam connection system
CN203394079U (en) Large overweight box-type beam mounting assisting parallel truss
CN110593299A (en) Leveling device for embedded part of transformer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 441004 Xiangyang hi tech Zone Auto Industrial Park in Hubei

Patentee after: New torch Technology Co., Ltd.

Address before: 441004 Xiangyang Province, Xiangfan Province High-tech Zone, Hubei Automobile Industrial Park

Patentee before: Xiangyang New Torch Science and Technology Co., Ltd

CP03 Change of name, title or address