CN205604737U - Light slat integral hoisting system - Google Patents

Light slat integral hoisting system Download PDF

Info

Publication number
CN205604737U
CN205604737U CN201620306646.7U CN201620306646U CN205604737U CN 205604737 U CN205604737 U CN 205604737U CN 201620306646 U CN201620306646 U CN 201620306646U CN 205604737 U CN205604737 U CN 205604737U
Authority
CN
China
Prior art keywords
plate
steel
light lath
steel plate
hoisting system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620306646.7U
Other languages
Chinese (zh)
Inventor
张国标
倪冬雁
杲跃
李媛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinyuhang Jialvjian Technology Co ltd
Original Assignee
Hangzhou Zetong Architecture Energy Saving New Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Zetong Architecture Energy Saving New Materials Co Ltd filed Critical Hangzhou Zetong Architecture Energy Saving New Materials Co Ltd
Priority to CN201620306646.7U priority Critical patent/CN205604737U/en
Application granted granted Critical
Publication of CN205604737U publication Critical patent/CN205604737U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a light slat integral hoisting system belongs to building frock field, it includes the light slat, steel frame and counter weight device, frame girder steel in the counter weight device, frame bracing and first fixed counter weight plate and steel frame welding, it is fixed that the light slat passes through the steel frame, the counter weight steel sheet passes through the fixed counter weight plate of second and is connected with first fixed counter weight plate, the light slat, steel frame and counter weight device are whole to be lifted by crane, then cut off being connected of light slat and steel frame, steel frame and counter weight device dump. The utility model has the advantages of the wall body wholeness is strong, and wall surface flat, efficiency of construction height, high altitude construction volume are lacked.

Description

A kind of light lath integral hoisting system
Technical field
This utility model belongs to building frock field, more particularly, it relates to a kind of integral hoisting and the bar of installation Plate assembled tool technology.
Background technology
At present, the materials for wall of building mainly has two kinds: one to be with clay brick, porous brick, cement brick, cinder Brick, aerated blocks are main masonry wall, two be with GRC plate, fiver cement board grouting light foam concrete plate, The light lath walls such as ALC plate.
Masonry wall, in work progress, belongs to half wet trade, and labour demand is intensive, and wall leveling degree deviation is big Difficult quality controls, and construction easily causes airborne dust, affect environment, exterior-wall heat insulation and body of wall can not synchronous construction, Long construction period and external wall construction are affected by rainy weather.
Light lath wall is a kind of novel energy-conserving walling material, and it is a kind of external form walling as cored slab, it There is male and female tongue-and-groove on both sides, only need to be erected by sheet material during installation, and male and female tenon is coated after a small amount of filleting mortar assembly Get up.Light lath wall is by various industrial waste residues groups such as innoxious ardealite, lightweight slag, flyash Become, form through the pressurization maintenance of frequency conversion steam.Light lath has light weight, intensity environmental protection high, multiple, insulation The advantages such as heat insulation, sound insulation, breathing damping, fire prevention, rapid construction, reduction body of wall cost.But due to monoblock wall Body is combined at the construction field (site) by the batten of polylith width 300~600mm, and it is low that it exists efficiency of construction, installs Speed is slow, the shortcomings such as amount of high-altitude operation is big.
Utility model content
The purpose of this utility model is to overcome traditional lightweight batten monolithic at the construction field (site) the most assembled, construction speed Slowly, inefficiency, the shortcoming that amount of high-altitude operation is big, it is provided that a kind of globality is strong, lifting rapidly, reduces degree Work high above the ground, the light lath integral hoisting system of job site entirety assembling.
For the attainment of one's purpose, the technical scheme that this utility model provides is:
A kind of light lath integral hoisting system of the present utility model, it is characterised in that: it include light lath, Steel frame and counter weight device, described steel frame includes interior working plate and outer working plate, and interior working plate two ends are welded First side steel plate, the second side steel plate, the first side steel plate and the second side steel plate are welded in outer working plate two ends Employing plain bolt connects, and outer working plate upper surface symmetry is welded with the first lifting plate, and described light lath is arranged Between interior working plate and outer working plate;Described counter weight device includes framework girder steel, framework diagonal brace, first solid Determine Weight plate, the second fixed weight plate and counterweight steel plate, framework girder steel and framework diagonal brace one end to weld with outer working plate Connecing, the other end and the welding of the first fixed weight plate, the first fixed weight plate and the second fixed weight plate are correspondingly provided with Bolt hole, counterweight steel plate uses fixing being bolted between the first fixed weight plate and the second fixed weight plate, The framework girder steel upper surface symmetry of end bay is welded with on the second lifting plate, the first lifting plate and the second lifting plate and is all provided with hanging Dress hole.
Described light lath includes 4~6 pieces of batten monomers, and batten monomer thickness is 100mm~250mm, two The position of the corresponding second side steel plate of the batten monomer of side is provided with the groove of 20mm, the two ends up and down of batten monomer It is all provided with installing hole.4~6 pieces of batten monomers are lifted by this technical scheme together, add the globality of body of wall, with Time accelerate wall construction speed, the groove of both sides is easy to steel frame can preferably clamp light lath.
Described batten monomer uses precast slab.
As preferably, described batten monomer uses autoclaved lightweight concrete board.
It is equipped with some bolts hole on the first described side steel plate and the second side steel plate.
As preferably, described interior working plate, the first side steel plate and the second side steel plate all use bar steel plate, Outer working plate uses channel-section steel.
As preferably, described framework girder steel, framework diagonal brace, the first fixed weight plate and the second fixed weight plate It is respectively adopted the combination of one or more of the steel plate of bar steel plate or channel-section steel or other section forms.
As preferably, the contact surface of described interior working plate, outer working plate, the second side steel plate and light lath It is additionally provided with rubber sheet gasket.Owing to interior working plate, side steel plate and outer working plate width are less, in hoisting process Under the effect of light lath deadweight, the stationary plane of light lath is easy to damage, and the setting of rubber sheet gasket can guarantee that Body of wall is in hoisting process, and light lath is not destroyed by steel frame.
The technical scheme using this utility model to provide, compared with prior art, has the advantages that
(1) the light lath integral hoisting system that this utility model relates to adds the globality of body of wall, reduces Because installing the bar sheet separation produced.
(2) the light lath integral hoisting system that this utility model relates to can reduce amount of high-altitude operation, installs matter Amount is more easy to be effectively controlled, and makes and on-site hoisting speed is fast, climate conditionality is little, save labour force And construction quality controllability can be improved.
Accompanying drawing explanation
Fig. 1 is this utility model light lath integral hoisting system structure schematic diagram;
Fig. 2 is the alien invasion figure before this utility model light lath integral hoisting system does not installs Weight plate;
Fig. 3 is elevation in this utility model light lath integral hoisting system.
Mark explanation in schematic diagram: 1-installing hole;2-light lath;3-plain bolt;Working plate in 4-; 51-the first side steel plate;52-the second side steel plate;6-groove;The outer working plate of 7-;8-framework girder steel;9-first Fixed weight plate;10-framework diagonal brace;11-first lifts plate;12-the second fixed weight plate;13-counterweight steel plate; 14-fixes bolt;15-second lifts plate;16-rubber sheet gasket.
Detailed description of the invention
For further appreciating that content of the present utility model, in conjunction with the accompanying drawings and embodiments this utility model is retouched in detail Stating, following example are used for illustrating this utility model, but are not limited to scope of the present utility model.
In conjunction with Fig. 1~Fig. 3, the present embodiment one light lath integral hoisting system includes light lath 2, steel framework Frame and counter weight device.
Described light lath 2 is spliced by the autoclaved lightweight concrete board that 5 pieces of thickness is 150mm, The autoclaved lightweight concrete board of both sides grinds the groove 6 of 20mm, every piece of steam pressure in the position of side steel plate Lightweight aerated concrete plate monomer be equipped with installing hole 1 up and down.Described steel frame includes interior working plate 4 He Outer working plate 7, interior working plate 4 two ends are respectively welded the first side steel plate 51, corresponding outer working plate 7 two ends are all welded with the second side steel plate 52, and on the first side steel plate 51 and the second side steel plate 52, correspondence is opened If bolt hole, light lath 2 is close to inside outer working plate 7 install, and uses interior working plate 4 to fix light lath After 2, connect the first side steel plate 51 and the second side steel plate 52 with plain bolt 3, if interior working plate 4 with Between light lath 2, between outer working plate 7 and light lath 2 or the second side steel plate 52 and light lath Having space, filled rubber pad 16 between 2, outer working plate 7 upper surface symmetry is welded with the first lifting plate 11, First lifting plate 11 is provided with hole for hoist.
Described counter weight device includes that framework girder steel 8, framework diagonal brace the 10, first fixed weight plate 9, second are solid Determine Weight plate 12 and counterweight steel plate 13, its middle frame girder steel 8, framework diagonal brace 10 and the first fixed weight plate 9 Directly welding with outer working plate 7 in factory, framework girder steel 8 uses the channel-section steel of Q235B, framework diagonal brace 10 to adopt Q235B angle steel, the first fixed weight plate 9 is used to use Q235B bar steel plate, table on its middle frame girder steel 8 Face is provided with the second lifting plate 15, and the second lifting plate 15 is provided with hole for hoist, and the first fixed weight plate 9 is provided with Bolt hole, also is provided with bolt hole on the second fixed weight plate 12 the most one to one, and counterweight steel plate 13 passes through Calculate and select its quality, and be close to the first fixed weight plate 9 and install, then use the second fixed weight plate 12 Clamp, use fixing bolt 14 to fix.
The installation method of a kind of light lath integral hoisting system that the present embodiment relates to includes:
Step one: splice in die station and need light lath 2 to be mounted, and needing light lath to be mounted Groove 6 deep for 20mm is offered in the left and right sides of 2, needs light lath 2 to be mounted to use autoclaved lightweight Concrete slab (i.e. ALC plate).
Step 2: after needing light lath 2 to be mounted to be in place, by outer working plate 7 and interior working plate 4 It is respectively mounted and puts in place, and connect the first side steel plate 51 and the second side steel plate 52, gently by plain bolt 3 Matter batten 2 is connected with frock has the local of space to use sheet rubber 16 to fill, and makes light lath 2 and steel frame Laminating puts in place, locks with plain bolt 3.
Step 3: draw counterweight steel plate 13 weight according to Lofting Calculation, matches suitable counterweight steel plate 13, will Clip with the second fixed weight plate 12 after counterweight steel plate 13 is in place, and fix with fixing bolt 14.
Step 4: light lath 2 is lifted to specifying position together with steel frame and counter weight device, during lifting, The hoist cable of hoisting machine ties up at the hole for hoist of the first lifting plate 11 and the second lifting plate 15, now the first lifting plate Hoist cable on 11 applies active force, and the hoist cable on the second lifting plate 15 does not apply power.
Step 5: unclamp plain bolt 3, takes off interior working plate 4, is converted to the hoist cable on the second lifting plate 15 Applying active force, the hoist cable on the first lifting plate 11 does not apply power, hoisting steel framework and counter weight device.
Schematically being described this utility model and embodiment thereof above, this description does not has restricted, Shown in accompanying drawing is also one of embodiment of the present utility model, and actual structure is not limited thereto.Institute Enlightened by it with those of ordinary skill in the art, in the case of creating objective without departing from this utility model, no Design the frame mode similar to this technical scheme and embodiment through creative, this utility model all should be belonged to Protection domain.

Claims (8)

1. a light lath integral hoisting system, it is characterised in that: it include light lath, steel frame and Counter weight device, described steel frame includes that interior working plate and outer working plate, interior working plate two ends weld the first side Steel plate, outer working plate two ends are welded the second side steel plate, the first side steel plate and the second side steel plate and are used common Bolt connects, and outer working plate upper surface symmetry is welded with the first lifting plate, and described light lath is arranged on interior frock Between plate and outer working plate;Described counter weight device include framework girder steel, framework diagonal brace, the first fixed weight plate, Second fixed weight plate and counterweight steel plate, framework girder steel and framework diagonal brace one end are welded with outer working plate, the other end Welding with the first fixed weight plate, the first fixed weight plate and the second fixed weight plate are correspondingly provided with bolt hole, join Weight steel plate uses fixing being bolted between the first fixed weight plate and the second fixed weight plate, the framework of end bay Girder steel upper surface symmetry is welded with on the second lifting plate, the first lifting plate and the second lifting plate and is all provided with hole for hoist.
A kind of light lath integral hoisting system the most according to claim 1, it is characterised in that: described Light lath include 4~6 pieces of batten monomers, batten monomer thickness is 100mm~250mm, the batten of both sides The position of the corresponding second side steel plate of monomer is provided with the groove of 20mm, and the two ends up and down of batten monomer are all provided with installing Hole.
A kind of light lath integral hoisting system the most according to claim 1 and 2, it is characterised in that: Described batten monomer uses precast slab.
A kind of light lath integral hoisting system the most according to claim 1 and 2, it is characterised in that: Described batten monomer uses autoclaved lightweight concrete board.
A kind of light lath integral hoisting system the most according to claim 1, it is characterised in that: described The first side steel plate and the second side steel plate on be equipped with some bolts hole.
A kind of light lath integral hoisting system the most according to claim 1, it is characterised in that: described Interior working plate, the first side steel plate and the second side steel plate all use bar steel plate, outer working plate uses channel-section steel.
A kind of light lath integral hoisting system the most according to claim 1, it is characterised in that: described Framework girder steel, framework diagonal brace, the first fixed weight plate and the second fixed weight plate be respectively adopted bar steel plate or The combination of one or more of channel-section steel or angle steel.
A kind of light lath integral hoisting system the most according to claim 1, it is characterised in that: described Interior working plate, outer working plate, the contact surface of the second side steel plate and light lath be additionally provided with rubber sheet gasket.
CN201620306646.7U 2016-04-13 2016-04-13 Light slat integral hoisting system Active CN205604737U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620306646.7U CN205604737U (en) 2016-04-13 2016-04-13 Light slat integral hoisting system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620306646.7U CN205604737U (en) 2016-04-13 2016-04-13 Light slat integral hoisting system

Publications (1)

Publication Number Publication Date
CN205604737U true CN205604737U (en) 2016-09-28

Family

ID=56972936

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620306646.7U Active CN205604737U (en) 2016-04-13 2016-04-13 Light slat integral hoisting system

Country Status (1)

Country Link
CN (1) CN205604737U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107130757A (en) * 2017-06-19 2017-09-05 南京旭建新型建材股份有限公司 Large autoclaved lightweight aerated concrete slab component
CN108978926A (en) * 2017-05-31 2018-12-11 五冶集团上海有限公司 A kind of installation method of Double-layer profiled steel sheet composite thermal-insulating wall inside profiled sheet
CN110700551A (en) * 2019-11-11 2020-01-17 浙江宇之航科技工程有限公司 Hoisting assembly applied to attached lifting scaffold

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978926A (en) * 2017-05-31 2018-12-11 五冶集团上海有限公司 A kind of installation method of Double-layer profiled steel sheet composite thermal-insulating wall inside profiled sheet
CN107130757A (en) * 2017-06-19 2017-09-05 南京旭建新型建材股份有限公司 Large autoclaved lightweight aerated concrete slab component
CN110700551A (en) * 2019-11-11 2020-01-17 浙江宇之航科技工程有限公司 Hoisting assembly applied to attached lifting scaffold
CN110700551B (en) * 2019-11-11 2021-07-09 浙江宇之航科技工程有限公司 Hoisting assembly applied to attached lifting scaffold

Similar Documents

Publication Publication Date Title
US11655641B2 (en) Construction building equipment and construction method thereof
CN103015565B (en) Prefabricated and assembled type integrated reinforced concrete load bearing wall and building construction method
CN103374986B (en) A kind of multifunction combined light weight concrete construction curtain wall and preparation method thereof
WO2016062224A1 (en) Integrated column-equipped heat insulation wallboard, manufacturing and building processes and corollary equipment thereof
CN100513717C (en) Steel structure assisted layered installation and construction method for superhigh PRC partition plate
CN101892717B (en) Large autoclaved lightweight aerated concrete slab and installation method thereof
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN203924471U (en) Precast concrete external wall panel
CN111926910A (en) Installation method of fabricated building
CN208718152U (en) Embedded ALC wallboard shock-resistant node structure
CN205604737U (en) Light slat integral hoisting system
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN104947846B (en) A kind of prefabricated integral frame light filling lining and preparation method thereof
CN109235702B (en) Assembled double-steel-plate combined shear wall structure with ribs and construction method thereof
CN104120883A (en) Construction method for non-removal fire-prevention heat-preservation building component formwork
CN105672664A (en) Integral heat insulation wallboard building system
CN107989238A (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method
CN105019598A (en) Reinforced lightweight plate for grooved reinforced concrete pavement
CN208009698U (en) A kind of modular architectural structural of combination shear wall and frame structure
CN103669872A (en) Walling method and walling device
CN112459307A (en) Construction method of prefabricated heat-preservation-structure integrated wall external formwork
CN205502377U (en) Hanging wallboard is partly inlayed to unit -installment light
CN101538904B (en) Gypsum powder poured integral wall and manufacturing method thereof
CN102127942A (en) Energy-saving earthquake-resistant cored beam-free building floor slab
CN204662771U (en) A kind of cutting arrangement of reinforcement formula for building strengthens light weight board

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 311419 Building No. 53, Yushan Village, Yushan Township, Fuyang City, Hangzhou City, Zhejiang Province

Patentee after: Zhejiang Hangjiazetong Building Energy Saving New Materials Co.,Ltd.

Address before: 311419 Building No. 53, Yushan Village, Yushan Township, Fuyang City, Hangzhou City, Zhejiang Province

Patentee before: HANGZHOU ZETONG BUILDING ENERGY SAVING NEW MATERIAL CO.,LTD.

CP03 Change of name, title or address

Address after: 311419 building 4, No. 53, zhumufan, Yushan village, Yushan Township, Fuyang District, Hangzhou City, Zhejiang Province

Patentee after: Zhejiang Jinyuhang Jialvjian Technology Co.,Ltd.

Country or region after: China

Address before: 311400 building 4, No. 53, Zhumu fan, Yushan village, Yushan Township, Fuyang City, Hangzhou City, Zhejiang Province

Patentee before: Zhejiang Hangjiazetong Building Energy Saving New Materials Co.,Ltd.

Country or region before: China