CN205637280U - Dry tile hanging structure of light steel slope roof basic level - Google Patents

Dry tile hanging structure of light steel slope roof basic level Download PDF

Info

Publication number
CN205637280U
CN205637280U CN201620512919.3U CN201620512919U CN205637280U CN 205637280 U CN205637280 U CN 205637280U CN 201620512919 U CN201620512919 U CN 201620512919U CN 205637280 U CN205637280 U CN 205637280U
Authority
CN
China
Prior art keywords
sheet
piece
plank
preformed hole
tile sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620512919.3U
Other languages
Chinese (zh)
Inventor
葛主强
楼少敏
程昉
赵可成
彭春晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG PROVINCIAL ERJIAN CONSTRUCTION GROUP CO Ltd
Original Assignee
ZHEJIANG PROVINCIAL ERJIAN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG PROVINCIAL ERJIAN CONSTRUCTION GROUP CO Ltd filed Critical ZHEJIANG PROVINCIAL ERJIAN CONSTRUCTION GROUP CO Ltd
Priority to CN201620512919.3U priority Critical patent/CN205637280U/en
Application granted granted Critical
Publication of CN205637280U publication Critical patent/CN205637280U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a dry tile hanging structure of light steel slope roof basic level, it includes light steel slope roof basic level and duo gen stand, light steel slope roof basic level upper berth is equipped with one deck plank (6), has laid one deck waterproofing membrane (7) on plank (6), is fixed with many the counter batten parallel with the slant girder (8) on waterproofing membrane (7), be equipped with perpendicular be listed as tiling piece (10) on every counter batten (8), every tiling piece (10) comprise arc main part (10.1) and last arc piece (10.2), the upper surface of going up arc piece (10.2) rear end is fixed with the lower surface laminating of arc main part (10.1) front end, upward be equipped with the second preformed hole on arc piece (10.2), follow closely on plank (6) through the self tapping screw who passes second preformed hole and counter batten (8) every tiling piece (10). This structural seismic performance is good, construction cycle short, simple to operate.

Description

The cladding tile structure of Qing Gang pitched roof basic unit
Technical field
This utility model relates to the renovation of building in field of civil engineering and decoration construction technology, is especially a kind of light steel The cladding tile structure of pitched roof basic unit.
Background technology
China is during carrying out new Urbanization Construction, ecology botanical garden city and reconstruction of the old city town, and being frequently run onto needs will building The flat roof deck of thing is transformed into the situation of pitched roof.
Conventional mode adds, on the basis of being utilized in Yuanping City's roofing, the pitched roof watering one layer of reinforced concrete structure, surface layer watt Construction is usually taken dry-laid and two kinds of modes of wet-laying: dry-laid method refers on the pitched roof reached concrete design strength solid The most horizontal fixed tile batten, is hooked on the most successively by tile on each self-corresponding tile batten, but this form of construction work is Big drawback is that every block of tile is all to be hooked on tile batten and pushed down by the tile of top, and the connected mode of tile is the most firm, Its poor seismic behavior, tile runs into vibration, strong wind etc. and easily drops.Another kind is exactly wet-laid process, and it is in coagulation slight slope room One layer of cement mortar is glued on upper berth, face, then is bondd by tile block-by-block, although this form of construction work improves tile compared with dry-laid method Anti-seismic performance, but its to execute engineering process loaded down with trivial details and the load of former roof structure is also greatly increased, thus cause needing First carry out original structure basic unit (basis in the most former house) reinforcing and just carrying out pitched roof rebuilding construction after reinforcement, this Sample not only increases construction cost and also extends construction period, is also unfavorable for carrying out of green construction and environmental protection work.
Utility model content
The technical problems to be solved in the utility model is to provide that a kind of anti-seismic performance is good, short construction period, easy for installation, knot Structure is from the cladding tile structure of Qing Gang pitched roof basic unit of heavy and light and economical rationality.
Technical solution of the present utility model is to provide the cladding tile structure of a kind of Qing Gang pitched roof basic unit, and it includes by level To girder, oblique girder, level is to secondary beam and the Qing Gang pitched roof basic unit of oblique linking beam composition and supports light steel pitched roof Many root posts of basic unit;It is equipped with one layer of plank in Qing Gang pitched roof basic unit, plank has been laid one layer of waterproof roll, waterproof The many counter battens parallel with oblique girder it are fixed with on coiled material;
Being provided with one between every two adjacent counter battens and erect row under tile sheet, the upper end of every piece of under tile sheet is provided with the first preformed hole, often Block under tile sheet is followed closely on plank through the self-tapping screw through the first preformed hole, and the lower end of every piece of under tile sheet covers in next of same column First preformed hole of block under tile sheet;
Every counter battens is provided with one and erects row cover tile sheet, and every piece of cover tile sheet is made up of curved body and upper arc-like sheet, upper arc-like sheet The upper surface of rear end is fixing with the lower surface laminating of curved body front end, and upper arc-like sheet is provided with the second preformed hole, every piece of cover tile Sheet is followed closely on plank through the self-tapping screw through the second preformed hole and counter battens, and every piece of cover tile sheet lower end covers in next of same column The upper arc-like sheet of block cover tile sheet.
The cladding tile structure of this utility model Qing Gang pitched roof basic unit is utilized to change the construction method of pitched roof to carry out flat roof deck, its step Suddenly include:
A, fix on flat roof deck multiple rows of along ridge direction extend column, the many root posts being positioned at same row are contour;And from The direction that ridge is vertical is seen, many root posts are again in column distribution, and in every string column, the column on both sides is low and the column of centre high;
B, fixing two oblique girders at every string column top, two oblique girders of same column are that herringbone is symmetrical, use Oblique girder is coupled together integrant frame structure to girder by many levels;
C, between every two adjacent oblique girders weld multiple tracks level to secondary beam, then two adjacent levels to secondary beam it Between or between girder, weld oblique linking beam to secondary beam and level, to constitute light steel pitched roof base two adjacent levels Layer;
D, in Qing Gang pitched roof basic unit, fix one layer of plank, and stick one layer of waterproof roll on plank upper berth;
E, on waterproof roll, fix the many counter battens parallel with oblique girder;
F, fixing one from the bottom up erect row under tile sheet between every two adjacent counter battens, every piece of under tile sheet is through pre-through first Boxing out and the self-tapping screw of waterproof roll is followed closely on plank, the lower end of every piece of under tile sheet covers in next block under tile sheet of same column First preformed hole;
G, fixing one erect row cover tile sheet on every counter battens, every piece of cover tile sheet is through through the second preformed hole and the self tapping of counter battens Screw is on plank, and every piece of cover tile sheet lower end covers in the upper arc-like sheet of next block cover tile sheet of same column so that with string Whole curved body of cover tile sheet are positioned in same cambered surface.
The cladding tile structure of this utility model Qing Gang pitched roof basic unit compared with prior art, has the following advantages and effect:
First, each piece of cover tile sheet and each piece of under tile sheet are all to be clenched in the way of cladding by self-tapping screw, so, watt Sheet fixation, shock resistance is good, runs into strong wind or vibrations are difficult to drop;Secondly, this roof structure is ensureing the premise of intensity Under, deadweight is relatively light, compared to the roofing of pouring reinforcement concrete structure and with mortar bonding, the technical program quick construction side Just, consumption material is few;And, above-mentioned cover tile sheet and under tile sheet all can use the aluminium alloy tile that length is longer than plain tiles, So, originally one erect that every meter of row tile must lay 3 to 4 and one to erect row tile every after using now lengthening aluminium alloy tile Rice has only to lay a piece of, so, further speeds up speed of application, also considerably reduces labor intensity, while the most also Greatly strengthen the perception effect of roofing.
Accompanying drawing explanation
Fig. 1 is the structural representation of the Qing Gang pitched roof basic unit of the cladding tile structure of this utility model Qing Gang pitched roof basic unit.
Fig. 2 is that the section of the cladding tile structure of this utility model Qing Gang pitched roof basic unit looks up structural representation.
Fig. 3 is the partial side sectional structure signal that the one of the cladding tile structure of this utility model Qing Gang pitched roof basic unit erects row under tile sheet Figure.
Fig. 4 is the partial side sectional structure signal that the one of the cladding tile structure of this utility model Qing Gang pitched roof basic unit erects row cover tile sheet Figure.
Fig. 5 is the structure for amplifying schematic diagram of the cover tile sheet of the cladding tile structure of this utility model Qing Gang pitched roof basic unit.
Shown in figure 1, column, 2, horizontal girder, 3, oblique linking beam, 4, level to secondary beam, 5, room, light steel slope Face basic unit, 6, plank, 7, waterproof roll, 8, counter battens, 9, under tile sheet, 10, cover tile sheet, 10.1, curved body, 10.2, upper arc-like sheet, 11, oblique girder.
Detailed description of the invention
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, the cladding tile structure of this utility model Qing Gang pitched roof basic unit, its bag Include the Qing Gang pitched roof basic unit 5 being made up of to secondary beam 4 and oblique linking beam 3 to girder 2, oblique girder 11, level level And many root posts of supporting Qing Gang pitched roof basic unit 5.Convenient for statement, first unify a concept, level to refer to The direction that ridge is parallel, and the oblique width referring to namely roofing vertical with ridge.Whole water on same roofing Put down to girder 2, oblique girder 11, oblique linking beam 3 and level to the components such as secondary beam 4 connect node upper surface in room On face the most concordant, so constitute Qing Gang pitched roof basic unit 5.
It is equipped with one layer of plank 6 in Qing Gang pitched roof basic unit 5, plank 6 has been laid thick adhesive waterproof of one layer of 2mm Coiled material 7, waterproof roll 7 is fixed with the many aluminium alloy counter battens 8 parallel with oblique girder 11.
Being provided with one between every two adjacent counter battens 8 and erect row under tile sheet 9, the upper end of every piece of under tile sheet 9 is provided with first and reserves Hole, every piece of under tile sheet 9 is followed closely on plank 6 through the self-tapping screw through the first preformed hole and waterproof roll 7 in the way of cladding. The lower end of every piece of under tile sheet 9 covers in the first preformed hole of next block under tile sheet 9 of same column;Certainly, position in same perpendicular row First preformed hole of the highest under tile sheet 9 can be covered by cover plate fixing on ridge realize waterproof.
Every counter battens 8 is provided with one and erects row cover tile sheet 10, and every piece of cover tile sheet 10 is by curved body 10.1 and upper arc-like sheet 10.2 Constituting, the upper surface of upper arc-like sheet 10.2 rear end is fixing with the lower surface laminating of curved body 10.1 front end, curved body 10.1 It is integrated with upper both arc-like sheets 10.2, curved body 10.1 and upper arc-like sheet 10.2 concentric.On upper arc-like sheet 10.2 Being provided with the second preformed hole, every piece of cover tile sheet 10 is followed closely through the self-tapping screw through the second preformed hole and counter battens 8 in the way of cladding On plank 6, every piece of cover tile sheet 10 lower end covers in the upper arc-like sheet 10.2 of next block cover tile sheet 10 of same column.So, The curved body 10.1 of all cover tile sheets 10 of same perpendicular row is positioned on same arcwall face, and in same perpendicular row, position is the highest The second preformed hole of one piece of cover tile sheet 10 can be covered by cover plate fixing on ridge realize waterproof.
As shown in Figure 1, Figure 2, shown in Fig. 3, Fig. 4, Fig. 5, the cladding tile structure of this utility model Qing Gang pitched roof basic unit is utilized to enter Row flat roof deck changes the construction method of pitched roof, and its step includes.
A, fix on flat roof deck multiple rows of along ridge direction extend column 1, the many root posts 1 being positioned at same row are contour;And In terms of the direction vertical with ridge, many root posts 1 are again in column distribution, in every string column 1 column 1 on both sides low and in Between column 1 high;The base for post of flat roof deck can be spirally connected by fixing means with column 1 bottom, it would however also be possible to employ is welded and fixed.
B, column 1 top being distributed with ridge vertical direction on every string edge are fixed as welded two oblique girders 11, same column Two oblique girders 11 symmetrical in herringbone, oblique girder 11 is connected as welded to girder 2 by many levels Carry out integrant frame structure.
C, between every two adjacent oblique girders 11 weld multiple tracks level to secondary beam 4, then two adjacent levels to Weld oblique linking beam 3 between secondary beam 4, or a level to girder 2 and with this level to adjacent one of girder 2 Level welds oblique linking beam 3 between secondary beam 4, to constitute Qing Gang pitched roof basic unit 5.
Whole levels on same roofing to girder 2, oblique girder 11, level to structures such as secondary beam 4 and oblique linking beams 3 The upper surface that part connects node is the most concordant, to constitute Qing Gang pitched roof basic unit 5.
D, in Qing Gang pitched roof basic unit 5, fix one layer of anti-corrosion wood board 6, and stick the thick band of one layer of 2mm on plank 6 upper berth The waterproof roll 7 of autohension.
E, on waterproof roll 7, fix the many counter battens 8 parallel with oblique girder 11, specifically, be with through zinc-plated The brill tail self-drilling screw of antirust treatment is fixed through after aluminium alloy counter battens 8 and plank 6 with Qing Gang pitched roof basic unit 5.
F, fixing one from the bottom up erect row under tile sheet 9 between every two adjacent counter battens 8, every piece of under tile sheet 9 is through passing The self-tapping screw of the first preformed hole and waterproof roll 7 is followed closely on plank 6, and the lower end of every piece of under tile sheet 9 covers under same column First preformed hole of one piece of under tile sheet 9.
G, every counter battens 8 fixed one erect row cover tile sheet 10, every piece of cover tile sheet 10 in the way of cladding through through second The self-tapping screw of preformed hole and counter battens 8 is followed closely on plank 6, and every piece of cover tile sheet 10 lower end covers in next block cover tile of same column The upper arc-like sheet 10.2 of sheet 10 so that be positioned in same cambered surface with whole curved body 10.1 of the cover tile sheet 10 of string.
H, a level the highest in ridge position i.e. position are to the long lid of the system that top constant cross-section is circular arc of girder 2 Plate, for covering the second preformed hole of the highest cover tile sheet 10 of the first preformed hole of the highest under tile sheet 9 in position and position.This The facade Construction treatment of sample, had both seemed tall and straight, attractive in appearance, had had again rainwater leakage prevention function.

Claims (1)

1. a cladding tile structure of Zhong Qinggang pitched roof basic unit, it is characterised in that: it includes by level to girder (2), oblique Qing Gang pitched roof basic unit (5) that girder (11), level are constituted to secondary beam (4) and oblique linking beam (3) and supporting Many root posts of Qing Gang pitched roof basic unit (5);One layer of plank (6), plank it is equipped with on Qing Gang pitched roof basic unit (5) (6) laid one layer of waterproof roll (7) on, waterproof roll (7) is fixed with many parallel with oblique girder (11) Counter battens (8);
Being provided with one between every two adjacent counter battens (8) and erect row under tile sheet (9), the upper end of every piece of under tile sheet (9) sets The first preformed hole, every piece of under tile sheet (9) is had to follow closely on plank (6) through the self-tapping screw through the first preformed hole, every piece The lower end of under tile sheet (9) covers in the first preformed hole of next block under tile sheet (9) of same column;
Every counter battens (8) is provided with one and erects row cover tile sheet (10), and every piece of cover tile sheet (10) is by curved body (10.1) Constitute with upper arc-like sheet (10.2), the upper surface of upper arc-like sheet (10.2) rear end and curved body (10.1) front end Lower surface laminating is fixing, and upper arc-like sheet (10.2) is provided with the second preformed hole, and every piece of cover tile sheet (10) is through through second The self-tapping screw of preformed hole and counter battens (8) is followed closely on plank (6), and every piece of cover tile sheet (10) lower end covers in same column The upper arc-like sheet (10.2) of next block cover tile sheet (10).
CN201620512919.3U 2016-05-30 2016-05-30 Dry tile hanging structure of light steel slope roof basic level Withdrawn - After Issue CN205637280U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620512919.3U CN205637280U (en) 2016-05-30 2016-05-30 Dry tile hanging structure of light steel slope roof basic level

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620512919.3U CN205637280U (en) 2016-05-30 2016-05-30 Dry tile hanging structure of light steel slope roof basic level

Publications (1)

Publication Number Publication Date
CN205637280U true CN205637280U (en) 2016-10-12

Family

ID=57051181

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620512919.3U Withdrawn - After Issue CN205637280U (en) 2016-05-30 2016-05-30 Dry tile hanging structure of light steel slope roof basic level

Country Status (1)

Country Link
CN (1) CN205637280U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888114A (en) * 2016-05-30 2016-08-24 浙江省二建建设集团有限公司 Light steel slope roof foundation layer dry tile hanging structure and construction method of changing plane roof into slope roof
CN108798060A (en) * 2018-07-09 2018-11-13 四川农业大学 A kind of anti-skid and waterproof reinforcing slips strip device suit being suitable for traditional tile roofing
CN108798061A (en) * 2018-07-09 2018-11-13 四川农业大学 One kind being suitable for traditional tile roofing anti-skid mesh bracing means suit
CN114961069A (en) * 2022-07-14 2022-08-30 中建三局第一建设工程有限责任公司 Steel structure frame system small blue tile roof structure and construction method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105888114A (en) * 2016-05-30 2016-08-24 浙江省二建建设集团有限公司 Light steel slope roof foundation layer dry tile hanging structure and construction method of changing plane roof into slope roof
CN105888114B (en) * 2016-05-30 2018-06-05 浙江省二建建设集团有限公司 The cladding tile structure of Qing Gang pitched roofs base and flat roof deck change the construction method of pitched roof
CN108798060A (en) * 2018-07-09 2018-11-13 四川农业大学 A kind of anti-skid and waterproof reinforcing slips strip device suit being suitable for traditional tile roofing
CN108798061A (en) * 2018-07-09 2018-11-13 四川农业大学 One kind being suitable for traditional tile roofing anti-skid mesh bracing means suit
CN108798061B (en) * 2018-07-09 2023-08-15 四川农业大学 Reinforcing apparatus suit suitable for traditional tile roofing antiskid net
CN108798060B (en) * 2018-07-09 2023-08-15 四川农业大学 Slip strip device suit is consolidated in waterproof antiskid suitable for traditional tile roofing
CN114961069A (en) * 2022-07-14 2022-08-30 中建三局第一建设工程有限责任公司 Steel structure frame system small blue tile roof structure and construction method thereof
CN114961069B (en) * 2022-07-14 2023-10-27 中建三局第一建设工程有限责任公司 Small green tile roof structure of steel structure frame system and construction method thereof

Similar Documents

Publication Publication Date Title
CN106401040B (en) The method that the cladding tile structure of Qing Gang pitched roofs base and flat roof deck change pitched roof
CN205637280U (en) Dry tile hanging structure of light steel slope roof basic level
CN1231647C (en) Cellular-core structural panel and building structure incorporating same
CN103711262A (en) Surface magnesium manganese alloy roof boarding system construction method
CN106284857A (en) A kind of construction technology of aluminium sheet roofing standing-seam system
CN103195214A (en) Wood roof cornice decking and concrete composite structure in archaized buildings and construction method thereof
CN104612246A (en) Assembled monolithic concrete large-span frame structure system and assembling method thereof
CN205637279U (en) Dry tile hanging structure of light steel slope roof basic level
CN204738462U (en) Portable building photovoltaic roofing
CN202430876U (en) Floor system with structure of steel and concrete precast slabs
CN207296117U (en) Integral type steel bar truss floor support plate structure
CN105888114B (en) The cladding tile structure of Qing Gang pitched roofs base and flat roof deck change the construction method of pitched roof
CN106149986A (en) A kind of cold bending thin wall steel construction steel tile roofing system
CN106193410A (en) A kind of precast concrete small-sized self waterproofing heat insulation house surface system
CN109838024B (en) Method for constructing roof of fabricated building
CN209924293U (en) Reinforced concrete archaizing building cornice
CN210597802U (en) Flat change slope roofing node structure
CN210738078U (en) Slope roof formwork system for multiple slopes
CN210127563U (en) Connection structure of Ether plate curtain wall
CN203462631U (en) Energy-saving and heat-insulating waterproof wooden truss roofing system construction structure
CN209179288U (en) Joist under a kind of interior gutter
CN203361431U (en) Steel bar connection structure for prefabricated parapet wall
CN208184043U (en) A kind of prefabrication floor framing
CN207277534U (en) A kind of batten wall building with roof truss that can quickly assemble
CN205531042U (en) Upright lock stitches steel tile roofing system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20161012

Effective date of abandoning: 20180605

AV01 Patent right actively abandoned