CN206128595U - Scaffold that encorbelments frame shaped steel platform - Google Patents

Scaffold that encorbelments frame shaped steel platform Download PDF

Info

Publication number
CN206128595U
CN206128595U CN201621080279.XU CN201621080279U CN206128595U CN 206128595 U CN206128595 U CN 206128595U CN 201621080279 U CN201621080279 U CN 201621080279U CN 206128595 U CN206128595 U CN 206128595U
Authority
CN
China
Prior art keywords
steel
platform
cantilever beams
section
steel platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621080279.XU
Other languages
Chinese (zh)
Inventor
诸纪萍
金齐伟
钱恒泽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Dadongwu Group Construction Co Ltd
Original Assignee
Zhejiang Dadongwu Group Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Dadongwu Group Construction Co Ltd filed Critical Zhejiang Dadongwu Group Construction Co Ltd
Priority to CN201621080279.XU priority Critical patent/CN206128595U/en
Application granted granted Critical
Publication of CN206128595U publication Critical patent/CN206128595U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a scaffold that encorbelments frame shaped steel platform, including at least two the shaped steel platforms of encorbelmenting that are used for support scaffold that set up side by side, the shaped steel platform of encorbelmenting include a plurality of I -steel cantilever beam that set up side by side, with I -steel cantilever beam vertical cross and welded fastening's a plurality of channel -section steels and the full profiled sheet of spreading on this encorbelments the shaped steel platform to it encorbelments the steel that is equipped with the butt joint between the shaped steel platform and turns over the board to arrange double -phase neighbour, the steel turns over board and I -steel cantilever beam, and to pass through the hinge articulated, and the steel of two butt joints turns over and is equipped with connecting reinforcement between the board, welded fastening had the steel bar ring who supplies connecting reinforcement to pass on the steel turned over the board, still included the protection network device. The utility model discloses encorbelmenting the steel that is equipped with the butt joint between the shaped steel platform double -phase neighbour side by side and turning over the board, there is the potential safety hazard in the position of avoiding meeting, and the outside edge of the shaped steel platform of encorbelmenting simultaneously is equipped with the guardrail and adopts the protection network device, and can effectually make scaffold rest base portion and the outer facade of building protects.

Description

Builder's jack section steel platform
Technical field
This utility model is related to building construction technology, more particularly to builder's jack.
Background technology
Builder's jack section steel platform is the common structure in construction, will not only carry scaffold, will also meet and apply The convenient requirement with safety of work.
Utility model content
Technical problem to be solved in the utility model is just to provide a kind of builder's jack section steel platform, meets construction just The requirement of prompt and safety.
To solve above-mentioned technical problem, this utility model is adopted the following technical scheme that:Builder's jack section steel platform, including At least two overhanging type steel platforms for support scaffolding being arranged side by side, the overhanging type steel platform include some setting side by side The I-steel Cantilever Beams put and the square crossing of I-steel Cantilever Beams some channel-section steels for being welded and fixed and completely it is layered on the type of encorbelmenting Profiled sheet in steel platform, the I-steel Cantilever Beams are included with the anchoring section of lower floor structural plane anchoring and from lower floor Section that what Rotating fields face extended out encorbelment, the outer end of the section of encorbelmenting is connected with steel wire rope, the upper end and upper strata of the steel wire rope Floor structure face is fixed, and the anchoring section is fixed with lower floor structural plane by anchor, and the anchor includes pre- The U-shaped reinforcing bar being embedded in lower floor structural plane, the peristome of the U-shaped reinforcing bar is above lower floor structural plane and by work Word steel Cantilever Beams are surrounded, and the peristome both sides termination of the U-shaped reinforcing bar is provided with the bending being pressed abd fixed on I-steel Cantilever Beams Portion, is provided with the steel turnover panel of docking side by side between two adjacent overhanging type steel platforms, the steel turnover panel is with I-steel Cantilever Beams by closing Page is hinged, and is provided with connection reinforcing bar between the steel turnover panel of two docking, is welded with what is passed through for connection reinforcing bar on the steel turnover panel Reinforced steel bar ring, also including protective net apparatus, the protective net apparatus include that some being extended to from overhanging type steel platform obliquely is encorbelmented Longitudinal steel pipe and some horizontal steel pipes fixed by fastener with longitudinal steel pipe of top, the protection network on the outside of section steel platform Device is provided with protection network in guardrail Outboard Sections.
Preferably, the outer ledge of the overhanging type steel platform is provided with guardrail, and the guardrail includes square steel skeleton and paving The steel wire being located on square steel skeleton.
Preferably, the bottom of the guardrail is provided with foot guard plate made by profiled sheet, and the square steel skeleton is hanged with I-steel Oblique pull reinforcing bar is provided between outrigger.
Preferably, on guardrail, the inner of longitudinal steel pipe is connected with short steel pipes to longitudinal steel pipe support, described short Steel pipe is welded and fixed with I-steel Cantilever Beams.
Preferably, the I-steel Cantilever Beams are welded with spacer bar, and the lower floor structural plane is provided with for fixed The location hole of position reinforcing bar insertion.
The technical solution adopted in the utility model, serves not only as overhanging scaffold erection there is provided operation platform, and and Arrange the steel turnover panel that docking is provided between two adjacent overhanging type steel platforms, it is to avoid connecting part has potential safety hazard, while type of encorbelmenting The outer ledge of steel platform is provided with guardrail and adopts protective net apparatus, can effectively carry out scaffold bottom and facade is anti- Shield.
Description of the drawings
With reference to the accompanying drawings and detailed description this utility model is further described:
Fig. 1 is the planar structure schematic diagram (not laying profiled sheet) of overhanging type steel platform;
Fig. 2 is the connection diagram of steel turnover panel;
Fig. 3 is general structure schematic diagram of the present utility model;
Fig. 4 is the structure chart anchored to I-steel Cantilever Beams by anchor;
Fig. 5 is the elevational schematic view of guardrail.
Specific embodiment
As shown in Figure 1 to Figure 3, builder's jack section steel platform, including at least two be arranged side by side for support feet handss The overhanging type steel platform 1 of frame 6, the overhanging type steel platform include some I-steel Cantilever Beams 11 being arranged side by side, and I-steel Cantilever Beams square crossing some channel-section steels 12 for being welded and fixed and the profiled sheet being completely layered on the overhanging type steel platform, it is described I-steel Cantilever Beams 11 include the anchoring section with the anchoring of lower floor structural plane and from hanging that lower floor structural plane is extended out Section is chosen, the outer end of the section of encorbelmenting is connected with steel wire rope 5, and upper end and the upper floors structural plane of the steel wire rope are fixed, described Anchoring section is fixed with lower floor structural plane by anchor.It is provided with the steel of docking side by side between two adjacent overhanging type steel platforms Turnover panel 2, the steel turnover panel are hinged by hinge 22 with I-steel Cantilever Beams, are provided with attachment structure between the steel turnover panel of two docking 21, the attachment structure includes connecting reinforcing bar 212, and the reinforced steel bar ring 211 passed through for connection reinforcing bar is welded with the steel turnover panel. The I-steel Cantilever Beams are welded with spacer bar 111, and the lower floor structural plane is provided with for spacer bar insertion Location hole.
As shown in figure 4, the anchor 10 includes the pre- U-shaped reinforcing bar 101 being embedded in lower floor structural plane, the U The peristome of steel bar is surrounded above lower floor structural plane and by I-steel Cantilever Beams, the peristome of the U-shaped reinforcing bar Both sides termination is provided with the bending part being pressed abd fixed on I-steel Cantilever Beams.Be provided with the lower floor structural plane series connection through The stiffener 102 of U-shaped reinforcing bar inside bottom, the aperture of the U-shaped reinforcing bar are provided with I-steel Cantilever Beams both sides wedge Tight timber wedge 103.
The outer ledge of the overhanging type steel platform is provided with guardrail 3.As shown in figure 5, the guardrail includes square steel skeleton 31 And the steel wire 32 being laid on square steel skeleton.The bottom of the guardrail is provided with foot guard plate 33 made by profiled sheet, described Oblique pull reinforcing bar 34 is provided between square steel skeleton and I-steel Cantilever Beams.
In addition, also including protective net apparatus 4, the protective net apparatus include some extending from overhanging type steel platform obliquely Longitudinal steel pipe 41 and some horizontal steel pipes 42 fixed by fastener with longitudinal steel pipe of top to overhanging type steel platform, The protective net apparatus are provided with protection network 43 in guardrail Outboard Sections.Longitudinal steel pipe support on guardrail, longitudinal steel The inner of pipe is connected with short steel pipes 411, and the short steel pipes are welded and fixed with I-steel Cantilever Beams.
Every section of platform connects integral using three or two 8# channel-section steels of a plurality of 16# I-steel Cantilever Beams, upper completely to spread 4mm Thick profiled sheet.Cantilever steel girder anchoring depth is no less than builder's jack position and encorbelments 1.25 times of segment length.Protection network Span length will guarantee to meet height operation falling-preventing and fall the requirement of radius.
Using method:
1) make each component at the scene by rod member full-page proof size, it is desirable to size accurately, welding portion full weld, steel plate and shaped steel Connected using spot welding.
2) first be hoisted to concentrate in the floor structure plane that need to install with tower crane and stack, after the completion of with tower crane by section steel platform It is hoisted to above installation site, platform is slowly put down, then distance structure plane 1.5m or so, installation personnel is by section steel platform end The I-steel in portion is slowly put down into pre-buried good U-shaped reinforcing bar after buttressing.
3), after section steel platform is put in place, U-shaped reinforcing bar sleeve pipe is bent and is embraced after steel I-beam, welded immediately, Single-sided welding length is not less than 10d.
4), after each segment type steel platform is installed in place, turned on the I-steel of adjacent segment using steel turnover panel in the middle of each section of platform, And connect reinforcing bar through the reinforced steel bar ring being welded with steel plate with three ф 20HPB300, hang form junction steel plate.After the completion of, Dismountable guard rail is installed again.
5) stage+module completes to carry out immediately thereon setting up for scaffold and horizontal protective frame.
6) after builder's jack is removed, if if scene adopts hanging basket, can be used as the stopping platform of hanging basket.

Claims (5)

1. builder's jack section steel platform, including at least two overhanging type steel platforms for support scaffolding being arranged side by side, The overhanging type steel platform includes some I-steel Cantilever Beams being arranged side by side and the square crossing of I-steel Cantilever Beams and welds solid Fixed some channel-section steels and the profiled sheet being completely layered on the overhanging type steel platform, the I-steel Cantilever Beams include and lower floor The anchoring section and the section of encorbelmenting extended out from lower floor structural plane of Rotating fields face anchoring, the outer end of the section of encorbelmenting is connected with Steel wire rope, upper end and the upper floors structural plane of the steel wire rope are fixed, and the anchoring section passes through anchor and lower floor Structural plane is fixed, it is characterised in that:The anchor includes the pre- U-shaped reinforcing bar being embedded in lower floor structural plane, described U-shaped The peristome of reinforcing bar is surrounded above lower floor structural plane and by I-steel Cantilever Beams, the peristome two of the U-shaped reinforcing bar Side head is provided with the bending part being pressed abd fixed on I-steel Cantilever Beams, is provided with docking side by side between two adjacent overhanging type steel platforms Steel turnover panel, the steel turnover panel is hinged by hinge with I-steel Cantilever Beams, is provided with connection reinforcing bar between the steel turnover panels of two docking, The reinforced steel bar ring passed through for connection reinforcing bar, also including protective net apparatus, the protective net apparatus are welded with the steel turnover panel Including it is some from overhanging type steel platform extend on the outside of overhanging type steel platform obliquely top longitudinal steel pipe and it is some with it is vertical To the horizontal steel pipe that steel pipe is fixed by fastener, the protective net apparatus are provided with protection network in guardrail Outboard Sections.
2. builder's jack section steel platform according to claim 1, it is characterised in that:The outside of the overhanging type steel platform Edge is provided with guardrail, the steel wire that the guardrail includes square steel skeleton and is laid on square steel skeleton.
3. builder's jack section steel platform according to claim 2, it is characterised in that:The bottom of the guardrail is provided with die mould Foot guard plate made by steel plate, is provided with oblique pull reinforcing bar between the square steel skeleton and I-steel Cantilever Beams.
4. builder's jack section steel platform according to claim 1, it is characterised in that:Longitudinal steel pipe support is in guardrail On, the inner of longitudinal steel pipe is connected with short steel pipes, and the short steel pipes are welded and fixed with I-steel Cantilever Beams.
5. builder's jack section steel platform according to claim 1, it is characterised in that:The I-steel Cantilever Beams welding is solid Surely there is spacer bar, the lower floor structural plane is provided with the location hole for spacer bar insertion.
CN201621080279.XU 2016-09-26 2016-09-26 Scaffold that encorbelments frame shaped steel platform Expired - Fee Related CN206128595U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621080279.XU CN206128595U (en) 2016-09-26 2016-09-26 Scaffold that encorbelments frame shaped steel platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621080279.XU CN206128595U (en) 2016-09-26 2016-09-26 Scaffold that encorbelments frame shaped steel platform

Publications (1)

Publication Number Publication Date
CN206128595U true CN206128595U (en) 2017-04-26

Family

ID=58570606

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621080279.XU Expired - Fee Related CN206128595U (en) 2016-09-26 2016-09-26 Scaffold that encorbelments frame shaped steel platform

Country Status (1)

Country Link
CN (1) CN206128595U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108301631A (en) * 2018-03-27 2018-07-20 中铁十六局集团城市建设发展有限公司 A kind of horizontal hard protection system of integrated form floor edge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108301631A (en) * 2018-03-27 2018-07-20 中铁十六局集团城市建设发展有限公司 A kind of horizontal hard protection system of integrated form floor edge

Similar Documents

Publication Publication Date Title
CN108643544B (en) High-altitude overhanging construction platform support system and construction method
CN104196222B (en) The suspension scaffold of tools type section steel builder's jack
CN110952763A (en) Construction method of externally-hung type externally-hung overhanging scaffold
CN108677962B (en) Subway entrance and exit segment foundation pit formwork installing and dismantling method
CN111779248A (en) High formwork system and construction method thereof
CN202481956U (en) Attached climbing type conventionalized dual-purpose platform
CN107227814B (en) A kind of large cantilever concrete structure section construction method
CN206128595U (en) Scaffold that encorbelments frame shaped steel platform
CN105971110A (en) Construction method for fire control corridor steel structure supporting system
CN107882065B (en) Operating platform for concrete beam construction above rail-mounted area and building method thereof
CN206128596U (en) Scaffold that encorbelments frame shaped steel platform package assembly
CN203307733U (en) Construction platform system of concrete pier of viaduct
CN115627912A (en) Construction method of assembled externally-mounted flower basket type overhanging scaffold
CN212201400U (en) Assembled steel structure external hanging type protective frame
CN104831928A (en) Construction method for high-altitude large-span concrete connected structure formwork supporting steel platform
CN106522566B (en) A kind of roof system steel truss sliding rail and assembly and disassembly methods
CN211313380U (en) Ultrahigh independent frame beam template supporting system
CN114215333A (en) Rapid construction method for outer cornice of high-rise building
CN112854702A (en) Large-span silo roof construction platform and erection method
CN111962850A (en) Construction method of overhanging scaffold
CN207633583U (en) A kind of connection structure of prefabricated post and prefabricated partition wall
CN110952764A (en) Externally hung type externally hung overhanging scaffold
CN215858988U (en) Reinforced attachment structure for attached lifting scaffold and system thereof
CN215167934U (en) Large-span silo roofing construction platform bottom pillar
CN215107081U (en) Large-span silo roofing construction platform shore

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170426

Termination date: 20210926