CN208310789U - A kind of integrated bracket for tunnel pre-buried channel flow - Google Patents

A kind of integrated bracket for tunnel pre-buried channel flow Download PDF

Info

Publication number
CN208310789U
CN208310789U CN201820652997.2U CN201820652997U CN208310789U CN 208310789 U CN208310789 U CN 208310789U CN 201820652997 U CN201820652997 U CN 201820652997U CN 208310789 U CN208310789 U CN 208310789U
Authority
CN
China
Prior art keywords
plate
channel flow
buried channel
fixed plate
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820652997.2U
Other languages
Chinese (zh)
Inventor
林森斌
李敬梅
杨毅秋
田巧焕
信磊磊
田小芳
祁寒
林家桢
李光京
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Design Corp
Original Assignee
China Railway Design Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Design Corp filed Critical China Railway Design Corp
Priority to CN201820652997.2U priority Critical patent/CN208310789U/en
Application granted granted Critical
Publication of CN208310789U publication Critical patent/CN208310789U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses a kind of integrated brackets for tunnel pre-buried channel flow, including tunnel, pre-buried channel flow is provided at the tunnel, the pre-buried channel flow side-walls are provided with arc fixed plate, and the side of the arc fixed plate, which is provided with, to be located above and support the platform support plate of evacuation platform and be located below and support multiple cable bearer plates of cable.The utility model solves traditional evacuation platform bracket and power cable bracket in the conflict of same conduit position and the disadvantage that cannot install, reduce the crossed construction problem of fixing link, the fixation to arc fixed plate is realized by middle part pre-embedded steel slab, edge pre-embedded steel slab, the support to platform support plate, cable bearer plate is realized by arc fixed plate, construction and installation are convenient, have wide industrialization prospect.

Description

A kind of integrated bracket for tunnel pre-buried channel flow
Technical field
The utility model belongs to the field of support structures of conduit, and in particular to a kind of integral type for tunnel pre-buried channel flow Bracket.
Background technique
Urban track traffic tunnel construction develops rapidly in recent years, and most newly built tunnels start using pre-buried slide groove Structure to avoid evacuation platform and cable testing bridge damage of the installation to tunnel structure.It was installed carrying out gantry using slide groove It is had the following problems in journey:
1, evacuation platform bracket and the conflict of cable bearer position, it is difficult to install;
2, there are crossed construction, construction efficiency is low for bracket installation;
3, existing integrated bracket uses bearing diagonal, causes evacuation platform plate down space utilization rate low, influences cable arrangements.
Summary of the invention
The utility model proposes in order to solve the problems existing in the prior art, a kind of pre-buried for tunnel the purpose is to provide The integrated bracket of conduit.
The technical solution of the utility model is: a kind of integrated bracket for tunnel pre-buried channel flow, including tunnel, described Pre-buried channel flow is provided at tunnel, the pre-buried channel flow side-walls are provided with arc fixed plate, the side of the arc fixed plate It is provided with and is located above and supports the platform support plate of evacuation platform and be located below and support multiple cable bearer plates of cable.
The platform support plate, cable bearer plate are horizontal.
The platform support plate, arc fixed plate, cable bearer plate are an integral molding structure.
The platform support plate, arc fixed plate free end equal thickness, platform support plate, arc fixed plate phase connection Position thickness is maximum and has round hole, and the platform support plate, arc fixed plate thickness are put down from free end to phase connection Degree of slipping over.
Middle part pre-embedded steel slab is provided in the middle part of the arc fixed plate, two edge are provided with edge to arc fixed plate up and down Pre-embedded steel slab.
Middle part T-bolt is provided in the pre-buried channel flow, the middle part T-bolt passes through middle part pre-embedded steel slab, arc Fastening nut is cased with after fixed plate.
A part of the edge pre-embedded steel slab leans out arc fixed plate, and edge T-type spiral shell is provided in the pre-buried channel flow Bolt, the edge T-bolt pass through edge pre-embedded steel slab lean out portion after be cased with fastening nut.
The middle part pre-embedded steel slab, edge pre-embedded steel slab side-walls are respectively formed vertical plate.
Platform support plate upper end forms the fixed lobe of fixed evacuation platform.
The platform support plate, arc fixed plate, cable bearer plate material are Reactive Powder Concrete material.
The utility model solves traditional evacuation platform bracket and power cable bracket and conflicts in same conduit position and not The disadvantage that can be installed, reduces the crossed construction problem of fixing link, passes through middle part pre-embedded steel slab, the realization pair of edge pre-embedded steel slab The fixation of arc fixed plate realizes the support to platform support plate, cable bearer plate, construction and installation side by arc fixed plate Just, there is wide industrialization prospect.
Detailed description of the invention
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the side schematic view of the utility model;
Wherein:
1 tunnel, 2 pre-buried channel flow
3 arc fixed plate, 4 middle part pre-embedded steel slab
5 edge pre-embedded steel slab, 6 edge T-bolt
7 middle part T-bolt, 8 platform support plate
9 cable bearer plate, 10 evacuation platform.
Specific embodiment
Hereinafter, the utility model is described in detail referring to drawings and examples:
As shown in Figure 1 and 2, a kind of integrated bracket for tunnel pre-buried channel flow, including tunnel 1 are set at the tunnel 1 It is equipped with pre-buried channel flow 2,2 side-walls of pre-buried channel flow are provided with arc fixed plate 3, the side setting of the arc fixed plate 3 There is the platform support plate 8 for being located above and supporting evacuation platform 10 and is located below and supports multiple cable bearer plates 9 of cable.
The platform support plate 8, cable bearer plate 9 are horizontal.
The platform support plate 8, arc fixed plate 3, cable bearer plate 9 are an integral molding structure.
The platform support plate 8,3 free end equal thickness of arc fixed plate, platform support plate 8, arc fixed plate 3 are connected It is maximum and have round hole to connect part thickness, the platform support plate 8,3 thickness of arc fixed plate are from free end to being connected Socket part smooth excessiveness.
Middle part pre-embedded steel slab 4 is provided in the middle part of the arc fixed plate 3, about 3 two edge of arc fixed plate is provided with Edge pre-embedded steel slab 5.
Be provided in the pre-buried channel flow 2 middle part T-bolt 7, the middle part T-bolt 7 pass through middle part pre-embedded steel slab 4, Fastening nut is cased with after arc fixed plate 3.
A part of the edge pre-embedded steel slab 5 leans out arc fixed plate 3, is provided with edge T-type in the pre-buried channel flow 2 Bolt 6, the edge T-bolt 6 pass through edge pre-embedded steel slab 5 lean out portion after be cased with fastening nut.
The middle part pre-embedded steel slab 4,5 side-walls of edge pre-embedded steel slab are respectively formed vertical plate.
8 upper end of platform support plate forms the fixed lobe of fixed evacuation platform 10.
A through-hole is formed in the middle part pre-embedded steel slab 4, the portion of leaning out of the edge pre-embedded steel slab 5 is respectively formed two and leads to Hole,
The cable bearer plate 9 is three.
The platform support plate 8, arc fixed plate 3,9 material of cable bearer plate are Reactive Powder Concrete (RPC) material.
The application method of the utility model is as follows:
1, platform support plate 8 is connected to 3 top of arc fixed plate, and 9 horizontal parallel of cable bearer plate is connected to arc and fixes Plate 3 it is ipsilateral, and be located at platform support plate 8 lower section.
2, it after the completion of the tunnel structure wait be embedded with slide groove is constructed, is incited somebody to action by edge T-bolt 6, middle part T-bolt 7 Arc fixed plate 3 with middle part pre-embedded steel slab 4, edge pre-embedded steel slab 5 is fixed on slide groove.
3, evacuation platform 10 is placed on platform support plate 8, power cable is placed on cable bearer plate 9.
The utility model solves traditional evacuation platform bracket and power cable bracket and conflicts in same conduit position and not The disadvantage that can be installed, reduces the crossed construction problem of fixing link, passes through middle part pre-embedded steel slab, the realization pair of edge pre-embedded steel slab The fixation of arc fixed plate realizes the support to platform support plate, cable bearer plate, construction and installation side by arc fixed plate Just, there is wide industrialization prospect.

Claims (10)

1. a kind of integrated bracket for tunnel pre-buried channel flow, including tunnel (1), built-in groove is provided at the tunnel (1) Road (2), it is characterised in that: pre-buried channel flow (2) side-walls are provided with arc fixed plate (3), the arc fixed plate (3) Side, which is provided with, to be located above and supports the platform support plate (8) of evacuation platform (10) and be located below and support the multiple of cable Cable bearer plate (9).
2. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 1, it is characterised in that: the platform Supporting plate (8), cable bearer plate (9) are horizontal.
3. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 1, it is characterised in that: the platform Supporting plate (8), arc fixed plate (3), cable bearer plate (9) are an integral molding structure.
4. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 3, it is characterised in that: the platform Supporting plate (8), arc fixed plate (3) free end equal thickness, platform support plate (8), arc fixed plate (3) be connected position thickness Degree is maximum and has round hole, and the platform support plate (8), arc fixed plate (3) thickness are from free end to phase connection Smooth excessiveness.
5. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 1, it is characterised in that: the arc Middle part pre-embedded steel slab (4) is provided in the middle part of fixed plate (3), two edge are provided with edge pre-buried steel to arc fixed plate (3) up and down Plate (5).
6. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 5, it is characterised in that: described pre-buried Middle part T-bolt (7) is provided in conduit (2), the middle part T-bolt (7) passes through middle part pre-embedded steel slab (4), arc is fixed Plate is cased with fastening nut after (3).
7. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 6, it is characterised in that: the edge A part of pre-embedded steel slab (5) is leant out arc fixed plate (3), is provided with edge T-bolt (6), institute in the pre-buried channel flow (2) State edge T-bolt (6) across edge pre-embedded steel slab (5) lean out portion after be cased with fastening nut.
8. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 7, it is characterised in that: the middle part Pre-embedded steel slab (4), edge pre-embedded steel slab (5) side-walls are respectively formed vertical plate.
9. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 1, it is characterised in that: the platform Supporting plate (8) upper end forms the fixed lobe of fixed evacuation platform (10).
10. a kind of integrated bracket for tunnel pre-buried channel flow according to claim 1, it is characterised in that: described flat Platform supporting plate (8), arc fixed plate (3), cable bearer plate (9) material are Reactive Powder Concrete material.
CN201820652997.2U 2018-05-04 2018-05-04 A kind of integrated bracket for tunnel pre-buried channel flow Active CN208310789U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820652997.2U CN208310789U (en) 2018-05-04 2018-05-04 A kind of integrated bracket for tunnel pre-buried channel flow

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820652997.2U CN208310789U (en) 2018-05-04 2018-05-04 A kind of integrated bracket for tunnel pre-buried channel flow

Publications (1)

Publication Number Publication Date
CN208310789U true CN208310789U (en) 2019-01-01

Family

ID=64713853

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820652997.2U Active CN208310789U (en) 2018-05-04 2018-05-04 A kind of integrated bracket for tunnel pre-buried channel flow

Country Status (1)

Country Link
CN (1) CN208310789U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374670A (en) * 2019-07-05 2019-10-25 洛阳双瑞橡塑科技有限公司 A kind of tunnel composite material evacuation platform
CN110397471A (en) * 2019-07-05 2019-11-01 洛阳双瑞橡塑科技有限公司 A kind of subway tunnel composite material evacuation platform
CN110593943A (en) * 2019-01-31 2019-12-20 洛阳双瑞橡塑科技有限公司 Evacuation platform for tunnel

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593943A (en) * 2019-01-31 2019-12-20 洛阳双瑞橡塑科技有限公司 Evacuation platform for tunnel
CN110374670A (en) * 2019-07-05 2019-10-25 洛阳双瑞橡塑科技有限公司 A kind of tunnel composite material evacuation platform
CN110397471A (en) * 2019-07-05 2019-11-01 洛阳双瑞橡塑科技有限公司 A kind of subway tunnel composite material evacuation platform

Similar Documents

Publication Publication Date Title
CN208310789U (en) A kind of integrated bracket for tunnel pre-buried channel flow
CN202074119U (en) Circular pipe rack support and circular pipe rack
CN202810209U (en) Support carrier of beam framework
CN204753357U (en) Cast -in -place pavement of voiced protective screen of inter -city railway
CN207314295U (en) A kind of structure of down-the-hole arc door siding track
CN201610978U (en) Pipe rack convenient for installing and repairing multilayer pipeline
CN211468220U (en) Contact net suspension installation device in assembled subway station
CN205985998U (en) But regulation cable mount
CN207959267U (en) A kind of pipe gallery C-type steel holder
CN208415732U (en) A kind of standing-seam color steel roofing photovoltaic support structure
CN205078923U (en) Fastening type cable support
CN216086076U (en) Utility tunnel gallows device
CN109625162A (en) The installation method of pipe in ship double bottom block
CN204753382U (en) Prefabricated pavement of voiced protective screen of inter -city railway
CN211713712U (en) Incremental launching sliding rail device with limiting function for bridge construction
CN208934466U (en) A kind of tool-type riding track
CN209653192U (en) Slidably curtain wall connecting node constructs four barrel
CN210529486U (en) Cable bridge construction
CN202730638U (en) Mounting support
CN203282585U (en) Movable steel mould with prefabricated T beam hanging belt position
CN203701282U (en) Pre-buried channel and support structure matched with same
CN106638184B (en) Multi-working-condition movable type traveling rail supporting device and using method
CN204793910U (en) Large -span cable testing bridge
CN204845598U (en) Busbar support insulator
CN201093122Y (en) Cable support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant