CN205805609U - A kind of underground mine powder ore recovery system - Google Patents

A kind of underground mine powder ore recovery system Download PDF

Info

Publication number
CN205805609U
CN205805609U CN201620740486.7U CN201620740486U CN205805609U CN 205805609 U CN205805609 U CN 205805609U CN 201620740486 U CN201620740486 U CN 201620740486U CN 205805609 U CN205805609 U CN 205805609U
Authority
CN
China
Prior art keywords
fine ore
shaft
ore
auxiliary shaft
belt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620740486.7U
Other languages
Chinese (zh)
Inventor
李万涛
闫满志
刘万富
王磊
刘辉
范天文
程晓博
张继伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Iron and Steel Group Mining Co Ltd
HBIS Co Ltd
Original Assignee
HBIS Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HBIS Co Ltd filed Critical HBIS Co Ltd
Priority to CN201620740486.7U priority Critical patent/CN205805609U/en
Application granted granted Critical
Publication of CN205805609U publication Critical patent/CN205805609U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of underground mine powder ore recovery system, belong to mining technique field, for reducing the cost recovery of fine ore, its technical scheme is, it includes auxiliary shaft, auxiliary shaft fine ore haulage drift, fine ore drop shaft, vibrations ore drawing machine, fine ore collection lane and belt-conveying tunnel, and bottom with main shaft and auxiliary shaft respectively, the two ends in described fine ore collection lane is connected;Described belt-conveying tunnel is positioned at the top in fine ore collection lane, and the tail end in belt-conveying tunnel is connected with main shaft;Described auxiliary shaft fine ore haulage drift is higher than belt-conveying tunnel, and the head end of auxiliary shaft fine ore haulage drift is connected with auxiliary shaft, and tail end is connected by the head end of fine ore drop shaft with belt-conveying tunnel;Described vibrations ore drawing machine is arranged on the lower end of fine ore drop shaft.This utility model utilizes main shaft, auxiliary shaft and tunnel therebetween to reclaim the fine ore bottom main shaft, it is to avoid building in a large number of special facilities, substantially reduces the quantities of powder ore recovery system, thus effectively reduces the cost recovery of fine ore.

Description

A kind of underground mine powder ore recovery system
Technical field
This utility model relates to the powder ore recovery system of a kind of underground mine slip-breaking system, belongs to mining technique field.
Background technology
When the main shaft hoisting system of underground mine runs, Ore can be scattering into shaft bottom to some extent, forms fine ore, fine ore Accumulate and will affect the properly functioning of main shaft hoisting system to a certain extent, it is therefore necessary to clear up in time.Generally, The fine ore being scattered mostly is Ore, has value, need to be again with main shaft hoisting system and carry to earth's surface.Traditional fine ore collection Method is both needed to build a set of special powder ore recovery system, including promote interior shaft, drainage system, fine ore bin, Pass drawing machine, A series of fine ore collection facility such as elevator, could be by the fine ore collection in shaft bottom to earth's surface.There is system knot in this recovery method The shortcomings such as structure is complicated, big, the performance difficulty of quantities, considerably increase the cost recovery of fine ore.
Utility model content
The purpose of this utility model is the drawback for prior art, it is provided that a kind of underground mine powder ore recovery system, To reduce recovery system quantities, reduce the cost recovery of fine ore.
Problem described in the utility model realizes with following technical proposals:
A kind of underground mine powder ore recovery system, composition includes that auxiliary shaft, auxiliary shaft fine ore haulage drift, fine ore slip Well, vibrations ore drawing machine, fine ore collection lane and belt-conveying tunnel, the two ends in described fine ore collection lane respectively with main shaft and pair The bottom of well shaft connects;Described belt-conveying tunnel is positioned at the top in fine ore collection lane, the tail end in belt-conveying tunnel and master Well shaft is connected;Described auxiliary shaft fine ore haulage drift is higher than belt-conveying tunnel, the head end of auxiliary shaft fine ore haulage drift and auxiliary shaft Pit shaft is connected, and tail end is connected by the head end of fine ore drop shaft with belt-conveying tunnel;Described vibrations ore drawing machine is arranged on fine ore and slips The lower end of well.
Above-mentioned underground mine powder ore recovery system, one end that described auxiliary shaft fine ore haulage drift connects with auxiliary shaft is provided with Auxiliary shaft great Jian road ingate;One end that described belt-conveying tunnel connects with main shaft is provided with main shaft dress stage casing, ore deposit ingate; One end that described fine ore collection lane connects with main shaft is provided with main shaft fine ore collection stage casing ingate, connects with auxiliary shaft One end is provided with auxiliary shaft fine ore stage casing ingate.
This utility model utilizes main shaft, auxiliary shaft and tunnel therebetween to carry out back the fine ore being scattering into bottom main shaft Receive, it is to avoid building in a large number of special facilities, substantially reduce the quantities of powder ore recovery system, thus effectively reduce fine ore Cost recovery.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model.
In figure, labelling is as follows: 1, auxiliary shaft;2, auxiliary shaft great Jian road ingate;3, auxiliary shaft fine ore haulage drift;4, fine ore Drop shaft;5, vibrations ore drawing machine;6, auxiliary shaft fine ore stage casing ingate;7, fine ore collection lane;8, belt-conveying tunnel;9, the big part of main shaft Road ingate;10, main shaft;11, main shaft dress stage casing, ore deposit ingate;12, main shaft fine ore collection stage casing ingate.
Detailed description of the invention
The utility model is described in further detail below in conjunction with the accompanying drawings.
Referring to Fig. 1, this utility model include auxiliary shaft 1, auxiliary shaft great Jian road ingate 2, auxiliary shaft fine ore haulage drift 3, Fine ore drop shaft 4, vibrations ore drawing machine 5, auxiliary shaft fine ore stage casing ingate 6, fine ore collection lane 7, belt-conveying tunnel 8, main shaft 10, main shaft dress stage casing, ore deposit ingate 11 and main shaft fine ore collection stage casing ingate 12.
When this powder ore recovery system runs, lodge in the fine ore bottom main shaft 10 and loaded onto electronic fortune by electric loader Defeated car, electric transporting vehicle is in fine ore collection lane 7 travels the cage to auxiliary shaft 1, then is promoted to skin through auxiliary shaft 1 With the great Jian road height of haulage drift more than 8, then travel to fine ore drop shaft 4 and by fine ore through auxiliary shaft fine ore haulage drift 3 Unload to fine ore drop shaft 4, the vibrations ore drawing machine 5 bottom fine ore drop shaft 4 fine ore is progressively transferred to the skin in belt-conveying tunnel 8 In band, then transport to main shaft metering loading chamber, be finally promoted to earth's surface.
This underground mine powder ore recovery system Appropriate application lane through between auxiliary-well takeup and main shaft, auxiliary shaft Road, simplifies the technological process of powder ore recovery system, is not required to arrange the fine ore collection facilities such as special interior shaft, decreases fine ore The quantities of recovery system, has saved engineering construction investment.

Claims (2)

1. a underground mine powder ore recovery system, is characterized in that, composition includes auxiliary shaft (1), auxiliary shaft fine ore transportation roadway Road (3), fine ore drop shaft (4), vibrations ore drawing machine (5), fine ore collection lane (7) and belt-conveying tunnel (8), described fine ore collection lane (7) bottom with main shaft (10) and auxiliary shaft (1) respectively, two ends is connected;Described belt-conveying tunnel (8) is positioned at powder The top in recovery lane, ore deposit (7), the tail end of belt-conveying tunnel (8) is connected with main shaft (10);Described auxiliary shaft fine ore transportation roadway Road (3) is higher than belt-conveying tunnel (8), and the head end of auxiliary shaft fine ore haulage drift (3) is connected with auxiliary shaft (1), and tail end passes through Fine ore drop shaft (4) connects with the head end of belt-conveying tunnel (8);Described vibrations ore drawing machine (5) is arranged under fine ore drop shaft (4) End.
A kind of underground mine powder ore recovery system the most according to claim 1, is characterized in that, described auxiliary shaft fine ore transportation roadway One end that road (3) connects with auxiliary shaft (1) is provided with auxiliary shaft great Jian road ingate (2);Described belt-conveying tunnel (8) and main shaft One end that pit shaft (10) connects is provided with main shaft dress stage casing, ore deposit ingate (11);Described fine ore collection lane (7) and main shaft (10) The one end connected is provided with main shaft fine ore collection stage casing ingate (12), and the one end connected with auxiliary shaft (1) is provided with auxiliary shaft fine ore Stage casing ingate (6).
CN201620740486.7U 2016-07-14 2016-07-14 A kind of underground mine powder ore recovery system Active CN205805609U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620740486.7U CN205805609U (en) 2016-07-14 2016-07-14 A kind of underground mine powder ore recovery system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620740486.7U CN205805609U (en) 2016-07-14 2016-07-14 A kind of underground mine powder ore recovery system

Publications (1)

Publication Number Publication Date
CN205805609U true CN205805609U (en) 2016-12-14

Family

ID=57511266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620740486.7U Active CN205805609U (en) 2016-07-14 2016-07-14 A kind of underground mine powder ore recovery system

Country Status (1)

Country Link
CN (1) CN205805609U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022121A (en) * 2019-12-24 2020-04-17 中矿金业股份有限公司 Fine ore recovery system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022121A (en) * 2019-12-24 2020-04-17 中矿金业股份有限公司 Fine ore recovery system

Similar Documents

Publication Publication Date Title
CN107100639B (en) Shield transportation system for large-particle-size sand pebbles
CN201574753U (en) Cantilever type tunneling machine
CN104033153A (en) Coal mine underground mining, dress and filling integral method
CN104653182B (en) A kind of coal-mining method that the bastard coal of coal seam containing thick dirt band point is adopted
CN102444401B (en) Coal mining method by filling on blasting mining face of thin coal seam and relevant equipment
CN110424966A (en) A kind of pumping of ultrahigh water material filling working face spoil stays lane without pillar mining method
CN101660414B (en) Method for conveying coal in end slope laneway in open pit coal mine
CN111322073A (en) Combined mine exploitation system based on vertical shaft and adhesive tape inclined shaft
CN205805609U (en) A kind of underground mine powder ore recovery system
CN1782326B (en) Method for treating waste rock in coal mine
CN1952349A (en) Mining method for replacement of pressed coal under village by waste rock
CN103821530A (en) Continuous excavating equipment and process for roadways
CN104763467B (en) Obturation and its placement method and system for Hazard in Deep Metal Mines goaf
CN104234714B (en) A kind of underground coal mine green high-efficient transporting method
CN203783634U (en) Mineral powder recycling structure for underground mine
CN208633835U (en) A kind of Mechanized that equipment train is separated with glue fortune crossheading
CN202544921U (en) Gangue discharging device in rock gangway rapid tunneling process
CN104481533A (en) Underground mine and ore lifting method
CN205311736U (en) Detachable is used for opencut coal mine developing conveyer
CN208294564U (en) Single track end type unloads mine system
RU2394158C1 (en) Procedure for open pit development of mineral deposits
CN102619558A (en) Rock roadway rapid excavation and gangue elimination system and gangue elimination method
CN205135700U (en) Continuous conveyor system of waste rock
CN103043077B (en) Quick shunting system for tunneling slag discharge mining cars in underground roadway of mine
CN201963354U (en) Float coal recycle machine at exit on thin seam coal face

Legal Events

Date Code Title Description
C14 Grant of patent or utility model