CN205999915U - A kind of adjustable standard component for reserving bolt suitable for each size - Google Patents

A kind of adjustable standard component for reserving bolt suitable for each size Download PDF

Info

Publication number
CN205999915U
CN205999915U CN201620981602.4U CN201620981602U CN205999915U CN 205999915 U CN205999915 U CN 205999915U CN 201620981602 U CN201620981602 U CN 201620981602U CN 205999915 U CN205999915 U CN 205999915U
Authority
CN
China
Prior art keywords
channel
section steel
manhole
bolt
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620981602.4U
Other languages
Chinese (zh)
Inventor
王志栋
文红宇
肖龙
鲁笑举
李彦稳
李俊烨
宋岩
祝广龙
古威
许新幸
沈朝营
罗冲
张书廷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Pingmei Shenma Construction and Engineering Group Co Ltd
Original Assignee
Pingmei Shenma Construction and Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Pingmei Shenma Construction and Engineering Group Co Ltd filed Critical Pingmei Shenma Construction and Engineering Group Co Ltd
Priority to CN201620981602.4U priority Critical patent/CN205999915U/en
Application granted granted Critical
Publication of CN205999915U publication Critical patent/CN205999915U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model is related to the adjustable standard component for reserving bolt suitable for each size,The versatility of effectively solving tradition grinding tool is not strong,Construction quality and accuracy are difficult to control to,Great inconvenience is brought for later stage Construction of Steel Structure,The problem of certain impact is there is also to integrated engineering quality,Structure is,Channel-section steel is mounted on supporting leg,Channel-section steel is vertically arranged with rectangular through holes in the middle of bottom surface,The first manhole is correspondingly arranged on channel-section steel two sides,Lateral connection screw rod is installed in the first manhole,And fix through lateral adjustments nut,Pad is installed with channel-section steel,Pad is provided centrally with the second manhole,Reserved bolt is installed in the second manhole,And be fixed on channel-section steel through clamp nut,The utility model is applied to various sizes and reserves bolt,Efficiency of construction is improve while construction cost is saved,And can reuse,Guarantee that precision reserved by bolt,Improve construction quality,Guarantee that once mounting puts in place,Avoid damaging steel construction.

Description

A kind of adjustable standard component for reserving bolt suitable for each size
Technical field
The utility model is related to field of steel structure construction, particularly a kind of adjustable feast-brand mark for reserving bolt suitable for each size Quasi- part.
Background technology
At present during bolt construction is reserved on steel-structure factory building basis, generally will using the sized data be given in drawing Reserved bolt is respectively fixed on reinforcing bar or foundation forms, or makes grinding tool according to reserved Bolt sizes.
This conventional construction method workload is big, and the versatility of grinding tool is not strong, and construction quality and accuracy are difficult to control to, and are Later stage Construction of Steel Structure brings great inconvenience, there is also certain impact to integrated engineering quality, and therefore invention one kind can Guarantee construction quality, be suitable for each size and bolt is reserved, cost-effective technical method is extremely urgent.
Content of the invention
For above-mentioned situation, it is the defect for solving prior art, the purpose of the utility model is exactly to provide one kind to be applied to Each size reserves the adjustable standard component of bolt, can effectively solving tradition grinding tool versatility not strong, construction quality and accuracy Be difficult to control to, be that later stage Construction of Steel Structure brings great inconvenience, the problem of certain impact is there is also to integrated engineering quality.
The technical scheme that the utility model is solved is that, including base, base is made up of channel-section steel and supporting leg, and channel-section steel is mounted in supporting leg On, rectangular through holes are vertically arranged with the middle of channel-section steel bottom surface, be correspondingly arranged on the first manhole, laterally connect on channel-section steel two sides Connect screw rod to be installed in the first manhole, and fix through lateral adjustments nut, pad in channel-section steel, is installed with, pad is centrally disposed There is the second manhole, reserved bolt is installed in the second manhole, and is fixed on channel-section steel through clamp nut.
The various sizes that the utility model occurs suitable for conventional project reserve bolt, while construction cost is saved Efficiency of construction is improve, and can be reused, it is ensured that precision reserved by bolt, construction quality is improved, is later stage Steel Structure Installation There is provided advantage, it is ensured that once mounting puts in place, it is to avoid steel construction is damaged, be to reserve the innovation on bolt device.
Description of the drawings
Fig. 1 is structural front view of the present utility model.
Fig. 2 is structure top view of the present utility model.
Fig. 3 is structural side view of the present utility model.
Fig. 4 is the structure top view of the utility model channel-section steel.
Fig. 5 is the structural side view of the utility model channel-section steel.
Fig. 6 is the structural representation of the utility model pad.
Specific embodiment
Specific embodiment of the present utility model is described in further detail below in conjunction with accompanying drawing.
Be given by Fig. 1-6, the utility model includes base, base is made up of channel-section steel 1 and supporting leg 6, and channel-section steel 1 is mounted in supporting leg 6 On, rectangular through holes 9 are vertically arranged with the middle of 1 bottom surface of channel-section steel, are correspondingly arranged on the first manhole 10 on 1 two sides of channel-section steel, Lateral connection screw rod 5 is installed in the first manhole 10, and is fixed through lateral adjustments nut 4, is installed with pad 8 in channel-section steel 1, Pad 8 is provided centrally with the second manhole 11, reserves bolt 2 and is installed in the second manhole 11, and solid through clamp nut 3 It is scheduled on channel-section steel 1.
In order to ensure using effect, described 1 bottom surface two ends of channel-section steel are provided with the 3rd manhole 12, and supporting leg 6 is through supporting leg Adjusting nut 7 is installed in the 3rd manhole 12.
Described channel-section steel 1 has several, between be cascaded through lateral connection screw rod 5, be installed with each channel-section steel 1 many Individual pad 8, several described refer to more than 3, multiple refer to more than 2.
The a diameter of Φ 24- Φ 36 of described reserved bolt 2.
Described channel-section steel 1 is 10# channel-section steel, and length is justified for 1200mm, a size of 60mm × 800mm of rectangular through holes 9, first 10 a diameter of Φ 12 of shape through hole, for regulating bolt horizontal spacing, 12 a diameter of Φ 20 of the 3rd manhole, for adjusting mould Integral level degree.
The described a size of 83mm × 83mm of pad 8, its center is provided with a diameter of Φ 24, Φ 27, Φ 30, Φ 36 or Φ 40 The second manhole 11, according to requirement of engineering select corresponding standard component be combined fixing after use.
Service condition of the present utility model is to make the mold base with channel-section steel, in view of the steel knot of my unit construction at present Structure engineering and conventional structural steelwork experience, it is usually Φ 24- Φ 36 to need pre-buried Bolt sizes, on the basis of every pillar Bolt quantity is 6-12, and each key dimension is 200*200 600*800.According to data above, this mold base is adopted 10# channel-section steel, length 1200mm, the rectangle hole of 60mm*800mm is cut in the middle of channel-section steel, and respectively bores Φ 12 at side two ends 2, hole, for regulating bolt horizontal spacing, two side bottoms respectively bore 1,20 hole of Φ for adjusting mould integral level degree.Make circle Pass bolt mounting assembly(Pad), according to each size bolt occurred in conventional project, 10# channel-section steel is selected as standard component bottom Seat, calculated by channel-section steel parameter, pad standard component a size of 83mm*83mm, and respectively standard component bore Φ 24, Φ 27, Φ 30, Φ 36, the hole of Φ 40, select corresponding standard component to use after being combined fixing according to requirement of engineering.
Embodiment 1, by taking Ye County saltworks Toothpaste Factory factory building as an example, reserves bolt quantity and arrangement mode choosing according to scene first Select 3 channel-section steel components, according to bolt size Φ 27 select 8 Φ 30 circular hole pad 8, by reserved bolt 2 through channel-section steel with Pad 8, and temporarily being fixed with 30 nut of Φ up and down, fixes 3 bolts on every channel-section steel component, according to drawing dimensional requirement, 3 The relative spacing of bolt is 250mm, is fastened with 30 nut of Φ respectively, with 12 lateral connection screw rod of Φ after adjustment bolt relative size Three channel-section steel component two ends are connected in series, according to drawing dimensional requirement, bolt horizontal spacing is 350mm, adjusts the phase of channel-section steel 1 To being fastened with 12 lateral adjustments nut 4 of Φ after size.After the black box for assembling is put in basis, by four angles of channel-section steel On supporting leg 6 be fixed on bed course and adjusted with supporting leg nut 7 levelling, after concrete setting remove component cleaning after repeat profit With.
The utility model various models can reserve being accurately positioned and fixing difficult for bolt in all kinds of engineering constructions of effectively solving Topic, prevents occurring offset phenomena in concreting process, it is ensured that construction quality, it is to avoid construction in later period is because of pre-embedded bolt The constructional difficulties that position skew is caused, while accelerate construction speed.Ensure level interval and the relative altitude of bolt is reserved, lead to Cross die assembly and being accurately positioned for reserved bolt is achieved, used as a kind of standard component, the technology is from versatility and the circulation of grinding tool Construction cost is saved using aspect, the precision of reserved bolt has been effectively guaranteed, reduced labour intensity, solve traditional work Bolt precision is reserved in method wayward, the big and uppity difficult problem of perpendicularity of later stage Steel Structure Installation difficulty, using peace Entirely, environmental protection, revolving good, the utility model highly versatile, by channel-section steel, the selection of pad, can be required to bolt according to different Spacing and the diameter of bolt are adjusted, and the various sizes for making the utility model occur suitable for conventional project reserve bolt, Efficiency of construction, and repeatable utilization is improve while construction cost is saved, and is to reserve the innovation on bolt device, with good Good economic and social benefit.

Claims (6)

1. a kind of suitable for each size reserve bolt adjustable standard component, including base, it is characterised in that base is by channel-section steel (1) constitute with supporting leg (6), channel-section steel (1) is mounted on supporting leg (6), is vertically arranged with rectangular through holes (9) in the middle of channel-section steel (1) bottom surface, The first manhole (10) is correspondingly arranged on channel-section steel (1) two sides, and lateral connection screw rod (5) is installed on the first manhole (10) in and fixing through lateral adjustments nut (4), pad (8) is installed with channel-section steel (1), pad (8) is provided centrally with the second circle Shape through hole (11), reserves bolt (2) and is installed in the second manhole (11), and be fixed on channel-section steel (1) through clamp nut (3) On.
2. according to claim 1 suitable for each size reserve bolt adjustable standard component, it is characterised in that described Channel-section steel (1) bottom surface two ends are provided with the 3rd manhole (12), and it is circular that supporting leg (6) is installed on the 3rd through supporting leg adjusting nut (7) In through hole (12).
3. according to claim 1 suitable for each size reserve bolt adjustable standard component, it is characterised in that described Channel-section steel (1) has several, between be cascaded through lateral connection screw rod (5), is installed with multiple pads in each channel-section steel (1) (8).
4. according to claim 1 suitable for each size reserve bolt adjustable standard component, it is characterised in that described Reserved bolt (2) a diameter of Φ 24- Φ 36.
5. according to claim 1 suitable for each size reserve bolt adjustable standard component, it is characterised in that described Channel-section steel (1) is 10# channel-section steel, and length is 1200mm, rectangular through holes (9) a size of 60mm × 800mm, the first manhole (10) A diameter of Φ 12, a diameter of Φ 20 of the 3rd manhole (12).
6. according to claim 1 suitable for each size reserve bolt adjustable standard component, it is characterised in that described Pad (8) a size of 83mm × 83mm, the second circle that its center is provided with a diameter of Φ 24, Φ 27, Φ 30, Φ 36 or Φ 40 are logical Hole (11).
CN201620981602.4U 2016-08-30 2016-08-30 A kind of adjustable standard component for reserving bolt suitable for each size Expired - Fee Related CN205999915U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620981602.4U CN205999915U (en) 2016-08-30 2016-08-30 A kind of adjustable standard component for reserving bolt suitable for each size

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620981602.4U CN205999915U (en) 2016-08-30 2016-08-30 A kind of adjustable standard component for reserving bolt suitable for each size

Publications (1)

Publication Number Publication Date
CN205999915U true CN205999915U (en) 2017-03-08

Family

ID=58194613

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620981602.4U Expired - Fee Related CN205999915U (en) 2016-08-30 2016-08-30 A kind of adjustable standard component for reserving bolt suitable for each size

Country Status (1)

Country Link
CN (1) CN205999915U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109138155A (en) * 2017-06-15 2019-01-04 苏州阳地钢装配式建筑技术有限公司 Steel house frame
CN113338326A (en) * 2021-05-12 2021-09-03 中核工程咨询有限公司 Support device and method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109138155A (en) * 2017-06-15 2019-01-04 苏州阳地钢装配式建筑技术有限公司 Steel house frame
CN113338326A (en) * 2021-05-12 2021-09-03 中核工程咨询有限公司 Support device and method

Similar Documents

Publication Publication Date Title
CN102619235B (en) Concrete foundation embedded bolt bracket and embedding method for concrete foundation embedded bolts
CN202577336U (en) Positioner for square column foundation bolts
CN212002364U (en) Foundation bolt mounting and positioning device for steel structure stand column
CN202611261U (en) Preset embedded bolt support of concrete foundation
CN202913420U (en) Reusable positioning device for installing foundation bolts
CN103161177B (en) Integrated equipment quick centering device and equipment aligning method
CN205999915U (en) A kind of adjustable standard component for reserving bolt suitable for each size
CN203625921U (en) Precision control device for pre-embedded mounting of foundation bolts
CN104032969A (en) Precise positioning and process regulation and control device for vibration isolation support embedded plate
CN103835308A (en) Method for installing embedded base plate of machine tool
CN102561695A (en) Construction method for building buildings by aluminum templates
CN204570393U (en) A kind of double-block type bed plate limited impression builds servicing unit
CN206448177U (en) A kind of bridge pinner fixture components
CN210134654U (en) Adjustable floor control device
CN205791363U (en) A kind of electrical engineering positioning installation apparatus
CN205276166U (en) Guardrail stand positioner
CN201605595U (en) Equipment anchor bolt installation device
CN107059913A (en) A kind of reactor built-in fitting supporting construction and method for embedding
CN209699419U (en) A kind of formwork leveling device
JP2630623B2 (en) Anchor bolt installation method and anchor bolt support device used for it
CN217027823U (en) Installation device for embedded part of stair railing made of aluminum die technology
CN106703296A (en) Rebar locator
CN204826640U (en) Steel construction rag bolt's installation mould
CN104532743A (en) Tower girder fixed-connection mechanism, corresponding cable-stayed bridge and building method of cable-stayed bridge
JP2004036103A (en) Anchor frame and method for fixing the same

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170308

Termination date: 20200830

CF01 Termination of patent right due to non-payment of annual fee