CN104912080B - The construction equipment of a kind of mud filling bag embankment and technique - Google Patents

The construction equipment of a kind of mud filling bag embankment and technique Download PDF

Info

Publication number
CN104912080B
CN104912080B CN201510262799.6A CN201510262799A CN104912080B CN 104912080 B CN104912080 B CN 104912080B CN 201510262799 A CN201510262799 A CN 201510262799A CN 104912080 B CN104912080 B CN 104912080B
Authority
CN
China
Prior art keywords
mud
bag
curing agent
embankment
hull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510262799.6A
Other languages
Chinese (zh)
Other versions
CN104912080A (en
Inventor
董江平
卜凡波
徐贺彪
王海建
孙晓峰
孔海荣
张纪祥
张伯水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Shanghai Dredging Co Ltd.
Original Assignee
SDC WATERWAY CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SDC WATERWAY CONSTRUCTION CO Ltd filed Critical SDC WATERWAY CONSTRUCTION CO Ltd
Priority to CN201510262799.6A priority Critical patent/CN104912080B/en
Publication of CN104912080A publication Critical patent/CN104912080A/en
Application granted granted Critical
Publication of CN104912080B publication Critical patent/CN104912080B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to construction equipment and the technique of a kind of mud filling bag embankment, the construction equipment of mud filling bag embankment, it is characterised in that: include hull;The chain-bucket dredging plant being arranged on hull;Disintegrating machine, is arranged on hull, and the output of chain-bucket dredging plant is connected with the entrance of pulverizer;Mixer, is arranged on hull, and the outlet of pulverizer is connected with the entrance of mixer, for being stirred the mud after crushing;Poly-hopper dredger, is arranged on hull, is positioned at below mixer, and the outlet of mixer is connected with poly-hopper dredger by chute;Pulp pump, is arranged on hull, and the entrance of Pulp pump connects with poly-hopper dredger;Curing agent adds and conveying device, for adding curing agent in mud;Mixing plant, slurry delivery side of pump and curing agent add and the outlet of conveying device all connects with mixing plant;Slush pump, the entrance of slush pump connects with mixing plant, and mud delivery side of pump connects with the bag completed in advance.Efficiency of construction of the present invention is high, low cost.

Description

The construction equipment of a kind of mud filling bag embankment and technique
Technical field
The present invention relates to construction equipment and the technique of a kind of mud filling bag embankment.
Background technology
In coastal provinces city, for solving the urban sprawl constant demand to soil, the commonly used method reclaimed fields from the sea.? Reclamation by pumping filling on ultra-soft foundation, cofferdam is key link.At present, in engineering, the general cofferdam structure form used has packed Sand cofferdam, slag cofferdam, the pool and sand are combined cofferdam.In recent years, environmental protection is increasingly paid attention to by people, adopt under water sand, Fried mountain takes stone and is all restricted by environmental protection, embankment construction and make ground the cycle receive the biggest impact, if can utilize along seabeach The mud that painting is enriched, as the filling material of embankment, will greatly facilitate the exploitation of Coastal beach.
In the last few years, people attempt mixing curing agent filling bag in mud and form cofferdam, but owing to mudflat sludge is aqueous Rate height, poor permeability, clay content high, existing construction equipment and technique do not simply fail to meet executing of quick fill Work requires and construction cost is higher, therefore fails to be promoted in engineering.Therefore, a kind of mud rapid filling bag of invention The complete set of equipments of fill and construction technology, the exploitation to coastal cities has highly important meaning.
Summary of the invention
To be solved by this invention primarily technical problem is that for above-mentioned prior art provide one can collect fetch earth, stir, Carry, charge in the construction equipment of mud filling bag embankment integrally.
The further primary technical problem to be solved of the present invention is to provide and a kind of uses above-mentioned construction equipment to carry out mud to fill Filling out the construction technology of bag fill, this technique can be greatly improved efficiency of construction and save a large amount of engineering cost.
The present invention solves the technical scheme that above-mentioned technology matter of utmost importance used: the construction of a kind of mud filling bag embankment sets It is standby, it is characterised in that: include
Hull;
The chain-bucket dredging plant being arranged on hull, for directly taking seabed original state mud;
Pulverizer, is arranged on hull, and the output of chain-bucket dredging plant is connected with the entrance of pulverizer, for sea End original state mud crushes;
Mixer, is arranged on hull, and the outlet of pulverizer is connected with the entrance of mixer, for the mud after crushing It is stirred;
Poly-hopper dredger, is arranged on hull, is positioned at below mixer, and the outlet of mixer is connected with poly-hopper dredger by chute;
Pulp pump, is arranged on hull, and the entrance of Pulp pump connects with poly-hopper dredger;
Curing agent adds and conveying device, for adding curing agent in mud;
Mixing plant, slurry delivery side of pump and curing agent add and the outlet of conveying device all connects with mixing plant, and mud exists Abundant mix is carried out to uniformly with curing agent in this mixing plant;
Slush pump, the entrance of slush pump connects with mixing plant, and mud delivery side of pump connects with the bag completed in advance.
As improvement, it is provided with, in described poly-hopper dredger, the reducing mechanism that mud is carried out second-time breakage.
Preferably, the pipeline using caliber to be 250mm between Pulp pump with poly-hopper dredger is connected.
Improve again, between Pulp pump and poly-hopper dredger, be provided with relay pump.
Preferably, described pulverizer includes three groups of crushing shafts, and often group crushing shaft is provided with multi-disc free end towards different leaf Sheet, often group crushing shaft spacing is 1.5m.
Preferably, two helical axis, spacing 90cm between two helical axis, every helical axis it are provided with in described mixer Height be 80cm.
The present invention solve above-mentioned further technical problem technical scheme used be: use said structure mud filling bag to build The construction method of the mud filling bag embankment that the construction equipment of dike is carried out, it is characterised in that:
Before construction, taking mud scope according to the position of embankment is selected, size and drinking water further according to hull require excavation ship nest, Moisturizing passage, the barrier of cleaning borrow areas scope are set;
After the measured unwrapping wire in embankment position, manually carry out the laying of bag, during construction, take silt depending on chain-bucket dredging plant The water content situation of mud, carries out the moisturizing mobility with raising mud before mud enters pulverizer, and mud is through disintegrating machine Enter poly-hopper dredger after broken, mixer stirring, flow to mixing plant by Pulp pump the most again, curing agent interpolation simultaneously and Conveying device carries curing agent toward mixing plant, is filled by slush pump after in mixing plant, mud is sufficiently stirred for curing agent Fill to bag;
During bag charges, change in time and charge a mouthful position, be aided with simultaneously and manually trample bag leveling, it is to avoid locally Too high phenomenon occurs, and bag charges THICKNESS CONTROL at 60cm, and control errors is at 2cm, in order to accelerate whole bag Solidification effect, arranges outside the thin mud of pools zone discharged bag by temporary drainage mouth in time, thickness to be charged on bag Meet after requiring, carry out charging of next bag, because of filling in bag be slurry mixture, in work progress, hold Easily sliding, therefore need compartment to construct, i.e. next bag construction location is the position after sky opens a bag, then fills Fill, but ensure there is the overlap joint not less than 1m between each bag;
Lower pocket charge complete after, then upper strata bag is progressively charged superposition, charges and complete stick to bag table The mud giant in face cleans up, and reserves the discharging consolidation time between layers simultaneously, ultimately forms design requirement Embankment section.
Compared with prior art, it is an advantage of the current invention that: the silt soil substitution of resources routine using Coastal beach to enrich Sand as embankment filling material, the construction equipment utilizing the present invention to provide is delivered to after it being stirred with curing agent Bag forms cofferdam, and the construction equipment collection that the present invention provides fetches earth, stirs, carries, charges whole process by once, Efficiency of construction can greatly be improved, and save a large amount of engineering cost.
Accompanying drawing explanation
Fig. 1 is the structural representation of the construction equipment of mud filling bag embankment in the embodiment of the present invention.
Detailed description of the invention
Below in conjunction with accompanying drawing embodiment, the present invention is described in further detail.
The construction equipment of mud filling bag embankment as shown in Figure 1, it includes
Hull 1;
The chain-bucket dredging plant 2 being arranged on hull, for directly taking seabed original state mud;
Pulverizer 3, is arranged on hull, and the output of chain-bucket dredging plant is connected with the entrance of pulverizer, for right Seabed original state mud crushes;
Mixer 4, is arranged on hull, and the outlet of pulverizer is connected with the entrance of mixer, for the silt after crushing Mud is stirred;
Poly-hopper dredger 5, is arranged on hull, is positioned at below mixer, and the outlet of mixer is connected with poly-hopper dredger by chute;
Pulp pump 6, is arranged on hull, and the entrance of Pulp pump connects with poly-hopper dredger;
Curing agent adds and conveying device 7, for adding curing agent in mud;
Mixing plant 8, slurry delivery side of pump and curing agent add and the outlet of conveying device all connects with mixing plant, mud Abundant mix is carried out to uniformly with curing agent in this mixing plant;
Slush pump 9, the entrance of slush pump connects with mixing plant, and mud delivery side of pump connects with the bag completed in advance.
In order to overcome the drawback that the moisture content that fetches earth in conventional equipment is big, soil extracting efficiency is low, the present invention directly uses chain-bucket Dredger transformation form, hull 1 is the hull of bucket dredge, then pulverizer 3, mixer 4, poly-hopper dredger 5, Pulp pump 6 is directly installed on hull 1;Chain-bucket dredging plant 2 uses existing conventional structure, directly takes seabed former Shape soil, fetch earth degree of depth 6m, full-load draft 1m, and in order to adapt to the power match requirement of whole system, chain bucket rotating speed is adopted With stepless speed regulation scheme (rotating speed can arbitrarily regulate from 0 to setting value), soil extracting efficiency is up to 200m3/h。
In order to make mud slurry matter uniform, mud is stable, first the block undisturbed soil taken is carried out physical treatment, to reach The requirement of conveying;Here physical processing apparatus is by including that pulverizer and pusher biaxial rneader form, and pulverizer comprises Three groups of crushing shafts, every crushing shaft is provided with free end towards different blade, and often the spacing between group rotating shaft is 1.5m. Pusher biaxial rneader sets two helical axis, two helical axis spacing 90cm, every helical axis height 80cm, uses Right-handed screw formula structure.Owing to muck soil clay content is high, in order to effectively mud original soil to be carried out broken stirring, become silted up Mud original soil sets the poly-hopper dredger of rectangle of a 2m*2m after double-axle stirrer, adds two groups of crushing shafts in poly-hopper dredger again.Become silted up Mud induction system uses high-power Pulp pump, lift 52m, output pressure 1Mpa;Use between Pulp pump and poly-hopper dredger Caliber is that the pipeline of 250mm is connected, and in order to improve fed distance, can in position add small-sized relay pump.
Curing agent adds and conveying device includes curing agent automatic feeding device and curing agent conveying device, and curing agent divides pulvis And liquid agent, therefore, curing agent automatic feeding device is the spiral continuous metering for controlling fixed curing agent addition Device or for controlling the flow pump of liquid curing-agent addition, curing agent conveying device uses conventional plunger pump.
For making curing agent and the abundant mix of mud, stable performance, a mixing plant, mud and solidification are set near hull Agent is delivered in this mixing plant, charges to bag after stirring.
The running technology scheme of whole construction equipment is: chain-bucket dredging plant 2 first carries out taking seabed original state mud, sea End original state mud is discharged into pulverizer 3 and crushes, and is stirred subsequently into mixer 4, then enters poly-along chute 10 In hopper dredger 5, setting mud secondary crushing device in poly-hopper dredger 5, the mud after crushing enters Pulp pump 6, then by pipe Road 11 is delivered in neighbouring mixing plant 8, and curing agent is also delivered in this mixing plant 8 by plunger displacement pump simultaneously, mud and Curing agent action of forced stirring uniformly after be delivered in bag, the power of whole system is 200kw, charge efficiency up to 170-180m3/ h, fully meets practice of construction needs.
The construction method of the mud filling bag embankment that the construction equipment of the mud filling bag embankment of employing said structure is carried out is:
Before construction, taking mud scope according to the position of embankment is selected, size and drinking water further according to hull require excavation ship nest, Moisturizing passage, the barrier of cleaning borrow areas scope are set;
After the measured unwrapping wire in embankment position, manually carry out the laying of bag, during construction, take silt depending on chain-bucket dredging plant The water content situation of mud, carries out the moisturizing mobility with raising mud before mud enters pulverizer, and mud is through disintegrating machine Enter poly-hopper dredger after broken, mixer stirring, flow to mixing plant by Pulp pump the most again, curing agent interpolation simultaneously and Conveying device carries curing agent toward mixing plant, is filled by slush pump after in mixing plant, mud is sufficiently stirred for curing agent Fill to bag;
During bag charges, change in time and charge a mouthful position, be aided with simultaneously and manually trample bag leveling, it is to avoid locally Too high phenomenon occurs, and bag charges THICKNESS CONTROL at 60cm, and control errors is at 2cm, in order to accelerate whole bag Solidification effect, arranges outside the thin mud of pools zone discharged bag by temporary drainage mouth in time, thickness to be charged on bag Meet after requiring, carry out charging of next bag;Because of filling in bag be slurry mixture, in work progress, hold Easily sliding, therefore need compartment to construct, i.e. next bag construction location is the position after sky opens a bag, then fills Fill, but ensure there is the overlap joint not less than 1m between each bag;
Lower pocket charge complete after, then upper strata bag is progressively charged superposition, charges and complete stick to bag table The mud giant in face cleans up, and reserves the discharging consolidation time between layers simultaneously, ultimately forms design requirement Embankment section.

Claims (8)

1. the construction equipment of a mud filling bag embankment, it is characterised in that: include
Hull;
The chain-bucket dredging plant being arranged on hull, for directly taking seabed original state mud;
Pulverizer, is arranged on hull, and the output of chain-bucket dredging plant is connected with the entrance of pulverizer, for sea End original state mud crushes;
Mixer, is arranged on hull, and the outlet of pulverizer is connected with the entrance of mixer, for the mud after crushing It is stirred;
Poly-hopper dredger, is arranged on hull, is positioned at below mixer, and the outlet of mixer is connected with poly-hopper dredger by chute;
Pulp pump, is arranged on hull, and the entrance of Pulp pump connects with poly-hopper dredger;
Curing agent adds and conveying device, for adding curing agent in mud;
Mixing plant, slurry delivery side of pump and curing agent add and the outlet of conveying device all connects with mixing plant, and mud exists Abundant mix is carried out to uniformly with curing agent in this mixing plant;
Slush pump, the entrance of slush pump connects with mixing plant, and mud delivery side of pump connects with the bag completed in advance.
The construction equipment of mud filling bag embankment the most according to claim 1, it is characterised in that: described poly-hopper dredger Inside it is provided with the reducing mechanism that mud is carried out second-time breakage.
The construction equipment of mud filling bag embankment the most according to claim 1, it is characterised in that: Pulp pump is with poly- The pipeline using caliber to be 250mm between hopper dredger is connected.
The construction equipment of mud filling bag embankment the most according to claim 1, it is characterised in that: Pulp pump is with poly- Relay pump it is provided with between hopper dredger.
The construction equipment of mud filling bag embankment the most according to claim 1, it is characterised in that: described pulverizer Including three groups of crushing shafts, often group crushing shaft is provided with multi-disc free end towards different blade, and often group crushing shaft spacing is 1.5m。
The construction equipment of mud filling bag embankment the most according to claim 1, it is characterised in that: described mixer Inside being provided with two helical axis, spacing 90cm between two helical axis, the height of every helical axis is 80cm.
The construction equipment of mud filling bag embankment the most according to claim 1, it is characterised in that: curing agent adds And conveying device includes the spiral continuous batcher for controlling fixed curing agent addition or for controlling liquid curing The flow pump of agent addition, and for carrying the plunger displacement pump of curing agent.
8. the mud filling bag that the construction equipment of an employing mud filling bag embankment as claimed in claim 1 is carried out is built The construction method of dike, it is characterised in that:
Before construction, taking mud scope according to the position of embankment is selected, size and drinking water further according to hull require excavation ship nest, Moisturizing passage, the barrier of cleaning borrow areas scope are set;
After the measured unwrapping wire in embankment position, manually carry out the laying of bag, during construction, take silt depending on chain-bucket dredging plant The water content situation of mud, carries out the moisturizing mobility with raising mud before mud enters pulverizer, and mud is through pulverizer Enter poly-hopper dredger after broken, mixer stirring, flow to mixing plant by Pulp pump the most again, curing agent interpolation simultaneously and Conveying device carries curing agent toward mixing plant, is filled by slush pump after in mixing plant, mud is sufficiently stirred for curing agent Fill to bag;
During bag charges, change in time and charge a mouthful position, be aided with simultaneously and manually trample bag leveling, it is to avoid locally Too high phenomenon occurs, and bag charges THICKNESS CONTROL at 60cm, and control errors is at 2cm, in order to accelerate whole bag Solidification effect, arranges outside the thin mud of pools zone discharged bag by temporary drainage mouth in time, thickness to be charged on bag Meet after requiring, carry out charging of next bag;Because of filling in bag be slurry mixture, in work progress, hold Easily sliding, therefore need compartment to construct, i.e. next bag construction location is the position after sky opens a bag, then fills Fill;
Treat lower pocket charge completely complete after, then upper strata bag is progressively charged superposition, charges complete sticking to The mud giant on bag surface cleans up, and reserves the discharging consolidation time between layers simultaneously, ultimately forms and set The embankment section that meter requires.
CN201510262799.6A 2015-05-21 2015-05-21 The construction equipment of a kind of mud filling bag embankment and technique Active CN104912080B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510262799.6A CN104912080B (en) 2015-05-21 2015-05-21 The construction equipment of a kind of mud filling bag embankment and technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510262799.6A CN104912080B (en) 2015-05-21 2015-05-21 The construction equipment of a kind of mud filling bag embankment and technique

Publications (2)

Publication Number Publication Date
CN104912080A CN104912080A (en) 2015-09-16
CN104912080B true CN104912080B (en) 2016-08-31

Family

ID=54081484

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510262799.6A Active CN104912080B (en) 2015-05-21 2015-05-21 The construction equipment of a kind of mud filling bag embankment and technique

Country Status (1)

Country Link
CN (1) CN104912080B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109208537A (en) * 2017-06-29 2019-01-15 武汉二航路桥特种工程有限责任公司 A kind of dredging markets solidify the construction method for building island
CN108277778A (en) * 2018-01-22 2018-07-13 中交四航局港湾工程设计院有限公司 A kind of filling mud bag supports compound fill structure and filling mud bag fill construction method
CN110510842A (en) * 2019-08-28 2019-11-29 中交一航局第三工程有限公司 A kind of sludge solidification and build island technique
CN115043558B (en) * 2022-06-16 2023-07-14 长江生态环保集团有限公司 Silt in-situ curing device and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2626428B2 (en) * 1992-10-27 1997-07-02 鹿島建設株式会社 Construction method of embankment body using excavated sludge
CN202644544U (en) * 2012-06-15 2013-01-02 天津济润石油海运服务有限公司 Filling device of filling bag
CN103452117A (en) * 2013-09-10 2013-12-18 中交上航局航道建设有限公司 Deepwater bagged sand construction device and deepwater bagged sand construction technology
CN204238282U (en) * 2014-10-12 2015-04-01 童玉兰 For construction work embankment dredged mud filling Mixing Machine
CN204676546U (en) * 2015-05-21 2015-09-30 中交上航局航道建设有限公司 A kind of construction equipment of mud filling bag embankment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2626428B2 (en) * 1992-10-27 1997-07-02 鹿島建設株式会社 Construction method of embankment body using excavated sludge
CN202644544U (en) * 2012-06-15 2013-01-02 天津济润石油海运服务有限公司 Filling device of filling bag
CN103452117A (en) * 2013-09-10 2013-12-18 中交上航局航道建设有限公司 Deepwater bagged sand construction device and deepwater bagged sand construction technology
CN204238282U (en) * 2014-10-12 2015-04-01 童玉兰 For construction work embankment dredged mud filling Mixing Machine
CN204676546U (en) * 2015-05-21 2015-09-30 中交上航局航道建设有限公司 A kind of construction equipment of mud filling bag embankment

Also Published As

Publication number Publication date
CN104912080A (en) 2015-09-16

Similar Documents

Publication Publication Date Title
CN104912080B (en) The construction equipment of a kind of mud filling bag embankment and technique
CN101824820B (en) Construction process for reclamation by hydraulic filling of silt and device thereof
CN103437786B (en) Shield structure body refuse Recovery Purifying reutilization system is used for the method for Shield Construction Method Used
CN105155511B (en) Rotating drum type swirl curing and stirring device and dredged sludge hydraulic reclamation method
CN105696640B (en) For architectural engineering embankment dredged mud filling Mixing Machine
CN206408628U (en) Diaphram wall Large Copacity mud recycles equipment
CN201738297U (en) Construction device for filling silt and reclaiming land
CN102767156A (en) Diking method through filling sludge and curing agent into mold bags
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN107513992B (en) continuous construction method for solidifying curing agent on shallow surface layer of sludge
CN204676546U (en) A kind of construction equipment of mud filling bag embankment
CN204644106U (en) Dredging markets dehydrating and curing integrated device
CN111893947A (en) Blasting and silt squeezing construction method for deep soft foundation of breakwater in fishing port
CN205115266U (en) Harbour deposited silt solidification ratio experimental apparatus
CN204238282U (en) For construction work embankment dredged mud filling Mixing Machine
CN210597200U (en) Device for fluidized treatment of dredged sludge
CN107299620A (en) Sluice main structure construction scheme
CN205055914U (en) Channel deposit silt solidification ratio experimental apparatus
CN205115265U (en) Pier deposited silt solidification ratio experimental apparatus
CN105672389A (en) Dredged sediment adding mixing machine for building engineering filling and construction method of machine
CN205009390U (en) Incline a little to mixing from formula earth material that falls and mix device
CN204416578U (en) A kind of subway shield tunnel construction feeding device
CN104475215A (en) Integrated production technology of rock-fill dam high-standard transition material
CN218654184U (en) Mobile fluidized solidified soil production equipment
CN104942997B (en) Small concrete mixing plant and concrete mixing method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20170314

Address after: 200002 Shanghai City, Huangpu District Zhongshan East Road No. 13

Patentee after: Shanghai Waterway Bureau Co., Ltd., China Traffic

Address before: Along the road 315200 in Zhejiang province Ningbo City Zhenhai District No. 221

Patentee before: SDC Waterway Construction Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211025

Address after: 200002 No.13, Zhongshan East 1st Road, Huangpu District, Shanghai

Patentee after: CCCC SHANGHAI DREDGING Co.,Ltd.

Patentee after: NATIONAL ENGINEERING RESEARCH CENTER OF DREDGING TECHNOLOGY AND EQUIPMENT

Address before: 200002 No.13, Zhongshan East 1st Road, Huangpu District, Shanghai

Patentee before: CCCC SHANGHAI DREDGING Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220309

Address after: 200002 No.13, Zhongshan East 1st Road, Huangpu District, Shanghai

Patentee after: CCCC SHANGHAI DREDGING Co.,Ltd.

Address before: 200002 No.13, Zhongshan East 1st Road, Huangpu District, Shanghai

Patentee before: CCCC SHANGHAI DREDGING Co.,Ltd.

Patentee before: CCCC dredging technology and equipment National Engineering Research Center Co., Ltd