CN205576858U - A gravel soil core -wall material preparation facilities for embankment dam engineering - Google Patents

A gravel soil core -wall material preparation facilities for embankment dam engineering Download PDF

Info

Publication number
CN205576858U
CN205576858U CN201620397072.9U CN201620397072U CN205576858U CN 205576858 U CN205576858 U CN 205576858U CN 201620397072 U CN201620397072 U CN 201620397072U CN 205576858 U CN205576858 U CN 205576858U
Authority
CN
China
Prior art keywords
hopper
belt
earth
preparation facilities
wall material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620397072.9U
Other languages
Chinese (zh)
Inventor
钟权
龙军飞
王峰
周德彦
王勇胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201620397072.9U priority Critical patent/CN205576858U/en
Application granted granted Critical
Publication of CN205576858U publication Critical patent/CN205576858U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)

Abstract

The utility model relates to a gravel soil core -wall material preparation facilities for embankment dam engineering. The utility model discloses a plurality of hoppers of establishing ties and setting up are connected through the compounding belt between two adjacent hoppers, and the feed end of compounding belt cooperates the discharge gate below of locating the hopper, the feed inlet that a back hopper was located in the discharge end cooperation, and the feed inlet cooperation of hopper foremost is equipped with gravel feed belt, earth material feed belt. The utility model discloses simple structure, convenient operation, low cost, convenient implementation.

Description

Gravelly soil core-wall material preparation facilities for earth-rock works
Technical field
This utility model relates to a kind of gravelly soil core-wall material preparation facilities for earth-rock works, belongs to Hydraulic and Hydro-Power Engineering field.
Background technology
Along with the Devoting Major Efforts To Developing of China's western part hydroelectric resources, the construction of high earth-rock works is on the increase, domestic construction or plan to build into A collection of 200~the high earth and rockfill dam of 300m level, its core-wall material demand often reaches hundreds of all places.
It is said that in general, seepage prevention of core wall body does not require nothing more than has preferable barrier properties, and should have higher shear resistance.But, According to the domestic complete 300m level high earth and rockfill dam construction built and plan to build and reconnoitre analysis in detail, natural impermeable soil material source is difficult to meet rule Model requirement, needs the mode using admixture gravel to be modified, forms gravelly soil, to improve its shear resistance.
At present, earth-rock works precordial distress blends " tiling is vertical adopts " arrangement and method for construction that general employing is traditional, its main technique stream Cheng Wei: stock ground exploitation → earth material and building stones transport to blend facade in layering tiling in field → blendings field → blend field exploit blending → The upper dam of admixture transport.
Traditional tiling Li Caifa construction also exists that automatization level is low, production efficiency is low, quality stability is poor, floor space Greatly, high cost problem big by weather influences such as rainfalls;Additionally, the hydroelectric project of China's construction is located in high waterway between mountains mostly Canyon, construction site is narrow, uses the vertical mode of adopting of tiling to carry out blending and certainly will be limited by field, affects engineering construction progress. High earth and rockfill dam gravelly soil core-wall material quantities is big, and core-wall material blends and needs efficient and stable blending technique badly, to guarantee engineering construction Construction speed and the permanent operation of dam body.
Utility model content
Technical problem to be solved in the utility model is: provide a kind of structural manufacturing process to be simple and convenient to operate, use with low cost In the gravelly soil core-wall material preparation facilities of earth-rock works, to solve that existing blending mode construction technology is loaded down with trivial details, with high costs, to execute The difficult problems such as work lack of space, to improve blending ability, to reduce blending cost.
The gravelly soil core-wall material for earth-rock works is the technical scheme is that by solving above-mentioned technical problem this utility model Preparation facilities, including the multiple hoppers being arranged in series, is connected by batch mixing belt between adjacent two hoppers, batch mixing belt Feed end coordinate be located at below the discharging opening of hopper, discharge end coordinate be located at after the charging aperture of a hopper, being subject to foremost The charging aperture cooperation of hopper is provided with gravel feed belt, earth material feed belt.
Further: hopper is taper.
Further: the inclination angle of hopper sidewall is 50 °~60 °.
Further: hopper discharging opening at the width of side, batch mixing belt width direction, for batch mixing belt width 0.55~ 0.65 times.
Further: the discharge end of gravel feed belt, the discharge end of earth material feed belt are located at same vertical plane.
Further: the discharging opening cooperation of the hopper of least significant end is provided with outfeed belt.
Further: outfeed belt cooperation is provided with water replanishing device.
The beneficial effects of the utility model are: during enforcement, simultaneously toward hopper charging aperture conveying gravel material foremost and earth material, Transferred by multiple hoppers, a plurality of batch mixing belt again, earth material and gravel material during free-falling by hopper sidewall Counteracting force, changes running orbit, and meanwhile, between earth material and gravel material, internal friction angle is different, therefore makes two kinds in motor process Material constantly collides with each other, blends, and after the blending of multiple hoppers, reaches the purpose blended.This apparatus structure letter Single, easy to operate, with low cost, convenient enforcement.
Accompanying drawing explanation
Fig. 1 is structural representation of the present utility model;
Labelling in figure: 1-hopper, 2-batch mixing belt, 3-gravel feed belt, 4-earth material feed belt, 5-outfeed belt.
Detailed description of the invention
The utility model is described in further detail below in conjunction with the accompanying drawings.
As it is shown in figure 1, this utility model includes the multiple hoppers 1 being arranged in series, by mixed between adjacent two hoppers 1 Material belt 2 connects, and the feed end cooperation of batch mixing belt 2 is located at below the discharging opening of hopper 1, discharge end cooperation is located at rear one The charging aperture of hopper 1, the charging aperture cooperation of hopper 1 foremost is provided with gravel feed belt 3, earth material feed belt 4. Hopper 1 quantity and corresponding batch mixing belt 2 quantity should determine according to scene test, and hopper 1 quantity is generally 3 or 4.
Hopper 1 is preferably taper, it addition, the inclination angle of hopper 1 sidewall is preferably 50 °~60 °.Under so can facilitating Material, thus prevent putty, blend effect preferable simultaneously.
For avoiding material to trickle down, it is preferable that hopper 1 discharging opening width in batch mixing belt 2 width side, for batch mixing 0.55~0.65 times of belt 2 width.
Preferably, the discharge end of gravel feed belt 3, the discharge end of earth material feed belt 4 are located at same vertical plane, and i.e. two Person overlaps in vertical direction, is beneficial to soil stone mixing.It addition, gravel feed belt 3, earth material feed belt 4 are preferably disposed to The same side of hopper 1 charging aperture.
Deliver to destination for convenience of the material after blending, outfeed belt can be equipped with at the discharging opening of the hopper 1 of least significant end 5, it addition, also water replanishing device can be equipped with at outfeed belt 5, the moisture content of the material after regulating blending.Certainly, also Can use other transloading equipment, the material after blending is transported to store up field watering and shelving.

Claims (7)

1. for the gravelly soil core-wall material preparation facilities of earth-rock works, it is characterised in that: include the multiple hoppers being arranged in series (1), being connected by batch mixing belt (2) between adjacent two hoppers (1), the feed end of batch mixing belt (2) coordinates to be located at Below the discharging opening of hopper (1), discharge end coordinate be located at after the charging aperture of a hopper (1), hopper (1) foremost Charging aperture coordinate be provided with gravel feed belt (3), earth material feed belt (4).
2. the gravelly soil core-wall material preparation facilities for earth-rock works as claimed in claim 1, it is characterised in that: hopper (1) it is taper.
3. the gravelly soil core-wall material preparation facilities for earth-rock works as claimed in claim 2, it is characterised in that: hopper (1) inclination angle of sidewall is 50 °~60 °.
4. the gravelly soil core-wall material preparation facilities for earth-rock works as claimed in claim 1, it is characterised in that: hopper (1) discharging opening is at the width of batch mixing belt (2) width side, for 0.55~0.65 times of batch mixing belt (2) width.
5. the gravelly soil core-wall material preparation facilities for earth-rock works as claimed in claim 1, it is characterised in that: gravel enters The discharge end of material belt (3), the discharge end of earth material feed belt (4) are located at same vertical plane.
6. the gravelly soil core-wall material preparation facilities for earth-rock works as claimed in claim 1, it is characterised in that: least significant end Hopper (1) discharging opening coordinate be provided with outfeed belt (5).
7. the gravelly soil core-wall material preparation facilities for earth-rock works as claimed in claim 6, it is characterised in that: discharging skin Band (5) cooperation is provided with water replanishing device.
CN201620397072.9U 2016-05-05 2016-05-05 A gravel soil core -wall material preparation facilities for embankment dam engineering Active CN205576858U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620397072.9U CN205576858U (en) 2016-05-05 2016-05-05 A gravel soil core -wall material preparation facilities for embankment dam engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620397072.9U CN205576858U (en) 2016-05-05 2016-05-05 A gravel soil core -wall material preparation facilities for embankment dam engineering

Publications (1)

Publication Number Publication Date
CN205576858U true CN205576858U (en) 2016-09-14

Family

ID=56858294

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620397072.9U Active CN205576858U (en) 2016-05-05 2016-05-05 A gravel soil core -wall material preparation facilities for embankment dam engineering

Country Status (1)

Country Link
CN (1) CN205576858U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108382874A (en) * 2018-05-07 2018-08-10 广州市致顺科技有限公司 A kind of tandem drawing-in device
CN110667787A (en) * 2019-10-28 2020-01-10 中交第三航务工程局有限公司 A throw stone ship for pile foundation is thrown and is filled

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108382874A (en) * 2018-05-07 2018-08-10 广州市致顺科技有限公司 A kind of tandem drawing-in device
CN110667787A (en) * 2019-10-28 2020-01-10 中交第三航务工程局有限公司 A throw stone ship for pile foundation is thrown and is filled

Similar Documents

Publication Publication Date Title
CN102305069B (en) Technology and equipment for separating coal and gangue and refilling gangue
CN112814732B (en) Waste stone and tailing mixed slurry preparation and pumping filling device
WO2018176892A1 (en) Network integrated and coordinated control system and method for thin coal seam comprehensive mining and gas control
CN102924010A (en) Self-compaction filling paste body and preparation process thereof
CN101915100B (en) Loess-filling coal-mining method in a coal mine
CN205576858U (en) A gravel soil core -wall material preparation facilities for embankment dam engineering
CN202266260U (en) Technical equipment for separating coal from gangue and backfilling gangue
CN106194249B (en) A kind of coal mine gob totipotency Paste-filling System and method
CN201982137U (en) Underground preparation device taking waste rock as aggregate concrete filling material
CN106065782A (en) A kind of big flow high concentration structure stream full tail sand cemented filling technique
CN104912080B (en) The construction equipment of a kind of mud filling bag embankment and technique
CN101749047B (en) Paste filling simulation test system
CN105257000B (en) A kind of grouter device and its control system and concrete conveying process
CN102661170A (en) Process and device for continuously stirring and filling paste-like body for mine manufactured by use of building waste
CN210343417U (en) Realize closely knit filling system that full roof was met in collecting space area filling tunnel in pit
CN214303937U (en) Preparation of mixed ground paste of barren rock and tailings and pump sending filling device
CN104446640A (en) Foam tail mortar and pulping and grouting process thereof
CN110645044A (en) Grouting filling system
CN201587031U (en) Automatic mixing device for ointment filling system
CN204221981U (en) Clay core wall of earth dam antiseepage gravel earth material preparation facilities
CN102775105A (en) Mine paste filling aggregate prepared from building waste materials and preparation method of mine paste filling aggregate
CN108191365A (en) A kind of method using ardealite material cementing fill metal mine
CN108167017A (en) A kind of metal mine consolidated fill method of environmental protection cementitious material
CN105833771A (en) Gravelly soil core material blending device
CN109020374A (en) More solid-state modification clay cream slurry preparation processes and equipment

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant