CN205882613U CN201620716501.4U CN201620716501U CN205882613U CN 205882613 U CN205882613 U CN 205882613U CN 201620716501 U CN201620716501 U CN 201620716501U CN 205882613 U CN205882613 U CN 205882613U
Authority
CN
China
Prior art keywords
layer frame
electric power
piping lane
pccp
detachable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620716501.4U
Other languages
Chinese (zh)
Inventor
王荣
侯方
张玥
李义皓
李健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
XINJIANG GUOTONG TUBE CO Ltd
Original Assignee
XINJIANG GUOTONG TUBE CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINJIANG GUOTONG TUBE CO Ltd filed Critical XINJIANG GUOTONG TUBE CO Ltd
Priority to CN201620716501.4U priority Critical patent/CN205882613U/en
Application granted granted Critical
Publication of CN205882613U publication Critical patent/CN205882613U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

Fast -assembling layer frame can be dismantled to PCCP electric power piping lane includes tension type ring carrier (1), can dismantle mobile layer frame (2) and rises by tight bolt vice (3), the local disconnection of circle annular tension type ring carrier (1) end section, the installation is risen tight bolt vice (3) between the section of the both sides of this part in addition, and the installation is gone up in tension type ring carrier (1) can dismantle mobile layer frame (2). Nimble design is arranged and to be dismantled the mobile layer frame on the loop type support, satisfies the cable and neatly lays and standardize the requirement, and the quality is controlled easily, and the packaging efficiency is high, simple structure, the simple installation is swift, the superior performance can improve the cable installation effectiveness greatly, the installation with dismantle very conveniently, be favorable to the popularization and application of prestressing force steel cylinder concrete pipe as the foundation structure of electric power piping lane.

Description

PCCP electric power piping lane detachable fast-assembling layer frame
Technical field
This utility model relates to the structure improvement technology of electric power piping lane engineering equipment device, and especially PCCP electric power piping lane can Dismounting fast-assembling layer frame.
Background technology
PCCP electric power piping lane is i.e. to be called for short PCCP with Prestressed concrete cylinder pipe, as the corridor body structure of piping lane, at it Internally installed ring cable support system, mark time, illuminator, a kind of pipe gallery laid for electric power cable.
In urban construction, city capital construction, power supply facilities, electric power network auxiliary construction in view of current country about " by Step eliminate arterial street Aranea formula aerial line " construction demand, the promotion and application prospect of electric power piping lane will be the most extensive.
Traditional piping lane internal structure has a two ways:
1. use internal-wall concrete pre-embedded steel slab, then cable bearer is welded on pre-embedded steel slab, makes piping lane and support Base firmly connects, and forms stable overall structure, thus provides the carrying basis of sufficient intensity for cabling.
2. punching on piping lane inwall, utilize expansion bolt to be fixed by support, this mode may destroy xoncrete structure, It is unfavorable for the use of piping lane.
Utility model content
The purpose of this utility model is to provide PCCP electric power piping lane detachable fast-assembling layer frame, is not destroying electric power Pipe rack On the basis of, it is achieved the layer frame of inwall is easily installed or dismantles.
The purpose of this utility model will be realized by techniques below measure: includes swelled ring support, detachably live Dynamic layer frame and tension bolt are secondary;At the bottom of the swelled ring support of annular, section local disconnects, and at two side sections of this part Between to install tension bolt secondary, swelled ring support is installed detachable mobile layer frame.
Especially, detachable mobile layer frame is bar structure, and there is mounting seat end.
Especially, swelled ring support is spaced uniformly and arranges T-shaped mounting groove.
Especially, T-shaped mounting groove is set in swelled ring support lateral symmetry position.
Especially, bossed spacer structure on detachable mobile layer frame.
Especially, connect suspension at swelled ring support top, this suspension is installed detachable mobile layer frame.
Advantage of the present utility model and effect: on ring-like support, flexible design arranges detachable mobile layer frame, meet electricity Code requirement neatly laid by cable, and quality is easily controlled, and packaging efficiency is high, simple in construction, and simple installation is quick, and superior performance can To be greatly improved cable installation effectiveness, it is the most convenient to mount and dismount, and beneficially Prestressed concrete cylinder pipe is as power pipe The popularization and application of the base structure of corridor.
Accompanying drawing explanation
Fig. 1 is this utility model embodiment 1 structural representation.
Reference includes: swelled ring support 1, detachable mobile layer frame 2, tension bolt pair 3.
Detailed description of the invention
This utility model principle is, neat for being put in PCCP electric power piping lane by cable, is not destroying PCCP self Under structural condition, at PCCP electric power piping lane inwall, annular tensioner support is installed, and, prefabricated T-shaped groove on a toroidal support, can Dismounting mobile layer frame grafting, it is not necessary to install other components additional.
This utility model includes: swelled ring support 1, detachable mobile layer frame 2 and tension bolt pair 3.
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings.
Embodiment 1: as shown in Figure 1, swelled ring support 1 end section local of annular disconnects, and in this part Two side sections between install tension bolt pair 3, swelled ring support 1 is installed detachable mobile layer frame 2.
In aforementioned, detachable mobile layer frame 2 is bar structure, and there is mounting seat end.
In aforementioned, swelled ring support 1 is spaced uniformly and arranges T-shaped mounting groove.Detachable mobile layer frame 2 passes through tensioner T-shaped mounting groove socket connection on formula ring support 1.
In aforementioned, T-shaped mounting groove is set in swelled ring support 1 lateral symmetry position.T-shaped mounting groove installing space with And spacing determines according to the demand installing cable bearer spacing.
In aforementioned, bossed spacer structure on detachable mobile layer frame 2.This structure i.e. contributes to being relatively fixed load, And it is also prevented from the transverse shifting of cable.
In aforementioned, connect suspension at swelled ring support 1 top, this suspension is installed detachable mobile layer frame 2.
In this utility model, swelled ring support 1 external diameter is slightly less than PCCP piping lane internal diameter, and detachable mobile layer frame 2 carries Lotus and length lay number of cables and Mass Calculation with required carrying.
In the present embodiment, prefabricated mounting groove batch production on swelled ring support 1, and leave between certain cooperation Gap, steady quality.It is adjacent to swelled ring support 1 be installed on PCCP electric power piping lane inwall, and it is secondary to adjust tension bolt 3 so that swelled ring support 1 is solid and reliable;By detachable mobile layer frame 2 by side laterally inserted swelled ring support 1 On T-shaped mounting groove in, T-shaped connector bears the fastening force of ring support, firmly links together with ring support, detachably I.e. firm being connected on swelled ring support 1 of mobile layer frame 2, it is possible to bear the tiling of some cables;When certain is detachably lived When dynamic layer frame need not, in the T-shaped mounting groove of ring support, laterally extract detachable mobile layer frame out, the most convenient.

Claims (6)

1.PCCP electric power piping lane detachable fast-assembling layer frame, including swelled ring support (1), detachable mobile layer frame (2) with rise Tight bolt pair (3);It is characterized in that, swelled ring support (1) end section local of annular disconnects, and in the two of this part Installing tension bolt between side section secondary (3), swelled ring support (1) is upper installs detachable mobile layer frame (2).
2. PCCP electric power piping lane detachable fast-assembling layer frame as claimed in claim 1, it is characterised in that detachable mobile layer frame (2) it is bar structure, and there is mounting seat end.
3. PCCP electric power piping lane detachable fast-assembling layer frame as claimed in claim 1, it is characterised in that swelled ring support (1) uniform interval arranges T-shaped mounting groove.
4. PCCP electric power piping lane detachable fast-assembling layer frame as claimed in claim 1, it is characterised in that at swelled ring support (1) lateral symmetry position arranges T-shaped mounting groove.
5. PCCP electric power piping lane detachable fast-assembling layer frame as claimed in claim 1, it is characterised in that detachable mobile layer frame (2) upper bossed spacer structure.
6. PCCP electric power piping lane detachable fast-assembling layer frame as claimed in claim 1, it is characterised in that at swelled ring support (1) top connects suspension, installs detachable mobile layer frame (2) on this suspension.
CN201620716501.4U 2016-06-30 2016-06-30 Fast -assembling layer frame can be dismantled to PCCP electric power piping lane Active CN205882613U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620716501.4U CN205882613U (en) 2016-06-30 2016-06-30 Fast -assembling layer frame can be dismantled to PCCP electric power piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620716501.4U CN205882613U (en) 2016-06-30 2016-06-30 Fast -assembling layer frame can be dismantled to PCCP electric power piping lane

Publications (1)

Publication Number Publication Date
CN205882613U true CN205882613U (en) 2017-01-11

Family

ID=57695931

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620716501.4U Active CN205882613U (en) 2016-06-30 2016-06-30 Fast -assembling layer frame can be dismantled to PCCP electric power piping lane

Country Status (1)

Country Link
CN (1) CN205882613U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106921142A (en) * 2017-03-31 2017-07-04 中冶南方城市建设工程技术有限公司 Rack arrangement method when pipe gallery electric power cabin circuit sinusoidal lays straight line arranged in parallel
CN108487314A (en) * 2018-05-09 2018-09-04 湖南飞山奇建筑科技有限公司 A kind of city integrated piping lane
CN108718061A (en) * 2018-06-20 2018-10-30 昆明理工大学 A kind of pipe gallery cable bearer set shoe apparatus, its application method and application

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106921142A (en) * 2017-03-31 2017-07-04 中冶南方城市建设工程技术有限公司 Rack arrangement method when pipe gallery electric power cabin circuit sinusoidal lays straight line arranged in parallel
CN108487314A (en) * 2018-05-09 2018-09-04 湖南飞山奇建筑科技有限公司 A kind of city integrated piping lane
CN108718061A (en) * 2018-06-20 2018-10-30 昆明理工大学 A kind of pipe gallery cable bearer set shoe apparatus, its application method and application

Similar Documents

Publication Publication Date Title
CN205882613U (en) Fast -assembling layer frame can be dismantled to PCCP electric power piping lane
CN102734558A (en) Sliding system used in cable expansion arc
CN208310789U (en) A kind of integrated bracket for tunnel pre-buried channel flow
CN102996585B (en) Embracing hoop applied transformer rack assembling method
CN102040165B (en) Temporary supporting piece for installation of ropeway of cabling machine
CN201610978U (en) Pipe rack convenient for installing and repairing multilayer pipeline
CN210531750U (en) Pipeline mounting bracket convenient to use
CN211468220U (en) Contact net suspension installation device in assembled subway station
CN207959267U (en) A kind of pipe gallery C-type steel holder
CN111720626A (en) Adjustable support and hanger
CN215009423U (en) Assembled arc power cable support
CN103510521A (en) Connecting component
CN103015718A (en) Storey-through structural steel fixing support for concrete pump
CN205882644U (en) Cable is fixed with dismantling fast -assembling device in PCCP electric power piping lane
CN212359760U (en) Hydraulic arc-shaped jacking iron for jacking pipe
CN209555973U (en) The board-like electric integrated piping lane F type push pipe of pre-buried steel
CN202716030U (en) Expanding device for replacing flange gasket
CN209278631U (en) Suspension and support fixed structure
CN209607651U (en) A kind of reusable field railway high voltage isolator support device
CN203377560U (en) A cable branch box support
CN202689570U (en) Concrete distributing device and concrete pump truck
CN211172065U (en) Shared equipment foundation for multi-pipeline space
CN202658906U (en) Insertion type heel mounting device for steel structure