CN206035504U - Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel - Google Patents

Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel Download PDF

Info

Publication number
CN206035504U
CN206035504U CN201620962282.8U CN201620962282U CN206035504U CN 206035504 U CN206035504 U CN 206035504U CN 201620962282 U CN201620962282 U CN 201620962282U CN 206035504 U CN206035504 U CN 206035504U
Authority
CN
China
Prior art keywords
lining
hopper
construction
tunnel
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620962282.8U
Other languages
Chinese (zh)
Inventor
陈力
刘昌盛
吴海龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, Fourth Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN201620962282.8U priority Critical patent/CN206035504U/en
Application granted granted Critical
Publication of CN206035504U publication Critical patent/CN206035504U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model provides a two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel, includes hopper (1), the upper end of hopper (1) is provided with feed inlet (2), is provided with in the middle of hopper (1) bottom splitter box (3), and the symmetrical both sides in hopper (1) bottom are provided with feed pipe opening (4) respectively. Simple structure, it is easy and simple to handle, can effectually realize two lining bilateral symmetry nature concreting construction through the reposition of redundant personnel.

Description

A kind of tunnel double-lining both sides synchronization pouring construction shunting magazine attachment
Technical field
The utility model is related to a kind of shunting magazine attachment, and more specifically to a kind of tunnel double-lining both sides synchronously pour Construction shunting magazine attachment, belongs to railway and highway tunnel lining technical field of construction.
Background technology
The construction of tunnel double-lining is related to the final construction quality of engineering, and its construction speed is also related to whole Tunnel Engineering The cycle of construction.At present, the construction with major long tunnel at home increases, and the construction quality and construction period to tunnel double-lining will Seek more and more higher.
During construction, tunnel double-lining require from the bottom up, the symmetrical pouring construction in the left and right sides.Existing traditional form of construction work is adopted A side window is directly accessed with pump line to pour, wait pour height reach about 1m it is high after, then by tear open pipe shifting be filled to another side window, Exchanging successively is carried out until vault.But, there is following substantially drawback in this form of construction work:1st, lining trolley complex structure, Position is more to ask pump line to turn round, and in pumping procedure, generation plugging probability increases;2nd, the engineering time is longer, and effect is low, is mainly reflected in Pump line left and right sides replaces disassembly process, and time-consuming;3rd, it is difficult to preferably control the symmetry of left and right sides construction, is also easy to produce bias, plus Gu easily producing termination in the case of loosely runs mould phenomenon.Meanwhile, these problems can cause two lining concrete construction progresses to delay Slowly, seriously delay the duration.
The content of the invention
The purpose of this utility model is to be difficult to a preferably control left side for what existing tunnel double-lining form of construction work was present The symmetry of right side construction, the problems such as construction speed is slow, there is provided a kind of tunnel double-lining both sides synchronization pouring construction shunting hopper Device.
For achieving the above object, technical solution of the present utility model is:A kind of tunnel double-lining both sides synchronously pour applies Work point stream magazine attachment, including hopper, the upper end of the hopper is provided with charging aperture, and feed hopper bottom middle setting has splitter box, The symmetrical both sides of feed hopper bottom are respectively arranged with the discharging mouth of pipe.
A diameter of 200mm of the discharging mouth of pipe.
The described discharging mouth of pipe is connected with chute.
Handle is provided with the top of the hopper.
Compared with prior art, the beneficial effects of the utility model are:
1st, simple structure, it is easy to operate, two lining Zygomorphy pouring constructions can be realized by shunting effectively.Construction When, concrete is divided right and left by the utility model by splitter box 3, concrete is sent by the chute again through being connected with the discharging mouth of pipe To left and right sides lining cutting window, so as to effectively realize two lining both sides while symmetry pouring construction by shunting.
2nd, mounting-dismounting programme greatly reduces, and saves the engineering time, and speed of application is fast, and effect is high.
Description of the drawings
Fig. 1 is the utility model structural representation.
Fig. 2 is hopper installation schematic diagram.
In figure, hopper 1, charging aperture 2, splitter box 3, discharge the mouth of pipe 4, handle 5.
Specific embodiment
The utility model is described in further detail below in conjunction with description of the drawings and specific embodiment.
Referring to Fig. 1, a kind of tunnel double-lining both sides synchronization pouring construction shunting magazine attachment can realize two lining both sides synchronizations Symmetrically and evenly casting concrete, including hopper 1.The upper end of the hopper 1 is provided with charging aperture 2, and 1 bottom middle setting of hopper has Splitter box 3,1 bottom symmetrical both sides of hopper are respectively arranged with the discharging mouth of pipe 4.
Referring to Fig. 1, a diameter of 200mm of the discharging mouth of pipe 4.
Referring to Fig. 1, the described discharging mouth of pipe 4 is connected with chute.
Referring to Fig. 1, the top of the hopper 1 is provided with handle 5.Handle 5 is easy to lift dress.
Referring to Fig. 1-Fig. 2, during construction, concrete falls into bottom after entering material bin 1 by charging aperture 2, by the splitter box 3 of bottom Concrete is divided right and left;Concrete is delivered to by the discharging mouth of pipe 4 of both sides, the chute again through being connected with the discharging mouth of pipe 4 Left and right sides lining cutting window, so that realize synchronous casting process.
Referring to Fig. 1-Fig. 2, the construction method of this shunting magazine attachment, comprise the following steps:
Step one, the mounting and fixing bracket above the lining trolley door frame make support height not little higher than both sides cloth window In 1 meter, it is beneficial to the flowing of concrete, hopper 1 is placed on support and is fixed.Window herein to refer to and open one in template Hole, for constructing, is commonly referred to as window.
Step 2, concrete is sent into the charging aperture 2 of hopper 1 by ground pump, by the splitter box 3 of 1 bottom of hopper by coagulation Soil is separated to both sides.
Step 3, by chute at the both sides discharging mouth of pipe 4 by concrete conveyance to two side windows, so as to be poured simultaneously Concrete construction.
Above content is with reference to specific preferred embodiment further detailed description of the utility model, it is impossible to Identification is of the present utility model to be embodied as being confined to these explanations.For the ordinary skill of the utility model art For personnel, without departing from the concept of the premise utility, some simple deduction or replace, said structure can also be made Protection domain of the present utility model should be all considered as belonging to.

Claims (4)

1. a kind of tunnel double-lining both sides synchronization pouring construction shunts magazine attachment, it is characterised in that:Including hopper(1), the material Bucket(1)Upper end be provided with charging aperture(2), hopper(1)Bottom middle setting has splitter box(3), hopper(1)Bottom symmetrical both sides It is respectively arranged with the discharging mouth of pipe(4).
2. a kind of tunnel double-lining both sides synchronization pouring construction according to claim 1 shunts magazine attachment, it is characterised in that: The discharging mouth of pipe(4)A diameter of 200mm.
3. a kind of tunnel double-lining both sides synchronization pouring construction according to claim 1 shunts magazine attachment, it is characterised in that: The described discharging mouth of pipe(4)It is connected with chute.
4. a kind of tunnel double-lining both sides synchronization pouring construction according to claim 1 shunts magazine attachment, it is characterised in that: The hopper(1)Top be provided with handle(5).
CN201620962282.8U 2016-08-26 2016-08-26 Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel Active CN206035504U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620962282.8U CN206035504U (en) 2016-08-26 2016-08-26 Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620962282.8U CN206035504U (en) 2016-08-26 2016-08-26 Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel

Publications (1)

Publication Number Publication Date
CN206035504U true CN206035504U (en) 2017-03-22

Family

ID=58305761

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620962282.8U Active CN206035504U (en) 2016-08-26 2016-08-26 Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel

Country Status (1)

Country Link
CN (1) CN206035504U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437762A (en) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 Flow divided hopper device for synchronous pouring construction on two sides of tunnel secondary lining and construction method
CN107091104A (en) * 2017-06-20 2017-08-25 中铁隧道集团二处有限公司 The concrete placings device and its installation method of single-track railway tunnel hogging wall lining platform building cart
CN111173538A (en) * 2020-01-20 2020-05-19 中建商品混凝土有限公司 Pouring device for pouring tunnel secondary lining concrete

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437762A (en) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 Flow divided hopper device for synchronous pouring construction on two sides of tunnel secondary lining and construction method
CN107091104A (en) * 2017-06-20 2017-08-25 中铁隧道集团二处有限公司 The concrete placings device and its installation method of single-track railway tunnel hogging wall lining platform building cart
CN107091104B (en) * 2017-06-20 2019-12-27 中铁隧道集团二处有限公司 Concrete pouring device of single-track railway tunnel middle arch wall lining trolley and installation method thereof
CN111173538A (en) * 2020-01-20 2020-05-19 中建商品混凝土有限公司 Pouring device for pouring tunnel secondary lining concrete

Similar Documents

Publication Publication Date Title
CN106437762A (en) Flow divided hopper device for synchronous pouring construction on two sides of tunnel secondary lining and construction method
CN206035504U (en) Two lining bilateral synchronous concreting construction reposition of redundant personnel magazine attachments in tunnel
CN104260185B (en) Multifunctional concrete prefabricated components battery mould production equipment and production line
CN207131072U (en) A kind of super thick shear wall corner template reinforcing device
CN104746639B (en) A kind of installation method that the prefabricated window that floats is installed in composite wallboard
CN204298828U (en) Foundation ditch concreting elephant trunk cushioning control structure
CN105927249B (en) A kind of construction method for pouring tunnel double-lining self-compacting concrete
CN206467993U (en) A kind of Overhanging Outside Scaffold I-steel sealing hole device
CN206971732U (en) A kind of doubly-linked beam forms pouring structure
CN107803467A (en) A kind of running gate system of large-scale valve casing class steel-casting
CN106499411B (en) A kind of single-track tunnel macroportion inverted arch self-propelled suspension template and construction method
CN106836013A (en) Ballasting method under closure section both sides bridge flexibility is asymmetric during cantilever construction
CN102425110A (en) Cast-in-situ concrete construction method for full section of urban overpass box girder
CN102383352A (en) Method for constructing foam lightweight concrete poured roadbed
CN208343130U (en) A kind of dismoulding system of road surface cement brick
CN104746875B (en) A kind of portable block-shaped discarded concrete pours device
CN209163447U (en) A kind of tool-type mould bases of constructional column top one-piece casting
CN208743624U (en) A kind of knitting machine main plate running gate system
CN206913378U (en) It is a kind of can quickly pull the demoulding hollow wall plank of concrete rectangle duct drilling template
CN206329043U (en) A kind of concrete shunts slot device
CN109113338A (en) A kind of tool-type mould bases of constructional column top one-piece casting
CN105587053B (en) A kind of industrialization house wall bottom grouting construction method
CN206448272U (en) Roadbed side slope arched framework one-time-shaped mould
CN201874242U (en) Quantitative foam concrete pouring machine
CN205437044U (en) Casting device

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant