CN205677226U CN201620586800.0U CN201620586800U CN205677226U CN 205677226 U CN205677226 U CN 205677226U CN 201620586800 U CN201620586800 U CN 201620586800U CN 205677226 U CN205677226 U CN 205677226U
Authority
CN
China
Prior art keywords
channel
steel
section steel
girder
node
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620586800.0U
Other languages
Chinese (zh)
Inventor
王保健
黄革
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HUASHEN STEEL STRUCTURE SICHUAN LLC
Original Assignee
HUASHEN STEEL STRUCTURE SICHUAN LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUASHEN STEEL STRUCTURE SICHUAN LLC filed Critical HUASHEN STEEL STRUCTURE SICHUAN LLC
Priority to CN201620586800.0U priority Critical patent/CN205677226U/en
Application granted granted Critical
Publication of CN205677226U publication Critical patent/CN205677226U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

This utility model discloses a kind of post beam and installs the safe operation platform of node, and including girder steel and channel-section steel A, described girder steel includes that web and flange plate, described channel-section steel A include waist and leg;Described girder steel is two, and two girder steels are the most right, and the web of two girder steels is parallel;Being respectively equipped with two through holes on the flange plate of both sides, described girder steel top, through hole is symmetrical arranged;Described channel-section steel A is two, and described channel-section steel A is separately positioned on the both sides of girder steel, the waist of channel-section steel A and the flange plate laminating of girder steel;Described channel-section steel A is vertical with girder steel direction, and channel-section steel A and girder steel are bolted;This utility model is when carrying out steel column, steel beam joint welding or high-strength bolt and connecting, and workmen may stand on safe and reliable operating surface, carries out weld job or high-strength bolt operation, it is possible to is easy to construction and ensures safety.

Description

A kind of post beam installs the safe operation platform of node
Technical field
This utility model relates to building field, particularly relates to a kind of post beam and installs the safe operation platform of node.
Background technology
When carrying out steel column, steel beam joint welding or high-strength bolt and connecting, workmen needs to stand in safe and reliable behaviour Make on face.Generally way is that workmen stands in and carries out weld job on steel cat ladder (or steel hanging ladder, rope ladder) or high-strength bolt is made Industry, this kind of mode is not easy to construction and safety is poor.
Utility model content
This utility model aims to provide a kind of post beam and installs the safe operation platform of node, it is possible to make workmen stand in peace Full operating surface reliably carries out operation.
For reaching above-mentioned purpose, the technical solution adopted in the utility model is as follows:
A kind of post beam installs the safe operation platform of node, and including girder steel and channel-section steel A, described girder steel includes web and the edge of a wing Plate, described channel-section steel A includes waist and leg;Described girder steel is two, and two girder steels are the most right, and the web of two girder steels is parallel, steel Beam is vertically arranged;Being respectively equipped with two through holes on the flange plate of both sides, described girder steel top, through hole is symmetrical arranged;Described channel-section steel A Being two, described channel-section steel A is separately positioned on the both sides of girder steel, the waist of channel-section steel A and the flange plate laminating of girder steel;Described channel-section steel A Vertical with girder steel direction, channel-section steel A and girder steel are bolted;It is additionally provided with channel-section steel B, channel-section steel B outside described channel-section steel A two ends to include Waist and leg;Described channel-section steel B leg flushes with channel-section steel A leg, and channel-section steel B and channel-section steel A direction is vertical;Above described channel-section steel A also Being provided with scaffold board, described scaffold board is placed on channel-section steel B, channel-section steel A;The right part upper surface of described channel-section steel B upper end leg is provided with hurdle Bar vertical rod, passes through fastener for connection between adjacent handrails vertical rod.
Preferably, described bolt isDouble end stay bolt, quantity is 2.
Preferably, described channel-section steel A and channel-section steel B is welded to connect, and described channel-section steel B is welded to connect with railing vertical rod, described steel pipe It is welded to connect with railing vertical rod.
Preferably, described railing vertical rod is up and down formula railing vertical rod.
Preferably, described steel pipe is upper and lower two-layer, and steel pipe model isSteel pipe.
Preferably, described scaffold board is connected by galvanized wire with channel-section steel B, channel-section steel A.
Preferably, described steel beam web plate being additionally provided with rope ladder, rope ladder top is additionally provided with seat belt.
Preferably, described steel beam web plate is additionally provided with catching device.
Preferably, described channel-section steel A length is more than channel-section steel B length.
This utility model is when carrying out steel column, steel beam joint welding or high-strength bolt and connecting, and workmen may stand in peace Entirely, on reliable operating surface, carry out weld job or high-strength bolt operation, it is possible to be easy to construction and ensure safety.
Accompanying drawing explanation
Fig. 1 is this utility model structural representation.
In figure:, 1-girder steel, 2-channel-section steel A 3-channel-section steel B, 4-bolt, 5-scaffold board, 6-railing vertical rod, 7-steel pipe, 8-rope Ladder, 9-catching device, 10-seat belt.
Detailed description of the invention
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing, to this reality It is further elaborated with novel.
As it is shown in figure 1, a kind of post beam installs the safe operation platform of node, including girder steel 1 and channel-section steel A2, described girder steel 1 Including web and flange plate, described channel-section steel A2 includes waist and leg;Described girder steel 1 is two, and two girder steels 1 are the most right, two The web of girder steel 1 is parallel, and girder steel 1 is vertically arranged;It is respectively equipped with two through holes on the flange plate of both sides, described girder steel 1 top, logical Hole is symmetrical arranged;Described channel-section steel A2 is two, and described channel-section steel A2 is separately positioned on the both sides of girder steel 1, the waist of channel-section steel A2 and steel The flange plate laminating of beam 1;Described channel-section steel A2 is vertical with girder steel 1 direction, and channel-section steel A2 and girder steel 1 are connected by bolt 4;Described channel-section steel It is additionally provided with channel-section steel B3, channel-section steel B3 outside A2 two ends and includes waist and leg;Described channel-section steel B3 leg flushes with channel-section steel A2 leg, groove Steel B3 and channel-section steel A2 direction is vertical;Described channel-section steel A2 is also arranged above scaffold board 5, and described scaffold board 5 is placed on channel-section steel B3, channel-section steel On A2;The right part upper surface of described channel-section steel B3 upper end leg is provided with railing vertical rod 6, between adjacent handrails vertical rod 6 by steel pipe 7 even Connect.
Preferably, described bolt 4 isDouble end stay bolt, quantity is 2.
Preferably, described channel-section steel A2 and channel-section steel B3 is welded to connect, and described channel-section steel B3 is welded to connect with railing vertical rod 6, described Steel pipe 7 is welded to connect with railing vertical rod 6.
Preferably, described railing vertical rod 6 is up and down formula railing vertical rod.
Preferably, described steel pipe 7 is upper and lower two-layer, and steel pipe 7 model isSteel pipe.
Preferably, described scaffold board 5 is connected by galvanized wire with channel-section steel B3, channel-section steel A2.
Preferably, described girder steel 1 web being additionally provided with rope ladder 8, rope ladder 8 top is additionally provided with seat belt 10.
Preferably, described girder steel 1 web is additionally provided with catching device 9.
Preferably, described channel-section steel A2 length is more than channel-section steel B3 length.
This utility model is when carrying out steel column, steel beam joint welding or high-strength bolt and connecting, and workmen may stand in peace Entirely, on reliable operating surface, carry out weld job or high-strength bolt operation, it is possible to be easy to construction and ensure safety.
Certainly, this utility model also can have other various embodiments, spiritual and essence without departing substantially from this utility model In the case of, those of ordinary skill in the art can make various corresponding change and deformation according to this utility model, but these phases Change and the deformation answered all should belong to the scope of the claims appended by this utility model.

Claims (9)

1. the safe operation platform of a post beam installation node, it is characterised in that: including girder steel and channel-section steel A, described girder steel includes Web and flange plate, described channel-section steel A includes waist and leg;Described girder steel is two, and two girder steels are the most right, the abdomen of two girder steels Plate is parallel, and girder steel is vertically arranged;Being respectively equipped with two through holes on the flange plate of both sides, described girder steel top, through hole is symmetrical arranged; Described channel-section steel A is two, and described channel-section steel A is separately positioned on the both sides of girder steel, the waist of channel-section steel A and the flange plate laminating of girder steel; Described channel-section steel A is vertical with girder steel direction, and channel-section steel A and girder steel are bolted;It is additionally provided with channel-section steel B outside described channel-section steel A two ends, Channel-section steel B includes waist and leg;Described channel-section steel B leg flushes with channel-section steel A leg, and channel-section steel B and channel-section steel A direction is vertical;Described groove Steel A is also arranged above scaffold board, and described scaffold board is placed on channel-section steel A and channel-section steel B;On the right part of described channel-section steel B upper end leg Surface is provided with railing vertical rod, passes through fastener for connection between adjacent handrails vertical rod.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described bolt isDouble end stay bolt, quantity is 2.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described channel-section steel A Being welded to connect with channel-section steel B, described channel-section steel B is welded to connect with railing vertical rod, and described steel pipe is welded to connect with railing vertical rod.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described railing stands Bar is up and down formula railing vertical rod.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described steel pipe is Two-layer up and down, steel pipe model isSteel pipe.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described scaffold board It is connected by galvanized wire with channel-section steel B, channel-section steel A.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described girder steel abdomen Being additionally provided with rope ladder on plate, rope ladder top is additionally provided with seat belt.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described girder steel abdomen Catching device it is additionally provided with on plate.
A kind of post beam the most according to claim 1 installs the safe operation platform of node, it is characterised in that: described channel-section steel A Length is more than channel-section steel B length.
CN201620586800.0U 2016-06-14 2016-06-14 A kind of post beam installs the safe operation platform of node Expired - Fee Related CN205677226U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620586800.0U CN205677226U (en) 2016-06-14 2016-06-14 A kind of post beam installs the safe operation platform of node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620586800.0U CN205677226U (en) 2016-06-14 2016-06-14 A kind of post beam installs the safe operation platform of node

Publications (1)

Publication Number Publication Date
CN205677226U true CN205677226U (en) 2016-11-09

Family

ID=57432680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620586800.0U Expired - Fee Related CN205677226U (en) 2016-06-14 2016-06-14 A kind of post beam installs the safe operation platform of node

Country Status (1)

Country Link
CN (1) CN205677226U (en)

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN203905425U (en) Elevator shaft construction-tool operating platform and safety protection integrated structure
CN202099993U (en) Lift type external scaffold made of square steel pipes
CN207609153U (en) A kind of elevator liftable construction operation platform
CN210217095U (en) Hanging basket suspension operation system for steel beam
CN207191310U (en) One kind is used for ship plank construction portable unit
CN205743040U (en) A kind of integrated form material hoisting platform
CN205677226U (en) A kind of post beam installs the safe operation platform of node
CN206707237U (en) Cable-stayed type top layer construction platform for elevator installation
CN101695984B (en) Assembly method and assembly lifting appliance of vertical beam and horizontal beam under arc of midheight deck steel pipe concrete arch bridge
CN205840289U (en) A kind of suspension type vertical operating platform
CN209194362U (en) Rod piece connects levelling device between a kind of suspension bridge steel truss beam section
CN205577451U (en) Instrument formula protection frame suitable for assemble integral concrete horizontal element
CN205259573U (en) A hanging flower basket hangs mechanism for high -rise roofing transformation
CN208309394U (en) A kind of template assembly platform of prefabricated stand column
CN211228177U (en) Slurry splashing prevention device used during bridge flange plate dismantling
CN209367678U (en) Crane rail structure
CN208869171U (en) One kind lifting reusable porous grade for steelwork tower truss and hangs lid
CN208830767U (en) A kind of assembled architecture hoistway regularization protection and vertical passageway device
CN205555882U (en) Heavy single track hangs
CN206128595U (en) Scaffold that encorbelments frame shaped steel platform
JP2021075967A (en) Suspended scaffolding
CN105464218B (en) One kind landing truss bearing pin connecting joint structure
CN208981813U (en) A kind of safety device of roof system installation
CN211472213U (en) Deck type railway steel truss bridge construction hanging basket

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161109