CN205875227U - Utilize pore pressure to provide foundation structure of bearing capacity - Google Patents

Utilize pore pressure to provide foundation structure of bearing capacity Download PDF

Info

Publication number
CN205875227U
CN205875227U CN201620817955.0U CN201620817955U CN205875227U CN 205875227 U CN205875227 U CN 205875227U CN 201620817955 U CN201620817955 U CN 201620817955U CN 205875227 U CN205875227 U CN 205875227U
Authority
CN
China
Prior art keywords
soft clay
clay layer
bed course
ground
saturated soft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620817955.0U
Other languages
Chinese (zh)
Inventor
魏纲
黄文�
姜鑫
林雄
朱田宇
王霄
蔡诗淇
姜婉青
黄絮
张佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University City College ZUCC
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN201620817955.0U priority Critical patent/CN205875227U/en
Application granted granted Critical
Publication of CN205875227U publication Critical patent/CN205875227U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The utility model provides an utilize pore pressure to provide foundation structure of bearing capacity, including stereoplasm water proof bed course, stagnant water curtain, impermeable stratum and saturated soft clay layer, stereoplasm water proof bed course is laid on ground base surface, plays to prevent ground to emit the purpose of water and deformation. The soft clay layer of saturation clamp is located between stereoplasm water proof bed course and the impermeable stratum, wherein: stereoplasm water proof bed course lies in the up end on saturated soft clay layer, and impermeable stratum lies in the lower terminal surface on saturated soft clay layer, stagnant water curtain parcel is in the side end face on the soft clay layer of saturation. The utility model adopts the above technical scheme, little this unfavorable factor of clay osmotic coefficient turns into the favorable factor in foundation treatment originally, utilizes the higher balanced additional stress of hole water osmotic pressure in the clay. Recoverable engineering materials after the ground function is accomplished pulls out the slip casting pipe, retrieves upper portion stereoplasm water proof bed course, recovers the nature original appearance, compares present ground project organization, and this foundation structure time limit for a project is shorter, more green.

Description

A kind of foundation structure utilizing pore pressure to provide bearing capacity
Technical field
This utility model belongs to field of foundation treatment, particularly relates to a kind of ground base junction utilizing pore pressure to provide bearing capacity Structure.
Background technology
In actual production, the more scheme of general employing has soil cement reinforcing, draining concretion method or close compacting method of shaking to reinforce Ground.
When the reinforcement means using cement mixing pile, high-pressure rotary jet grouting pile etc. to pour into solidfied material, soil body composition is permanent Changing, the later stage also is difficult to recover original appearance.The solidfied material such as cement enter the soil body can cause soil and groundwater for a long time and There is the pollution of persistence.
When using draining concretion method consolidated subsoil in saturated soft clay, owing to Permeability Coefficient of Foundation is little, Super-void Water Pressure Power dissipates and needs the long period, for the beta site needing short-period used, i.e. can not meet construction period also inadequate warp Ji.Also due to the dissipation of excess pore-water pressure time is long, the duration that rammer method of shaking reinforces saturated clay ground is the most relatively long, and DeGrain.
Utility model content
In order to solve above-mentioned technical problem, the purpose of this utility model is to provide one and utilizes pore pressure to provide carrying The foundation structure of power, including hard waterproof cushion, water-stop curtain, impermeable stratum and saturated soft clay layer, hard waterproof cushion spreads It is located on foundation surface, plays the purpose stoping ground to emit water and deformation.Saturated soft clay layer be located in hard waterproof cushion and Between impermeable stratum, wherein: hard waterproof cushion is positioned at the upper surface of saturated soft clay layer, impermeable stratum is positioned at saturated soft clay The lower surface of layer;Water-stop curtain is wrapped in the side end face of saturated soft clay layer.
As preferably, in saturated soft clay layer, also it is injected with mud.
As preferably, described hard waterproof cushion is reinforced concrete floor.
As preferably, described water-stop curtain is steel sheet pile, and steel sheet pile, in addition to preferable water-resisting property, also can be carried out after using Reclaim.Set around Ground Treatment water-stop curtain play prevention the soil body squeeze to around, slow down pore water pressure and dissipate to around Purpose.
As preferably, lay the hard plate material of water proof as bed course at foundation surface, play prevention ground and emit water and deformation Purpose.Selection for bed course needs to consider the difference of field condition, original ground is existed to the feelings of higher-strength crust layer Condition can select board-like bed course, such as the steel plate of suitable thickness.Can when there is no crust layer or crust layer intensity is the highest To use the prefabricated box bed course that rigidity is bigger, material can select steel or armored concrete according to requirement of strength and recovery convenience Material.Around Ground Treatment, plug slip casting steel pipe, inject the mud of suitable severe to the bottom of Ground Treatment with suitable pressure, It is continuously replenished the pore water pressure dissipated during ground uses.Mud severe determines according to concrete engineering, and main purpose is not The pore water pressure that disconnected supplementary ground dissipates during using.A large amount of mud is not required to for saturated soft clay layer, but ties up Hold the pore water pressure in stratum.
Compared with prior art, the beneficial effects of the utility model are:
This utility model uses technique scheme, will originally in basement process clay infiltration coefficient little this unfavorable because of Element is converted into favorable factor, utilizes pore water osmotic pressure balance additional stress higher in clay.
Ground function is recyclable engineering material after completing, and pulls out Grouting Pipe, reclaims top hard waterproof cushion, recovers nature Original appearance, compares existing Foundation Design structure, and this foundation structure duration is shorter, more environmental protection.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Detailed description of the invention
Below in conjunction with the accompanying drawings detailed description of the invention of the present utility model is made a detailed explanation.
Embodiment 1:
As it is shown in figure 1, this utility model provides the concrete real of a kind of foundation structure utilizing pore pressure to provide bearing capacity Executing example, including hard waterproof cushion, water-stop curtain, impermeable stratum and saturated soft clay layer, hard waterproof cushion is laid on ground On surface, play the purpose stoping ground to emit water and deformation.Saturated soft clay layer is located in hard waterproof cushion and impermeable stratum Between, wherein: hard waterproof cushion is positioned at the upper surface of saturated soft clay layer, impermeable stratum is positioned at the lower end of saturated soft clay layer Face;Water-stop curtain is wrapped in the side end face of saturated soft clay layer.
Wherein: being also injected with mud in saturated soft clay layer, described hard waterproof cushion is reinforced concrete floor, described Water-stop curtain is steel sheet pile, and steel sheet pile, in addition to preferable water-resisting property, also may be recovered after using.Beat around Ground Treatment If water-stop curtain plays prevention, the soil body squeezes to around, slows down pore water pressure to the purpose around dissipated.
Lay the hard plate material of water proof as bed course at foundation surface, play the purpose stoping ground to emit water and deformation.Right Selection in bed course needs to consider the difference of field condition, can select when there is higher-strength crust layer for original ground Board-like bed course, such as the steel plate of suitable thickness.Rigidity can be used when there is no crust layer or crust layer intensity is the highest Bigger prefabricated box bed course, material can select steel or Reinforced Concrete Materials according to requirement of strength and recovery convenience.At place Plug slip casting steel pipe around reason ground, inject the mud of suitable severe to the bottom of Ground Treatment with suitable pressure, be continuously replenished The pore water pressure that ground dissipates during using.Mud severe determines according to concrete engineering, and main purpose is for being continuously replenished ground The pore water pressure that base dissipates during using.A large amount of mud is not required to for saturated soft clay layer, but maintains in stratum Pore water pressure.
This utility model uses technique scheme, will originally in basement process clay infiltration coefficient little this unfavorable because of Element is converted into favorable factor, utilizes pore water osmotic pressure balance additional stress higher in clay.
Ground function is recyclable engineering material after completing, and pulls out Grouting Pipe, reclaims top hard waterproof cushion, recovers nature Original appearance, compares the design of existing basement process, and this foundation structure duration is shorter, more environmental protection.
It is emphasized that: be the most only preferred embodiment of the present utility model, not this utility model appointed What pro forma restriction, every according to technical spirit of the present utility model, above example is made any simple modification, etc. With change and modification, all still fall within the range of technical solutions of the utility model.

Claims (4)

1. one kind utilizes the foundation structure that pore pressure provides bearing capacity, it is characterised in that include hard waterproof cushion, sealing curtain Curtain, impermeable stratum and saturated soft clay layer, hard waterproof cushion is laid on foundation surface, and saturated soft clay layer is located in hard Between waterproof cushion and impermeable stratum, wherein: hard waterproof cushion is positioned at the upper surface of saturated soft clay layer, and impermeable stratum is positioned at The lower surface of saturated soft clay layer;Water-stop curtain is wrapped in the side end face of saturated soft clay layer.
2. according to a kind of foundation structure utilizing pore pressure to provide bearing capacity described in claim 1, it is characterised in that Mud also it is injected with in saturated soft clay layer.
3., according to a kind of foundation structure utilizing pore pressure to provide bearing capacity described in claim 1 or 2, its feature exists In, described hard waterproof cushion is steel plate or reinforced concrete floor.
4., according to a kind of foundation structure utilizing pore pressure to provide bearing capacity described in claim 1 or 2, its feature exists In, described water-stop curtain is steel sheet pile.
CN201620817955.0U 2016-07-28 2016-07-28 Utilize pore pressure to provide foundation structure of bearing capacity Expired - Fee Related CN205875227U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620817955.0U CN205875227U (en) 2016-07-28 2016-07-28 Utilize pore pressure to provide foundation structure of bearing capacity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620817955.0U CN205875227U (en) 2016-07-28 2016-07-28 Utilize pore pressure to provide foundation structure of bearing capacity

Publications (1)

Publication Number Publication Date
CN205875227U true CN205875227U (en) 2017-01-11

Family

ID=57699880

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620817955.0U Expired - Fee Related CN205875227U (en) 2016-07-28 2016-07-28 Utilize pore pressure to provide foundation structure of bearing capacity

Country Status (1)

Country Link
CN (1) CN205875227U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241662A (en) * 2018-10-19 2019-09-17 北京恒祥宏业基础加固技术有限公司 A kind of high-speed railway subgrade differential settlement reinforcing lifting leveling method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110241662A (en) * 2018-10-19 2019-09-17 北京恒祥宏业基础加固技术有限公司 A kind of high-speed railway subgrade differential settlement reinforcing lifting leveling method

Similar Documents

Publication Publication Date Title
CN101270571B (en) Reinforcing method for layered dead weight, prepressing water discharge concretion combination dynamic consolidation soft ground base
CN101591904B (en) Method for strengthening composite pile foundation by prepressing drainage and following grouting for drainage body
CN103233454B (en) Processing method of soaking, vacuum preloading and slurry injecting for sand piles of collapsible loess foundation
CN101265701A (en) Soft soil foundation reinforcing means
CN101914918B (en) High-steep side slope and intensely weathered bed rock solid waste landfill site seepage prevention structure and treatment method thereof
CN103215960A (en) Grouting method for high polymer vertical support system
CN103437371B (en) Construction method of water drainage uplift pile
CN203393530U (en) Anti-floating lightweight high-fill embankment structure
CN105804007B (en) A kind of reinforced earth quaywall structure based on the soft base of beach
CN101838984A (en) Afforestation ecological fabric reinforcing method and structure
CN205636721U (en) Strain equipment that well vacuum preloading consolidated deep soft soil foundation
CN104060601B (en) The construction method of utilizing precast construction stake pile foundation to carry out ground processing
CN101597898B (en) Rigid drainage pile and construction method thereof
CN105672323A (en) Compound soil nail wall supporting structure system with steel pipe piles and construction method of compound soil nail wall supporting structure system
CN108203985A (en) A kind of prestressed soil nailing assembled supporting construction and its construction method
CN205134303U (en) Compound reinforced structure of soft base of ecological bamboo raft among road engineering of field
CN105804045A (en) Equipment for strengthening deep soft soil foundation by vacuum preloading of filter well and method
CN205875227U (en) Utilize pore pressure to provide foundation structure of bearing capacity
CN206666956U (en) A kind of highway subgrade soft soil slope composite reinforcing structure
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN208803456U (en) A kind of structure for reinforcing peat soil using sand pile and drain bar
CN102787608A (en) Gravity type foundation pit supporting system under vacuum effect and construction method
CN105484270A (en) Reinforcement protection construction method of high steep old rubble retaining wall adjacent to deep foundation pit
KR20130090596A (en) Eco-composite type steel temporary construction and construction method thereof
CN216040465U (en) Ecological roadbed structure in sponge city based on original road

Legal Events

Date Code Title Description
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Wei Gang

Inventor after: Zhang Xinhai

Inventor after: Lin Xiong

Inventor after: Wang Xiao

Inventor after: Hua Xinxin

Inventor after: Li Jing

Inventor after: Zhu Tianyu

Inventor after: Cui Chenghong

Inventor after: Yu Haoqiang

Inventor before: Wei Gang

Inventor before: Zhang Jia

Inventor before: Huang Wen

Inventor before: Jiang Xin

Inventor before: Lin Xiong

Inventor before: Zhu Tianyu

Inventor before: Wang Xiao

Inventor before: Cai Shiqi

Inventor before: Jiang Wanqing

Inventor before: Huang Xu

COR Change of bibliographic data
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170111